Monthly State Let Construction Report For Houston District As Of Jan 11, 2017 Page 8 Of 10

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayCS
FromMEMORIAL DR AT DRAINAGE DITCH
To.
CSJ0912-72-285
Proj IDBR 2012(397)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.001548724.86399482.6380.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-03-15
Work Began04-11-16
Work Completed
Time Computed09-30-15
Contract Working Days90
Addl Days Granted0
Working Days Charged160
Percent Time Used177
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-285
ROADSAFE TRAFFIC SYSTEMS, INC. (1.55)
EPCS ENVIRONMENTAL, LLC (4.61)
NACC, INC. (26.31)
GROUND HOG FOUNDATION DRILLING (0.58)
Contract #02153015
Totals548724.860.00399482.6380.5

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS CNTY
To.
CSJ0912-72-294
Proj IDNH 2016(269)
Work TypeRECON CONC APPR, DRAIN IMP
 
10.5711678207.721773678.5199.9
Work Order03-24-16
Work Began05-13-16
Work Completed
Time Computed04-23-16
Contract Working Days190
Addl Days Granted0
Working Days Charged185
Percent Time Used97
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-294
CHERRY DEMOLITION (0.99)
Contract #11153037
Totals1678207.72406.801773678.5199.9

CountyHARRIS
HighwayCS
FromHEMPSTEAD RD, FROM E OF LONG POINT
ToWEST OF WEST LITTLE YORK ROAD
CSJ0912-72-296
Proj IDSTP 2017(440)
Work TypeINTERSECTION IMPROVEMENTS
 
1.3164496496.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-296
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163220
Totals4496496.000.000.000.0

CountyHARRIS
HighwayVA
FromON FM 270 FROM NASA ROAD 1
ToHENDERSON ROAD
CSJ0912-72-302
Proj IDSTP 2014(138)TE
Work TypeSHARED USE PATH
 
1.9021755575.5015637.280.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-15
Work Began00-00-00
Work Completed
Time Computed10-05-15
Contract Working Days150
Addl Days Granted0
Working Days Charged36
Percent Time Used24
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-302
BATTERSON,LLP (2.94)
GEORGE MEEKS LANDPRO, INC. (3.12)
J KRU LAND SERVICES, LLC (0.78)
CURB PLANET INC. (0.11)
Contract #05153226
Totals1755575.500.0015637.280.8

CountyHARRIS
HighwayVA
FromFALLS STREET
ToLOCKWOOD DRIVE
CSJ0912-72-315
Proj IDSTP 2014(142)TE
Work TypeCONSTRUCT MULTI-USE PATH
 
0.8671323726.00560711.2942.3
Work Order06-22-16
Work Began08-10-16
Work Completed
Time Computed07-22-16
Contract Working Days136
Addl Days Granted0
Working Days Charged22
Percent Time Used16
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-315
SPECIALTY DRILLING, LTD. (1.17)
Contract #04163021
Totals1323726.0042643.90560711.2942.3

CountyHARRIS
HighwayVA
FromAT HERMANN PARK/BRAYS BAYOU TRAIL
ToFROM ALMEDA RD TO HOLCOMBE BLVD
CSJ0912-72-319
Proj IDSTP 2014(141)TE
Work TypeCONSTRUCT MULTI-USE PATH CONNECTORS
 
0.467792114.50242640.2230.6
Work Order07-27-16
Work Began10-17-16
Work Completed
Time Computed10-25-16
Contract Working Days151
Addl Days Granted0
Working Days Charged43
Percent Time Used28
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-319
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05163231
Totals792114.5021829.50242640.2230.6

CountyHARRIS
HighwayCR
FromWEST LAKE HOUSTON PKWY, FROM UPRR
ToWILL CLAYTON PKWY
CSJ0912-72-335
Proj IDCC 912-72-335
Work TypeITS FOR HIGH DEMAND ARTERIAL STREET
 
0.0011789743.301126799.7762.9
Work Order05-16-16
Work Began09-06-16
Work Completed
Time Computed09-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged93
Percent Time Used46
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-335
STRIPE-A-LINE, INC. (1.88)
SOUTH RANGER CONSTRUCTION, INC. (9.79)
MENADE, INC. (15.51)
Contract #12153013
Totals1789743.30312488.451126799.7762.9

CountyGALVESTON
HighwayVA
FromAT GALVESTON FERRY OFFICE
To.
CSJ0912-73-203
Proj IDC 912-73-203
Work TypeRENO OF GALV-BOL FERRY MAINT BLDG
 
