Monthly State Let Construction Report For Houston District As Of Mar 13, 2017 Page 8 Of 10

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayVA
FromON FM 270 FROM NASA ROAD 1
ToHENDERSON ROAD
CSJ0912-72-302
Proj IDSTP 2014(138)TE
Work TypeSHARED USE PATH
 
1.9021755575.5015637.280.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-15
Work Began00-00-00
Work Completed
Time Computed10-05-15
Contract Working Days150
Addl Days Granted0
Working Days Charged36
Percent Time Used24
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-302
BATTERSON,LLP (2.94)
GEORGE MEEKS LANDPRO, INC. (3.12)
J KRU LAND SERVICES, LLC (0.78)
CURB PLANET INC. (0.11)
Contract #05153226
Totals1755575.500.0015637.280.8

CountyHARRIS
HighwayVA
FromFALLS STREET
ToLOCKWOOD DRIVE
CSJ0912-72-315
Proj IDSTP 2014(142)TE
Work TypeCONSTRUCT MULTI-USE PATH
 
0.8671323726.00563211.2942.5
Work Order06-22-16
Work Began08-10-16
Work Completed
Time Computed07-22-16
Contract Working Days136
Addl Days Granted0
Working Days Charged22
Percent Time Used16
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-315
SPECIALTY DRILLING, LTD. (1.17)
Contract #04163021
Totals1323726.001250.00563211.2942.5

CountyHARRIS
HighwayVA
FromAT HERMANN PARK/BRAYS BAYOU TRAIL
ToFROM ALMEDA RD TO HOLCOMBE BLVD
CSJ0912-72-319
Proj IDSTP 2014(141)TE
Work TypeCONSTRUCT MULTI-USE PATH CONNECTORS
 
0.467792114.50365952.4246.1
Work Order07-27-16
Work Began10-17-16
Work Completed
Time Computed10-25-16
Contract Working Days151
Addl Days Granted0
Working Days Charged71
Percent Time Used47
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-319
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05163231
Totals792114.5088477.14365952.4246.1

CountyHARRIS
HighwayCR
FromWEST LAKE HOUSTON PKWY, FROM UPRR
ToWILL CLAYTON PKWY
CSJ0912-72-335
Proj IDCC 912-72-335
Work TypeITS FOR HIGH DEMAND ARTERIAL STREET
 
0.0011789743.301522428.7485.0
Work Order05-16-16
Work Began09-06-16
Work Completed
Time Computed09-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged127
Percent Time Used63
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-335
STRIPE-A-LINE, INC. (1.88)
SOUTH RANGER CONSTRUCTION, INC. (9.79)
MENADE, INC. (15.51)
Contract #12153013
Totals1789743.30123867.601522428.7485.0

CountyGALVESTON
HighwayVA
FromAT GALVESTON FERRY OFFICE
To.
CSJ0912-73-203
Proj IDC 912-73-203
Work TypeRENO OF GALV-BOL FERRY MAINT BLDG
 
0.0011529400.001905027.2099.9
Work Order12-02-15
Work Began12-16-15
Work Completed
Time Computed12-16-15
Contract Working Days180
Addl Days Granted155
Working Days Charged291
Percent Time Used86
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-203
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07153261
Totals1529400.0089107.811905027.2099.9

CountyGALVESTON
HighwayVA
FromAT GALVESTON FERRY
To.
CSJ0912-73-205
Proj IDFT 912-73-205
Work TypeRECON OF FERRY BULKHEAD & WORK DOCK
 
0.00121325783.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-03-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days450
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-205
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163006
Totals21325783.000.000.000.0

CountyHARRIS
HighwayFM 865
FromALMEDA-GENOA
ToBW 8
CSJ0976-01-019
Proj IDC 976-1-19
Work TypeGR, BS & SURF
 
1.27213285921.4410707487.5380.5
Work Order02-12-14
Work Began09-28-15
Work Completed
Time Computed11-09-14
Contract Working Days305
Addl Days Granted8
Working Days Charged269
Percent Time Used85
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
INTERSTATE BARRICADES & MARKINGS, INC. (0.15)
BREDA COMPANY, INC. (0.56)
CPAV SPECIALTIES, LP (0.20)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (2.48)
JOHN REED AND COMPANY, LLC (7.70)
PEREZ CONSTRUCTION CO. (2.23)
TEXOP CONSTRUCTION (1.40)
DURWOOD GREENE CONSTRUCTION CO. (1.87)
ROSALES TRUCKING (2.32)
NATIONAL DEWATERING SYSTEMS (0.15)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.99)
RAY"S THREADING AND FAB SHOP (0.28)
ABLE PAVING (0.09)
INTERSTATE BARRICADES & MARKINGS, INC. (0.78)
BORTUNCO (0.11)
MICKIE SERVICE, INC. (0.51)
TRAF-TEX, INC. (0.07)
Contract #11133025
Totals13285921.44604323.3310707487.5380.5

