US 285 North Corridor from FM 1216 to 0.1 mile south of the New Mexico state line
Permian Promise
Corridor description
TxDOT is proposing improvements to US 285 North from FM 1216 north of Pecos, Texas to 0.1 mile south of the New Mexico state line. The corridor is approximately 51 miles long and passes through Culberson and Reeves counties.
The corridor is split into three separate projects, which are described in detail below. The goals of this project are to improve safety and mobility on US 285. Between 2016 and 2021, traffic along this roadway increased by 34.5 percent and there were 839 crashes recorded between 2016 and 2021.
The proposed corridor improvements would include:
- Widening to a four-lane divided highway with two lanes in each direction, as well as both inside and outside shoulders
- New interchanges at SH 302 and RM 652
- A wide center median and/or barrier
- Providing median openings as needed. Median openings would include left-turn/deceleration lanes
Project information
The proposed improvements are being broken up into three projects. Each of these projects will have their own public involvement opportunities and environmental documents.
Project 1: FM 1216 to SH 302
CSJ: 0139-04-052
Project timeline
- Virtual public meeting #1 – Wednesday, June 16, 2021
- Schematic development and environmental documentation – ongoing
- Notice and opportunity to comment – through July 8, 2024
- Opportunity for public hearing – late 2024
- Approval of schematic and environmental documentation – early 2025
- Construction – 2028
Note: All schedules are subject to change
Project 2: SH 302 to RM 652
CSJ: 0139-03-046
Project timeline
- Virtual public meeting #1 – Wednesday, June 16, 2021
- Schematic development and enviornmental documentaion – ongoing
- Virtual public meeting with in-person open house – mid 2024
- Opportunity for public hearing – early 2025
- Approval of schematic and enviornmental documentation – mid 2025
- Construction – 2028
Note: All schedules are subject to change
Project 3: RM 652 to 0.1 mile south of New Mexico state line
CSJ: 0139-01-021 and 0139-02-030
Project timeline
- Virtual public meeting #1 – Wednesday, June 16, 2021
- Schematic development and enviornmental documentaion – ongoing
- Notice and opportunity to comment – through Aug. 9, 2024
- Opportunity for public hearing – late 2024
- Approval of schematic and enviornmental documentation – early 2025
- Construction – 2028
Note: All schedules are subject to change