Detail Letting Schedule for Kaufman County (FY 2021)

Last Update: Monday, November 16, 2020

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Kaufman County (FY 2021)

CCSJ: 0173-04-058

District:DALLASLet Date:Jun 2021
Highway:SH 34Let Status:Tentative
Project ID:CM 2021(335)CSJ:0173-04-058
Description:INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANESHandling
Code:
 
Limits From:AT KINGS CREEK DRIVEFund Cat:5
Limits To:.ESTIMATE:$746,776
Length:0.2Actual$0
 
District:DALLASLet Date:Jun 2021
Highway:SH 34Let Status:Tentative
Project ID:CSJ:0173-01-050
Description:INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANESHandling
Code:
 
Limits From:1200' WEST OF NOVY RDFund Cat:8
Limits To:600' EAST OF NOVY RDESTIMATE:$678,000
Length:0.6Actual$0
 
District:DALLASLet Date:Jun 2021
Highway:SH 34Let Status:Tentative
Project ID:CSJ:0568-01-054
Description:INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TURN LANESHandling
Code:
 
Limits From:1025' EAST OF CR 682 (HIGH VIEW ROAD)Fund Cat:8
Limits To:500' WEST OF CR 682 (HIGH VIEW ROAD)ESTIMATE:$172,000
Length:0.3Actual$0
 
Back...
Totals for 0173-04-058
Length:1.1
Estimate:$1,596,776
Actual:

CCSJ: 0173-04-060

District:DALLASLet Date:Feb 2021
Highway:SH 34Let Status:Approved
Project ID:STP 2021(336)CSJ:0173-04-060
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:AT FM 2728Fund Cat:8
Limits To:.ESTIMATE:$825,000
Length:0.5Actual$0
 
District:DALLASLet Date:Feb 2021
Highway:FM 548Let Status:Approved
Project ID:STP 2021(336)CSJ:1014-02-045
Description:HAZARD ELIMINATION & SAFETYHandling
Code:
 
Limits From:NORTH OF SH 276Fund Cat:8
Limits To:0.20 MILE NORTH OF MUNSON RDESTIMATE:$825,000
Length:0.2Actual$0
 
Back...
Totals for 0173-04-060
Length:0.7
Estimate:$1,650,000
Actual:

CCSJ: 0197-03-054

District:DALLASLet Date:Oct 2020
Highway:US 175Let Status:Actual
Project ID:C 197-3-54CSJ:0197-03-054
Description:CONSTRUCT FRONTAGE ROADSHandling
Code:
 
Limits From:FM 148Fund Cat:11
Limits To:CR 4106 IN CRANDALLESTIMATE:$13,198,381
Length:2.8Actual$12,972,961
 
Proposal Request
List Showing Order
Bid List
Addenda
Bid Tabulations
Award Status
Back...
Totals for 0197-03-054
Length:2.8
Estimate:$13,198,381
Actual:$12,972,961

CCSJ: 0197-03-076

District:DALLASLet Date:Jun 2021
Highway:US 175Let Status:Tentative
Project ID:NH ( )CSJ:0197-03-076
Description:REMOVE/REPLACE BRIDGE RAILHandling
Code:
 
Limits From:VARIOUS LOCATIONS FROM DALLAS C/LFund Cat:6
Limits To:FM 1390ESTIMATE:$1,921,262
Length:6.8Actual$0
 
District:DALLASLet Date:Jun 2021
Highway:US 175Let Status:Tentative
Project ID:BR ( )CSJ:0197-04-081
Description:REMOVE/REPLACE BRIDGE RAILHandling
Code:
 
Limits From:AT LITTLE COTTONWOOD CREEKFund Cat:6
Limits To:.ESTIMATE:$191,924
Length:0.1Actual$0
 
Back...
Totals for 0197-03-076
Length:6.9
Estimate:$2,113,186
Actual:

CCSJ: 0918-11-096

District:DALLASLet Date:Nov 2020
Highway:CRLet Status:Actual
Project ID:BR 1902(106)CSJ:0918-11-096
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT SOUTH DRAWFund Cat:6
Limits To:.ESTIMATE:$442,262
Length:0.1Actual$425,983
 
District:DALLASLet Date:Nov 2020
Highway:CRLet Status:Actual
Project ID:BR 1902(117)CSJ:0918-11-098
Description:BRIDGE REPLACEMENTHandling
Code:
 
Limits From:AT NORTH DRAWFund Cat:6
Limits To:.ESTIMATE:$439,583
Length:0.1Actual$413,537
 
Proposal Request
List Showing Order
Bid List
Bid Tabulations
Award Status
Back...
Totals for 0918-11-096
Length:0.2
Estimate:$881,845
Actual:$839,520

CCSJ: 2982-01-007

District:DALLASLet Date:Feb 2021
Highway:FM 1390Let Status:Approved
Project ID:C 2982-1-7CSJ:2982-01-007
Description:ADDING SHOULDERS WITH NO ADDED CAPACITYHandling
Code:
 
Limits From:SH 34Fund Cat:1
Limits To:FM 148ESTIMATE:$7,865,433
Length:5.5Actual$0
 
Back...
Totals for 2982-01-007
Length:5.5
Estimate:$7,865,433
Actual:

Handling CodeDefinition
XXProject not processed through statewide letting
TRTransfer of funds
LCProject let through local entity
LCProject not charged against district apportionment



Let StatusDefinition
TentativeEstimated letting date for this project
ApprovedProject has administrative approval to be let
ActualProject was let to contract