Detail Letting Schedule for Dallas County (FY 2021)

Last Update: Wednesday, June 09, 2021

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Dallas County (FY 2021)

CCSJ: 0009-02-067

District:DALLASLet Date:May 2021
Highway:SH 78Let Status:Actual
Project ID:CM 2021(533)CSJ:0009-02-067
Description:INTERSECTION IMPROVEMENTHandling
Code:
 
Limits From:AT GASTON AVEFund Cat:5
Limits To:.ESTIMATE:$6,018,989
Length:0.3Actual$6,336,367
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0009-02-067
Length:0.3
Estimate:$6,018,989
Actual:$6,336,367

CCSJ: 0009-11-241

District:DALLASLet Date:Mar 2021
Highway:IH 30Let Status:Actual
Project ID:C 9-11-241CSJ:0009-11-241
Description:WIDEN ROAD - ADD LANESHandling
Code:
 
Limits From:BASS PRO DRIVEFund Cat:1
Limits To:DALROCK RDESTIMATE:109,728,865
Length:1.7Actual120,678,632
 
District:DALLASLet Date:Mar 2021
Highway:IH 30Let Status:Actual
Project ID:C 9-11-238CSJ:0009-11-238
Description:REHABILITATE EXISTING ROADWAYHandling
Code:
 
Limits From:BASS PRO DRIVE IN GARLANDFund Cat:1
Limits To:DALROCK RDESTIMATE:$21,666,876
Length:1.4Actual$13,601,005
 
District:DALLASLet Date:Mar 2021
Highway:IH 30Let Status:Actual
Project ID:C 9-12-221CSJ:0009-12-221
Description:INTERCHANGE IMPROVEMENTHandling
Code:
 
Limits From:DALROCK RD (ROCKWALL C/L)Fund Cat:1
Limits To:EAST OF DALROCK RDESTIMATE:$6,694,422
Length:0.5Actual$8,124,858
 
List Showing Order
Proposal Request
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0009-11-241
Length:3.6
Estimate:$138,090,164
Actual:$142,404,495

CCSJ: 0009-11-250

District:DALLASLet Date:Sep 2020
Highway:IH 30Let Status:Actual
Project ID:C 9-11-250CSJ:0009-11-250
Description:REHABILITATE EXISTING ROADWAYHandling
Code:
 
Limits From:HASKELL AVEFund Cat:1
Limits To:WEST OF BUCKNER BLVDESTIMATE:$15,885,060
Length:5.0Actual$13,277,123
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0009-11-250
Length:5
Estimate:$15,885,060
Actual:$13,277,123

CCSJ: 0047-07-228

District:DALLASLet Date:Feb 2021
Highway:US 75Let Status:Actual
Project ID:CM 2021(434)CSJ:0047-07-228
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
 
Limits From:AT NORTHAVEN RDFund Cat:3
Limits To:.ESTIMATE:$6,068,922
Length:0.1Actual$3,844,283
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:CM 2021(434)CSJ:0918-47-242
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
 
Limits From:NORTHAVEN TR FROM W OF US 75Fund Cat:3
Limits To:E OF US 75 WHITE ROCK CR /COTTONWOOD TRESTIMATE:$4,392,745
Length:0.5Actual$5,450,960
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0047-07-228
Length:0.6
Estimate:$10,461,667
Actual:$9,295,242

CCSJ: 0048-01-067

District:DALLASLet Date:May 2021
Highway:SH 342Let Status:Actual
Project ID:F 2021(501)CSJ:0048-01-067
Description:LANDSCAPE DEVELOPMENTHandling
Code:
LC
Limits From:CEDARDALE RDFund Cat:3
Limits To:ALEXANDER AVEESTIMATE:$2,170,456
Length:0.0Actual$1,307,026
 
Back...
Totals for 0048-01-067
Length:0
Estimate:$2,170,456
Actual:$1,307,026

CCSJ: 0092-01-057

District:DALLASLet Date:Nov 2020
Highway:SH 310Let Status:Actual
Project ID:BR 2021(105)CSJ:0092-01-057
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT LAMAR ST AND UNION PACIFIC RRFund Cat:6
Limits To:.ESTIMATE:$13,853,637
Length:0.6Actual$13,814,473
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0092-01-057
Length:0.6
Estimate:$13,853,637
Actual:$13,814,473

