Courtyard Drive/RM 2222
Loop 360 Projects
This project will remove the traffic signal from Loop 360 mainlanes at Courtyard Drive and construct an underpass. The project will also reconfigure RM 2222 at Loop 360 to a Diverging Diamond Interchange (DDI) and add shared-use paths and sidewalks within the project limits.
Lane closures
TxDOT asks drivers to be patient. Road signs have been placed to alert drivers of the upcoming changes. Pay attention to flaggers and traffic control. All closures are weather permitting.
- Northbound Loop 360 exit ramp to RM 2222 left lane closed
- ongoing
- Northbound and southbound Loop 360 between Pennybacker Bridge and RM 2222 alternating single-lane closures. Northbound Loop 360 exit ramp to RM 2222 and RM 2222 entrance ramp to southbound Loop 360 alternating single-lane closures
- Monday, April 27, 8 p.m. to 5 a.m.
- Eastbound and westbound RM 2222 between Champion Grandview Way and Lakewood Drive alternating single-lane closures
- Tuesday, April 28, 8 p.m. to 5 a.m.
Construction activity
Crews have started work to stabilize the upper limestone cliffs on the west side of Courtyard Drive adjacent to southbound Loop 360 mainlanes. An estimated 155,000 cubic yards will be excavated.
Construction takes place on weekdays between 7 a.m. and 7 p.m. and on Saturdays between 7 a.m. and 3 p.m.
Neighbors and businesses may experience an increase in noise, vibration, and dust during excavation and night work.
TxDOT asks drivers to be patient. Plan ahead and expect delays.
Schedule
The project was environmentally cleared in spring 2021. Construction is anticipated to begin in April 2026.
TxDOT’s environmental guidance requires that vegetation removal be done outside the nesting season and follow the federal Migratory Bird Treaty Act which protects nongame birds, their eggs and nests. Brush clearance was completed Feb. 2026.
Utility relocation will occur prior to the beginning of construction. Occasional lane closures may be required for utility relocation. While service interruptions are not anticipated, contact your service provider if you have any questions.
- AT&T: 800-288-2020
- Austin Energy: 512-322-9100
- Texas Gas: 800-959-5325
Construction phases
Work on this project will take place in four phases:
Phase 1: Set up work zone, construct waterlines and excavate cliffs.
Phase 2: Construct new northbound and southbound connector roads, drainage systems, braided ramps and Courtyard Drive bridge. Start shared-use paths.
Phase 3: Construct RM 2222 Diverging Diamond Interchange and complete shared-use paths.
Phase 4: Perform final paving and striping and open to permanent traffic patterns.
Contractor: Webber
Documents
Project images
Past public involvement and events
Courtyard Drive/RM 2222 Public Hearing | Oct. 6, 2020
- Public hearing meeting summary
- Presentation video
- Presentation transcript
- Display boards
- Exhibit
- Handouts