Project updates for the week of Nov. 17, 2025
Skip to main content

Project updates for the week of Nov. 17, 2025

Anderson County

Palestine crews are scheduled to perform repairs on FM 319 at various locations. Motorists should expect lane closures with flaggers controlling traffic.

Anderson County construction projects updates:

US 175 Widening Project

  • Limits: From 0.4 miles SE of SH 155, SE to Cuney
  • Contractor: Big Creek Construction, LTD
  • Cost: $55.5 million
  • Anticipated Completion Date: Spring 2026

Traffic is currently being switched to the new pavement on the westbound lane, while the contractor works on the eastbound lane. Crews are scheduled to continue removing the old bridge while continuing to build the new eastbound bridge. Crews will also finalize ditches and slopes. The project will expand the roadway to four lanes with new bridges across the Neches River.

FM 1990; FM 861; FM 19 – Safety Improvement Project

  • Limits: FM 1990 – 0.1 mile north of Gum Creek to CR 2137; FM 861 – Box culvert to CR 100; FM 19 – SH 155 to 0.125 miles south of Caddo Creek
  • Contractor: THK Construction
  • Cost: $1.6 million
  • Anticipated Completion Date: Spring 2026

The contractor is scheduled to continue work on FM 1990, widening and clearing the area near the structures. The project consists of improving drainage, driveways, culverts, and upgrading the guard rail for safety.

----------------------------------------

Cherokee County

Cherokee County construction projects updates:


US 175 Widening Project

  • Limits: From 0.5 miles E of the Anderson County line (CR 3509) to FM 347 in Jacksonville
  • Contractor: A.L. Helmcamp, INC.
  • Cost: $168 million
  • Anticipated Completion Date: Fall 2028

The following county road intersections will be closed within the project limits:

  • CR 3407: local traffic will need to use the posted detour route.
  • CR 3407: local traffic will need to use the posted detour route.

The contractor is scheduled to continue work on the eastbound side through Cuney. Right of way prep work will also continue on the westbound side. The contractor will also continue drainage work, bridge work, and clearing utilities. Motorists should use caution when traveling through the work limits. The speed limit has been reduced to 55 mph throughout the project limits. The project consists of expansion to a four-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage. (This project is in Cherokee County but is managed by the Athens Area Office.)

FM 855 Improvements

  • Limits: From US 175 to US 69
  • Contractor: 3LW Civil LLC
  • Cost: $4.1 million
  • Anticipated Completion Date: Winter 2027

The contractor is scheduled to begin driveway installation and storm water plan operations. Motorists should drive with caution within the construction zone. No lane closures are anticipated. This project consists of improving drainage, cross culverts, driveways, mailbox turnouts, signage, and metal beam guard rail.

SH 204

  • Limits: From SH 110 to the Rusk County line
  • Contractor: Madden Contracting Company, LLC
  • Cost: $22.5 million
  • Anticipated Completion Date: Fall 2025

This week, the contractor is scheduled to begin permanent striping, sign installation, culvert work, and more. Motorists should drive with caution within the construction zone. Lane closures are anticipated. This project consists of adding a super-two highway section.

US 79

  • Limits: Rusk County line, southwest to 0.160 mile east of SH 110
  • Contractor: Madden Contracting Company, LLC
  • Cost: $4.25 million
  • Anticipated Completion Date: Fall 2025

The contractor has completed all work items. This project consists of rehabilitation of the existing road, including pavement repair, resurfacing, metal beam guard fence, and pavement markings.

US 69 and FM 2493 Grade Separated Interchange Realignment

  • Limits: US 69 – From 0.5 mi N of FM 2493 W to 0.5 mi south of FM 2493 E; FM 2493 – From 0.3 mi south of FM 344 to US 69 near Bullard
  • Contractor: East Texas Bridge, Inc.
  • Cost: $38.5 million
  • Anticipated Completion Date: Spring 2027

The contractor is scheduled to continue frontage road construction adjacent to US 69. Crews will also continue work on the inlets for FM 2493. The project consists of a grade separated interchange and realignment of FM 2493 West of US 69.

