I-35 NEX Central - request for qualifications (RFQ)
I-35 Northeast Expansion Central
Authorizations and approvals
On April 25, 2019, the Texas Transportation Commission (TTC), in Minute Order 115466, authorized the issuance of a request for qualification (RFQ) to design, develop, construct, and maintain the I-35 Northeast Expansion Project in Bexar, Comal, and Guadalupe counties.
On August 5, 2019, TxDOT posted the list of qualification teams and their equity members for the I-35 NEX Project.
RFQ documents
TxDOT issued the initial RFQ on May 20, 2019, and there was one subsequent addenda. The RFQ documents and Q&A matrices issued by TxDOT are available below.
Addendum No. 01 - Issued June 21, 2019 |
---|
Cover Letter |
Request for Qualifications (RFQ) |
RFQ Redline |
RFQ Forms (Word) |
RFQ Forms (PDF) |
Original - Issued May 20, 2019 |
---|
Cover Letter |
Request for Qualifications (RFQ) |
Design-Build Contract (DBC) Term Sheet |
Capital Maintenance Contract (CMC) Term Sheet |
RFQ Forms |
Document | Date Issued |
---|---|
RFQ Q&A Matrix No. 01 | June 21, 2019 |
RFQ Q&A Matrix No. 02 | July 22, 2019 |