FM 2493 - Loop 323 to FM 2813
Skip to main content
Texas Department of Transportation
Connecting You With Texas
  • Family
  • Jobs
  • Education
  • Opportunities
  • Attractions
  • Entertainment
  • Wide Open Spaces
  • History
  • Quality of Life
  • Sports
  • Parks
  • Shopping
  • Services
  • People
  • Wildflowers
  • BBQ
  • Shores
  • Schools
  • Rodeos
  • Music
  • Tacos
  • Adventure
  • Trails
  • Traditions
  • Safely
  • Sunsets
  • Culture
  • Festivals
  • Friends
  • Life
  • Possibilities
  • Legends

 


Project Overview

FM 2493, commonly known as Old Jacksonville Highway, is in the southern portion of the city of Tyler. It is a major north-south corridor and serves as a parallel roadway to South Broadway Avenue, one of the most congested roadways in the state. The proposed project extends from SL 323 south to FM 2813 in the community of Gresham. Its total length is 5.6 miles.

In 2019, approximately 32,000 vehicles per day travelled along Old Jacksonville Highway. Traffic projections show this volume increases to 53,000 vpd by year 2045, resulting in a 65 percent increase in vehicles along the corridor. FM 2493 is unable to efficiently accommodate its current or future traffic volumes, resulting in widespread congestion and reduced mobility. Safety concerns will also increase with the higher volume of turning movements at driveways and cross streets. The purpose of the proposed project is to improve mobility and safety along the corridor through additional travel lanes, upgraded intersections and raised medians.

TxDOT’s preliminary plans for FM 2493 include:

  • Widening from four lanes with a continuous turn lane to six lanes with a raised median
  • Bicycle and pedestrian accommodations along the corridor
  • Intersection improvements at all signalized intersections

The project will require additional ROW. The exact amount and location are dependent on the ultimate design, which is not final until a preferred alternative is identified, and the project receives environmental clearance. TxDOT will use the abandoned railroad corridor to the fullest extent possible to minimize ROW acquisitions.

Anticipated Project Schedule

Current financial forecasts show roadway construction funds would be available in 2026. The project’s total cost estimate is dependent on the ultimate design, which is not final until a preferred alternative is identified, and the project receives environmental clearance.

Construction is scheduled to begin in 2026. TxDOT may accelerate the project by one or two years if construction funding becomes available earlier. The duration of construction is unknown until a final design is selected and a detailed construction schedule can be developed.

Get Involved

Your participation is a key part of the project’s development. Public involvement opportunities will be provided throughout this process and you are encouraged to get involved.

TxDOT hosted the project’s first public meeting on Tuesday, April 23, 2019. Several design alternatives were presented for public consideration and comment. Below is a summary of the presented options. The meeting’s exhibits are available under the ‘Downloads’ section:

  • At the intersection of Loop 323, two grade-separated alternatives were presented. In both options, Loop 323 bridged over FM 2493. The difference between alternatives centered around the configuration of FM 2493. The first alternative showed a conventional design, where the Loop 323 ramps meet FM 2493 and the connections are controlled with traffic signals. The second alternative showed a Departed Left-Turn configuration, where left-turning vehicles along FM 2493 cross the opposing traffic ahead of the signalized ramp intersections. This configuration is considered an innovated design and it increases the amount of green time all drivers get to pass through the intersection.
  • Between Capital Drive south to Three Lakes Blvd, one alternative that widens the roadway to the west onto the abandoned railroad right-of-way was presented. TxDOT owns the old railroad right of way and plans to utilize it to the fullest extent possible to minimize impacts to other property owners.
  • From Three Lakes Blvd south to FM 2813, three widening alternatives were presented because the abandoned railroad right of way is no longer adjacent to the existing roadway. The three alternatives included widening to the east, widening to the west, and widening equal distances to both sides of the roadway. 

Next steps include:

  • Second Public Meeting - Fall 2021
  • Public Hearing – Fall 2022
  • Environmental Clearance – Winter 2022
  • Right-of-Way Acquisition - 2023 (tentatively)

Downloads

Contact Us

TxDOT Tyler District
Attention: Advanced Project Development Office
2709 West Front Street
Tyler, Texas 75702
(903) 510-9100
Contact Us

 

Copyright 2021  •  Texas Department of Transportation  •  All Rights Reserved  •  Disclaimer  •  Privacy & Security Policy  •  Accessibility
125 East 11th Street  •  Austin, Texas 78701