Project updates for the week of Sept. 22, 2025
Anderson County
Palestine crews are scheduled to make asphalt repairs on FM 1892. Motorists should expect lane closures with flaggers controlling traffic. A second crew will be making edge repairs at various locations throughout the county. This will be a mobile operation with minimal impact on traffic.
Anderson County construction projects updates:
US 175 Widening Project
- Limits: From 0.4 miles SE of SH 155, SE to Cuney
- Contractor: Big Creek Construction, LTD
- Cost: $55.5 million
- Anticipated Completion Date: Spring 2026
Traffic is currently being switched to the new pavement on the westbound lane, while the contractor works on the eastbound lane. Crews are building the new eastbound roadbed. The contractor is also constructing driveways and ditches. Crews will continue work on the bridge deck and rail on the eastbound bridge. Crews will also finalize ditches and slopes. The project will expand the roadway to four lanes with new bridges across the Neches River.
----------------------------------------
Cherokee County
Jacksonville crews will be performing base repairs on SH 110 between New Summerfield and Troup. Rusk crews will be repairing edges on FM 2274. Motorists should expect daytime lane closures with flaggers directing traffic.
Cherokee County construction projects updates:
US 175 Widening Project
- Limits: From 0.5 miles E of the Anderson County line (CR 3509) to FM 347 in Jacksonville
- Contractor: A.L. Helmcamp, INC.
- Cost: $168 million
- Anticipated Completion Date: Fall 2028
The following county road intersections will be closed within the project limits:
- CR 3410/CR 3416 intersections: local traffic will need to use the detour route to FM 855
- CR 3306/CR 3407 intersections: local traffic will need to use the posted detour route.
The contractor has shifted traffic onto the new westbound roadbed from CR 3416 through Cuney. The contractor will continue drainage work through Cuney for the new eastbound lanes. Right of way preparation will continue on the westbound side, towards Jacksonville. The contractor is scheduled to continue culvert install, bridge elements, and drainage systems. Motorists should use caution when traveling through the work limits. The speed limit has been reduced to 55 mph throughout the project limits. The project consists of expansion to a four-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage. (This project is in Cherokee County but is managed by the Athens Area Office.)
SH 204
- Limits: From SH 110 to the Rusk County line
- Contractor: Madden Contracting Company, LLC
- Cost: $22.5 million
- Anticipated Completion Date: Summer 2025
This week, the contractor is scheduled to continue laying asphalt, placing topsoil, and seeding. Crews will also continue storm water prevention plan operations. Motorists should drive with caution in the work zone. Lane closures are anticipated. This project consists of adding a super-two highway section.
US 79
- Limits: Rusk County line, southwest to 0.160 mile east of SH 110
- Contractor: Madden Contracting Company, LLC
- Cost: $4.25 million
- Anticipated Completion Date: Fall 2025
The contractor is scheduled to lay rumble strips and begin cutting bridge joints. The speed limit has been reduced to 55 mph throughout the project limits. This project consists of rehabilitation of the existing road, including pavement repair, resurfacing, metal beam guard fence, and pavement markings.
US 69 and FM 2493 Grade Separated Interchange Realignment
- Limits: US 69 – From 0.5 mi N of FM 2493 W to 0.5 mi south of FM 2493 E; FM 2493 – From 0.3 mi south of FM 344 to US 69 near Bullard
- Contractor: East Texas Bridge, Inc.
- Cost: $38.5 million
- Anticipated Completion Date: Spring 2027
The contractor is scheduled to perform dirt work on the northbound FM 2493 frontage road. Crews are also scheduled to perform concrete work on FM 2493 East. While no lane closures are expected, motorists should proceed with caution. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.
----------------------------------------
Gregg County
Crews in Longview are scheduled to continue mill and inlay operations on SH 135, in both northbound and southbound lanes from I-20 to SH 31 West. Lane closures are expected during active work hours.
Gregg County construction projects updates:
FM 2275
- Limits: FM 3272 (White Oak Rd) to FM 1845 (Pine Tree Rd)
- Contractor: Longview Bridge and Road
- Cost: $22.8 million
- Anticipated Completion Date: May 2027
The project consists of widening from two lanes to four lanes. This will include a new bridge structure, pavement, metal beam guard fence, and striping. Crews will be clearing the right of way. Crews may also place temporary asphalt for traffic control, depending on progress. The contractor is also expected to install storm culverts.