CCSJ: 0092-14-099

District:DALLASLet Date:Aug 2021
Highway:IH 45Let Status:Approved
Project ID:F 2021(905)CSJ:0092-14-099
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:1 MILE SOUTH OF IH 20Fund Cat:8
Limits To:OVERTON RDESTIMATE:$1,762,096
Length:5.3Actual$0
 
Back...
Totals for 0092-14-099
Length:5.3
Estimate:$1,762,096
Actual:

CCSJ: 0196-03-274

District:DALLASLet Date:Aug 2021
Highway:IH 35ELet Status:Tentative
Project ID:NH ( )CSJ:0196-03-274
Description:CONSTRUCT NEW ROADWAY LANESHandling
Code:
DB
Limits From:IH 635Fund Cat:1
Limits To:DENTON COUNTY LINEESTIMATE:614,317,018
Length:6.4Actual$0
 
District:DALLASLet Date:Aug 2021
Highway:IH 35ELet Status:Tentative
Project ID:CSJ:0196-03-282
Description:RECONSTRUCT EXISTING ROADWAYHandling
Code:
DB
Limits From:IH 635Fund Cat:1
Limits To:DENTON COUNTY LINEESTIMATE:$93,951,732
Length:0.0Actual$0
 
Back...
Totals for 0196-03-274
Length:6.4
Estimate:$708,268,750
Actual:

CCSJ: 0196-06-033

District:DALLASLet Date:Dec 2020
Highway:SL 354Let Status:Actual
Project ID:STP 2021(151)HESCSJ:0196-06-033
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:AT WILLOWBROOK RDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$366,165
Length:0.2Actual$351,679
 
District:DALLASLet Date:Dec 2020
Highway:SL 12Let Status:Actual
Project ID:STP 2021(151)HESCSJ:0353-04-110
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:AT LOMBARDY LN / TECHNOLOGY BLVDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$326,752
Length:0.2Actual$315,362
 
District:DALLASLet Date:Dec 2020
Highway:SL 12Let Status:Actual
Project ID:STP 2021(151)HESCSJ:0353-05-123
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:AT SS 244Fund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$324,270
Length:0.2Actual$300,530
 
District:DALLASLet Date:Dec 2020
Highway:SH 352Let Status:Actual
Project ID:STP 2021(151)HESCSJ:0430-01-063
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:AT JIM MILLER RDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$233,158
Length:0.2Actual$212,167
 
District:DALLASLet Date:Dec 2020
Highway:SL 12Let Status:Actual
Project ID:STP 2021(151)HESCSJ:0581-01-155
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:AT MARSALIS AVEFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$277,457
Length:0.2Actual$260,264
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0196-06-033
Length:1
Estimate:$1,527,802
Actual:$1,440,000

CCSJ: 0197-02-124

District:DALLASLet Date:Oct 2020
Highway:US 175Let Status:Actual
Project ID:C 197-2-124CSJ:0197-02-124
Description:CONSTRUCT RAMPSHandling
Code:
 
Limits From:EAST OF E. MALLOY BRIDGE RDFund Cat:1
Limits To:KAUFMAN COUNTY LINEESTIMATE:$1,012,040
Length:0.7Actual$907,339
 
District:DALLASLet Date:Oct 2020
Highway:US 175Let Status:Actual
Project ID:C 197-3-74CSJ:0197-03-074
Description:CONSTRUCT RAMPSHandling
Code:
 
Limits From:DALLAS COUNTY LINEFund Cat:1
Limits To:WEST OF FM 1389ESTIMATE:$1,498,391
Length:0.7Actual$1,238,789
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0197-02-124
Length:1.4
Estimate:$2,510,431
Actual:$2,146,128

CCSJ: 0197-02-132

District:DALLASLet Date:Aug 2021
Highway:US 175Let Status:Approved
Project ID:F 2021(907)CSJ:0197-02-132
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:SH 310Fund Cat:8
Limits To:MALLOY BRIDGE RDESTIMATE:$1,801,910
Length:15.1Actual$0
 
District:DALLASLet Date:Aug 2021
Highway:SH 114Let Status:Approved
Project ID:F 2021(918)CSJ:0353-02-081
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:WISE COUNTY LINEFund Cat:8
Limits To:DOUBLE EAGLE BLVDESTIMATE:$80,364
Length:5.8Actual$0
 
