Letting Schedule for San Angelo District (FY 2021)

Last Update: Tuesday, October 05, 2021

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

San Angelo District (FY 2021)
Coke | Concho | Crockett | Edwards | Glasscock | Kimble | Menard | Runnels | Sterling | Sutton | Tom Green |

Coke County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0907-14-009CRActualApr 2021$364,8476BRIDGE REPLACEMENT0.0

Concho County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0035-04-038US 83ActualDec 2020$11,546,5691PREVENTIVE MAINTENANCE0.0

Crockett County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0140-13-021IH 10ActualJul 2021$9,322,4778HAZARD ELIMINATION & SAFETY0.0

Edwards County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0830-01-021RM 335ActualMay 2021$1,762,4041REPAIR ROADWAY0.0
0830-03-013RM 335ActualJan 2021$1,129,3691REPAIR ROADWAY0.0

Glasscock County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0463-04-024SH 158ActualJan 2021$28,510,93211HIGHWAY IMPROVEMENT8.0
0494-08-015SH 137ActualDec 2020$30,651,5341SURFACING/ROADWAY RESTORATION4.0

Kimble County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0148-03-027US 377ActualAug 2021$4,163,5768HAZARD ELIMINATION & SAFETY0.0
0907-20-005PWActualJun 2021$1,099,86010STATE PARK IMPROVEMENTS0.0
0474-01-005PR 73ActualAug 2021$2,705,63310BRIDGE REPLACEMENT0.0

Menard County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0035-05-061US 83ActualAug 2021$2,708,1386BRIDGE MAINTENANCE0.0

Runnels County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0034-03-019US 83ActualNov 2020$27,205,2951HIGHWAY IMPROVEMENT8.5

Sterling County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0069-03-060US 87ActualJul 2021$3,746,6988HAZARD ELIMINATION & SAFETY0.0

Sutton County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
0160-02-025US 277ActualFeb 2021$23,984,4021HIGHWAY IMPROVEMENT6.0
0160-01-036US 277ActualJun 2021$8,510,2411HIGHWAY IMPROVEMENT6.0

Tom Green County

CCSJHighwayLet StatusLetting
Date
Contract
Cost
Fund
Cat
DescriptionDBE Goal
2574-01-049CSActualAug 2021$373,3648TRAFFIC SIGNAL IMPROVEMENTS0.0
0907-00-197VAActualJan 2021$2,375,5791HIGHWAY IMPROVEMENT0.0
0070-02-096US 87ActualDec 2020$6,776,6391PREVENTIVE MAINTENANCE0.0
0907-00-175VAActualSep 2020$965,28511HAZARD ELIMINATION & SAFETY0.0
0907-24-048CSActualJun 2021$2,272,8523CONSTRUCT PEDESTRIAN INFRASTRUCTURE0.0
0158-02-092US 67ActualFeb 2021$1,262,3251BRIDGE MAINTENANCE0.0
0907-00-223VAActualMay 2021$1,121,5438HAZARD ELIMINATION & SAFETY0.0


Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract