Traffic impacts
Skip to main content

Traffic impacts

To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.

For a list of lane closures across Texas, visit TxDOT’s interactive map website DriveTexas™.

Loop 1604 North Expansion lane closures

Throughout construction of these improvements, drivers will experience temporary traffic shifts and overnight lane closures on the mainlanes and frontage roads, as well as temporary daytime and overnight ramp closures.

Daytime work is anticipated to take place Mondays through Saturdays, while nighttime work and any necessary lane closures are anticipated to take place between 9 p.m. and 5 a.m., Sunday evenings through Friday mornings.

Permanent and temporary digital message boards placed along the route will alert drivers in real-time to lane closures, traffic congestion and construction activity.

This page is updated weekly. To find the most up to date and current lane closures, follow us on the San Antonio TxDOT Facebook and X pages or visit the San Antonio District’s Go Ahead! Blog

All closures are subject to change due to weather or other unforeseen circumstances.

Weekly lane closures as of July 19, 2024

Due to the sales tax holiday, there will be no planned major closures from Friday, August 9 through Sunday, August 11 for the Loop 1604 North Expansion project. 

Segment 1 | SH 16 (Bandera Rd.) to I-10

Weeknight lane closures

  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from Bandera Road (SH 16) to I-10 for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from I-10 to Bandera Road (SH 16) for portable concrete barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound frontage road lane closure from Bandera Road (SH 16) to I-10 for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound frontage road lane closure from I-10 to Bandera Road (SH 16) for portable concrete traffic barrier installation. Nightly alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound mainlane exit ramp closure to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 westbound to Loop 1604 westbound for westbound collector-distributor bridge construction on the bridge at Leon Creek. Nightly closure. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road lane closure from John Peace Boulevard/La Cantera Parkway to I-10 for eastbound flyover ramp bridge construction. Nightly frontage road closure. Only one frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road lane closure from I-10 to John Peace Boulevard/La Cantera Parkway for westbound collector-distributor bridge construction. Nightly frontage road closure. Only one frontage lane closure to occur per direction. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane exit ramp to La Cantera Parkway closure for westbound flyover ramp bridge construction. Nightly closure. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane exit ramp to I-10 eastbound closure for westbound flyover ramp bridge construction. Nightly closure. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road entrance ramp from I-10 closure for westbound flyover ramp bridge construction. Nightly closure. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Hausman Road intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Kyle Seale Parkway intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Babcock Road intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and Chase Hill Boulevard intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 and La Cantera Parkway intersection closure (both directions, including turnarounds) for demolition work/bridge construction. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlane closure from the Kyle Seale Parkway exit ramp to the Hausman Road temporary entrance ramp for overhead sign bridge installation. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from Hausman Road exit ramp to the Kyle Seale Parkway temporary entrance ramp for overhead sign bridge installation. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp to Babcock Road closure for drill shaft installation. Only one ramp to be closed at a time. Excluding weekends.
  • Sunday, July 21 until Monday, August 5. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound exit ramp to Babcock Road closure for drill shaft installation. Only one ramp to be closed at a time. Excluding weekends.

Weekday lane closures

  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Alternating Loop 1604 eastbound frontage road lane closure from Bandera Road (SH 16) to I-10 for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Alternating Loop 1604 westbound frontage road lane closure from I-10 to Bandera Road (SH 16) for traffic barrier, sidewalk construction and beam placement/bridge construction. Daily alternating frontage road closures. One lane to remain open at all times. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Hausman Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Babcock Road for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound to westbound turnaround closure at Chase Hill Boulevard/Brennan Avenue for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at Kyle Seale Parkway for bridge widening. Only one turnaround to be closed at a time. Excluding weekends.
  • Monday, July 22 until Monday, August 5. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound to eastbound turnaround closure at La Cantera Parkway/John Peace Boulevard for bridge widening. Only one turnaround to be closed at a time. 

Weekend lane closures

  • Saturday, July 20 until Sunday, July 21. Weekend nights only. 12 a.m. until 5 a.m. Loop 1604 westbound to eastbound turnaround closure at La Cantera Parkway/John Peace Boulevard for bridge widening.
  • Saturday, July 20 until Sunday, July 21. Nightly. 12 a.m. until 5 a.m. Loop 1604 eastbound to westbound turnaround closure at La Cantera Parkway/John Peace Boulevard for bridge widening. 

