Design-build guide schedule
Materials
Research of sampling and testing rates for project tests listed in the current Design build guide schedule - May 2020 shows that the risk of either rejecting "good" material or accepting "bad" material ranges from 20% to 40%. Use this baseline for sampling and testing. The frequency of testing for high-variablity materials should be increased for high-variability materials when testing results do not meet specifications.