SH 130/SH 45N Improvement Project
Skip to main content

SH 130/SH 45N Improvement Project

Overview

TxDOT is planning to improve 16 miles of SH 130 from I-35 to RM 685 and four miles of SH 45 N from A.W. Grimes to SH 130 in Travis and Williamson counties. The project will:

  • Add a lane to northbound and southbound SH 130 in the median
  • Construct a third lane for eastbound SH 45 N

No new right of way is required for the project.

Project information

Below is the comment response matrix used to record and communicate comments and responses generated as a result of the environmental review. For a copy of the complete notice and opportunity to comment summary report, please contact the TxDOT Austin District at 512-832-7000.

Questions or comments

All input will be considered as TxDOT works to improve safety and mobility on SH 130 and SH 45 N.

Timeline

  • Environmental development: early 2025
  • Community update: early 2026
  • Design finalized: mid-2026
  • Project out to bid: January 2027
  • Construction start: mid-2027
  • Anticipated construction end: mid-2032
Horizontal project timeline from left to right: environmental development, early 2025; community update, early 2026; design finalized, mid-2026; project out to  bid, January 2027; construction start, mid-2027; anticipated construction end, mid-2032