Information
March 20, 2006
Authorization by the Texas Transportation Commission to issue request for proposals and qualifications.
December 29, 2006
TxDOT issues request for proposals and qualifications.
May 1, 2007
Deadline to submit proposals and qualifications
- Gateway Connector Constructors JV
- North Gate Constructors
- Trinity Infrastructure
- Archer Western Team
Completed
TxDOT evaluation and short list of teams.
October 25, 2007
Authorization by the Texas Transportation Commission to issue request for detailed proposals.
March 31, 2008
TxDOT issues request for detailed proposals.
January 12, 2009
Deadline to submit detailed proposals.
March 26, 2009
Selection of best-value proposal and conditional award to NorthGate Constructors.
May 26, 2009
CDA Public Hearings
Summer 2009
Team opens local office.
October 6, 2009
Commercial close.
Fall 2009
Begin design.
Late 2009
Begin right-of-way acquisition and utility relocations.
Early 2010
Construction begins.
RFP Addendum No. 8 (March 6, 2009)
- Cover Letter
- DFW Connector Exhibits A, C and E (Addendum 8)
- DFW Connector ITP (Addendum 8)
- DFW Connector ITP Forms (Addendum 8)
RFP Addendum No. 7 (December 10, 2008)
- Cover Letter
- Addendum 7 Request for BAFO
- DFW Connector Book 2
- DFW Connector ITP, CDA, CMA Documents
- DFW ITP Forms (12-10) Addendum 7 doc.
- DFW Connector Maintenance Specifications Addendum 7 pdf.
RFP Addendum No. 6 (July 8, 2008)
RFP Addendum No. 5 (July 3, 2008)
- Cover Letter
- Instruction to Proposers
- Book 1 Comprehensive Development Agreement
- Book 2 Technical Provisions
- Capital Maintenance Agreement
- Maintenance Specifications
RFP Addendum No. 4 (June 17,2008)
- Cover Letter
- Instructions to Proposers
- Book 1
- Book 2
- Capital Maintenance Agreement
- Maintenance Specification
RFP Addendum No. 3 (June 4, 2008)
RFP Addendum No. 2 (April 30, 2008)
RFP Addendum No. 1 (April 17, 2008)
Other Documents
- Cover Letter
- Instructions to Proposers
- Comprehensive Development Agreement
- Technical Provisions
- CDA Programmatic for Design-Build (Book 3)
- Capital Maintenance Agreement
- Maintenance Specifications
RFQ Addendum No. 2 (April 4, 2007)
RFQ Addendum No. 1 (March 9, 2007)
Additional Documents