Traffic impacts
Skip to main content
Traffic impacts

To provide the most accurate information about upcoming traffic impacts, the project team will provide as much notice as possible for lane closures and traffic switches. See below for a live map of traffic closures in San Antonio.

For a list of lane closures across Texas, visit TxDOT’s interactive map website DriveTexas™.

Loop 1604 North Expansion lane closures

Throughout construction of these improvements, drivers will experience temporary traffic shifts and overnight lane closures on the mainlanes and frontage roads, as well as temporary daytime and overnight ramp closures.

Daytime work is anticipated to take place Mondays through Saturdays, while nighttime work and any necessary lane closures are anticipated to take place between 9 p.m. and 5 a.m., Sunday evenings through Friday mornings.

Permanent and temporary digital message boards placed along the route will alert drivers in real-time to lane closures, traffic congestion and construction activity.

This page is updated weekly. To find the most up to date and current lane closures, follow us on the San Antonio TxDOT Facebook and X pages or visit the San Antonio District’s Go Ahead! Blog

All closures are subject to change due to weather or other unforeseen circumstances.

Weekly lane closures as of Jan. 9, 2025

Segment 1 | Loop 1604 from I-10 to SH 16 (Bandera Road)

Weeknight lane closures

  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 and Hausman Road intersection closure for sign installation. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 and Kyle Seale Parkway intersection closure for sign installation. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 and Babcock Road intersection closure for sign installation. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 and Chase Hill Boulevard intersection closure for sign installation. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating Loop 1604 and La Cantera Parkway intersection closure for sign installation. Nightly closure. Only one intersection to be closed at a time. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating westbound Loop 1604 mainlane closure between I-10 and Babcock Road for paving operations. Nightly alternating single lane closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound Loop 1604 mainlane closure between Babcock Road and I-10 for paving operations. Nightly alternating single lane closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 mainlane exit ramp closure to I-10 for flyover ramp bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound Loop 1604 frontage road lane closure from Bandera Road (SH 16) to I-10 for concrete work. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating westbound Loop 1604 frontage road lane closure from I-10 to Bandera Road (SH 16) for concrete work. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.

Weekday lane closures

  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Alternating eastbound Loop 1604 frontage road lane closure from Bandera Road (SH 16) to I-10 for sidewalk construction. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Alternating westbound Loop 1604 frontage road lane closure from I-10 to Bandera Road (SH 16) for sidewalk construction. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at Hausman Road for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound Loop 1604 U-turn closure at Hausman Road for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at Kyle Seale Parkway for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound Loop 1604 U-turn closure at Kyle Seale Parkway for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at Babcock Road for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound Loop 1604 U-turn closure at Babcock Road for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at Chase Hill Boulevard for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound Loop 1604 U-turn closure at Chase Hill Boulevard for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at La Cantera Parkway for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound Loop 1604 U-turn closure at La Cantera Parkway for sign installation. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.

Weekend lane closures

  • None

Long-term closures

  • Monday, Jan. 12 until Monday, Jan. 26. Daily/Nightly. 24 hours a day. Agave Pass closure from westbound Loop 1604 frontage road closure to Via La Cantera for paving operations.

All closures are subject to change due to weather or other unforeseen circumstances.

Segment 2 | Loop 1604 and I-10 Interchange

Weeknight lane closures

  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound I-10 frontage road lane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating westbound I-10 frontage road lane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound I-10 mainlane closure from Camp Bullis Road to De Zavala Road for portable concrete traffic barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Alternating westbound I-10 mainlane closure from De Zavala Road to Camp Bullis Road for portable concrete traffic barrier installation. Nightly alternating mainlane closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound I-10 frontage road closure from Via La Cantera to the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 8 p.m. until 5 a.m. Eastbound I-10 frontage road closure from the Loop 1604 interchange to UTSA Boulevard for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 8 p.m. until 5 a.m. Westbound I-10 frontage road closure from UTSA Boulevard to the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 mainlane closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 mainlane closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound I-10 mainlane closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound I-10 mainlane closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 frontage road closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 frontage road closure at the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound I-10 frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound I-10 frontage road closure at the Loop 1604 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 mainlane exit ramp closure to I-10 westbound for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 frontage road closure from the I-10 interchange to Vance Jackson Road to the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 frontage road closure from Vance Jackson Road to the I-10 interchange for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. I-10 and La Cantera Parkway intersection closure (both directions, including U-turns) for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound I-10 exit ramp closure to La Cantera Parkway for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 flyover ramp to eastbound and westbound I-10 closure for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 flyover ramp to I-10 eastbound closure for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Westbound I-10 flyover ramp to eastbound and westbound Loop 1604 closure for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Monday, Jan. 19. Weeknights. 9 p.m. until 5 a.m. Eastbound I-10 flyover ramp to eastbound and westbound Loop 1604 closure for bridge construction. Nightly closure. Excluding weekends.