US 80
- Limits: Lake Divernia east to FM 3272
- Contractor: Longview Bridge
- Cost: $3.43 million
- Anticipated Completion Date: September 2025
The project consists of removing four inches of existing surface and replacing with new hot mix. The project will also include striping and pavement markings. This week, the contractor is scheduled to perform striping operations.
Young St. – City of Longview
- Limits: Mobberly Ave. to MLK Blvd.
- Contractor: C&W Southern, LLC
- Cost: $620,200
- Anticipated Completion Date: October 2025
This project consists of constructing sidewalks and accessible ramps for people with disabilities on both sides of Mobberly Ave. Once completed, crews will switch to the north side of the street. This week, the contractor will be clearing right of way and pouring concrete for the sidewalk on the north side of the street. If completed, crews will then switch to the south side of the street.
SH 135 – Kilgore Traffic Circle
- Limits: Traffic circle in Kilgore to Rusk County line
- Contractor: East Texas Bridge
- Cost: $8.37 million
- Anticipated Completion Date: September 2025
This project involves rebuilding the traffic circle and the entire width of the roadway to the Rusk County line. This week, crews are scheduled to complete final punch list items, including finishing touches and inspections.
I-20 Resurfacing
- Limits: Sabine River bridge to the Harrison County line
- Contractor: Grey Sky Construction LLC
- Cost: $2.9 million
- Anticipated Completion Date: September 2025
This project consists of milling asphalt off the surface and placing new hot mix asphalt from the Sabine River bridge to the Harrison County line. Work will be done in both the east and westbound lanes. Work is scheduled for overnight hours. One lane will be closed at a time. The contractor is scheduled to lay asphalt beginning Sunday night, September 21st. Crews will alternate work between the eastbound and westbound lanes.
----------------------------------------
Henderson County
Athens crews will be performing overlay on FM 2613. Motorists should expect lane closures with flaggers controlling traffic. Herbicide operations will also continue at various locations throughout the county.
Henderson County construction projects updates:
FM 316 Rehabilitation
- Limits: From FM 1861 to US 175
- Contractor: Baker & Company Construction, LLC
- Cost: $7.9 million
- Anticipated Completion Date: Major items of work have been completed.
The project is currently in time suspension, pending final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
- Limits: From Ben Belt Frontage Rd. To S Loop 7 ramps
- Contractor: 3LW Civil, LCC
- Cost: $2.6 million
- Anticipated Completion Date: Summer 2025
The contractor is placing concrete for the sidewalks and driveways on the west side of the road. Motorists should expect lane closures while work is in progress. The project includes sidewalk and pedestrian access improvements.
SH 19 Super 2 Project
- Limits: From 0.3 miles south of FM 1861 (Van Zandt C/L) south to 0.1 Mi. north of SL 7 in Athens (Watson)
- Contractor: Big Creek Construction LTD
- Cost: $20.8 million
- Anticipated Completion Date: Summer 2026
The contractor has begun cement treating for roadway widening in the southbound lane. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding passing lanes in both directions at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.
BUS 31 Rehabilitation
- Limits: From BUS 19 to SL 7
- Contractor: Big Creek Construction LTD
- Cost: $8.1 million
- Anticipated Completion Date: Late 2025
Nighttime operations are scheduled to continue this week. Motorists should expect lane closures. The project includes removal of current surface, base repairs, resurfacing, striping, and signage. Motorists should use caution when traveling through the nighttime work zone and expect pavement striping operations during the day.
SH 31 at Sawmill Rd.
- Limits: Sawmill Rd.
- Contractor: Striping Technology, L.P.
- Cost: $342,000
- Anticipated Completion Date: Fall 2025
The new traffic signal is operational. This project consists of installing a traffic control and pedestrian control signal.
----------------------------------------
Rusk County
Crews in Henderson are scheduled to repair base failures and pavement edges on FM 1798. Motorists should expect lane closures with flaggers controlling traffic. Contractor crews are also scheduled to trim and remove trees at various locations. Another contractor crew will be picking up litter throughout the county.
