Monthly State Let Construction Report For Houston District As Of May 11, 2017 Page 5 Of 10

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 10
FromON ELYSIAN ST: FROM COMMERCE ST
ToHARRINGTON STREET
CSJ0508-01-351
Proj IDC 508-1-351
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.20435654481.314277855.6611.9
Work Order08-23-16
Work Began01-20-17
Work Completed
Time Computed11-21-16
Contract Working Days809
Addl Days Granted0
Working Days Charged34
Percent Time Used4
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-351
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.10)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.98)
GMJ PAVING CO. (0.48)
THIRD COAST SERVICES LLC (1.32)
ROYAL REBAR (7.84)
RDI FOUNDATION DRILLING (9.30)
WILLOW CITY SIGN & RAIL, INC. (0.16)
SCOTT DERR PAINTING CO, LLC (0.36)
STATEWIDE SERVICES, INC (2.58)
HOUSTON SAWING & DRILLING (0.09)
CHOCTAW ERECTORS, INC. (1.94)
CURB PLANET INC. (0.01)
UNDER CONSTRUCTION INC. (0.40)
MAK FENCING (0.11)
Contract #06163002
Totals35654481.311625283.064277855.6611.9

CountyHARRIS
HighwaySS 330
FromSAN JACINTO AVE/ROLLINGBROOK STREET
ToBAKER ROAD
CSJ0508-07-286
Proj IDCC 508-7-286
Work TypeLEFT TURN LN & UTURN IMPROVEMENTS
 
0.4272251558.842674355.9299.9
Work Order03-20-15
Work Began06-22-15
Work Completed
Time Computed05-19-15
Contract Working Days52
Addl Days Granted60
Working Days Charged100
Percent Time Used89
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-07-286
REGIONAL TRAFFIC SERVICES LLC (1.36)
LONE STAR TRAFFIC SERVICE, INC. (0.10)
JASSO"S SAWING & SEALING (0.88)
OSCAR ORDUNO, INC. (16.23)
CENTURY ASPHALT MATERIALS (0.79)
HOLES INCORPORATED (1.19)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.82)
MESA ROD BUSTERS, INC. (0.57)
CURB PLANET INC. (0.07)
BATTERSON,LLP (1.11)
Contract #01153024
Totals2251558.840.002674355.9299.9

CountyWALLER
HighwayFM 362
From2.159 MI S OF FM 1488
To2.923 MI N OF US 290
CSJ0523-02-046
Proj IDSTP 2016(466)HES
Work TypeINSTALL LED FLASHING CHEVRONS
 
7.4781069740.001291540.0099.9
Work Order03-09-16
Work Began10-01-16
Work Completed
Time Computed06-07-16
Contract Working Days180
Addl Days Granted0
Working Days Charged57
Percent Time Used31
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01163239
Totals1069740.0021100.001291540.0099.9

CountyMONTGOMERY
HighwayFM 1488
FromFM 149
To0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ0523-10-034
Proj IDC 523-10-34
Work TypeCONSTRUCT RR GRADE SEPARATION
 
2.77927649979.1119682325.5371.1
Work Order10-22-13
Work Began02-16-15
Work Completed
Time Computed07-19-14
Contract Working Days478
Addl Days Granted0
Working Days Charged327
Percent Time Used68
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC (1.11)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67)
EUBANK EXCAVATION, L.L.C. (0.76)
BREDA COMPANY, INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (0.51)
GMJ PAVING CO. (5.71)
RDI FOUNDATION DRILLING (4.28)
HOUSTON SAWING & DRILLING (0.04)
TEX OP CONSTRUCTION, LP (0.60)
SCOTT DERR PAINTING CO (0.13)
NORTHWEST MATERIALS (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.15)
CREACOM, INC. (1.18)
VALLEY PLACERS, LLC (0.27)
APCON SERVICES, LLC (0.00)
FORDE CONSTRUCTION COMPANY, INC. (0.19)
CEN TEX HYDROSEED, INC. (0.42)
B & R WATER WELL SERVICES, LLC (0.01)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.13)
Contract #07133003
Totals27649979.111445207.8019682325.5371.1

CountyFORT BEND
HighwayFM 360
FromSH 36
ToUS 59
CSJ0527-06-019
Proj IDSTP 2017(113)
Work TypeBASE REP, MILL, O/L & PV MKS
 
11.3281482901.931676959.4799.9
Work Order10-19-16
Work Began01-03-17
Work Completed
Time Computed12-18-16
Contract Working Days90
Addl Days Granted0
Working Days Charged44
Percent Time Used48
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0527-06-019
WEST TEXAS RUMBLE STRIP (0.41)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.02)
BATTERSON,LLP (4.96)
Contract #09163230
Totals1482901.934903.191676959.4799.9

