Courtyard Drive/RM 2222
Loop 360 Projects
This project will remove the traffic signal from Loop 360 mainlanes at Courtyard Drive and construct an underpass. The project will also reconfigure RM 2222 at Loop 360 to a Diverging Diamond Interchange and add shared-use paths and sidewalks within the project limits.
Lane closures
- RM 2222 entrance ramp to southbound Loop 360 closed
- Monday, Nov. 16 to Wednesday, Nov. 18, 8 p.m. to 5 a.m,
- Courtyard Drive at Loop 360 alternating single lane closures
- Tuesday, Nov. 17, 8 p.m. to 5 a.m
Looking Ahead
New eastbound RM 2222 right turn lane to southbound Loop 360 opens as soon as Monday morning, Nov. 23. Drivers on eastbound RM 2222 will use the right lane and yield to westbound RM 2222 traffic
Construction activity
Construction takes place on weekdays between 7 a.m. and 7 p.m. and as needed on Saturdays between 7 a.m. and 3 p.m.
Neighbors and businesses may experience an increase in noise, vibration, and dust during excavation and night work. TxDOT asks drivers to be patient. Plan ahead and expect delays.
While service interruptions are not anticipated, contact your service provider if you have any questions.
- AT&T: 800-288-2020
- Austin Energy: 512-322-9100
- Texas Gas: 800-959-5325
Schedule
The project was environmentally cleared in spring 2021. Construction began in April 2026 and is expected to be complete in late 2029.
Construction phases
Work on this project will take place in four phases:
Phase 1: Set up work zone, construct waterlines and excavate cliffs.
Phase 2: Construct new northbound and southbound connector roads, drainage systems, braided ramps and Courtyard Drive bridge. Start shared-use paths.
Phase 3: Construct RM 2222 Diverging Diamond Interchange and complete shared-use paths.
Phase 4: Perform final paving and striping and open to permanent traffic patterns.
Contractor: Webber
Documents
Project images
Past public involvement and events
Courtyard Drive/RM 2222 Public Hearing | Oct. 6, 2020
- Public hearing meeting summary
- Presentation video
- Presentation transcript
- 2020 Display boards
- 2020 Exhibit
- 2020 Handouts
Courtyard Drive/RM 2222 Project Workshop | March 7, 2019
- March 2019 Workshop summary
- March 2019 Survey report
- March 2019 Boards
- March 2019 Exhibits
- March 2019 Handouts