Common Procurement Questions
This page provides answers to the most common procurement questions and answers the Public Transportation Division (PTN) receives.
An Invitation for Bid (IFB) is a sealed bid and the most common method used in the public sector to obtain specific goods, such as vehicles and equipment. This method is typically used when complete specifications or purchase descriptions are available or can be easily developed. The IFB process must involve two or more bidders and the award is made to the bidder who complies with the requirements and instructions of the IFB, and who offers the lowest total bid price while meeting all specifications and requirements. This type of procurement usually includes a design specification. Design specifications are a detailed description of the product.Advantages
This type of procurement usually includes a performance specification. Performance specifications describe how the end product should perform or what should be achieved at the project’s conclusion. Advantages
|
The level of communication depends on the procurement stage; at the onset, there are two stages where Subrecipients may community with potential vendors:
After these stages are complete, all communication should be made only through the subrecipient’s designated procurement staff as outlined in the solicitation. If a potential respondent contacts staff other than the designed staff outlined in the solicitation, the staff member should politely decline to discuss the procurement and forward the inquiry to the assigned person. |
A potential vendor should not be contacted to provide ICE information. Contacting them could give them an unfair advantage in the procurement process over other vendors because they now have knowledge of the exact item being procured in advance of other vendors. ICE information should be obtained using the following methods:
|
Cardinal changes are major deviations from the original purpose of the work or the intended method of achievement, or a revision of contract work so extensive, significant, or cumulative that, in effect, the contractor is required to perform very different work from that described in the original contract. |
Your procurement file will vary depending on the project; however, here is a list of items that are required for most procurements. The subrecipient shall determine which are appropriate for their procurement:
|
If a single bid is received, you should determine if competition was adequate or inadequate. The situation of a single bid received after a competitive solicitation is addressed in the FTA Circular 4220.1F, at Ch. VI, Section 3.i.(1)(b)2. If you find that competition was inadequate because of a restrictive specification that only one offeror could meet, then you must process this as a sole source contract award and obtain the requisite agency approvals prior to award. As a best practice, a subrecipient should contact the companies that were solicited to find out why they did not submit bids. If there was a problem with the specifications being restrictive, then you have inadequate competition and must fix the problem and re-solicit. The mere fact that only one bid was received does not automatically mean competition was inadequate since many unrelated factors could cause potential sources not to submit a bid or proposal. |
FTA Circular 4220.1F, Chapter VI, 2. a. (4) (g) prohibits geographical restrictions when evaluating all bids and proposals except for Architectural and Engineering and certain disaster or emergency relief contracts. |
When the recipient requires supplies or services available from only one responsible source, and no other supplies or services will satisfy its requirements, the recipient may make a sole source award. When the recipient requires an existing contractor to make a change to its contract that is beyond the scope of that contract, the recipient has made a sole source award that must be justified under one of the bases below. Grantees have the authority to make sole-source subcontract awards under certain conditions as discussed in FTA Circular 4220.1F, Chapter VI, Pages VI-16 through 20. |
Section 3019 of the Fast Act allows grantees to purchase rolling stock and related equipment via cooperative procurement contracts. A “cooperative procurement contract” means a contract entered into between a State government or eligible nonprofit entities and 1 or more vendors under which the vendors agree to provide an option to purchase rolling stock and related equipment to multiple participants. The contract term for a cooperative procurement contract may be for an initial term of not more than two years and may include three optional extensions of one year each.
|
All procurement documents are public information and must be maintained by the subrecipient for at least three years after grant closeout, or, in the case of a capital project, the life of the asset plus three years |
If your proposed purchase meets the procurement threshold, you will need to request concurrence from your PTC prior to issuing the solicitation and at every stage of the procurement process. |
Under the HGAC agreement, the actual purchase of vehicles is accomplished by HGAC members negotiating with participating vendors and placing purchase orders based on the prices listed in the HGAC agreement. However, given the requirements for full and open competition, FTA grantees are not free to simply place an order with a preferred vendor on a sole source basis based on a vendor’s catalog price. This would be a sole source procurement on the part of the grantee rather than a procurement using full and open competition. |