Rusk County construction projects updates:
US 84 – FM 225 East to CR 3155
- Limits: FM 225 east to CR 3155
- Contractor: Drewery Construction Company
- Cost: $12.8 Million
- Anticipated Completion Date: November 2025
This project includes reconstruction of US 84, extended structures, a hot mix asphalt surface, new signage, and striping. This week, the contractor is scheduled to work on the shoulder. Motorists should expect alternating lane closures.
SH 315
- Limits: US 259 to the Panola County line
- Contractor: Madden Construction
- Cost: $13.5 Million
- Anticipated Completion Date: September 2025
This project consists of widening pavement edges and installing a separation between opposing traffic lanes to improve safety. Work will also include adding a passing lane in each direction. This week, the contractor is scheduled to lay asphalt. Motorists should expect alternating lane closures. Crews will also perform striping and guard fence installation.
FM 2658
- Limits: FM 1251 to SH 43
- Contractor: Highway 19 Construction
- Cost: $9.6 Million
- Anticipated Completion Date: September 2025
The project involves full reconstruction of FM 2658, from CR 344 to FM 1251. Work includes a new guard fence, treating subgrade, base material, seal coat, and striping. This week, the contractor is scheduled to perform sealcoat and striping.
US 79 N
- Limits: CR 344 to CR 333
- Contractor: Garrett Shields Construction
- Cost: $718,000
- Anticipated Completion Date: September 2025
This project consists of repairing a slope failure within the TxDOT right of way. The site will be excavated, and a new embankment will be placed. This week, the contractor will be working on punch list items. Most work will occur off the roadway.
SH 43
- Limits: FM 1251 north to FM 2658
- Contractor: Madden Construction
- Cost: $21.2 million
- Anticipated Completion Date: September 2025
This project consists of milling approximately six inches off the surface and replacing it with new hot mix. The project also includes clearing the right of way, replacing driveway pipes, and striping. This week, the contractor is scheduled to place final striping and performing edge work along the pavement. Expect lane closures with flaggers controlling traffic.
----------------------------------------
Smith County
Tyler Maintenance crews will perform mill and inlay work on FM 346. Motorists should expect lane closures with flaggers controlling traffic. A second crew will assess ditch and drainage issues at various locations. Contractor mowing crews will also work throughout the county.
Smith County construction projects updates:
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
- Limits: Cumberland Road to 0.45 miles north of FM 346
- Contractor: Drewery Construction Company, INC
- Cost: $5.8 million
- Anticipated Completion Date: Summer 2025
The contractor is scheduled to clean and seal the bridge joints at the Mudd Creek bridge. This work will be done during daytime hours. No lane closures are expected. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at the FM 2813 intersection.
SH 31 Safety Improvements
- Limits: Neches River bridge to 0.0508 miles west of Toll 49
- Contractor: Highway 19 Construction, LLC
- Cost: $3.85 million
- Anticipated Completion Date: Summer 2025
The contractor has no work scheduled this week. Motorists should drive with caution in the work zones. The project consists of safety improvements, including installation of cable and concrete median barriers.
FM 2493 Widen Non-Freeway
- Limits: FM 346 in Flint, south to 0.3 miles south of FM 344
- Contractor: Longview Bridge and Road LTD
- Cost: $52 million
- Anticipated Completion Date: Spring 2027
The contractor has scheduled daily lane closures from 8:15 a.m. to 6 p.m. from S. Kimberly Dr. to CR 150. The closures are scheduled to last through Oct. 3. Beginning Monday, September 22, the entrance to CR 172 will be closed. This closure is scheduled to last for two weeks. Motorists should plan ahead and drive with caution. This project consists of widening the existing non-freeway roadway.
I-20 Bridge Maintenance
- Limits: I-20 bridges over CR 35 (Lavender Rd); FM 14; SH 155; FM 3311; CR 353; US 271; CR 3101 (Barber Rd); CR 3116 (Philpot Rd)
- Contractor: Olympus Painting Contractors, Inc.
- Cost: $3 million
- Anticipated Completion Date: Summer 2025
The contractor has no work scheduled this week. This project is bridge maintenance, consisting of cleaning and painting existing steel bridge superstructures.