CountyFORT BEND
HighwayFM 359
FromAT US 90A AND UPRR
To.
CSJ0543-02-055
Proj IDSTP 2013(734)RGS
Work TypeRR GRADE SEPARATION
 
0.40827124547.7710835403.3139.9
Work Order07-22-15
Work Began06-13-16
Work Completed
Time Computed01-19-16
Contract Working Days482
Addl Days Granted0
Working Days Charged131
Percent Time Used27
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
BUYERS BARRICADES, INC. (0.22)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.95)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36)
PRIMATE CONSTRUCTION, INC. (0.12)
JAMES CONSTRUCTION GROUP, L.L.C. (8.77)
SCOTT DERR PAINTING CO, LLC (0.30)
CHERRY CRUSHED CONCRETE (0.21)
HOUSTON SAWING & DRILLING (0.04)
W. W. FOUNDATION DRILLING, LTD. (4.51)
WILLOW CITY SIGN & RAIL, INC. (1.06)
ROYAL REBAR (4.06)
MTAM CORPORATION (0.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
CURB PLANET INC. (0.06)
DAVEY TREE & LAWN CARE (0.21)
Contract #05153205
Totals27124547.77779997.3510835403.3139.9

CountyFORT BEND
HighwayFM 762
From1.524 MI. SOUTH OF BRIDLEWOOD DRIVE
ToFM 1462
CSJ0543-03-072
Proj IDSTP 2017(822)
Work TypeBASE REPAIR AND OVERLAY
 
13.9211849419.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173019
Totals1849419.980.000.000.0

CountyBRAZORIA
HighwaySH 332
From0.102 MILES EAST OF LEVEE ROAD
To.
CSJ0586-01-065
Proj IDSTP 2017(823)
Work TypeREMOV & REPL DRAINS STR
 
0.024272166.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0586-01-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173020
Totals272166.320.000.000.0

CountyBRAZORIA
HighwaySH 288
FromCR 56
To0.35 MI S OF FM 1462 (FRTG RD)
CSJ0598-02-097
Proj IDNH 2016(695)
Work TypePV REP, SC, ACP OL AND PV MKS
 
17.2566895441.636222866.8791.2
Work Order04-20-16
Work Began06-28-16
Work Completed
Time Computed05-20-16
Contract Working Days156
Addl Days Granted0
Working Days Charged219
Percent Time Used140
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-097
WILLOW CITY SIGN & RAIL, INC. (3.22)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.87)
Contract #02163236
Totals6895441.630.006222866.8791.2

CountyBRAZORIA
HighwaySH 288
FromFM 2234
ToHAYES CREEK
CSJ0598-02-100
Proj IDNH 2017(494)
Work TypeMILL,SEAL & PFC O/L
 
9.4784993779.690.000.0
Work Order02-09-17
Work Began00-00-00
Work Completed
Time Computed04-10-17
Contract Working Days183
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-100
PROFFESSIONAL TRAFFIC CONTROL, LLC. (5.44)
STRIPE LINES, INC. (0.21)
CPAVE, INC. (2.63)
ODUM SERVICES, L.P. (2.97)
Contract #01173247
Totals4993779.690.000.000.0

CountyBRAZORIA
HighwaySH 288
FromCR 56
To.
CSJ0598-02-106
Proj IDNH 2015(708)
Work TypeCONST SB ON-RAMP & NB OFF-RAMP
 
2.9089196617.239300237.3399.9
Work Order07-13-15
Work Began11-30-15
Work Completed
Time Computed09-12-15
Contract Working Days290
Addl Days Granted22
Working Days Charged304
Percent Time Used97
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-106
WILLOW CITY SIGN & RAIL, INC. (2.03)
TRAF-TEX, INC. (1.43)
CPAVE, INC. (0.07)
BATTERSON,LLP (0.92)
WEBER-BALKE FOUNDATION COMPANY, INC (5.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SOUTHERN CRUSHED CONCRETE LLC (0.38)
DURWOOD GREENE CONSTRUCTION CO. (8.25)
NORTHWEST MATERIALS (0.18)
SCOTT DERR PAINTING CO (0.10)
MESA ROD BUSTERS, INC. (0.73)
RAY"S THREADING AND FAB SHOP (0.03)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.28)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (0.40)
PREMIUM HYDRO-SOLUTIONS (0.29)
Contract #03153206
Totals9196617.23296206.079300237.3399.9

CountyMONTGOMERY
HighwayFM 149
FromN. SOUTHERN MONTGOMERY CITY LIMITS
ToKEENAN CUTOFF ROAD
CSJ0720-02-085
Proj IDSTP 2017(635)
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
3.8602864063.570.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173208
Totals2864063.570.000.000.0