Long-term closures

  • Sunday, July 21 until Monday, August 5. Daily/Nightly. 24 hours a day. Loop 1604 eastbound to westbound turnaround closure at La Cantera Parkway/John Peace Boulevard for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Sunday, July 21 until Monday, August 5. Daily/Nightly. 24 hours a day. Loop 1604 eastbound to westbound turnaround closure at Kyle Seale Parkway for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.
  • Sunday, July 21 until Monday, August 5. Daily/Nightly. 24 hours a day. Loop 1604 westbound to eastbound turnaround closure at Chase Hill Boulevard/Brennan Avenue for bridge construction/retaining walls. Only one turnaround to be closed at a time on each direction.

Segment 2 | Loop 1604 and I-10 Interchange

Weeknight lane closures

  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 westbound frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 eastbound frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage closures. One lane to remain open at all times.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 westbound mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Alternating I-10 eastbound mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closures. One lane to remain open at all times.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound exit ramp closure to I-10 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 westbound exit ramp closure to Loop 1604 eastbound for portable concrete traffic barrier installation. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 eastbound to Loop 1604 eastbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound collector-distributor closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from Loop 1604 eastbound to I-10 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 westbound frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound frontage road closure from the Loop 1604 interchange to UTSA Boulevard for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlanes closure from La Cantera Parkway to Vance Jackson Road for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlanes closure from Vance Jackson Road to La Cantera Parkway for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound mainlane closure from La Cantera Parkway to UTSA Boulevard for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 westbound mainlane closure from UTSA Boulevard to La Cantera Parkway for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound frontage road closure at the I-10 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road closure at the I-10 interchange for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound exit ramp closure to Loop 1604 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from I-10 westbound to Loop 1604 westbound closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m.  Loop 1604 westbound collector-distributor closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Ramp/cloverleaf closure from Loop 1604 westbound to I-10 eastbound closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp closure to I-10 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. I-10 westbound frontage road closure from the Loop 1604 interchange to La Cantera Parkway for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound frontage road closure from Vance Jackson Road to the I-10 interchange closure for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound exit ramp closure to I-10 westbound for bridge construction. Nightly closures. Excluding weekends.
  • Sunday, July 21 until Friday, August 2. Weeknights. 10:30 p.m. until 5 a.m. I-10 westbound exit ramp to La Cantera Parkway closure for bridge construction. Nightly closures. 

Weekday lane closures

  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Alternating I-10 westbound frontage road lane closure from De Zavala Road to Camp Bullis Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Alternating I-10 eastbound frontage road lane closure from Camp Bullis Road to De Zavala Road to set portable concrete barrier. Daily alternating frontage road closures. One lane to remain open at all times.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound frontage road right turn lane closure onto I-10 westbound frontage road for bridge construction. Daily closures. Excluding weekends.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound frontage road at the I-10 interchange closure for bridge construction. Daily closures.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Loop 1604 westbound frontage road at the I-10 interchange closure for bridge construction. Daily closures.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound turnaround closure at I-10 and La Cantera Parkway for bridge construction. Daily closures. Excluding weekends.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. I-10 westbound frontage road outside lane from La Cantera Parkway to Worth Parkway for utilities construction. Daily closures. Excluding weekends.
  • Monday, July 22 until Friday, August 2. Weekdays. 9 a.m. until 3 p.m. I-10 westbound frontage road right lane closure from UTSA Boulevard to the Loop 1604 interchange for utilities construction. Daily closures. Excluding weekends.

Weekend Closures

  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 eastbound mainlane closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 eastbound collector-distributor closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 westbound mainlane closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 westbound collector-distributor closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. Loop 1604 eastbound exit ramp to I-10 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. Loop 1604 eastbound frontage road closure at the I-10 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. Loop 1604 westbound frontage road closure at the I-10 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 eastbound cloverleaf exit ramp to Loop 1604 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. Loop 1604 westbound cloverleaf exit ramp to I-10 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. Loop 1604 eastbound cloverleaf exit ramp to I-10 westbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 19 at 9 p.m. until Monday, July 22 at 5 a.m. Weekend closure. I-10 westbound cloverleaf exit ramp to Loop 1604 westbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. I-10 eastbound mainlane closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. I-10 eastbound collector-distributor closure at the Loop 1604 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. Loop 1604 westbound cloverleaf exit ramp to I-10 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. I-10 eastbound cloverleaf exit ramp to Loop 1604 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. Loop 1604 eastbound exit ramp to I-10 eastbound closure for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Monday, July 29 at 5 a.m. Weekend closure. Loop 1604 eastbound collector-distributor closure at the I-10 interchange for bridge construction. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.

Long-term closures

  • Sunday, July 21 until Friday, August 2. Daily/Nightly. 24 hours a day. I-10 eastbound frontage road right turn lane closure onto Loop 1604 westbound frontage road for bridge construction.
  • Sunday, July 21 until Friday, August 2. Daily/Nightly. 24 hours a day. Loop 1604 eastbound frontage road left lane closure between the I-10 eastbound frontage road and the I-10 westbound frontage road for bridge construction. 

