Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
July, 2020 (FY 2021) | (see Links) |
SEP 2019 | OCT 2019 | NOV 2019 | DEC 2019 | JAN 2020 | FEB 2020 | MAR 2020 | APR 2020 | MAY 2020 | JUN 2020 | JUL 2020 | AUG 2020 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0520-09-046 | Anderson/ Tyler | SL 256 | Tentative | $0 | 8 | IMPROVE/INSTALL RRX SIGNALS AND GATES | 0.0 |
0231-03-147 | Bell/ Waco | US 190 | Tentative | $5,000,000 | 1 | CONSTRUCTION OF A WEST TO EAST TURNAROUND @ FM 2410 | 0.0 |
0915-12-630 | Bexar/ San Antonio | CS | Tentative | $581,341 | 8 | SAFETY TREAT FIXED OBJECTS, CONSTRUCT A ROUNDABOUT | 0.0 |
0915-12-514 | Bexar/ San Antonio | CS | Tentative | $933,000 | 3 | CONSTRUCTION OF A HIKE AND BIKE TRAIL ALONG HUEBNER CREEK | 0.0 |
0915-12-633 | Bexar/ San Antonio | CS | Tentative | $914,673 | 8 | IMPROVE TRAFFIC SIGNALS | 0.0 |
0915-12-657 | Bexar/ San Antonio | CS | Tentative | $3,801,696 | 8 | CONSTRUCT INTERCHANGE | 0.0 |
0521-05-148 | Bexar/ San Antonio | IH 410 | Tentative | $15,100,000 | 1 | OPERATIONAL IMPROVEMENTS INCLUDING RAMP REVISIONS, | 0.0 |
0111-09-042 | Brazoria/ Houston | BS 288B | Tentative | $5,445,000 | 1 | WIDEN TO ADD 8 FT SHOULDERS, PAVEMENT REPAIR, OCST, 1.5 IN | 0.0 |
0921-06-310 | Cameron/ Pharr | CS | Tentative | $0 | 8 | INSTALLATION OF FLASHING LIGHT SIGNALS | 0.0 |
0919-00-080 | Cass/ Atlanta | VA | Tentative | $856,236 | 1 | Surfacing/Roadway Restoration | 0.0 |
0216-01-057 | Comal/ San Antonio | SL 337 | Tentative | $10,400,000 | 1 | CONSTRUCT GRADE SEPARATION | 0.0 |
0909-39-129 | Coryell/ Waco | CS | Tentative | $1,375,000 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0918-47-199 | Dallas/ Dallas | CS | Tentative | $300,000 | 8 | INSTALL RAILROAD CROSSING PROTECTION DEVICES | 0.0 |
0918-47-200 | Dallas/ Dallas | CS | Tentative | $200,000 | 8 | INSTALL RAILROAD CROSSING PROTECTION DEVICES | 0.0 |
0918-46-303 | Denton/ Dallas | CS | Tentative | $300,000 | 8 | INSTALL RAILROAD CROSSING PROTECTION DEVICES | 0.0 |
0924-06-557 | El Paso/ El Paso | CS | Tentative | $250,000 | 8 | GRADE CROSSING SAFETY UPGRADES DOT#019785U | 0.0 |
0924-06-558 | El Paso/ El Paso | CS | Tentative | $250,000 | 8 | GRADE CROSSING SAFETY UPGRADES DOT#019778J | 0.0 |
0924-06-559 | El Paso/ El Paso | CS | Tentative | $250,000 | 8 | GRADE CROSSING SAFETY UPGRADES DOT#019786B | 0.0 |
0902-49-070 | Erath/ Ft Worth | CS | Tentative | $250,000 | 8 | 2017 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0833-06-019 | Falls/ Waco | FM 2027 | Tentative | $1,849,675 | 1 | WIDEN ROAD - ADD SHOULDERS | 0.0 |
1482-01-014 | Fannin/ Paris | FM 1550 | Tentative | $2,860,000 | 1 | 2R REHAB | 0.0 |
0271-10-012 | Fort Bend/ Houston | US 90 | Tentative | $180,002 | 10 | LANDSCAPE DEVELOPMENT | 0.0 |
1534-02-008 | Gillespie/ Austin | RM 1623 | Tentative | $5,370,847 | 8 | IMPROVE GUARDRAIL, SAFETY TREAT OBJECTS,PROFILE EDGELINE | 0.0 |
0910-07-075 | Gregg/ Tyler | CS | Tentative | $0 | 8 | INSTALL/IMPROVE SIGNAL DEVICES | 0.0 |
0910-07-073 | Gregg/ Tyler | CS | Tentative | $0 | 8 | INSTALL/IMPROVE SIGNAL DEVICES | 0.0 |
0115-01-014 | Guadalupe/ San Antonio | FM 20 | Tentative | $7,323,787 | 8 | SAFETY TREAT FIXED OBJECTS | 0.0 |
0905-12-044 | Hale/ Lubbock | CR | Tentative | $371,305 | 6 | BRIDGE REPLACEMENT | 0.0 |
0912-72-541 | Harris/ Houston | CS | Tentative | $5,105,000 | 3 | CONSTRUCT 4-LANE DIVIDED ROADWAY ON NEW ALIGNMENT WITH | 0.0 |
0177-07-001 | Harris/ Houston | IH 69 | Tentative | $1,000,000 | 1 | CONSTRUCT U-TURN AT BF 1960A AND RAMP RELOCATION AT WILL | 0.0 |
