I-10 Widening West Project

Monday, August 10 – Friday, August 14 (As Needed)

Daily, 9 a.m. – 4 p.m.

  • I-10 east and westbound between Los Mochis and Mesa alternate lane closures
  • North and South Desert between Los Mochis and Mesa alternate lane closures
  • Entrance ramp, exit ramp, and U-turn, east and westbound between Los Mochis alternate lane closures

Crews will be working on construction punch list items.

I-10 Widening West 2 Project

Saturday, August 8

3 a.m. – 3 p.m.

  • I-10 eastbound between Anthony and Los Mochis full closure

Detour: Traffic will exit at Anthony, proceed onto South Desert through the Anthony and Vinton intersections, and enter at I-10 eastbound after Los Mochis.

Crews will be placing beams.

Monday, August 10 and Tuesday, August 11

Nightly, 9 p.m. – 6 a.m.

  • I-10 eastbound between Anthony and Artcraft full closure

Detour: Traffic will exit at Anthony, proceed onto South Desert through the Anthony and Vinton intersections, and enter I-10 eastbound after Los Mochis.

Crews will be placing beams.

Wednesday, August 12

9 p.m. - 6 a.m.

  • I-10 westbound between Anthony and Artcraft full closure

Crews will be working on bridges.

Monday, August 10 - Saturday, August 15 (As Needed)

Daily, 9 a.m. – 4 p.m.

Nightly, 9 p.m. – 6 a.m.

  • I-10 east and westbound between Anthony and Mesa alternate lane closures (No Detour Needed)
  • North and South Desert between Anthony and Mesa alternate lane closures (No Detour Needed)

Crews will be conducting dirt work and miscellaneous removals.

Monday, August 10 - Saturday, August 15 (As Needed)

9 a.m. – 4 p.m.

  • I-10 east and westbound Bypass lanes between Mesa and Redd full closure

Detour: Traffic will continue along South Desert, through the Thorn intersection, and enter I-10 before Mesa. Traffic will continue along North Desert, through Thorn intersection, and enter I-10 before Redd.

Crews will be completing construction of ornamental fences and landscaping at Thorn.

  • I-10 westbound exit Ramp 05 at Los Mochis full closure

Detour: Traffic to proceed on North Desert through the Vinton intersection.

Crews will be working on landscaping.

Continuous Closures Until Further Notice 24/7

  • Full U-turn underpass at Bridge C between Anthony and Vinton closed

Detour: Traffic on North Desert will need to proceed to Anthony, TX and utilize U-turn Bridge. Traffic on South Desert will need to proceed to Vinton, TX and utilize U-turn Bridge

Crews will be conducting Bridge Demolition and Bridge Construction on U-turns under I-10 at Bridge

  • South Desert between Valley Chile and Vinton Steel left lane closed

Detour: Traffic will be kept in one lane, with access to entrance ramp at Valley Chile, then continue in one lane of traffic until past Bridge D at Vinton Steel

Crews will be working on Walls 13 and 14.

  • South Desert between Transmountain and Isela Rubalcava left lane closed

Crews will be working on lane reconfiguration for South Desert at Tractor Supply.

  • North and South Desert at the Los Mochis intersection left lane closed

Crews will be working on Los Mochis intersection.

  • Campus Park intersection at South Desert closed

Crews will be conducting paving operations.

Monday, March 9 - End of August 2026 (Approx. 5 months)

  • I-10 westbound exit ramp to Transmountain closed
  • Secondary temporary exit ramp to Transmountain open

Crews will be working on various constructions.