District:DALLASLet Date:Aug 2021
Highway:IH 35ELet Status:Approved
Project ID:F 2021(907)CSJ:0442-02-167
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:ELLIS COUNTY LINEFund Cat:8
Limits To:ANN ARBOR AVE.ESTIMATE:$80,228
Length:9.9Actual$0
 
District:DALLASLet Date:Aug 2021
Highway:FM 1382Let Status:Approved
Project ID:F 2021(918)CSJ:1047-03-075
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:IH 20Fund Cat:8
Limits To:EAGLE FORD DRESTIMATE:$19,461
Length:2.1Actual$0
 
District:DALLASLet Date:Aug 2021
Highway:IH 30Let Status:Approved
Project ID:F 2021(907)CSJ:1068-04-177
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:TARRANT COUNTY LINEFund Cat:8
Limits To:HAMPTON RDESTIMATE:$97,345
Length:0.0Actual$0
 
Back...
Totals for 0197-02-132
Length:32.9
Estimate:$2,079,308
Actual:

CCSJ: 0581-01-159

District:DALLASLet Date:Jun 2021
Highway:SL 12Let Status:Actual
Project ID:F 2021(609)CSJ:0581-01-159
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:IH 35EFund Cat:8
Limits To:FERGUSON RDESTIMATE:$2,164,069
Length:16.0Actual$1,681,803
 
District:DALLASLet Date:Jun 2021
Highway:SH 352Let Status:Actual
Project ID:F 2021(609)CSJ:0430-01-064
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
 
Limits From:RENDA STFund Cat:8
Limits To:URBAN AVEESTIMATE:$312,875
Length:0.5Actual$242,739
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Back...
Totals for 0581-01-159
Length:16.5
Estimate:$2,476,944
Actual:$1,924,542

CCSJ: 0581-02-151

District:DALLASLet Date:Jul 2021
Highway:SL 12Let Status:Approved
Project ID:C 581-2-151CSJ:0581-02-151
Description:REHABILITATE EXISTING ROADWAYHandling
Code:
 
Limits From:SOUTHERN IRVING CITY LIMITSFund Cat:1
Limits To:ELM FORK TRINITY RIVERESTIMATE:$5,522,097
Length:5.2Actual$0
 
Proposal Request
Back...
Totals for 0581-02-151
Length:5.2
Estimate:$5,522,097
Actual:

CCSJ: 0918-00-277

District:DALLASLet Date:Apr 2021
Highway:VALet Status:Actual
Project ID:C 918-00-277CSJ:0918-00-277
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:VARIOUS LOCATIONSFund Cat:1
Limits To:.ESTIMATE:$300,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-277
Length:0
Estimate:$300,000
Actual:

CCSJ: 0918-00-285

District:DALLASLet Date:Oct 2020
Highway:VALet Status:Actual
Project ID:C 918-00-285CSJ:0918-00-285
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:VARIOUS LOCATIONSFund Cat:3
Limits To:.ESTIMATE:$670,000
Length:0.0Actual$670,000
 
Back...
Totals for 0918-00-285
Length:0
Estimate:$670,000
Actual:$670,000

CCSJ: 0918-00-297

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Tentative
Project ID:CM ( )CSJ:0918-00-297
Description:AIR QUALITY INITIATIVEHandling
Code:
XX
Limits From:M & O AIR QUAL. PUB ED & OUTREACH 2021Fund Cat:5
Limits To:IMP STR COMM EFFORTS TO EDU AND INFORMESTIMATE:$1,560,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-297
Length:0
Estimate:$1,560,000
Actual:

CCSJ: 0918-00-304

District:DALLASLet Date:Sep 2020
Highway:VALet Status:Actual
Project ID:STP 2021(204)MMCSJ:0918-00-304
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:CONGESTION MGMT/ASSET INFO PLANNING TOOLFund Cat:3
Limits To:DEVELOP TOOL TO INTEGRATE DATAESTIMATE:$409,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-304
Length:0
Estimate:$409,000
Actual:

