I-10 widening west closures
Phase 2
Saturday, November 14, 3 a.m. – Monday, November 16, 6 a.m. (51 hour closure)
- I-10 eastbound between Anthony and Transmountain full closure
Detour: Traffic on South Desert, proceed though intersection at Anthony and Vinton, then enter I-10 eastbound after Los Mochis.
Crews will be placing bridge deck.
Thursday, November 12
9 p.m. – 6 a.m.
- I-10 westbound between Los Mochis and Anthony full closure
Crews will be placing concrete girders and working on temp Anthony exit.
Detour: Traffic to exit at Los Mochis, proceed on North Desert through the intersection at Vinton and Anthony, enter I-10 westbound after Anthony.
Monday, November 9 –Saturday, November 14 (As Needed)
Daily, 9 a.m. – 4 p.m.
Nightly, 9 p.m. – 6 a.m.
- I-10 east and westbound between Anthony and Mesa alternate lane closures
- North and South Desert between Anthony and Mesa alternate lane closures
Crews will be conducting dirt work and miscellaneous removals.