Westlake Drive/Cedar Street
Loop 360 Projects
This project consists of improvements to the intersections at Westlake Drive and Cedar Street, including removing the traffic signals on the Loop 360 mainlanes and adding an underpass (where the mainlanes go under the cross street) at both locations.
Major activity
- Construction continues on Loop 360 mainlanes between Bold Ruler Way and Westlake Drive
- Excavation work takes place between 7 a.m. and 5 p.m. while hauling work takes place during night hours
- Excavation work takes place between 7 a.m. and 5 p.m. while hauling work takes place during night hours
- New Traffic Patterns
- Temporary northbound Loop 360 mainlanes open between Waymaker Way and Pennybacker Bridge
- Use Westlake Drive or Cedar Street signals to access southbound Loop 360
- Use two new signalized U-turn lanes at northbound Loop 360 and Cedar Street to access southbound Loop 360
- Crossovers between Bold Ruler and Pennybacker Bridge to access southbound Loop 360 are closed
- Temporary southbound Loop 360 mainlanes open between Pennybacker Bridge and Westlake Drive
- Use single U-turn lane at Cedar Street to access northbound Loop 360
- Crossovers between Pennybacker Bridge and Westlake Drive to access northbound Loop 360 are closed
- Protected crossover at Bold Ruler to access northbound Loop 360 remains open
- Local business driveway access to temporary mainlanes
- Map
- Temporary northbound Loop 360 mainlanes open between Waymaker Way and Pennybacker Bridge
Lane closures
There are no lanes closure at this time.
Documents
Schedule
Construction began in June 2022 and is expected to be complete late-2025, weather permitting.
Construction phases
Work on the Loop 360 Westlake Drive/Cedar Street project will take place in five phases:
- Phase 1: Set up work zone and construct waterlines.
- Phase 2: Construct new northbound and southbound connector roads, drainage systems and shared-use paths.
- Phase 3: Construct Westlake Drive bridge and begin northbound and southbound mainlanes.
- Phase 4: Construct Cedar Street bridge and complete northbound and southbound mainlanes.
- Phase 5: Perform final paving and striping and open to permanent traffic patterns.
Contractor: Copasa Group