0914-33-079 | Hays/ Austin | CS | Tentative | $0 | 3 | Construct Pedestrian Infrastructure | 0.0 |
0458-01-025 | Henderson/ Tyler | FM 59 | Tentative | $1,692,877 | 8 | WIDEN TO 28FT, IMPROVE DRAINAGE, UPGRADE GUARD RAIL | 0.0 |
1428-01-029 | Hidalgo/ Pharr | FM 1425 | Tentative | $0 | 8 | INSTALLATION OF FLASHING LIGHT SIGNALS | 0.0 |
0921-02-402 | Hidalgo/ Pharr | CS | Tentative | $0 | 8 | INSTALLATION OF FLASHING LIGHT SIGNALS | 0.0 |
0621-01-109 | Hidalgo/ Pharr | SH 336 | Tentative | $0 | 8 | INSTALLATION OF FLASHING LIGHT SIGNALS | 0.0 |
0039-04-129 | Hidalgo/ Pharr | BU 83-S | Tentative | $2,627,632 | 8 | IMPROVE TRAFFIC SIGNALS | 0.0 |
0902-51-030 | Hood/ Ft Worth | CS | Tentative | $250,000 | 8 | 2017 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0769-02-033 | Lamar/ Paris | FM 906 | Tentative | $2,475,000 | 1 | 2R REHABILITATION | 0.0 |
0045-09-105 | Lamar/ Paris | BU 82-H | Tentative | $1,057,836 | 8 | IMPROVE TRAFFIC SIGNALS, INTERCONNECT SIGNALS | 0.0 |
0913-29-048 | Lavaca/ Yoakum | CR | Tentative | $540,000 | 6 | REPLACE BRIDGE AND APPROACHES | 0.0 |
0074-06-230 | Nueces/ Corpus Christi | IH 37 | Tentative | $6,500,000 | 1 | MILL, UNDERSEAL AND OVERLAY | 0.0 |
0736-02-017 | Palo Pinto/ Ft Worth | FM 129 | Tentative | $129,988 | 8 | REHABILITATE EXISTING ROADWAY | 0.0 |
0649-01-022 | Palo Pinto/ Ft Worth | FM 52 | Tentative | $9,414 | 8 | REHABILITATE EXISTING ROADWAY | 0.0 |
0008-03-119 | Parker/ Ft Worth | US 180 | Tentative | $4,220,000 | 3 | PAVEMENT WIDENING, DRAINAGE & INTERSECTION IMPROVEMENTS | 0.0 |
0649-02-035 | Parker/ Ft Worth | FM 52 | Tentative | $30,000 | 8 | REHABILITATE EXISTING ROADWAY | 0.0 |
0717-01-025 | Parker/ Ft Worth | FM 113 | Tentative | $1,905,000 | 1 | Reconstruct Existing Roadway | 0.0 |
2737-01-018 | Parker/ Ft Worth | FM 2257 | Tentative | $68,550 | 8 | REHABILITATE EXISTING ROADWAY | 0.0 |
0139-03-041 | Reeves/ Odessa | US 285 | Tentative | $8,480,000 | 11 | IMPROVE PASSING & INTERSECTIONS | 0.0 |
0034-03-019 | Runnels/ San Angelo | US 83 | Tentative | $19,621,225 | 1 | ADD PASSING LANES | 0.0 |
0074-03-047 | San Patricio/ Corpus Christi | IH 37 | Tentative | $1,703,474 | 8 | INSTALL ILLUMINATION | 0.0 |
0074-05-098 | San Patricio/ Corpus Christi | IH 37 | Tentative | $70,000,000 | 1 | WIDEN ROAD - ADD LANES | 0.0 |
0910-16-142 | Smith/ Tyler | CS | Tentative | $0 | 8 | INSTALL OR IMPROVE SIGNAL DEVICE | 0.0 |
2208-01-071 | Tarrant/ Ft Worth | SS 303 | Tentative | $4,810,282 | 6 | Bridge Maintenance | 0.0 |
0902-48-579 | Tarrant/ Ft Worth | CS | Tentative | $6,141,600 | 3 | CONSTR NTP (6LNS) & WIDEN HARMON RD FR 2 TO 6 LN OVER US 287 | 0.0 |
0902-90-075 | Tarrant/ Ft Worth | CS | Tentative | $250,000 | 8 | 2017 FEDERAL RR SIGNAL PROGRAM | 0.0 |
0908-33-099 | Taylor/ Abilene | VA | Tentative | $876,747 | 3 | Construct Pedestrian Infrastructure | 0.0 |
0907-24-048 | Tom Green/ San Angelo | CS | Tentative | $2,272,852 | 3 | SIDEWALKS AND SHARED USE PATH | 0.0 |
0914-04-317 | Travis/ Austin | CS | Tentative | $22,875,000 | 3 | RECONSTRUCT FROM 4-LN TO 6-LN DIVIDED ROADWAY | 0.0 |
0024-02-075 | Uvalde/ San Antonio | US 90 | Tentative | $2,464,523 | 8 | Hazard Elimination & Safety | 0.0 |
0013-06-048 | Wise/ Ft Worth | US 81 | Tentative | $729,100 | 8 | CONSTRUCT PAVED SHOULDERS (>=5FT) | 0.0 |
0013-08-130 | Wise/ Ft Worth | US 81 | Tentative | $7,086,521 | 8 | CONSTRUCT GRADE SEPARATION AT CR 4227/CR 4228 | 0.0 |
0013-08-131 | Wise/ Ft Worth | US 81 | Tentative | $4,472,731 | 8 | CONSTRUCT GRADE SEPARATION | 0.0 |
|