Westlake Drive/Cedar Street
Loop 360 Projects
This project consists of improvements to the intersections at Westlake Drive and Cedar Street, including removing the traffic signals on the Loop 360 mainlanes and adding an underpass (where the mainlanes go under the cross street) at both locations.
New traffic pattern
Westlake Drive east/west crossover at Loop 360 intersection is closed for excavation and bridge construction. Westlake Drive is a right in/right out only. The Loop 360 mainlanes remain open. The closure is anticipated to last approximately six months, weather permitting.
- Drivers traveling westbound on Westlake Drive will U-turn at Cedar Street to access southbound Loop 360. detour map
- Drivers traveling eastbound on Westlake Drive will U-turn at new signals installed across the Shell Refuel Gas station to access northbound Loop 360. detour map
- New protected U-turn located north of Waymaker Way will provide additional access to southbound Loop 360 without driving north to Cedar Street. Bold Ruler U-turn provides additional northbound Loop 360 access south of Westlake Drive. detour map
Westlake Drive bridge construction detour
Lane closures
- Bold Ruler Way at northbound Loop 360 closed
- Ongoing dependent on weather
Construction activity
- Construction continues on Loop 360 mainlanes between Bold Ruler Way and Pennybacker Bridge
- Excavation work takes place between 7 a.m. and 5 p.m. while hauling work takes place during night hours
Progress update photos
Documents
Schedule
Construction began in June 2022 and is expected to be complete mid-2026, weather permitting.
Construction phases
Work on the Loop 360 Westlake Drive/Cedar Street project will take place in five phases:
- Phase 1 complete: Set up work zone and construct waterlines.
- Phase 2 ongoing: Construct new northbound and southbound connector roads, drainage systems and shared-use paths.
- Phase 3: Construct Westlake Drive bridge and begin northbound and southbound mainlanes.
- Phase 4: Construct Cedar Street bridge and complete northbound and southbound mainlanes.
- Phase 5: Perform final paving and striping and open to permanent traffic patterns.
Contractor: Copasa Group