Monthly State Let Construction Report For Houston District As Of Feb 10, 2017 Page 5 Of 10

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 10
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-344
Proj IDIM 0107(445)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0011351369.791139346.9084.3
Work Order07-02-14
Work Began09-04-14
Work Completed
Time Computed09-04-14
Contract Working Days90
Addl Days Granted0
Working Days Charged76
Percent Time Used84
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-344
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68)
ENVIRONMENTAL ALLIES, L.P. (1.26)
Contract #04143020
Totals1351369.7925186.951139346.9084.3

CountyHARRIS
HighwayIH 10
FromON ELYSIAN ST: FROM COMMERCE ST
ToHARRINGTON STREET
CSJ0508-01-351
Proj IDC 508-1-351
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.20435654481.311850350.005.1
Work Order08-23-16
Work Began01-20-17
Work Completed
Time Computed11-21-16
Contract Working Days809
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-351
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.10)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.98)
GMJ PAVING CO. (0.48)
THIRD COAST SERVICES LLC (1.32)
ROYAL REBAR (7.76)
RDI FOUNDATION DRILLING (9.30)
WILLOW CITY SIGN & RAIL, INC. (0.16)
SCOTT DERR PAINTING CO, LLC (0.36)
STATEWIDE SERVICES, INC (2.58)
HOUSTON SAWING & DRILLING (0.09)
CHOCTAW ERECTORS, INC. (1.94)
CURB PLANET INC. (0.01)
UNDER CONSTRUCTION INC. (0.40)
Contract #06163002
Totals35654481.311850350.001850350.005.1

CountyHARRIS
HighwaySS 330
FromSAN JACINTO AVE/ROLLINGBROOK STREET
ToBAKER ROAD
CSJ0508-07-286
Proj IDCC 508-7-286
Work TypeLEFT TURN LN & UTURN IMPROVEMENTS
 
0.4272251558.842674355.9299.9
Work Order03-20-15
Work Began06-22-15
Work Completed
Time Computed05-19-15
Contract Working Days52
Addl Days Granted60
Working Days Charged100
Percent Time Used89
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-07-286
REGIONAL TRAFFIC SERVICES LLC (1.36)
LONE STAR TRAFFIC SERVICE, INC. (0.10)
JASSO"S SAWING & SEALING (0.88)
OSCAR ORDUNO, INC. (16.23)
CENTURY ASPHALT MATERIALS (0.79)
HOLES INCORPORATED (1.19)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.82)
MESA ROD BUSTERS, INC. (0.57)
CURB PLANET INC. (0.07)
BATTERSON,LLP (1.11)
Contract #01153024
Totals2251558.84500.002674355.9299.9

CountyWALLER
HighwayFM 362
From2.159 MI S OF FM 1488
To2.923 MI N OF US 290
CSJ0523-02-046
Proj IDSTP 2016(466)HES
Work TypeINSTALL LED FLASHING CHEVRONS
 
7.4781069740.001253440.0099.9
Work Order03-09-16
Work Began10-01-16
Work Completed
Time Computed06-07-16
Contract Working Days180
Addl Days Granted0
Working Days Charged57
Percent Time Used31
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01163239
Totals1069740.004000.001253440.0099.9

CountyMONTGOMERY
HighwayFM 1488
FromFM 149
To0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ0523-10-034
Proj IDC 523-10-34
Work TypeCONSTRUCT RR GRADE SEPARATION
 
2.77927649979.1116976951.7761.3
Work Order10-22-13
Work Began02-16-15
Work Completed
Time Computed07-19-14
Contract Working Days478
Addl Days Granted0
Working Days Charged260
Percent Time Used54
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC (1.11)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67)
EUBANK EXCAVATION, L.L.C. (0.76)
BREDA COMPANY, INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (0.51)
GMJ PAVING CO. (5.71)
RDI FOUNDATION DRILLING (4.28)
HOUSTON SAWING & DRILLING (0.04)
TEX OP CONSTRUCTION, LP (0.60)
SCOTT DERR PAINTING CO (0.13)
NORTHWEST MATERIALS (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.15)
CREACOM, INC. (1.18)
VALLEY PLACERS, LLC (0.27)
APCON SERVICES, LLC (0.00)
FORDE CONSTRUCTION COMPANY, INC. (0.19)
CEN TEX HYDROSEED, INC. (0.42)
B & R WATER WELL SERVICES, LLC (0.01)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.13)
Contract #07133003
Totals27649979.11487124.7716976951.7761.3

CountyFORT BEND
HighwayFM 360
FromSH 36
ToUS 59
CSJ0527-06-019
Proj IDSTP 2017(113)
Work TypeBASE REP, MILL, O/L & PV MKS
 