0.0011529400.001634381.9399.9
Work Order12-02-15
Work Began12-16-15
Work Completed
Time Computed12-16-15
Contract Working Days180
Addl Days Granted155
Working Days Charged249
Percent Time Used74
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-203
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07153261
Totals1529400.00402095.921634381.9399.9

CountyGALVESTON
HighwayVA
FromAT GALVESTON FERRY
To.
CSJ0912-73-205
Proj IDFT 912-73-205
Work TypeRECON OF FERRY BULKHEAD & WORK DOCK
 
0.00121325783.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days450
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-205
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163006
Totals21325783.000.000.000.0

CountyHARRIS
HighwayFM 865
FromALMEDA-GENOA
ToBW 8
CSJ0976-01-019
Proj IDC 976-1-19
Work TypeGR, BS & SURF
 
1.27213285921.449829787.8673.9
Work Order02-12-14
Work Began09-28-15
Work Completed
Time Computed11-09-14
Contract Working Days305
Addl Days Granted8
Working Days Charged226
Percent Time Used72
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
INTERSTATE BARRICADES & MARKINGS, INC. (0.15)
BREDA COMPANY, INC. (0.56)
CPAV SPECIALTIES, LP (0.20)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (2.48)
JOHN REED AND COMPANY, LLC (7.70)
PEREZ CONSTRUCTION CO. (2.23)
TEXOP CONSTRUCTION (1.40)
DURWOOD GREENE CONSTRUCTION CO. (1.87)
ROSALES TRUCKING (2.32)
NATIONAL DEWATERING SYSTEMS (0.15)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.99)
RAY"S THREADING AND FAB SHOP (0.28)
ABLE PAVING (0.09)
INTERSTATE BARRICADES & MARKINGS, INC. (0.78)
BORTUNCO (0.11)
MICKIE SERVICE, INC. (0.51)
TRAF-TEX, INC. (0.07)
Contract #11133025
Totals13285921.44250021.749829787.8673.9

CountyBRAZORIA
HighwayFM 518
FromFM 865
ToSAN ANTONIO ST
CSJ0976-02-091
Proj IDNH 2016(810)
Work TypePAVEMENT REP AND OVERLAY
 
17.6405218685.975306247.6399.9
Work Order00-00-00
Work Began07-11-16
Work Completed
Time Computed07-09-16
Contract Working Days122
Addl Days Granted0
Working Days Charged98
Percent Time Used80
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-02-091
JMHP, INC. (2.08)
BATTERSON,LLP (0.24)
WEST TEXAS RUMBLE STRIP (0.16)
THIRD COAST SERVICES LLC (0.21)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.13)
INTERSTATE BARRICADES & MARKINGS, INC. (5.97)
Contract #03163015
Totals5218685.97207524.235306247.6399.9

CountyGALVESTON
HighwayFM 518
FromFRIENDSWOOD LINK ROAD
ToRIVERSIDE
CSJ0976-03-103
Proj IDNH 2016(627)
Work TypeLANDSCAPE DEV
 
2.310227694.6268691.3630.1
Work Order09-15-16
Work Began11-08-16
Work Completed
Time Computed10-17-16
Contract Working Days45
Addl Days Granted0
Working Days Charged37
Percent Time Used82
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-103
TRAF-TEX, INC. (2.70)
Contract #08163230
Totals227694.6266191.3668691.3630.1

CountyGALVESTON
HighwayFM 2094
FromAT DAVIS ROAD
To.
CSJ0976-04-020
Proj IDSTP 2017(497)HES
Work TypeTS IMPRVMTS
 
0.250213735.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0976-04-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173228
Totals213735.350.000.000.0

CountyGALVESTON
HighwayFM 646
FromFM 1764
ToSH 6
CSJ0978-01-034
Proj IDC 978-1-34
Work TypeGR, BASE, SURF, STRS
 
1.22212830994.004177268.5432.5
Work Order02-17-16
Work Began07-05-16
Work Completed
Time Computed05-17-16
Contract Working Days310
Addl Days Granted0
Working Days Charged103
Percent Time Used33
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-01-034
CPAVE, INC. (0.23)
DOUBLE OAK CONSTRUCTION, INC. (0.23)
WILLOW CITY SIGN & RAIL, INC. (0.42)
ROSALES TRUCKING (2.13)
MESA ROD BUSTERS, INC. (3.55)
TOM-MAC, INC. (0.70)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.53)
INTERSTATE BARRICADES & MARKINGS, INC. (0.99)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.72)
RAY"S THREADING AND FAB SHOP (0.21)
G. S. I. HIGHWAY PRODUCTS (0.26)
DURWOOD GREENE CONSTRUCTION CO. (5.63)
PEREZ CONSTRUCTION CO. (0.06)
Contract #12153206
Totals12830994.00527295.474177268.5432.5

