Bridge replacement on I-30 at FM 2642 – Hunt County
TxDOT has begun a $23.2 million bridge replacement project on I-30 in Hunt County at FM 2642. The 3.9-mile project runs from the Rockwall County line to FM 1565. Construction is expected to last approximately 18 months.
Planned Improvements
The reconstruction effort includes:
Construction Considerations
TxDOT is committed to working with the public to minimize impacts from construction projects as much as possible. Although some traffic delays are expected, traffic will continue to use the current bridge structure while building the new bridge structure in five phases:
Phase I
February 2017 - March 2017
Phase II
March 2017 - November 2017
Phase III
November 2017 - May 2018
Phase IV
May 2018 - June 2018
Phase V
June 2018 - December 2018
Construction Schedule
Downloads
Contact Us
TxDOT Paris District
Public Information Office
(903) 737-9213
Email
Copyright 2021
•
Texas Department of Transportation
•
All Rights Reserved
•
Disclaimer
•
Privacy & Security Policy
•
Accessibility
125 East 11th Street
•
Austin, Texas 78701