Weekday lane closures

  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Alternating eastbound I-10 frontage road closure from Camp Bullis Road to De Zavala Road for portable concrete barrier installation. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Alternating westbound I-10 frontage road closure from De Zavala Road to Camp Bullis Road for portable concrete barrier installation. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound Loop 1604 frontage road closure at the I-10 interchange for bridge construction. Daily closure. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound Loop 1604 frontage road closure at the I-10 interchange for bridge construction. Daily closure. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Westbound to eastbound I-10 U-turn closure at La Cantera Parkway for bridge construction. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.
  • Monday, Jan. 12 through Monday, Jan. 19. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound I-10 U-turn closure at La Cantera Parkway for bridge construction. Daily alternating U-turn closure. Only one U-turn to be closed at a time. Excluding weekends.

Weekend Closures

  • Friday, Jan. 9 at 9 p.m. through Monday, Jan. 12 at 5 a.m. Weekend closure. Eastbound Loop 1604 mainlanes closure at the I-10 interchange for bridge construction. Lanes are expected to remain closed for the duration.
  • Friday, Jan. 9 at 9 p.m. through Monday, Jan. 12 at 5 a.m. Weekend closure. Westbound Loop 1604 mainlanes closure at the I-10 interchange for bridge construction. Lanes are expected to remain closed for the duration.
  • Friday, Jan. 9 at 9 p.m. through Monday, Jan. 12 at 5 a.m. Weekend closure. Eastbound I-10 frontage road closure at the Loop 1604 interchange for bridge construction. Lanes are expected to remain closed for the duration.
  • Friday, Jan. 9 at 9 p.m. through Monday, Jan. 12 at 5 a.m. Weekend closure. Westbound I-10 frontage road closure at the Loop 1604 interchange for bridge construction. Lanes are expected to remain closed for the duration.

Long-term closures

  • Sunday, Jan. 11 through Monday, Jan. 19. Daily/Nightly. 24 hours a day. Westbound Loop 1604 frontage road right lane closure to westbound I-10 for bridge construction.
  • Sunday, Jan. 11 through Monday, Jan. 19. Daily/Nightly. 24 hours a day. Eastbound I-10 frontage road closure from La Cantera Parkway to the Loop 1604 interchange for bridge construction.
  • Sunday, Jan. 11 through Monday, Jan. 19. Daily/Nightly. 24 hours a day. Westbound I-10 frontage road closure from the Loop 1604 interchange to La Cantera Parkway for bridge construction.
  • Sunday, Jan. 11 through Monday, Jan. 19. Daily/Nightly. 24 hours a day. Westbound to eastbound Loop 1604 U-turn closure at the I-10 interchange for bridge construction.
  • Sunday, Jan. 11 through Monday, Jan. 19. Daily/Nightly. 24 hours a day. Westbound I-10 frontage road right lane closure from the Loop 1604 interchange to La Cantera Parkway for bridge construction.

All closures are subject to change due to weather or other unforeseen circumstances.

Segment 3 | I-10 to US 281

Weeknight lane closures

  • Monday, Jan. 12 and Tuesday, Jan. 13. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 mainlane closure from the Stone Oak Parkway entrance ramp to Blanco Road for sign installation. Nightly closure.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Eastbound and westbound Loop 1604 mainlane left lane closure from Panther Creek to west of Blanco Road for column work. Nightly closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating northbound Blanco Road closure from Huebner Road to the westbound Loop 1604 frontage road for asphalt work. Nightly alternating closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating westbound Loop 1604 frontage road closure from the Blanco Road exit ramp to the entrance ramp before Blanco Road for striping. Nightly alternating closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound Loop 1604 frontage road closure from Vance Jackson Road to Stone Oak Parkway for striping. Nightly alternating closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating westbound Loop 1604 mainlane closure from Vance Jackson Road to Stone Oak Parkway for striping. Nightly alternating closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound Loop 1604 mainlane closure from the I-10 intersection to the entrance ramp east of Vance Jackson Road for guardrail work. Nightly alternating closure. Excluding weekends.