CountyGALVESTON
HighwayFM 646
FromGRAND AVE
ToFM 517
CSJ0978-02-054
Proj IDSTP 2007(404)
Work TypeINST CULV,ADJ DRWAYS & RESTORE DRNG
 
3.7005827858.984860394.0683.7
Work Order12-10-14
Work Began02-12-15
Work Completed
Time Computed02-12-15
Contract Working Days135
Addl Days Granted0
Working Days Charged154
Percent Time Used114
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-054
BATTERSON,LLP (0.06)
TEXAS DRAINAGE INC. (0.91)
GEORGE MEEKS LANDPRO, INC. (7.34)
LONE STAR TRAFFIC SERVICE, INC. (0.20)
ARBOR CARE, INC. (0.06)
ROMAR UNLIMITED, INC. (2.36)
MULLEN ASPHALT PAVING CO. (0.75)
Contract #07143223
Totals5827858.980.004860394.0683.7

CountyGALVESTON
HighwayFM 517
FromFM 3436
ToSH 146
CSJ0978-02-076
Proj IDSTP 2017(161)
Work TypeBASE REP AND ACP O/L
 
1.449617038.320.000.0
Work Order11-16-16
Work Began01-09-17
Work Completed
Time Computed12-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-076
INTERSTATE BARRICADES & MARKINGS, INC. (5.58)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.02)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.61)
Contract #10163213
Totals617038.320.000.000.0

CountyBRAZORIA
HighwayFM 523
FromSH 35
ToFM 2004
CSJ1003-01-091
Proj IDSTP 2015(540)
Work TypeOCST, RBL AND ACP O/L
 
16.9427475838.937958598.0299.9
Work Order06-01-15
Work Began09-09-15
Work Completed
Time Computed08-01-15
Contract Working Days112
Addl Days Granted0
Working Days Charged124
Percent Time Used110
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1003-01-091
COX PAVING COMPANY, L.P. (11.09)
ISI CONTRACTING, INC. (1.55)
WEST TEXAS RUMBLE STRIP (0.21)
THIRD COAST SERVICES LLC (0.53)
RICE ENVIRONMENTAL SERVICES (2.71)
INTERSTATE BARRICADES & MARKINGS, INC. (3.35)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.69)
Contract #04153004
Totals7475838.930.007958598.0299.9

CountyHARRIS
HighwayFM 529
FromAPPROX. 0.25 MILES WEST OF PEEK RD
ToAPPROX. 0.41 MILES EAST OF PORTER R
CSJ1006-01-071
Proj IDCC 1006-1-71
Work TypeCONSTR OF A LT TN LN W/CULVERT
 
0.345937479.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163029
Totals937479.520.000.000.0

CountyHARRIS
HighwayFM 1942
FromUS 90
ToCROSBY LYNCHBURG RD
CSJ1062-05-009
Proj IDSTP 2015(614)MM
Work TypeWIDEN ROADWAY
 
0.3153477178.183866494.6499.9
Work Order03-30-15
Work Began10-26-15
Work Completed
Time Computed05-29-15
Contract Working Days157
Addl Days Granted0
Working Days Charged130
Percent Time Used82
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-05-009
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.16)
BATTERSON,LLP (1.29)
Contract #02153223
Totals3477178.18534837.563866494.6499.9

CountyMONTGOMERY
HighwayFM 1097
FromIH 45
ToSH 75
CSJ1259-01-036
Proj IDSTP 1502(201)
Work TypeWIDEN FOR CLTL & 2" OVERLAY
 
0.8205567522.752698262.3148.4
Work Order11-12-15
Work Began07-11-16
Work Completed
Time Computed03-11-16
Contract Working Days155
Addl Days Granted0
Working Days Charged106
Percent Time Used68
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-036
J & M CONTRACTING, COMPANY (50.28)
WILLOW CITY SIGN & RAIL, INC. (0.26)
STRIPE LINES, INC. (1.02)
THIRD COAST SERVICES LLC (11.67)
Contract #08153057
Totals5567522.75122915.252698262.3148.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10