CountyMONTGOMERY
HighwayFM 149
FromFM 1097
ToFM 1791
CSJ0720-02-087
Proj IDSTP 1502(606)HES
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
10.17010198541.185619681.8155.1
Work Order11-10-15
Work Began01-11-16
Work Completed
Time Computed01-09-16
Contract Working Days183
Addl Days Granted0
Working Days Charged121
Percent Time Used66
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-087
J & M CONTRACTING, COMPANY (5.60)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
TEXAS LAND CLEARING, INC. (18.16)
WATERS CONSTRUCTION CO., INC. (3.85)
WILLOW CITY SIGN & RAIL, INC. (1.56)
CEN TEX HYDROSEED, INC. (8.45)
Contract #08153044
Totals10198541.1843062.005619681.8155.1

CountyHARRIS
HighwaySH 249
FromAT VETERANS MEMORIAL DRIVE
To.
CSJ0720-03-128
Proj IDSTP 2014(743)HES
Work TypeIMPROVE TS
 
0.404254036.09293106.2799.9
Work Order07-25-14
Work Began02-10-15
Work Completed
Time Computed01-21-15
Contract Working Days58
Addl Days Granted0
Working Days Charged51
Percent Time Used87
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
STRIPE LINES, INC. (1.75)
AAA ASPHALT PAVING, INC. (6.40)
Contract #06143218
Totals254036.09171685.41293106.2799.9

CountyBRAZORIA
HighwayFM 521
FromSH 35
ToSH 332
CSJ0847-03-035
Proj IDSTP 2016(061)
Work TypeSHOULDER REP AND OVERLAY
 
29.3067645090.847759271.2399.9
Work Order11-13-15
Work Began01-13-16
Work Completed
Time Computed12-14-15
Contract Working Days191
Addl Days Granted20
Working Days Charged227
Percent Time Used107
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0847-03-035
STRIPE A LINE (4.54)
JMHP, INC. (4.90)
THIRD COAST SERVICES LLC (1.18)
MAIN LANE INDUSTRIES, LTD. (0.16)
Contract #09153010
Totals7645090.8417234.957759271.2399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-331
Proj IDCM 2008(055)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011482581.451227437.6782.7
Work Order09-11-07
Work Began04-04-08
Work Completed
Time Computed09-27-07
Contract Working Days235
Addl Days Granted0
Working Days Charged186
Percent Time Used79
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P. (1.04)
SPRING CREEK CONSTRUCTION, INC. (4.49)
Contract #08073244
Totals1482581.450.001227437.6782.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-336
Proj IDSTP 2011(578)G
Work TypeINSTALL VIVDS AND INSTALL LOOPS
 
0.003439963.75148701.4433.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-11
Work Began04-09-12
Work Completed
Time Computed01-22-11
Contract Working Days187
Addl Days Granted0
Working Days Charged115
Percent Time Used61
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11)
Contract #12103011
Totals439963.750.00148701.4433.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-350
Proj IDCM 2009(364)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011289999.251390703.9399.9
Work Order06-02-09
Work Began08-12-12
Work Completed
Time Computed06-18-09
Contract Working Days225
Addl Days Granted0
Working Days Charged221
Percent Time Used98
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC. (0.04)
SPRING CREEK CONSTRUCTION, INC. (3.15)
HIGHWAY TECHNOLOGIES, INC. (0.76)
KAM CONSTRUCTION, INC. (0.86)
WALLACE CONCRETE SAWING (0.14)
REGIONAL TRAFFIC SERVICES LLC (0.00)
VASQUEZ CONCRETE COMPANY (0.38)
Contract #04093209
Totals1289999.250.001390703.9399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-380
Proj IDSTP 2012(020)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011515998.781619598.4899.9
Work Order11-16-11
Work Began02-13-12
Work Completed
Time Computed12-02-11
Contract Working Days437
Addl Days Granted0
Working Days Charged285
Percent Time Used65
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP (5.72)
ISI CONTRACTING, INC. (6.40)
VASQUEZ CONCRETE COMPANY (0.32)
Contract #09113211
Totals1515998.7835260.101619598.4899.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-381
Proj IDSTP 2012(021)
Work TypeUPGRADE/RECONSTRUCT TRAFFIC SIGNALS
 
0.0011787199.581931000.6199.9
Work Order07-19-13
Work Began10-14-14
Work Completed
Time Computed08-04-13
Contract Working Days432
Addl Days Granted0
Working Days Charged382
Percent Time Used88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02)
PROFESSIONAL TRAFFIC CONTROL, LLC (2.54)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.77)
Contract #03133016
Totals1787199.58495.001931000.6199.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10