FM 1179 Widening
The TxDOT Bryan District is developing plans to widen FM 1179 from Steep Hollow Circle to FM 158 (Boonville Road) in Brazos County, Texas. The proposed improvements would enhance safety, reduce congestion, and improve mobility along the FM 1179 corridor, as well as modernize the roadway configuration to current design standards.
The project is being developed in collaboration with the Bryan/College Station Metropolitan Planning Organization (BCS MPO) to meet current and future traffic demand attributed to development growth in the area.
Proposed improvements
The existing FM 1179 is a two-lane roadway, one lane in each direction, with approximately 3 ft-wide outside shoulders. There are currently no sidewalks or bicycle accommodations within the project limits. The existing right of way along the project corridor is narrow, as little as approximately 80 feet wide.
Proposed FM 1179 improvements include the following:
- Widening the existing two-lane roadway to a four-lane roadway, two lanes in each direction separated by a raised median with dedicated left-turn lanes at selected intersections,
- Constructing roundabouts at the Coyote Run Road and Merka Road/Steep Hollow Road intersections,
- Providing pedestrian and bicycle accommodations within the project limits including the construction of a Shared Use Path (SUP)—a wide sidewalk that can be used by both pedestrians and cyclists, and
- Adjusting the roadway alignment to current design standards.
The total length of the project is about 3.6 miles and approximately 39 acres of proposed right of way would be required for the project.
The proposed FM 1179 widening project is in the preliminary design phase which includes developing the geometric schematic design and conducting environmental studies. A public meeting was held in July 2023. TxDOT continues to refine the working design and will present the revised layout in the next public meeting.
Near-term improvements
Ahead of the proposed widening project outlined above, TxDOT is also developing plans to enhance safety along the FM 1179 corridor under a separate project. This project will rehabilitate the existing roadway from FM 2038 to Steep Hollow Circle and replace the bridge at Wickson Creek. The anticipated start date for construction is Fall 2027.
Get involved
TxDOT is working closely with local stakeholders and the public to receive their input regarding project development. A public meeting is scheduled for late July 2023 to present the proposed project and related information and receive comments in an open house format.
- Public Meeting Notice – July 27, 2023: Open House Public Meeting