CCSJ: 0918-00-308

District:DALLASLet Date:Sep 2020
Highway:VALet Status:Actual
Project ID:STP 2021(200)MMCSJ:0918-00-308
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:REGIONAL PARKING MGMT TOOLS & STRGY PROGFund Cat:3
Limits To:.ESTIMATE:$520,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-308
Length:0
Estimate:$520,000
Actual:

CCSJ: 0918-00-309

District:DALLASLet Date:Oct 2020
Highway:VALet Status:Actual
Project ID:STP 2021(270)MMCSJ:0918-00-309
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:LU, BIKE/PEDESTRIAN SAFETY PROGRAMFund Cat:3
Limits To:TRANSIT ORIENTED DEV., REGIONAL PED SAFEESTIMATE:$749,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-309
Length:0
Estimate:$749,000
Actual:

CCSJ: 0918-00-312

District:DALLASLet Date:Oct 2020
Highway:VALet Status:Actual
Project ID:STP 2021(205)MMCSJ:0918-00-312
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:SMART TRANSIT CORRIDORS & WALKABLE PLACEFund Cat:3
Limits To:.ESTIMATE:$1,144,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-312
Length:0
Estimate:$1,144,000
Actual:

CCSJ: 0918-00-317

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Tentative
Project ID:STP ( )MMCSJ:0918-00-317
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:REGIONAL AIR QUALITY INITIATIVESFund Cat:3
Limits To:IDENTIFY & IMPL POLICIES/BEST PRAC FY21ESTIMATE:$2,543,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-317
Length:0
Estimate:$2,543,000
Actual:

CCSJ: 0918-00-326

District:DALLASLet Date:May 2021
Highway:VALet Status:Actual
Project ID:C 918-00-326CSJ:0918-00-326
Description:REHAB OF TRAFFIC MANAGEMENTHandling
Code:
 
Limits From:VARIOUS LOCATIONSFund Cat:1
Limits To:IN THE DALLAS DISTRICTESTIMATE:$285,848
Length:0.0Actual$202,387
 
District:DALLASLet Date:May 2021
Highway:VALet Status:Actual
Project ID:C 918-00-361CSJ:0918-00-361
Description:ADVANCED TRAFFIC MANAGEMENT SYSTEM CONNECTIONHandling
Code:
 
Limits From:VARIOUS INTERSECTIONSFund Cat:1
Limits To:IN THE DALLAS DISTRICTESTIMATE:$1,858,769
Length:0.0Actual$1,447,179
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0918-00-326
Length:0
Estimate:$2,144,617
Actual:$1,649,566

CCSJ: 0918-00-328

District:DALLASLet Date:Sep 2020
Highway:VALet Status:Actual
Project ID:STP 2B20(253)CSJ:0918-00-328
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:VARIOUS LOCATIONSFund Cat:1
Limits To:IN THE DALLAS DISTRICTESTIMATE:$2,483,550
Length:0.0Actual$2,315,000
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0918-00-328
Length:0
Estimate:$2,483,550
Actual:$2,315,000

CCSJ: 0918-00-343

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Tentative
Project ID:STP ( )MMCSJ:0918-00-343
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:DART VANPOOL PROGRAMFund Cat:3
Limits To:.ESTIMATE:$4,178,751
Length:0.0Actual$0
 
Back...
Totals for 0918-00-343
Length:0
Estimate:$4,178,751
Actual:

CCSJ: 0918-00-345

District:DALLASLet Date:Nov 2020
Highway:VALet Status:Actual
Project ID:STP 2021(376)MMCSJ:0918-00-345
Description:TRANSPORTATION NON-ROADWAYHandling
Code:
XX
Limits From:REGIONAL MOBILITY ASSISTANCE PATROLFund Cat:7
Limits To:(FY 2021)ESTIMATE:$4,250,000
Length:0.0Actual$4,250,000
 
Back...
Totals for 0918-00-345
Length:0
Estimate:$4,250,000
Actual:$4,250,000

CCSJ: 0918-00-347

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Tentative
Project ID:STP 2021(908)MMCSJ:0918-00-347
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
XX
Limits From:LU, BIKE/PEDESTRIAN SAFETY PROGRAMFund Cat:3
Limits To:TOD, REGIONAL PEDESTRIAN SAFETY -FY2021ESTIMATE:$1,503,000
Length:0.0Actual$0
 