CountyBRAZORIA
HighwayFM 518
FromFM 865
ToSAN ANTONIO ST
CSJ0976-02-091
Proj IDNH 2016(810)
Work TypePAVEMENT REP AND OVERLAY
 
17.6405218685.975352189.8399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-11-16
Work Completed
Time Computed07-09-16
Contract Working Days122
Addl Days Granted0
Working Days Charged114
Percent Time Used93
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-02-091
JMHP, INC. (2.08)
BATTERSON,LLP (0.24)
WEST TEXAS RUMBLE STRIP (0.16)
THIRD COAST SERVICES LLC (0.21)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.13)
INTERSTATE BARRICADES & MARKINGS, INC. (5.97)
Contract #03163015
Totals5218685.970.005352189.8399.9

CountyGALVESTON
HighwayFM 518
FromFRIENDSWOOD LINK ROAD
ToRIVERSIDE
CSJ0976-03-103
Proj IDNH 2016(627)
Work TypeLANDSCAPE DEV
 
2.310227694.62175284.2676.9
Work Order09-15-16
Work Began11-08-16
Work Completed
Time Computed10-17-16
Contract Working Days45
Addl Days Granted0
Working Days Charged41
Percent Time Used91
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-103
TRAF-TEX, INC. (2.70)
Contract #08163230
Totals227694.6213602.63175284.2676.9

CountyGALVESTON
HighwayFM 2094
FromAT DAVIS ROAD
To.
CSJ0976-04-020
Proj IDSTP 2017(497)HES
Work TypeTS IMPRVMTS
 
0.250213735.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0976-04-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173228
Totals213735.350.000.000.0

CountyGALVESTON
HighwayFM 646
FromFM 1764
ToSH 6
CSJ0978-01-034
Proj IDC 978-1-34
Work TypeGR, BASE, SURF, STRS
 
1.22212830994.005083676.1339.6
Work Order02-17-16
Work Began07-05-16
Work Completed
Time Computed05-17-16
Contract Working Days310
Addl Days Granted0
Working Days Charged136
Percent Time Used43
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-01-034
CPAVE, INC. (0.23)
DOUBLE OAK CONSTRUCTION, INC. (0.23)
WILLOW CITY SIGN & RAIL, INC. (0.42)
ROSALES TRUCKING (2.13)
MESA ROD BUSTERS, INC. (3.55)
TOM-MAC, INC. (0.70)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.53)
INTERSTATE BARRICADES & MARKINGS, INC. (0.99)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.72)
RAY"S THREADING AND FAB SHOP (0.21)
G. S. I. HIGHWAY PRODUCTS (0.26)
DURWOOD GREENE CONSTRUCTION CO. (5.63)
PEREZ CONSTRUCTION CO. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
Contract #12153206
Totals12830994.00576496.345083676.1339.6

CountyGALVESTON
HighwayFM 646
FromGRAND AVE
ToFM 517
CSJ0978-02-054
Proj IDSTP 2007(404)
Work TypeINST CULV,ADJ DRWAYS & RESTORE DRNG
 
3.7005827858.984951368.4084.9
Work Order12-10-14
Work Began02-12-15
Work Completed
Time Computed02-12-15
Contract Working Days135
Addl Days Granted70
Working Days Charged163
Percent Time Used79
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-054
BATTERSON,LLP (0.06)
TEXAS DRAINAGE INC. (0.91)
GEORGE MEEKS LANDPRO, INC. (7.34)
LONE STAR TRAFFIC SERVICE, INC. (0.20)
ARBOR CARE, INC. (0.06)
ROMAR UNLIMITED, INC. (2.36)
MULLEN ASPHALT PAVING CO. (0.75)
Contract #07143223
Totals5827858.9890974.344951368.4084.9

CountyGALVESTON
HighwayFM 517
FromFM 3436
ToSH 146
CSJ0978-02-076
Proj IDSTP 2017(161)
Work TypeBASE REP AND ACP O/L
 
1.449617038.32550292.5889.1
Work Order11-16-16
Work Began01-09-17
Work Completed
Time Computed12-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged28
Percent Time Used46
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-076
INTERSTATE BARRICADES & MARKINGS, INC. (5.58)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.02)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.61)
Contract #10163213
Totals617038.3231356.25550292.5889.1

CountyHARRIS
HighwayFM 529
FromAPPROX. 0.25 MILES WEST OF PEEK RD
ToAPPROX. 0.41 MILES EAST OF PORTER R
CSJ1006-01-071
Proj IDCC 1006-1-71
Work TypeCONSTR OF A LT TN LN W/CULVERT
 