11.3281482901.93329780.2622.2
Work Order10-19-16
Work Began00-00-00
Work Completed
Time Computed12-18-16
Contract Working Days90
Addl Days Granted0
Working Days Charged16
Percent Time Used17
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0527-06-019
WEST TEXAS RUMBLE STRIP (0.41)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.02)
BATTERSON,LLP (4.96)
Contract #09163230
Totals1482901.93329780.26329780.2622.2

CountyFORT BEND
HighwayFM 359
FromAT US 90A AND UPRR
To.
CSJ0543-02-055
Proj IDSTP 2013(734)RGS
Work TypeRR GRADE SEPARATION
 
0.40827124547.779087932.4533.5
Work Order07-22-15
Work Began06-13-16
Work Completed
Time Computed01-19-16
Contract Working Days482
Addl Days Granted0
Working Days Charged112
Percent Time Used23
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
BUYERS BARRICADES, INC. (0.22)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.95)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36)
PRIMATE CONSTRUCTION, INC. (0.12)
JAMES CONSTRUCTION GROUP, L.L.C. (8.77)
SCOTT DERR PAINTING CO, LLC (0.30)
CHERRY CRUSHED CONCRETE (0.21)
HOUSTON SAWING & DRILLING (0.04)
W. W. FOUNDATION DRILLING, LTD. (4.51)
WILLOW CITY SIGN & RAIL, INC. (1.06)
ROYAL REBAR (4.06)
MTAM CORPORATION (0.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
CURB PLANET INC. (0.06)
Contract #05153205
Totals27124547.77539739.309087932.4533.5

CountyBRAZORIA
HighwaySH 288
FromCR 56
To0.35 MI S OF FM 1462 (FRTG RD)
CSJ0598-02-097
Proj IDNH 2016(695)
Work TypePV REP, SC, ACP OL AND PV MKS
 
17.2566895441.636125482.6489.0
Work Order04-20-16
Work Began06-28-16
Work Completed
Time Computed05-20-16
Contract Working Days156
Addl Days Granted0
Working Days Charged171
Percent Time Used109
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-097
WILLOW CITY SIGN & RAIL, INC. (3.22)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.87)
Contract #02163236
Totals6895441.6341758.386125482.6489.0

CountyBRAZORIA
HighwaySH 288
FromFM 2234
ToHAYES CREEK
CSJ0598-02-100
Proj IDNH 2017(494)
Work TypeMILL,SEAL & PFC O/L
 
9.4784993779.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173247
Totals4993779.690.000.000.0

CountyBRAZORIA
HighwaySH 288
FromCR 56
To.
CSJ0598-02-106
Proj IDNH 2015(708)
Work TypeCONST SB ON-RAMP & NB OFF-RAMP
 
2.9089196617.238849276.7796.2
Work Order07-13-15
Work Began11-30-15
Work Completed
Time Computed09-12-15
Contract Working Days290
Addl Days Granted0
Working Days Charged277
Percent Time Used95
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-106
WILLOW CITY SIGN & RAIL, INC. (2.03)
TRAF-TEX, INC. (1.43)
CPAVE, INC. (0.07)
BATTERSON,LLP (0.92)
WEBER-BALKE FOUNDATION COMPANY, INC (5.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SOUTHERN CRUSHED CONCRETE LLC (0.38)
DURWOOD GREENE CONSTRUCTION CO. (8.25)
NORTHWEST MATERIALS (0.18)
SCOTT DERR PAINTING CO (0.10)
MESA ROD BUSTERS, INC. (0.73)
RAY"S THREADING AND FAB SHOP (0.03)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (5.28)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (0.40)
Contract #03153206
Totals9196617.236365.478849276.7796.2

CountyGALVESTON
HighwayFM 519
FromSH 3
ToLP 197
CSJ0628-01-022
Proj IDSTP 2016(117)
Work TypeMILL, BASE REP, OVERLAY & STRIPING
 
6.4213878490.983526440.1590.9
Work Order07-27-16
Work Began08-30-16
Work Completed
Time Computed09-01-16
Contract Working Days165
Addl Days Granted0
Working Days Charged79
Percent Time Used47
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0628-01-022
INTERSTATE BARRICADES & MARKINGS, INC. (6.14)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.52)
TRAF-TEX, INC. (3.16)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (5.09)
Contract #06163223
Totals3878490.98113055.003526440.1590.9

CountyMONTGOMERY
HighwayIH 45
FromCONROE PARK & RIDE ON IH 45
ToFM 2854
CSJ0675-08-108
Proj IDC 675-8-108
Work TypeCONROE PARK & RIDE
 