----------------------------------------

Gregg County

Gregg County construction projects updates:

FM 2275

  • Limits: FM 3272 (White Oak Rd) to FM 1845 (Pine Tree Rd)
  • Contractor: Longview Bridge and Road
  • Cost: $22.8 million
  • Anticipated Completion Date: May 2027

The project consists of widening from two lanes to four lanes. This will include a new bridge structure, pavement, metal beam guard fence, and striping. Crews are scheduled to place cement treatment, temporary asphalt for traffic control, and installing storm culverts.

Young St. – City of Longview

  • Limits: Mobberly Ave. to MLK Blvd.
  • Contractor: C&W Southern, LLC
  • Cost: $620,200
  • Anticipated Completion Date: November 2025

This project consists of constructing sidewalks and accessible ramps for people with disabilities on both sides of Mobberly Ave. This week, the contractor will be clearing right of way and pouring concrete for the sidewalk on the south side of the street.

I-20 Resurfacing

  • Limits: Sabine River bridge to the Harrison County line
  • Contractor: Grey Sky Construction LLC
  • Cost: $2.9 million
  • Anticipated Completion Date: November 2025

This project consists of milling asphalt off the surface and placing new hot mix asphalt from the Sabine River bridge to the Harrison County line. Work will be done in both the east and westbound lanes. The contractor is scheduled to perform punch list items and striping. Motorists should expect lane closures during overnight hours.

US 259

  • Limits: US 259 Bypass south to FM 850
  • Contractor: True Roads Construction, LLC
  • Cost: $2.49 million
  • Anticipated Completion Date: May 2026

This project consists of removing some crossovers for safety and adding left turn lanes to the remaining crossovers. The contractor is scheduled to remove culverts and modify the existing drainage structure.

----------------------------------------



Henderson County

Athens crews will be performing edge repair on FM 607. Additional crews will be performing base repair and erosion control at various locations. Motorists should expect lane closures with flaggers and a pilot car controlling traffic.

Henderson County construction projects updates:

BUS 19 Sidewalks

  • Limits: From Ben Belt Frontage Rd. To S Loop 7 ramps
  • Contractor: 3LW Civil, LCC
  • Cost: $2.6 million
  • Anticipated Completion Date: Winter 2025

The contractor is nearing completion. Motorists should expect lane closures while work is in progress. The project includes sidewalk and pedestrian access improvements.

SH 19 Super 2 Project

  • Limits: From 0.3 miles south of FM 1861 (Van Zandt C/L) south to 0.1 Mi. north of SL 7 in Athens (Watson)
  • Contractor: Big Creek Construction LTD
  • Cost: $20.8 million
  • Anticipated Completion Date: Summer 2026

The contractor has begun cement treating for roadway widening in the southbound lane. Crews are also expected to place flex base material in the southbound lane. Motorists should expect daily lane closures. The speed limit is reduced to 60 mph throughout the project limits. This project includes adding passing lanes in both directions at multiple locations. It also includes grading, drainage structures, pavement markings, and signage.

BUS 31 Rehabilitation

  • Limits: From BUS 19 to SL 7
  • Contractor: Big Creek Construction LTD
  • Cost: $8.1 million
  • Anticipated Completion Date: Major items of work are complete.

Crews are scheduled to continue project cleanup, repairing bridge joints, and sweeping. Motorists should expect lane closures. The project includes removal of current surface, base repairs, resurfacing, striping, and signage. Motorists should use caution when traveling through the nighttime work zone and expect pavement striping operations during the day.

----------------------------------------

Rusk County

Henderson crews will be repairing edges on FM 1798. Contractors will also be removing trees and mowing the right of way at various locations. Expect lane closures with flaggers and a pilot car controlling traffic.

Rusk County construction projects updates:

US 84 – FM 225 East to CR 3155

  • Limits: FM 225 east to CR 3155
  • Contractor: Drewery Construction Company
  • Cost: $12.8 Million
  • Anticipated Completion Date: November 2025

This project includes reconstruction of US 84, extended structures, a hot mix asphalt surface, new signage, and striping. This week, the contractor is scheduled to perform striping and edge work. Motorists should expect alternating lane closures.

SH 315

  • Limits: US 259 to the Panola County line
  • Contractor: Madden Construction
  • Cost: $13.5 Million
  • Anticipated Completion Date: November 2025

This project consists of widening pavement edges and installing a separation between opposing traffic lanes to improve safety. Work will also include adding a passing lane in each direction. This week, the contractor is scheduled to lay asphalt. Motorists should expect alternating lane closures. Crews will also perform striping and guard fence installation.

SH 43

  • Limits: FM 1251 north to FM 2658
  • Contractor: Madden Construction
  • Cost: $21.2 million
  • Anticipated Completion Date: November 2025

This project consists of milling approximately six inches off the surface and replacing it with new hot mix. The project also includes clearing the right of way, replacing driveway pipes, and striping. This week, the contractor is scheduled to place final striping, mow strips, pave driveways, and shoulder work. Expect lane closures with flaggers controlling traffic.

----------------------------------------

Smith County

Smith County crews are scheduled to mill and inlay on FM 2908 on Monday through Wednesday. Crews will then move to FM 850 from FM 2767 to SH 31. Expect lane closures at both locations. A second crew will be repairing potholes and edges at various locations throughout the county. Contractor crews will also be removing trees at various locations.

Smith County construction projects updates:

US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)

  • Limits: Cumberland Road to 0.45 miles north of FM 346
  • Contractor: Drewery Construction Company, INC
  • Cost: $5.8 million
  • Anticipated Completion Date: Major items of work are complete.

The contractor is scheduled to address any missed items and make corrections. No lane closures are anticipated. This work will be done during daytime hours. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at the FM 2813 intersection.

FM 2493 Widen Non-Freeway

  • Limits: FM 346 in Flint, south to 0.3 miles south of FM 344
  • Contractor: Longview Bridge and Road LTD
  • Cost: $52 million
  • Anticipated Completion Date: Spring 2027

The contractor has closed access to CR 172 (Goodson Spur) from FM 2493 for the next four to six weeks as crews work on edge drop-off repairs. Motorists should use CR 177 for the detour. This project consists of widening the existing non-freeway roadway.

Smith County Bridge Rehabilitation

  • Limits: Various locations in the Tyler city limits
  • Contractor: Tight Line Construction, LLC.
  • Cost: $3 million
  • Anticipated Completion Date: Summer 2026

This week, the contractor is scheduled to place material at the SH 19 bridge. Also, crews will be resealing the bridge joints on the SS 147 bridge. This project consists of cleaning and sealing the existing bridge joints, asphalt work, resurfacing the bridge deck, installing new metal beam guard fencing, steel and concrete repairs.

I-20 Bridge Maintenance

  • Limits: Bridge locations between Smith and Van Zandt Counties
  • Contractor: Southern Bridge and Road, LLC
  • Cost: $3 million
  • Anticipated Completion Date: May 2026

The U-turn from eastbound to westbound I-20 frontage road between Jim Hogg Rd. and US 69 will be closed to traffic. There will also be a left lane closure on the eastbound I-20 frontage road between US 69 and the U-turn. This project is bridge maintenance consisting of cleaning and painting the existing steel bridge structures.

FM 16 Widening and Realignment

  • Limits: Four miles west of FM 849 east to US 69 in Lindale
  • Contractor: Highway 19 Construction LLC
  • Cost: $44.4 million
  • Anticipated Completion Date: February 2027

The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. Embankment installation is ongoing. Crews will also install subgrade and flex base, then sealcoat from Toll 49 heading west. (This project is in Smith County but is managed by the Mineola Area Office.)

SH 31 Resurfacing

  • Limits: From Henderson County line to FM 206
  • Contractor: East Texas Bridge, Inc.
  • Cost: $7.4 million
  • Anticipated Completion Date: Fall 2025

The contractor is scheduled to continue final striping this week. Motorists should expect delays and use caution when traveling through area. This project includes base repairs, resurfacing, striping, and sign installation. (This project is in Smith County but is managed by the Athens Area Office.)

---------------------------------------

Van Zandt County

Canton crews are scheduled to mill and inlay on SH 64 between FM 1504 and US 80. Crews will then move to FM 751. Work will be done from FM 47 to the Hunt County line. Motorists should expect lane closures with flaggers controlling traffic.

Van Zandt County construction projects updates:

FM 17, FM 47, and FM 859 Bridge Replacement

  • Limits: Bridge at FM 17, FM 47, and FM 859 over I-20
  • Contractor: Indus Bridge and Road
  • Cost: $14.5 Million
  • Anticipated Completion Date: November 2025

This project includes construction of new bridges and approaches, grading, base and surface work, and installation of metal beam guard fencing. Motorists should expect reduced speed limits and narrowed shoulders on both the I-20 main lanes and frontage roads. The FM 17, FM 47, and FM 859 bridges are open to traffic. The contractor is working on punch list items on each bridge and removing concrete barriers. Crews will also continue driveway work near the FM 47 bridge.

FM 1255 Rehabilitate Existing Roadway

  • Limits: I-20 to SH 110
  • Contractor: Reynolds & Kay, LTD.
  • Cost: $17.1 Million
  • Anticipated Completion Date: February 2026

This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. Work will be completed under live traffic conditions. Right of way prep and tree trimming are ongoing. Roadway rehabilitation operations and cross structure installation are ongoing. This work also consists of milling the existing roadway. Lane closures and speed zone reductions are expected. Motorists should expect delays.

I-20 WB Exit Ramp at SH 19

  • Limits: From WB exit ramp to SH 19
  • Contractor: Reynolds & Kay, LTD
  • Cost: $1.4 million
  • Anticipated Completion Date: November 2025

This project consists of ramp improvements. Project closeout is underway.

E Tyler St. at Mill Creek Bridge

  • Limits: Tyler St. at Mill Creek near the Canton Trade Days facilities
  • Contractor: East Texas Bridge, Inc.
  • Cost: $1.17 million
  • Anticipated Completion Date: Fall 2025

This project includes bridge replacement, new approaches, grading, and base repairs. The contractor is working on closeout items. E. Tyler Street is closed to through traffic.

FM 1651 Rehabilitate Existing Roadway

  • Limits: From SH 198 east to SH 19
  • Contractor: Baker & Company Construction, LLC.
  • Cost: $10.5 million
  • Anticipated Completion Date: Summer 2026

The contractor is also scheduled to begin roadway widening and cement treatment between Tundra and SH 19. Work includes widening the road, repairing the base, adding signs, and painting new stripes. Crews will complete groundwork in one-mile segments. Drivers should expect lane closures and slower speed limits in the area. Motorists should expect delays. (This project is in Van Zandt County but is managed by the Athens Area Office.)

FM 279 Rehabilitation

  • Limits: 0.24 miles east of FM 314 to SH 64
  • Contractor: Big Creek LLC.
  • Cost: $7.8 million
  • Anticipated Completion Date: Late 2025

Crews are scheduled to perform edge repairs and bridge maintenance. Motorists should expect delays and use caution when traveling through the area. Lane closures are in place. The project consists of grading, drainage improvements, asphalt paving, striping, and signage. (This project is in Van Zandt County but is managed by the Athens Area Office.)

---------------------------------------

Wood County

This week, crews are scheduled to overlay on FM 778 between FM 49 and US 80. Motorists should expect lane closures with flaggers controlling traffic. Another crew will perform base repairs on FM 14 between SH 154 and FM 49. Crews are also scheduled to perform bridge maintenance at various locations.

Wood County construction projects updates:

US 69 Grade-Separated Interchange

  • Limits: From 0.96 miles north of FM 779 to 1.03 miles south of FM 779
  • Contractor: Lamar Companies, LLC
  • Cost: $37.9 million
  • Anticipated Completion Date: August 2026

This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. The project also includes curb and gutter work along the frontage roads. Crews are scheduled to continue work on the retaining walls. Crews are also scheduled to perform paving operations on the south side of the bridge. Crews are scheduled to place a barrier in preparation for a traffic shift in December. Motorists should use caution due to large equipment operating in the work zone. Motorists should expect delays.

----------------------------------------

I-20 Total Maintenance Contract

  • Limits: Gregg, Smith, and Van Zandt counties
  • Contractor: Firemen Excavation, maintenance activities, follow up action worksheet summary for bridge work repair in Gregg, Smith, and Van Zandt Counties.
  • Contractor: Andrews Diversified Industries, litter removal.
  • Debris Removal/Pothole Repair Inside Lanes: Thursdays in all three counties.
  • Debris Removal/Pothole Repair Outside Lanes: Monday, Tuesday, and Wednesday in all three counties.
  • Debris Removal/Pothole Repair Frontage Roads/Ramps: Friday in all counties.
  • Guardrail/Sign Repair: Emergency repairs due to vehicle crashes in all counties.
  • Tree Trimming/Removal: Smith County.
Media contact
Jeff Williford
November 14, 2025