0.345937479.522016.000.2
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed12-29-16
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-071
LONESTAR TRAFFIC SAFETY, LLC (0.27)
LONE STAR PAVING (35.85)
SCR CIVIL CONSTRUCTION, LLC (2.44)
STRIPE LINES, INC. (0.76)
Contract #10163029
Totals937479.522016.002016.000.2

CountyMONTGOMERY
HighwayFM 1485
FromFM 3083
ToIH 69
CSJ1062-03-051
Proj IDSTP 2017(637)HES
Work TypeSFTY TR FX OBJS
 
12.435978908.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1062-03-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173012
Totals978908.200.000.000.0

CountyHARRIS
HighwayFM 1942
FromUS 90
ToCROSBY LYNCHBURG RD
CSJ1062-05-009
Proj IDSTP 2015(614)MM
Work TypeWIDEN ROADWAY
 
0.3153477178.183905761.5599.9
Work Order03-30-15
Work Began10-26-15
Work Completed
Time Computed05-29-15
Contract Working Days157
Addl Days Granted0
Working Days Charged139
Percent Time Used88
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-05-009
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.16)
BATTERSON,LLP (1.29)
Contract #02153223
Totals3477178.183454.553905761.5599.9

CountyMONTGOMERY
HighwayFM 1097
FromIH 45
ToSH 75
CSJ1259-01-036
Proj IDSTP 1502(201)
Work TypeWIDEN FOR CLTL & 2" OVERLAY
 
0.8205567522.753641383.2565.4
Work Order11-12-15
Work Began07-11-16
Work Completed
Time Computed03-11-16
Contract Working Days155
Addl Days Granted0
Working Days Charged138
Percent Time Used89
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-036
J & M CONTRACTING, COMPANY (50.28)
WILLOW CITY SIGN & RAIL, INC. (0.26)
STRIPE LINES, INC. (1.02)
THIRD COAST SERVICES LLC (11.67)
Contract #08153057
Totals5567522.75439641.403641383.2565.4

CountyMONTGOMERY
HighwayFM 1774
From0.045 MI S OF W. LOST CREEK BLVD
ToFM 149
CSJ1400-04-011
Proj IDSTP 1402(182)
Work TypeGR, STRS, BS & CONC PAV
 
2.83118070204.053854693.6521.3
Work Order11-03-14
Work Began07-14-16
Work Completed
Time Computed11-19-14
Contract Working Days360
Addl Days Granted38
Working Days Charged55
Percent Time Used13
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
WILLOW CITY SIGN & RAIL, INC. (0.62)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.92)
SCMU (2.06)
INDUS CONSTRUCTION, L.P. (0.92)
TEX OP CONSTRUCTION, LP (0.89)
ANGEL BROTHERS ENTERPRISES, LTD. (6.34)
CURB PLANET INC. (0.01)
THIRD COAST SERVICES LLC (1.71)
EUBANK EXCAVATION, L.L.C. (0.54)
CPAVE, INC. (0.31)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.21)
ADF EXCAVATION, LLC (0.53)
ROMAR UNLIMITED, INC. (2.90)
Contract #08143203
Totals18070204.05646165.753854693.6521.3

CountyMONTGOMERY
HighwayFM 1774
FromFM 1486
To0.109 MILE NORTH OF FM 1488
CSJ1400-04-021
Proj IDSTP 1602(483)MM
Work TypeGR, STRS, BS & CONC PAV
 
1.17323247170.433986936.7617.1
Work Order11-01-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days687
Addl Days Granted0
Working Days Charged55
Percent Time Used8
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-021
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.43)
WILLOW CITY SIGN & RAIL, INC. (0.68)
THIRD COAST SERVICES LLC (1.48)
LONESTAR TRAFFIC SAFETY, LLC (0.08)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEX OP CONSTRUCTION, LP (0.26)
MESA ROD BUSTERS, INC. (1.26)
CPAVE, INC. (0.11)
SCOTT DERR PAINTING CO, LLC (0.45)
W. W. FOUNDATION DRILLING, LTD. (5.98)
CHOCTAW ERECTORS, INC. (16.77)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.20)
Contract #08163003
Totals23247170.43371787.213986936.7617.1

CountyMONTGOMERY
HighwayFM 1375
FromFM 149
ToWALKER C/L
CSJ1402-03-011
Proj IDSTP 2016(732)
Work TypeOCST AND PAVEMENT MARKINGS
 
24.5941297509.451382352.8499.9
Work Order03-01-16
Work Began07-05-16
Work Completed
Time Computed03-16-16
Contract Working Days55
Addl Days Granted0
Working Days Charged48
Percent Time Used87
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1402-03-011
INTERSTATE BARRICADES & MARKINGS, INC. (18.76)
SMITH & COMPANY (18.98)
Contract #01163242
Totals1297509.450.001382352.8499.9