Detail Letting Schedule for Galveston County (FY 2021)

Last Update: Wednesday, June 09, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Galveston County (FY 2021)

CCSJ: 0367-06-062

District:HOUSTONLet Date:Aug 2021
Highway:SH 87Let Status:Tentative
Project ID:ER 1802(624)CSJ:0367-06-062
Description:EMERGENCY RELIEFHandling
Code:
XX
Limits From:BOLIVAR FERRY N OF N HARBOR VIEW DRFund Cat:10
Limits To:.ESTIMATE:$6,655
Length:0.0Actual$0
 
Back...
Totals for 0367-06-062
Length:0
Estimate:$6,655
Actual:

CCSJ: 0912-73-212

District:HOUSTONLet Date:Jul 2021
Highway:CSLet Status:Approved
Project ID:BR 1802(833)CSJ:0912-73-212
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:MCFARLAND RD AT DRAINAGE DITCHFund Cat:6
Limits To:.ESTIMATE:$429,837
Length:0.0Actual$0
 
Proposal Request
Back...
Totals for 0912-73-212
Length:0
Estimate:$429,837
Actual:

CCSJ: 0976-03-105

District:HOUSTONLet Date:Mar 2021
Highway:FM 518Let Status:Actual
Project ID:C 976-3-105CSJ:0976-03-105
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:IH 45Fund Cat:1
Limits To:FM 270ESTIMATE:$4,518,475
Length:2.8Actual$5,323,155
 
List Showing Order
Proposal Request
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0976-03-105
Length:2.8
Estimate:$4,518,475
Actual:$5,323,155

CCSJ: 0976-03-111

District:HOUSTONLet Date:Feb 2021
Highway:FM 518Let Status:Actual
Project ID:STP 2021(344)CSJ:0976-03-111
Description:CONSTRUCT PEDESTRIAN INFRASTRUCTUREHandling
Code:
 
Limits From:FM 2351Fund Cat:10
Limits To:S OF WHISPERING PINESESTIMATE:$2,935,761
Length:1.4Actual$2,774,405
 
District:HOUSTONLet Date:Feb 2021
Highway:FM 518Let Status:Actual
Project ID:ROW 976-3-114CSJ:0976-03-114
Description:RIGHT OF WAYHandling
Code:
 
Limits From:FM 2351Fund Cat:ROW
Limits To:S OF WHISPERING PINESESTIMATE:
Length:1.4Actual$3,570
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0976-03-111
Length:2.8
Estimate:$2,935,761
Actual:$2,777,975

CCSJ: 0976-03-112

District:HOUSTONLet Date:Mar 2021
Highway:FM 518Let Status:Actual
Project ID:BR 2021(403)CSJ:0976-03-112
Description:BRIDGE MAINTENANCEHandling
Code:
 
Limits From:AT COWARTS CREEK AND CHIGGER CREEKFund Cat:6
Limits To:.ESTIMATE:$3,909,452
Length:0.0Actual$1,902,321
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0976-03-112
Length:0
Estimate:$3,909,452
Actual:$1,902,321

CCSJ: 2523-01-026

District:HOUSTONLet Date:Aug 2021
Highway:FM 2004Let Status:Approved
Project ID:C 2523-1-26CSJ:2523-01-026
Description:SURFACING/ROADWAY RESTORATIONHandling
Code:
 
Limits From:SH 6Fund Cat:1
Limits To:BRAZORIA C/LESTIMATE:$6,951,290
Length:7.0Actual$0
 
List Showing Order
Proposal Request
Back...
Totals for 2523-01-026
Length:7
Estimate:$6,951,290
Actual:

CCSJ: 3312-02-017

District:HOUSTONLet Date:Oct 2020
Highway:FM 270Let Status:Actual
Project ID:C 3312-2-17CSJ:3312-02-017
Description:HIGHWAY IMPROVEMENTHandling
Code:
 
Limits From:AT SH 96Fund Cat:1
Limits To:.ESTIMATE:$521,331
Length:0.4Actual$476,344
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 3312-02-017
Length:0.4
Estimate:$521,331
Actual:$476,344

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract