April 2026 construction photos
Crews spent much of April 2026 cleaning up construction areas, getting East Downtown ready for the 2026 FIFA World Cup fan services activities in the area.
All construction trench areas must be filled, permanent and temporary sidewalks must be built, and sod must be placed down. Work on this project will be on pause from June 1 - August 1, 2026, to accommodate events surrounding the huge soccer tournaments for which Houston will host seven games.
March 2026 construction photos
Crews completed placing 8-foot diameter storm sewer pipes underneath St. Emanuel Street between Jefferson and McIlhenny streets. That is a run of about 1800 feet!
February 2026 construction photos
Crews made great progress on the large detention pond between Runnels Street and Buffalo Bayou, and a company made sure rainwater in the pond was safe to push into the bayou.
January 2026 construction photos
This month saw the first portion of St. Emanuel Street completed in its final configuration, between St. Joseph Parkway and Gray Street.
November 2025 construction photos
Detention pond construction, pond will hold nearly 76 million gallons of stormwater once completed
Sept 2025 construction photos
Detention pond construction, pond will hold nearly 76 million gallons of stormwater once completed
May 2025 construction photos
Work Continues on Detention Pond near I-69 and Runnels Street
March 2025 construction photos
Crews Build Detention Pond near I-69 and Runnels Street