North Tarrant Express - request for proposals (rfp)
North Tarrant Express Projects
Authorizations and approvals
The Texas Transportation Commission (TTC) authorized the issuance for detailed proposals in Minute Order 111169 on December 13, 2007.
On January 29, 2009, the selection of best-value proposal was conditionally awarded to NTE Mobility Partners by the TTC in Minute Order 111661 for the construction of a proposed facility under the Segments 2-4 comprehensive development agreement.
Toll designations for NTE were authorized by the TTC for Segment 1 in Minute Order 111814 on May 28, 2009, and for Segment 2 to in Minute Order 112077 on December 17, 2009.
Documentation of these events are available in the support documents links in the section below.
RFP documents
On March 3, 2008, TxDOT issued the original request for proposal documents to the short-listed proposers. TxDOT issued twelve subsequent addenda and Addendum No. 12 was posted on November 25, 2008. These RFP documents are available below.