Pedestrian Sidewalks & Curb Ramps
- Limits: Stewart Park to Peete Elementary
- Contractor: Tight Line Construction, LLC.
- Cost: $870,000
- Anticipated Completion Date: Winter 2025
This work will be at various locations throughout the Tyler city limits. The contractor will be pouring concrete and preparing to relocate to the intersection of Glenwood and Front Street. Motorists should drive with caution. Lane closures are possible. The project consists of upgrading pedestrian safety measures at various intersections.
Smith County Bridge Rehabilitation
- Limits: Various locations in the Tyler city limits
- Contractor: Tight Line Construction, LLC.
- Cost: $3 million
- Anticipated Completion Date: Summer 2026
The contractor is scheduled to remove debris and material beneath the US 175 and SL 7 bridge. This project consists of cleaning and sealing the existing bridge joints, asphalt work, resurfacing the bridge deck, installing new metal beam guard fencing, steel and concrete repairs.
I-20 Bridge Maintenance
- Limits: Bridge locations between Smith and Van Zandt Counties
- Contractor: Southern Bridge and Road, LLC
- Cost: $3 million
- Anticipated Completion Date: May 2026
The contractor has installed temporary traffic signals on CR 496 under I-20 to manage one-lane traffic. Signals will operate at all times. One lane will remain open at all times. Crews are scheduled to begin bridge maintenance in this area. At Jim Hogg Rd (CR 431), the U-turn from eastbound to westbound I-20 frontage road will be closed. Motorists should expect reduced lane widths and intermittent shoulder closures under the bridges at Jim Hogg Rd. The U-turn from eastbound to westbound I-20 frontage road between Jim Hogg Rd and US 69 will be closed. Additionally, the westbound I-20 shoulder and entrance ramp after Jim Hogg Rd will be closed. Drivers will need to use the entrance ramp at US 69. This project is bridge maintenance consisting of cleaning and painting the existing steel bridge structures.
FM 16 Widening and Realignment
- Limits: Four miles west of FM 849 east to US 69 in Lindale
- Contractor: Highway 19 Construction LLC
- Cost: $44.4 million
- Anticipated Completion Date: February 2027
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. Embankment installation is ongoing. Crews are also scheduled to prepare surface for seal coat treatment. Bridge work, along with curb and gutter installation, is ongoing. (This project is in Smith County but is managed by the Mineola Area Office.)
SH 31 Resurfacing
- Limits: From Henderson County line to FM 206
- Contractor: East Texas Bridge, Inc.
- Cost: $7.4 million
- Anticipated Completion Date: Major items of work are complete.
Overlay operations have been completed. The project includes prep row, base repairs, resurfacing, striping, and signage. Motorists should use caution when traveling through area and expect delays. (This project is in Smith County but is managed by the Athens Area Office.)
---------------------------------------
Van Zandt County
Van Zandt County construction projects updates:
FM 17, FM 47, and FM 859 Bridge Replacement
- Limits: Bridge at FM 17, FM 47, and FM 859 over I-20
- Contractor: Indus Bridge and Road
- Cost: $14.5 Million
- Anticipated Completion Date: October 2025
This project includes construction of new bridges and approaches, grading, base and surface work, and installation of metal beam guard fencing. Motorists should expect reduced speed limits and narrowed shoulders on both the I-20 main lanes and frontage roads. On FM 17, crews are scheduled to place new asphalt on the westbound frontage road. The westbound frontage road ramp will be closed to traffic during this work. The new bridge is scheduled to open by the end of the week. On FM 47, crews are scheduled to install the traffic rail and driveways on the eastbound frontage road. Crews are scheduled to complete paving of the FM 47 tie-ins. Motorists should expect daily lane closures in this area. On FM 859, crews are scheduled to perform striping and install signage.
FM 1255 Rehabilitate Existing Roadway
- Limits: I-20 to SH 110
- Contractor: Reynolds & Kay, LTD.
- Cost: $17.1 Million
- Anticipated Completion Date: February 2026
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. Work will be completed under live traffic conditions. Right of way prep and tree trimming are ongoing. Roadway rehabilitation operations and cross structure installation are ongoing. This work also consists of milling the existing roadway. Lane closures and speed zone reductions are expected. Motorists should expect delays.
