Westlake Drive/Cedar Street
Loop 360 Projects
This project consists of improvements to the intersections at Westlake Drive and Cedar Street, including removing the traffic signals on the Loop 360 mainlanes and adding an underpass (where the mainlanes go under the cross street) at both locations.
Lane closures
TxDOT asks drivers to be patient. Neighbors and businesses may experience an increase in noise, vibration, dust and lighting during night work. Pay attention to flaggers and traffic control. All closures are weather permitting.
- Southbound Loop 360 between Pennybacker Bridge and Westlake Drive alternating single-lane closures
- Monday, March 23 to Friday, March 27, 9 a.m. to 3 p.m.
- Northbound Loop 360 between Westlake Drive and Cedar Street left lane closed
- Monday, March 23 to Tuesday, March 24, 9 a.m. to 3 p.m.
Cedar Street bridge
The new Cedar Street bridge provides east/west connectivity. Non signalized U-turns on the Westlake Drive bridge provide additional northbound and southbound Loop 360 access.
Westlake Drive bridge
The new Westlake Drive bridge provides east/west connectivity. Non-signalized U-turns on the bridge provide northbound and southbound Loop 360 access.
- Southbound U-turn located south of Bold Ruler Way continues to provide northbound Loop 360 access.
- Northbound U-turn located north of Waymaker Way continues to provide southbound Loop 360 access.
Construction activity
- Construction continues on Loop 360 mainlanes between Bold Ruler Way and Pennybacker Bridge
- Excavation work takes place on weekdays between 7 a.m. and 7 p.m. while hauling work takes place during night hours
- Excavation work at Loop 360 and Cedar Street
- Monday, March 23 to Friday, March 27, 9 a.m. to 3 p.m.
Progress update photos
Documents
Schedule
Construction began in June 2022 and is expected to be complete mid-2026, weather permitting.
Construction phases
Work on the Loop 360 Westlake Drive/Cedar Street project will take place in five phases:
- Phase 1 complete: Set up work zone and construct waterlines.
- Phase 2 ongoing: Construct new northbound and southbound connector roads, drainage systems and shared-use paths.
- Phase 3 ongoing: Construct Westlake Drive bridge and begin northbound and southbound mainlanes.
- Phase 4 ongoing: Construct Cedar Street bridge and complete northbound and southbound mainlanes.
- Phase 5: Perform final paving and striping and open to permanent traffic patterns.
Contractor: Copasa Group