This construction project includes design changes to the I-45 (Gulf Freeway) improvement and reconstruction project, from south of FM 518 to FM 1764, located within Galveston County, Texas.

Planned Construction Improvements

Planned improvements include the following:

  • Revising entrance and exit ramp locations
  • Constructing detention ponds; approximately 20 acres of additional right-of-way would be required for the proposed detention ponds

No additional displacements are anticipated.

Next Steps

  • Re-evaluation determination for these design changes was approved by TxDOT on Aug. 26, 2016
  • FM 518 to FM 517 segment is anticipated to be completed in April 2021
  • FM 517 to FM 1764 is anticipated to be completed in September 2022

Lane Closure and Detour Information