0.1611009482.551048360.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-16
Work Began07-25-16
Work Completed
Time Computed07-25-16
Contract Working Days75
Addl Days Granted0
Working Days Charged71
Percent Time Used94
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-108
J & M CONTRACTING, COMPANY (8.02)
NATIONAL FENCE CO. (2.47)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (7.80)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
STRIPE LINES, INC. (1.56)
CEN TEX HYDROSEED, INC. (3.04)
Contract #04163225
Totals1009482.550.001048360.7699.9

CountyMONTGOMERY
HighwayFM 149
FromN. SOUTHERN MONTGOMERY CITY LIMITS
ToKEENAN CUTOFF ROAD
CSJ0720-02-085
Proj IDSTP 2017(635)
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
3.8602864063.570.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173208
Totals2864063.570.000.000.0

CountyMONTGOMERY
HighwayFM 149
FromFM 1097
ToFM 1791
CSJ0720-02-087
Proj IDSTP 1502(606)HES
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
10.17010198541.185129181.9650.2
Work Order11-10-15
Work Began01-11-16
Work Completed
Time Computed01-09-16
Contract Working Days183
Addl Days Granted0
Working Days Charged82
Percent Time Used44
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-087
J & M CONTRACTING, COMPANY (5.60)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
TEXAS LAND CLEARING, INC. (18.16)
WATERS CONSTRUCTION CO., INC. (3.85)
WILLOW CITY SIGN & RAIL, INC. (1.56)
Contract #08153044
Totals10198541.1861782.565129181.9650.2

CountyHARRIS
HighwaySH 249
FromAT VETERANS MEMORIAL DRIVE
To.
CSJ0720-03-128
Proj IDSTP 2014(743)HES
Work TypeIMPROVE TS
 
0.404254036.09114013.8644.8
Work Order07-25-14
Work Began02-10-15
Work Completed
Time Computed01-21-15
Contract Working Days58
Addl Days Granted0
Working Days Charged14
Percent Time Used24
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06143218
Totals254036.090.00114013.8644.8

CountyBRAZORIA
HighwayFM 521
FromSH 35
ToSH 332
CSJ0847-03-035
Proj IDSTP 2016(061)
Work TypeSHOULDER REP AND OVERLAY
 
29.3067645090.847629938.1199.9
Work Order11-13-15
Work Began01-13-16
Work Completed
Time Computed12-14-15
Contract Working Days191
Addl Days Granted20
Working Days Charged227
Percent Time Used107
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0847-03-035
STRIPE A LINE (4.54)
JMHP, INC. (4.90)
THIRD COAST SERVICES LLC (1.18)
MAIN LANE INDUSTRIES, LTD. (0.16)
Contract #09153010
Totals7645090.8456550.147629938.1199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-331
Proj IDCM 2008(055)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011482581.451227437.6782.7
Work Order09-11-07
Work Began04-04-08
Work Completed
Time Computed09-27-07
Contract Working Days235
Addl Days Granted0
Working Days Charged186
Percent Time Used79
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P. (1.04)
SPRING CREEK CONSTRUCTION, INC. (4.49)
Contract #08073244
Totals1482581.450.001227437.6782.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-336
Proj IDSTP 2011(578)G
Work TypeINSTALL VIVDS AND INSTALL LOOPS
 
0.003439963.75148701.4433.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-11
Work Began04-09-12
Work Completed
Time Computed01-22-11
Contract Working Days187
Addl Days Granted0
Working Days Charged115
Percent Time Used61
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11)
Contract #12103011
Totals439963.750.00148701.4433.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-350
Proj IDCM 2009(364)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011289999.251390703.9399.9
Work Order06-02-09
Work Began08-12-12
Work Completed
Time Computed06-18-09
Contract Working Days225
Addl Days Granted0
Working Days Charged221
Percent Time Used98
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC. (0.04)
SPRING CREEK CONSTRUCTION, INC. (3.15)
HIGHWAY TECHNOLOGIES, INC. (0.76)
KAM CONSTRUCTION, INC. (0.86)
WALLACE CONCRETE SAWING (0.14)
REGIONAL TRAFFIC SERVICES LLC (0.00)
VASQUEZ CONCRETE COMPANY (0.38)
Contract #04093209
Totals1289999.250.001390703.9399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-380
Proj IDSTP 2012(020)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011515998.781600338.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-11
Work Began02-13-12
Work Completed
Time Computed12-02-11
Contract Working Days437
Addl Days Granted0
Working Days Charged274
Percent Time Used62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP (5.72)
ISI CONTRACTING, INC. (6.40)
VASQUEZ CONCRETE COMPANY (0.32)
Contract #09113211
Totals1515998.780.001600338.3899.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10