Courtyard Drive/RM 2222
Skip to main content

Courtyard Drive/RM 2222

This project will remove the traffic signal from Loop 360 mainlanes at Courtyard Drive and construct an underpass. The project will also reconfigure RM 2222 at Loop 360 to a Diverging Diamond Interchange and add shared-use paths and sidewalks within the project limits.

Lane closures

TxDOT asks drivers to be patient. Road signs have been placed to alert drivers of the upcoming changes. Pay attention to flaggers and traffic control. All closures are weather permitting.

  • Northbound Loop 360 exit ramp to RM 2222 left lane closed
    • Ongoing

Construction activity

Construction takes place on weekdays between 7 a.m. and 7 p.m.

Neighbors and businesses may experience an increase in noise, vibration, and dust during excavation and night work. TxDOT asks drivers to be patient. Plan ahead and expect delays.

While service interruptions are not anticipated, contact your service provider if you have any questions.

  • AT&T: 800-288-2020
  • Austin Energy: 512-322-9100
  • Texas Gas: 800-959-5325

Schedule

The project was environmentally cleared in spring 2021. Construction began in April 2026 and is expected to be complete in late 2029.

Construction phases

Work on this project will take place in four phases:

Phase 1: Set up work zone, construct waterlines and excavate cliffs.
Phase 2: Construct new northbound and southbound connector roads, drainage systems, braided ramps and Courtyard Drive bridge. Start shared-use paths.
Phase 3: Construct RM 2222 Diverging Diamond Interchange and complete shared-use paths.
Phase 4: Perform final paving and striping and open to permanent traffic patterns.

Contractor: Webber

Documents

Courtyard Drive RM-2222 Map
Courtyard Drive RM-2222 Map

Project images

Past public involvement and events

Courtyard Drive/RM 2222 Public Hearing | Oct. 6, 2020

Courtyard Drive/RM 2222 Project Workshop | March 7, 2019

Courtyard Drive/RM 2222 Neighborhood Workshop | Feb. 7, 2019