FM 3351 corridor projects – Bexar, Comal, and Kendall counties

The Texas Department of Transportation is making headway on critically needed improvements to the FM 3351 corridor. The corridor limits on FM 3351 are from I-10 to SH 46, in Fair Oaks Ranch and San Antonio, which includes portions of Bexar, Comal, and Kendall counties. The expansion of FM 3351 within these limits is listed in the Alamo Area Metropolitan Planning Organization’s (MPO) Metropolitan Transportation Plan (MTP) “Mobility 2040” as a critical piece of the transportation network. Capacity improvements are needed to help relieve congestion and improve access issues along FM 3351. Several concepts that could address capacity, safety, and mobility challenges within the study limits have emerged from initial studies. TxDOT is now moving forward with four separate projects on FM 3351 within these limits.

Construction projects

  • FM 3351 at Cibolo Creek
    The first project is currently under construction on the FM 3351 bridge at Cibolo Creek. During significant rainfall events, Cibolo Creek rises, covering the bridge roadway and limiting access for public and emergency vehicles. This project is currently listed in the MPO’s MTP “Mobility 2050.” The project was environmentally cleared in 2022. Construction started in 2024. For more information on the construction status of this project, please contact the TxDOT San Antonio District Office Public Information Officer for Comal and Kendall counties at 512-658-6177.

Proposed projects

  • FM 3351 from I-10 to Desperado Way
    The second project involves proposed improvements on FM 3351 from I-10 to Desperado Way in Bexar County. TxDOT is proposing to convert FM 3351 from a two-lane, undivided roadway to a four- to six-lane roadway. The proposed project would also include the construction of a 10-foot shared-use path on the west side of FM 3351 throughout the project limits. Environmental studies and schematic design are in progress for this proposed project. More details can be found here.
  • FM 3351 from Desperado Way to SH 46
    The third project involves the proposed improvement of FM 3351 from Desperado Way to SH 46 in Bexar, Comal, and Kendall counties. For these limits of FM 3351, the proposed number of travel lanes will be determined as the project develops. As part of the project development process, various environmental studies will be conducted, and the need for bicycle and pedestrian accommodations will be evaluated. The proposed typical section(s) will be based on enhanced safety and improved travel times while avoiding and minimizing environmental impacts to the extent practicable. More details can be found here.
  • I-10 Eastbound Frontage Road Turnaround Bridge
    The fourth project is a funded improvement anticipated to be let for construction in 2027. TxDOT is proposing a new turnaround bridge for the I-10 eastbound frontage road that would continue to the I-10 westbound frontage road. For more information on the status of this project, please contact the TxDOT San Antonio District Office Public Information Officer for Comal and Kendall counties at 512-658-6177.

Project information

Schedules outlining the major milestones of the project development process, including data collection, schematic development, environmental studies, and public involvement, can be found on the proposed project pages hyperlinked above.

Project updates

For construction updates, follow the San Antonio TxDOT District Facebook , X, and Nextdoor social media pages. For construction project information, please contact a TxDOT San Antonio Public Information Officer for Comal and Kendall counties at 512-658-6177 and for Bexas County at 210-615-5839. To receive email updates on the above proposed projects, Click Here to Opt-in. For questions on the proposed projects, please email your name and contact information to FM3351@pozcam.com. Please include “Updates on FM 3351” in the subject line.