Back...
Totals for 0918-00-347
Length:0
Estimate:$1,503,000
Actual:

CCSJ: 0918-00-353

District:DALLASLet Date:Oct 2020
Highway:VALet Status:Actual
Project ID:CM 2021(085)CSJ:0918-00-353
Description:TRAFFIC SURVEILLANCEHandling
Code:
 
Limits From:DIGITAL VIDEO PROJECTFund Cat:1
Limits To:.ESTIMATE:$1,342,842
Length:0.0Actual$1,052,808
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0918-00-353
Length:0
Estimate:$1,342,842
Actual:$1,052,808

CCSJ: 0918-00-360

District:DALLASLet Date:Sep 2020
Highway:VALet Status:Actual
Project ID:C 918-00-360CSJ:0918-00-360
Description:HIGHWAY IMPROVEMENTHandling
Code:
 
Limits From:VARIOUS LOCATIONSFund Cat:1
Limits To:IN THE DALLAS DISTRICTESTIMATE:$2,880,470
Length:0.0Actual$1,646,741
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0918-00-360
Length:0
Estimate:$2,880,470
Actual:$1,646,741

CCSJ: 0918-47-072

District:DALLASLet Date:Dec 2020
Highway:CSLet Status:Actual
Project ID:STP 2021(324)MMCSJ:0918-47-072
Description:INSTALL RAISED MEDIANHandling
Code:
LC
Limits From:8 INTERSECTIONS AT KCS RR IN DALLASFund Cat:3
Limits To:AT E DALLAS/KSC RR CROSSING, PEAVY RDESTIMATE:$2,260,000
Length:0.0Actual$479,493
 
Back...
Totals for 0918-47-072
Length:0
Estimate:$2,260,000
Actual:$479,493

CCSJ: 0918-47-096

District:DALLASLet Date:Jul 2021
Highway:FDLet Status:Approved
Project ID:C 918-47-96CSJ:0918-47-096
Description:STATE PARK IMPROVEMENTSHandling
Code:
 
Limits From:ON WEST SPINE ROADFund Cat:10
Limits To:WITHIN THE CEDAR HILL STATE PARKESTIMATE:$4,405,761
Length:4.3Actual$0
 
Proposal Request
Back...
Totals for 0918-47-096
Length:4.3
Estimate:$4,405,761
Actual:

CCSJ: 0918-47-199

District:DALLASLet Date:Dec 2020
Highway:CSLet Status:Actual
Project ID:STP 2021(421)FRS1CSJ:0918-47-199
Description:RAILROAD CROSSING IMPROVEMENTSHandling
Code:
XX
Limits From:CEDAR SPRINGS RD IN DALLASFund Cat:8
Limits To:AT DGNO DOT # 414 842TESTIMATE:$254,268
Length:0.0Actual$254,268
 
Back...
Totals for 0918-47-199
Length:0
Estimate:$254,268
Actual:$254,268

CCSJ: 0918-47-200

District:DALLASLet Date:Dec 2020
Highway:CSLet Status:Actual
Project ID:STP 2021(421)FRS1CSJ:0918-47-200
Description:RAILROAD CROSSING IMPROVEMENTSHandling
Code:
XX
Limits From:MARKET CENTER BLVD IN DALLASFund Cat:8
Limits To:AT TRE DOT# 597 759WESTIMATE:$433,821
Length:0.0Actual$433,821
 
Back...
Totals for 0918-47-200
Length:0
Estimate:$433,821
Actual:$433,821

CCSJ: 0918-47-202

District:DALLASLet Date:Aug 2021
Highway:CSLet Status:Approved
Project ID:STP 2021(789)TPCSJ:0918-47-202
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
LC
Limits From:S CLARK RD TR VELOWEB;RED OAK CR TRFund Cat:3
Limits To:E BELT LINE RDESTIMATE:$1,316,439
Length:0.0Actual$0
 
Back...
Totals for 0918-47-202
Length:0
Estimate:$1,316,439
Actual:

CCSJ: 0918-47-203

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Approved
Project ID:STP 1902(089)TPCSJ:0918-47-203
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
LC
Limits From:FM 1382 & CAMP WISDOM INTERSECTIONFund Cat:3
Limits To:MANSFIELD RDESTIMATE:$2,036,189
Length:0.0Actual$0
 