Weekday lane closures

  • none

Weekend closures

  • Friday, Jan. 16 at 9 p.m. until Saturday, Jan. 17 at 3 p.m. Alternating northbound and southbound Loop 1604 mainlane closure at the Lockhill Selma Road intersection for signal work.

Long-term closures

  • Sunday, Jan. 11 through early February 2026. Daily/Nightly. 24 hours a day. Westbound Loop 1604 Blanco Road exit ramp.
  • Sunday, Jan. 11 through mid-February 2026. Daily/Nightly. 24 hours a day. Eastbound Loop 1604 Blanco Road entrance ramp.

All closures are subject to change due to weather or other unforeseen circumstances.

Segment 4 | Loop 1604 from west of US 281 to Redland Road

Weeknight closures

  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 frontage road closure between Bulverde Road and Redland Road for barrier work. Nightly closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. US 281 and Loop 1604 intersection closure including U-turns for bridge work. Nightly closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Northbound and southbound US 281 mainlane closure between Redland Road and Donella Drive for bridge work. Nightly closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Eastbound to westbound U-turn closure and westbound to eastbound U-turn closure at Loop 1604 and Stone Oak Parkway for road work. Nightly closure. Excluding weekends.

Weekday closures

  • none

Weekend closures

  • none

Long-term closures

  • None

All closures are subject to change due to weather or other unforeseen circumstances.

Segment 5 | Redland Rd. to Judson Rd.

Weeknight closures

  • Sunday, Jan. 11 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Eastbound to westbound Loop 1604 U-turn closure at Bulverde Road for bridge construction. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Eastbound Loop 1604 mainlane closure from Bulverde Road to Judson Road for barrier placement. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Westbound Loop 1604 mainlane closure from Judson Road to Bulverde Road for barrier placement. Nightly closure. Excluding weekends.
  • Sunday, Jan. 11 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating westbound Loop 1604 frontage road closure from Judson Road to Bulverde Road for barrier placement. Westbound Loop 1604 frontage road closure and the westbound Loop 1604 mainlane closure will not occur simultaneously. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Sunday, Jan. 11 through Friday, Jan. 16. Weeknights. 9 p.m. until 5 a.m. Alternating eastbound Loop 1604 frontage road closure from Bulverde Road to Judson Road for barrier placement. Eastbound Loop 1604 frontage road closure and the eastbound Loop 1604 mainlane closure will not occur simultaneously. Nightly alternating frontage road closure. One lane to remain open at all times. Excluding weekends.

Weekday closures

  • Monday, Jan. 12 through Friday, Jan. 16. Weekdays. 9 a.m. until 3 p.m. Eastbound to westbound Loop 1604 U-turn closure at Bulverde Road for bridge construction. Daily closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weekdays. 9 a.m. until 3 p.m. Alternating northbound and southbound Bulverde Road intersection lane closures at Loop 1604 for drainage work. Daily alternating closure. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weekdays. 9 a.m. until 3 p.m. Alternating westbound Loop 1604 frontage road closure from Judson Road to Bulverde Road for barrier placement. Westbound Loop 1604 frontage road closure and the westbound Loop 1604 mainlane closure will not occur simultaneously. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.
  • Monday, Jan. 12 through Friday, Jan. 16. Weekdays. 9 a.m. until 3 p.m. Alternating eastbound Loop 1604 frontage road closure from Bulverde Road to Judson Road for barrier placement. Eastbound Loop 1604 frontage road closure and the eastbound Loop 1604 mainlane closure will not occur simultaneously. Daily alternating frontage road closure. One lane to remain open at all times. Excluding weekends.

Weekend closures

  • None

Long-term closures

  • Sunday, Jan. 11 until Friday, Jan. 16. Daily/Nightly. 24 hours a day. Westbound to eastbound Loop 1604 U-turn closure at Bulverde Road for barrier placement.
  • Sunday, Jan. 11 until Friday, Jan. 16. Daily/Nightly. 24 hours a day. Eastbound to westbound Loop 1604 U-turn closure at Bulverde Road for barrier placement.

All closures are subject to change due to weather or other unforeseen circumstances.