Northeast 24th Avenue

From North Lake Street to North Eastern Street

Virtual public meeting with in-person option

Virtual: Tuesday, Dec. 15, 2026 by 5 p.m.

In-person: Tuesday, Dec. 15, 2026 from 5 to 7 p.m.

Meeting details

Public comment deadlineAll comments must be received on or before Wednesday, Jan. 6, 2027 to be included in the official public meeting record.
Virtual details

The virtual meeting will consist of a pre-recorded video presentation and will include both audio and visual components. The presentation will be posted online by 5 p.m. on Tuesday, Dec. 15, 2026, and will remain available for at least 15 days. 

If you do not have internet access, you may call 806-378-9334 between the hours of 8 a.m. and 5 p.m. Monday through Friday, to ask questions and access project materials during the project development process.

In-person details

Tuesday, Dec. 15, 2026
5 to 7 p.m.

North Branch Amarillo Public Library
1500 NE 24th Ave.
Amarillo, TX 79107

The in-person option will be held in an open house format. In-person attendees will be able to view the same presentation delivered in the virtual public meeting, which will be playing on a screen, review hard copies of project materials, ask questions of city staff and/or consultants, and leave written comments.

PurposeThe City of Amarillo, in partnership with the Texas Department of Transportation (TxDOT), proposes to construct a grade-separated roadway overpass carrying Northeast 24th Avenue over the Burlington Northern Santa Fe (BNSF) Railway main line and reconstruct the roadway approaches along Northeast 24th Avenue from North Lake Street to North Eastern Street in Potter County, Texas.
Description 

The proposed bridge over the railroad would include four 12-foot travel lanes and a 10-foot shared-use path (SUP) on the south side with rails along both sides of the SUP. The roadway approaches would be reconstructed to accommodate the four 12-foot travel lanes, 16-foot local access roads for adjacent properties, retaining walls, curb and gutter, and a 10-foot-wide SUP on the south side with rails on both sides within a proposed right-of-way width varying from 90 feet to 140 feet.

Although additional right of way would be required, no residential or non-residential structures are anticipated to be displaced at this time. Information about services and benefits available to affected property owners and the tentative schedule for right-of-way acquisition and construction can be obtained by calling Edgar Arellano at Kimley-Horn and Associates, Inc. at 806-319-6378.

Any environmental documentation or studies, any maps and drawings showing the project location and design, tentative construction schedules, and other information regarding the proposed project are on file and available for inspection Monday through Friday between the hours of 8 a.m. and 4 p.m. at the City of Amarillo Simms Municipal Building, 808 S. Buchanan St., Amarillo, TX 79101 at 806-378-9363. Project materials are also available online at the City of Amarillo's project page. These materials will also be available in hard copy form for review at the in-person option.

AccessibilityThe virtual public meeting and in-person option will be conducted in English. If you need an interpreter or document translator because English is not your primary language or you have difficulty communicating effectively in English, one will be provided to you. If you have a disability and need assistance, special arrangements can be made to accommodate most needs. If you need interpretation or translation services or you are a person with a disability who requires an accommodation to attend and participate in the virtual public meeting or in-person option, please contact the City of Amarillo Engineering Department at 806-378-9334 no later than 4 p.m. CT, Thursday, Dec. 10, 2026. Please be aware that advance notice is required as some services and accommodations may require time for the City of Amarillo to arrange.
Meeting materials
How to make a comment

Written comments from the public regarding the proposed pedestrian improvements are requested and may be submitted beginning Wednesday, Jan. 6, 2027 by any of the following methods:

  • Email: as shown in the notice
  • Mail:
    NE 24th Ave Project Team
    13455 Noel Rd.
    Two Galleria Office Tower
    Suite 700
    Dallas, TX 75240

All comments must be received on or before Wednesday, Jan. 6, 2027 to be included in the official public meeting record. Responses to comments received will be available online at City of Amarillo's project page once responses have been prepared.

Nov. 24, 2026