Back...
Totals for 0918-47-203
Length:0
Estimate:$2,036,189
Actual:

CCSJ: 0918-47-205

District:DALLASLet Date:Sep 2020
Highway:VALet Status:Actual
Project ID:STP 2021(069)TPCSJ:0918-47-205
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
LC
Limits From:@ MARKET CENTER BLVD & TURTLE CREEKFund Cat:3
Limits To:INWOOD/LOVE FIELD DART STATIONESTIMATE:$6,250,000
Length:0.0Actual$5,498,972
 
Back...
Totals for 0918-47-205
Length:0
Estimate:$6,250,000
Actual:$5,498,972

CCSJ: 0918-47-212

District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-212
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:ZANGS BLVD AT CLARENDEN DRFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$270,742
Length:0.0Actual$272,656
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-213
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:JEFFERSON BLVD AT MARSALIS AVEFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$253,453
Length:0.0Actual$253,796
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-214
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:LAKE JUNE RD AT MASTERS DRFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$290,994
Length:0.0Actual$299,364
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-216
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:POLK ST AT REDBIRD LNFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$261,015
Length:0.0Actual$259,677
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-219
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:JEFFERSON BLVD AT CRAWFORD STFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$195,202
Length:0.0Actual$193,006
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-220
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:WESTMORELAND RD AT GANNON LNFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$257,100
Length:0.0Actual$259,812
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-47-223
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:CAMP WISDOM RD AT HAMPTON RDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$287,190
Length:0.0Actual$295,427
 
District:DALLASLet Date:Apr 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(496)HESCSJ:0918-48-002
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:BECKLEY AVE AT CLARENDON DRFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$210,234
Length:0.0Actual$206,262
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0918-47-212
Length:0
Estimate:$2,025,929
Actual:$2,040,000

CCSJ: 0918-47-215

District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-215
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:OATES DR AT LA PRADA DRFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$245,950
Length:0.2Actual$224,330
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-217
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:GASTON AVE AT MUNGER BLVDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$298,655
Length:0.2Actual$276,108
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-218
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:FOREST LN AT MARSH LNFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$308,664
Length:0.2Actual$288,474
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-221
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:FAIR OAKS AVE AT PINELAND DRFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$239,344
Length:0.0Actual$220,084
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-222
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:CESAR CHAVEZ BLVD AT HICKORY STFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$224,543
Length:0.2Actual$205,208
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-224
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:MLK BLVD AT ATLANTA STFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$209,804
Length:0.2Actual$189,929
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-225
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:HASKELL AVE AT CAPITOL AVEFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$260,426
Length:0.0Actual$231,845
 
District:DALLASLet Date:Feb 2021
Highway:CSLet Status:Actual
Project ID:STP 2021(337)HESCSJ:0918-47-226
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
 
Limits From:ARAPAHO RD AT HILLCREST RDFund Cat:3
Limits To:IN THE CITY OF DALLASESTIMATE:$272,305
Length:0.0Actual$250,423
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0918-47-215
Length:1
Estimate:$2,059,691
Actual:$1,886,400

CCSJ: 0918-47-279

District:DALLASLet Date:Jan 2021
Highway:VALet Status:Actual
Project ID:STP 2021(279)CSJ:0918-47-279
Description:CONSTRUCT PEDESTRIAN INFRASTRUCTUREHandling
Code:
 
Limits From:VARIOUS INTERSECTIONSFund Cat:10
Limits To:IN THE DALLAS COUNTYESTIMATE:$1,723,808
Length:0.1Actual$1,649,367
 
District:DALLASLet Date:Jan 2021
Highway:VALet Status:Actual
Project ID:STP 2021(279)CSJ:0918-25-026
Description:CONSTRUCT PEDESTRIAN INFRASTRUCTUREHandling
Code:
 
Limits From:VARIOUS INTERSECTIONSFund Cat:10
Limits To:IN THE ROCKWALL COUNTYESTIMATE:$507,337
Length:0.1Actual$476,245
 
Proposal Request
Bid List
List Showing Order
Bid Tabulations
Award Status
Back...
Totals for 0918-47-279
Length:0.2
Estimate:$2,231,145
Actual:$2,125,612