I-20 WB Exit Ramp at SH 19
- Limits: From WB exit ramp to SH 19
- Contractor: Reynolds & Kay, LTD
- Cost: $1.4 million
- Anticipated Completion Date: August 2025
This project consists of ramp improvements. Crews have begun work on drainage structures and frontage road alignment. Crews are scheduled to sealcoat over the new paved section, followed by striping operations. Final closeout activities will follow.
SH 64 at I-20 and SH 155 at I-20 Traffic Signal Installation
- Limits: Intersection of SH 64 at I-20 and intersection of SH 155 and I-20
- Contractor: East Texas Bridge, Inc.
- Cost: $2.2 million
- Anticipated Completion Date: Summer 2025
The project includes the construction and installation of traffic control devices including pedestrian signals. The SH 64 intersection striping layout has been completed. SH 155 intersection signals are complete and functioning. The frontage roads between SH 155 and Lawhon Ave. have been converted to one-way travel only. Major work and punch list items have been completed. The project is currently awaiting final acceptance.
E Tyler St. at Mill Creek Bridge
- Limits: Tyler St. at Mill Creek near the Canton Trade Days facilities
- Contractor: East Texas Bridge, Inc.
- Cost: $1.17 million
- Anticipated Completion Date: Fall 2025
This project includes bridge replacement, new approaches, grading, and base repairs. The contractor is nearing completion and is working on closeout items. E. Tyler Street is closed to through traffic.
FM 1651 Rehabilitate Existing Roadway
- Limits: From SH 198 east to SH 19
- Contractor: Baker & Company Construction, LLC.
- Cost: $10.5 million
- Anticipated Completion Date: Summer 2026
The contractor will be reworking the existing road and sealcoating. Construction continues on cross structures and headwalls. This project is focused on fixing and improving the existing road. Work includes widening the road, repairing the base, adding signs, and painting new stripes. Crews will complete groundwork in one-mile segments. Drivers should expect lane closures and slower speed limits in the area. Motorists should expect delays. (This project is in Van Zandt County but is managed by the Athens Area Office.)
FM 279 Rehabilitation
- Limits: 0.24 miles east of FM 314 to SH 64
- Contractor: Big Creek LLC.
- Cost: $7.8 million
- Anticipated Completion Date: Late 2025
Crews are scheduled to perform edge work throughout the project limits. Also, crews are scheduled to work on bridge elements. Motorists should expect delays and use caution when traveling through the area. Lane closures are in place. The project consists of grading, drainage improvements, asphalt paving, striping, and signage. (This project is in Van Zandt County but is managed by the Athens Area Office.)
---------------------------------------
Wood County
This week, crews are scheduled to overlay on FM 17 in downtown Alba. The work will be done from US 69 to FM 182. Work is scheduled to continue through Tuesday, September 23. Traffic will be detoured via US 69 and FM 182.
Wood County construction projects updates:
US 69 Grade-Separated Interchange
- Limits: From 0.96 miles north of FM 779 to 1.03 miles south of FM 779
- Contractor: Lamar Companies, LLC
- Cost: $37.9 million
- Anticipated Completion Date: August 2026
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. The project also includes curb and gutter work along the frontage roads. Also, crews are preparing foundations for the retaining wall. Crews are scheduled to place temporary pavement at the FM 779 intersection on the west side. Crews are also scheduled to work on the retaining walls. Motorists should use caution due to large equipment operating in the work zone. Lane closures are expected. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract
- Limits: Gregg, Smith, and Van Zandt counties
- Contractor: Firemen Excavation, maintenance activities, follow up action worksheet summary for bridge work repair in Gregg, Smith, and Van Zandt Counties.
- Contractor: Andrews Diversified Industries, litter removal.
- Debris Removal/Pothole Repair Inside Lanes: Thursdays in all three counties.
- Debris Removal/Pothole Repair Outside Lanes: Monday, Tuesday, and Wednesday in all three counties.
- Debris Removal/Pothole Repair Frontage Roads/Ramps: Friday in all counties.
- Guardrail/Sign Repair: Emergency repairs due to vehicle crashes in all counties.
- Tree Trimming/Removal: Smith County.
- Retaining wall drain cleanout: Smith County.