Segment 3 | I-10 to US 281

Weeknight lane closures

  • Sunday, July 21 until Friday, July 26. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound mainlane closure from Tradesman Drive to Stone Oak Parkway exit ramp for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
  • Sunday, July 21 until Friday, July 26.  Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound mainlane closure from Stone Oak Parkway exit ramp to Tradesman Drive for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
  • Sunday, July 21 until Friday, July 26. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 eastbound frontage road closure from I-10 to the Stone Oak Parkway exit ramp for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
  • Sunday, July 21 until Friday, July 26. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 westbound frontage road closure from Stone Oak Parkway exit ramp to I-10 for barrier setting and striping. Nightly alternating mainlane closures. Excluding weekends.
  • Sunday, July 21 until Friday, July 26. Weeknights. 10 p.m. until 5 a.m. Blanco Road northbound and southbound mainlanes from the Loop 1604 eastbound frontage road to West Blanco Road for storm drainage. Nightly closures.
  • Monday, July 22 until Saturday, July 27. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlane closure from the Vance Jackson Road exit ramp to the Lockhill Selma Road entrance ramp to set deck panels on the flyover ramp.
  • Monday, July 22 until Saturday, July 27. Weeknights. 9 p.m. until 5 a.m. I-10 westbound mainlane exit ramp closure to Loop 1604 eastbound mainlanes to set deck panels on the flyover ramp.
  • Monday, July 22 until Saturday, July 27. Weeknights. 9 p.m. until 5 a.m. I-10 eastbound cloverleaf exit (southwest cloverleaf) ramp closure to Loop 1604 eastbound mainlanes to set deck panels on the flyover ramp.
  • Monday, July 22 until Sunday, July 28. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound mainlanes from the Blanco Road exit ramp to the Blanco Road entrance ramp for setting deck panels on the Blanco Road bridge.
  • Monday, July 22 until Sunday, July 28. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound mainlanes from the Blanco Road exit ramp to the Blanco Road entrance ramp for setting deck panels on the Blanco Road bridge. 

Weekday lane closures

  • none

Weekend lane closures

  • Friday, July 26 at 9 p.m. until Sunday, July 28 at 5 a.m. Weekend closures. Loop 1604 westbound mainlanes from the Lockhill Selma Road exit ramp to the I-10 interchange for repavement. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.
  • Friday, July 26 at 9 p.m. until Saturday, July 27 at 5 a.m. Weekend closures. Vance Jackson Road northbound and southbound lane closure on top of the Loop 1604 bridge for deck pour on the eastbound flyover ramp. Lane closures to remain in place for the entire duration. Off-duty officers will direct traffic through intersections.

Long-term closures

  • Sunday, July 21 until Sunday, July 28. Daily/Nightly. 24 hours a day. Loop 1604 westbound to eastbound frontage road turnaround at Lockhill Selma Road for wall construction. 

Segment 4 | US 281 to Redland Rd.

Weeknight closures

  • Sunday, July 28 until Saturday, Aug. 3. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound exit ramp to Gold Canyon Road for light installation. Nightly closures.
  • Sunday, July 21 until Saturday, July 27. Weeknights. 10 p.m. until 5 a.m. Loop 1604 eastbound frontage road from Gold Canyon Road to Redland Road for high mast lighting. Nightly closures. Local traffic looking to access the Canyon View subdivision or the businesses between the Canyon View subdivision will retain access and be escorted through the closure area during this time.
  • Sunday, July 21 until Saturday, July 27. Weeknights. 9 p.m. until 5 a.m. Loop 1604 eastbound to westbound turnaround closure at Stone Oak Parkway for bridge construction. Nightly closures.
  • Sunday, July 21 until Saturday, Aug. 3. Weeknights. 9 p.m. until 5 a.m. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction. Nightly closures. 

Weekday closures

  • Monday, July 22 until Friday, July 26. Weekdays. 9 a.m. until 3 p.m. Loop 1604 eastbound frontage road left lane closure from Gold Canyon Road to Redland Road for high mast lighting foundation work. Daily closures.
  • Monday, July 22 until Friday, July 26. Weekdays. 9 a.m. until 4 p.m. Loop 1604 eastbound to westbound turnaround closure at Stone Oak Parkway for bridge construction. Daily closures.
  • Monday, July 22 until Friday, Aug. 2. Weekdays. 9 a.m. until 4 p.m. Loop 1604 westbound to eastbound turnaround closure at Stone Oak Parkway for bridge construction. Daily closures.