CCSJ: 0918-47-290

District:DALLASLet Date:May 2021
Highway:VALet Status:Actual
Project ID:CM 2021(661)CSJ:0918-47-290
Description:TRAFFIC SIGNAL IMPROVEMENTSHandling
Code:
LC
Limits From:ON WINTERGREEN ROADFund Cat:3
Limits To:AT NEW CLARK RDESTIMATE:$350,000
Length:0.0Actual$309,600
 
Back...
Totals for 0918-47-290
Length:0
Estimate:$350,000
Actual:$309,600

CCSJ: 0918-48-003

District:DALLASLet Date:Feb 2021
Highway:VALet Status:Actual
Project ID:STP 2021(322)TPCSJ:0918-48-003
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
TR
Limits From:DFW AIRPORT N COTTON BELT STATIONFund Cat:5
Limits To:SHILOH COTTON BELT STATIONESTIMATE:$14,980,000
Length:0.1Actual$0
 
Back...
Totals for 0918-48-003
Length:0.1
Estimate:$14,980,000
Actual:

CCSJ: 0918-48-004

District:DALLASLet Date:Aug 2021
Highway:VALet Status:Tentative
Project ID:CSJ:0918-48-004
Description:BICYCLE AND PEDESTRIAN IMPROVEMENTSHandling
Code:
TR
Limits From:DFW AIRPORT N COTTON BELT STATIONFund Cat:3
Limits To:SHILOH COTTON BELT STATIONESTIMATE:$14,001,990
Length:0.1Actual$0
 
Back...
Totals for 0918-48-004
Length:0.1
Estimate:$14,001,990
Actual:

CCSJ: 2374-02-156

District:DALLASLet Date:Jul 2021
Highway:IH 635Let Status:Approved
Project ID:F 2021(732)CSJ:2374-02-156
Description:REHABILITATE EXISTING ROADWAYHandling
Code:
 
Limits From:IH 20Fund Cat:1
Limits To:IH 30ESTIMATE:$12,190,624
Length:8.2Actual$0
 
Proposal Request
Back...
Totals for 2374-02-156
Length:8.2
Estimate:$12,190,624
Actual:

CCSJ: 2374-03-074

District:DALLASLet Date:May 2021
Highway:IH 20Let Status:Actual
Project ID:STP 2021(539)MMCSJ:2374-03-074
Description:WIDEN BRIDGEHandling
Code:
 
Limits From:AT BONNIE VIEW RDFund Cat:3
Limits To:IN CITY OF DALLASESTIMATE:$2,425,559
Length:0.0Actual$3,246,151
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 2374-03-074
Length:0
Estimate:$2,425,559
Actual:$3,246,151

CCSJ: 2964-10-008

District:DALLASLet Date:Jul 2021
Highway:SL 9Let Status:Approved
Project ID:F 2021(858)CSJ:2964-10-008
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:I-35EFund Cat:1
Limits To:DALLAS/ELLIS COUNTY LINEESTIMATE:$26,290,370
Length:5.6Actual$0
 
District:DALLASLet Date:Jul 2021
Highway:IH 45Let Status:Approved
Project ID:F 2021(791)CSJ:0092-02-130
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:AT SL 9Fund Cat:1
Limits To:.ESTIMATE:$4,601,441
Length:1.1Actual$0
 
District:DALLASLet Date:Jul 2021
Highway:SL 9Let Status:Approved
Project ID:F 2021(859)CSJ:2964-10-009
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:ELLIS/DALLAS COUNTY LINEFund Cat:1
Limits To:I-45ESTIMATE:$59,980,365
Length:3.2Actual$0
 
District:DALLASLet Date:Jul 2021
Highway:SL 9Let Status:Approved
Project ID:F 2021(860)CSJ:2964-12-001
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:I-35EFund Cat:1
Limits To:DALLAS COUNTY LINEESTIMATE:$4,865,169
Length:1.0Actual$0
 
District:DALLASLet Date:Jul 2021
Highway:SL 9Let Status:Approved
Project ID:F 2021(861)CSJ:2964-12-002
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:DALLAS/ELLIS COUNTY LINEFund Cat:1
Limits To:ELLIS/DALLAS COUNTY LINEESTIMATE:$5,199,791
Length:1.2Actual$0
 
Back...
Totals for 2964-10-008
Length:12.1
Estimate:$100,937,137
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract