North Tarrant Express
Skip to main content

North Tarrant Express

March 30, 2006

Authorization by the Texas Transportation Commission to issue request for proposals and qualifications.

December 8, 2006

TxDOT issues request for proposals and qualifications.

March 15, 2007

Deadline to submit proposals and qualifications

  • Acciona-Omega
  • B3 Connect Texas*
  • FCC Construccion, S.A.
  • Itinere Infrastructure, LLC*
  • NTE Mobility Partners*
  • OHL Infrastructure, Inc.*
  • T-Bar Mobility Alliance

Completed

TxDOT evaluation and short list of teams.*

December 13, 2007

Authorization by the Texas Transportation Commission to issue request for detailed proposals.

March 3, 2008

TxDOT issues Request for Proposals.

December 1, 2008

Deadline to submit detailed proposals.

January 29, 2009

Selection of best-value proposal and conditional award to NTE Mobility Partners

TBA

CDA Public Hearing

Spring 2009

Commercial close

Summer 2009

Team opens local office and begins design

Summer 2009

Team begins master plan for Phase 2

December 17, 2009

Financial close

Early 2010

Begin right of way purchases and utility relocations

Late 2010/Early 2011

Master plan developed

Early 2011

Construction begins on Phase 1

RFP Addendum #4 (August 1, 2008)

RFP Addendum #3 (July 11, 2008)

RFP Addendum #2 (June 4, 2008)

RFP Addendum #1 (May 5, 2008)

Request for Proposals (March 3, 2008)

Reference Documents

RFQ Addendum #2 (February 16, 2007)

RFQ Addendum #1 (February 12, 2007)

Additional Documents