| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | FORT BEND |
| Highway |
US 90A |
| From |
WHARTON COUNTY LINE |
| To |
SPUR 10 |
| CSJ |
0027-06-055 |
| Proj ID |
STP 2009(548)ES |
| Work Type |
BS REPR & O / L |
| |
|
9.741 |
1118221.98 |
31353.67 |
1370405.52 |
99.9 |
| Work Order |
06-04-09 |
| Work Began |
07-23-09 |
| Work Completed |
|
| Time Computed |
06-20-09 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
80 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-06-055 INTERSTATE BARRICADES & MARKINGS, INC. (0.45%) CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(3.29%) BATTERSON, L.L.P.(6.70%) JMHP, INC. (0.87%)
|
| Contract # |
04093649 |
|
Totals |
1118221.98 |
31353.67 |
1370405.52 |
99.9 |
|
| County | FORT BEND |
| Highway |
US 90A |
| From |
AT FM 762 |
| To |
. |
| CSJ |
0027-07-038 |
| Proj ID |
STP 2007(596) |
| Work Type |
ADD TURN LN |
| |
|
0.078 |
323853.49 |
20349.50 |
322026.35 |
99.4 |
| Work Order |
02-10-09 |
| Work Began |
03-16-09 |
| Work Completed |
|
| Time Computed |
02-26-09 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
57 |
| Percent Time Used |
95 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-07-038 THIRD COAST SERVICES, LLC( 25.92%) SEMARCK LANDSCAPE SERVICES, INC. (0.61%) HIGHWAY TECHNOLOGIES, INC. (1.43%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.96%) INTERSTATE BARRICADES & MARKINGS, INC. (6.40%)
|
| Contract # |
01093214 |
|
Totals |
323853.49 |
20349.50 |
322026.35 |
99.4 |
|
| County | FORT BEND |
| Highway |
US 90A |
| From |
0.1 MI W OF PRESENT STREET |
| To |
0.24 MI W OF FM 1092 |
| CSJ |
0027-08-145 |
| Proj ID |
STP 2005(475)MM |
| Work Type |
WIDEN GR, STRS, BASE & SURF |
| |
|
3.284 |
68927548.93 |
-19080.00 |
69080322.82 |
99.9 |
| Work Order |
10-12-05 |
| Work Began |
12-12-05 |
| Work Completed |
|
| Time Computed |
10-28-05 |
| Contract Working Days |
764 |
| Addl Days Granted |
0 |
| Working Days Charged |
719 |
| Percent Time Used |
94 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-08-145 A. H. BECK FOUNDATION CO., INC.(8.48%) BATTERSON, L.L.P.(0.46%) BOOTHE BROTHERS PAVING COMPANY, INC. (0.36%) DURWOOD GREENE CONSTRUCTION, L.P.(2.88%) GEORGE HEDGE CONTRACTOR, INC.(2.17%) HPP CORP (1.02%) J.H. PAINTING COMPANY(0.00%) NORTHWEST MATERIALS(0.10%) PELTIER BROTHERS CONS (SEE 15345),INC. (1.68%) PFEIFFER & SON LTD.(2.71%) PRIMATE CONSTRUCTION, INC. (0.18%) SLACK & CO. CONTRACTING, INC.(4.06%) W.W. WEBBER INC. (0.44%) WILLOW CITY SIGN & RAIL, INC.(0.32%) SIREN STEEL, INC.(1.81%) L. N. MCKEAN, INC. (0.08%) SPECIALTY SERVICES COMPANY (0.48%) KOSSMAN CONTRACTING COMPANY(0.74%) JV ENVIRONMENTAL SERVICES(0.13%) FLORES CURBS (0.10%) PFEIFFER & SON LTD.(0.14%) N. GARZA TRUCKING(3.04%) INDUS CONSTRUCTION, L.P. (0.28%) ROSALES TRUCKING (0.36%) GATEMAN, INC.(0.00%)
|
| Contract # |
07053255 |
|
Totals |
68927548.93 |
19080.00 |
69080322.82 |
99.9 |
|
| County | FORT BEND |
| Highway |
US 90A |
| From |
W OF SH 99 |
| To |
. |
| CSJ |
0027-08-165 |
| Proj ID |
CC 27-8-165 |
| Work Type |
GR, STRS, BASE AND PAVE |
| |
|
0.134 |
403676.48 |
11929.25 |
60194.35 |
14.9 |
| Work Order |
08-04-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
08-20-09 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
19 |
| Percent Time Used |
47 |
| Contractor(s) |
| SILVA CONTRACTING COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-08-165 BATTERSON, L.L.P.(2.89%) ENVIRONMENTAL ALLIES, L.P. (0.37%) ROZCO CONTRACTING, INC.( 12.77%) REGIONAL TRAFFIC SERVICES, LLC (0.63%) A-1 HYDRO-MULCHING OF TEXAS, INC.(2.37%)
|
| Contract # |
05093206 |
|
Totals |
403676.48 |
11929.25 |
60194.35 |
14.9 |
|
| County | HARRIS |
| Highway |
US 90A |
| From |
OLD SPANISH TRAIL AT BRAYS BAYOU |
| To |
. |
| CSJ |
0027-10-067 |
| Proj ID |
CC 27-10-67 |
| Work Type |
REPLACE BRIDGE |
| |
|
0.189 |
3948555.00 |
622686.95 |
2740432.09 |
69.0 |
| County | HARRIS |
| Highway |
US 90A |
| From |
OLD SPANISH TRAIL AT BRAYS BAYOU |
| To |
. |
| CSJ |
0027-10-068 |
| Proj ID |
CC 27-10-68 |
| Work Type |
ROW UTL. ADJ. (NON - REIMBURSABLE) |
| |
|
0.001 |
96445.00 |
150.00 |
20550.00 |
21.3 |
| Work Order |
03-20-09 |
| Work Began |
04-27-09 |
| Work Completed |
|
| Time Computed |
04-05-09 |
| Contract Working Days |
175 |
| Addl Days Granted |
0 |
| Working Days Charged |
162 |
| Percent Time Used |
92 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-10-067 BREDA COMPANY, INC.(0.79%) CREACOM, INC.(2.87%) JOE VALENCIK, INC. (0.31%) PROTECTIVE ENVIRONMENTAL STRATEGIES, INC.(0.85%) SCOTT DERR PAINTING CO (0.05%) REGIONAL TRAFFIC SERVICES, LLC (0.40%) CHERRY CRUSHED CONCRETE(0.40%) STOMPER DEMOLITION COMPANY, INC. (2.71%)
|
| Contract # |
02093206 |
|
Totals |
4045000.00 |
622836.95 |
2760982.09 |
67.9 |
|
| County | FORT BEND |
| Highway |
US 59 |
| From |
0.354 MI S OF UNIVERSITY BLVD |
| To |
0.678 MI N OF SH 6 |
| CSJ |
0027-12-062 |
| Proj ID |
NH 2004(368) |
| Work Type |
GR, STRS, BS & SURF |
| |
|
4.227 |
152255464.98 |
20267.10 |
147276603.18 |
97.1 |
| County | FORT BEND |
| Highway |
US 59 |
| From |
0.344 MI N OF FM 2759/SH 99 |
| To |
0.678 MI N OF SH 6 |
| CSJ |
0027-12-123 |
| Proj ID |
NH 2004(368) |
| Work Type |
ADJUSTMENT OF UTILITIES |
| |
|
0.001 |
314795.00 |
0.00 |
337022.00 |
99.9 |
| Work Order |
08-04-04 |
| Work Began |
08-25-04 |
| Work Completed |
|
| Time Computed |
08-20-04 |
| Contract Working Days |
1,227 |
| Addl Days Granted |
108 |
| Working Days Charged |
1,335 |
| Percent Time Used |
100 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-12-062 ODUM SERVICES, L.P.(0.74%) MICA CORPORATION (3.25%) BORING & TUNNELING COMPANY OF AMERI(0.07%) GEOSOURCE, INC.(0.09%) EROSION PREVENTION PRODUCTS(0.32%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.23%) SCOTT DERR PAINTING CO (0.14%) UNITED RENTALS HIGHWAY TECHNOLOGIES(0.84%) TREVCON(2.33%) BECO CONSTRUCTION., INC. (9.74%) SCOTT DERR PAINTING CO (0.28%) EROSION CONTROL, INC.(0.42%) PFEIFFER & SON LTD.(0.11%) SPECIALTY DRILLING (0.20%) VAQUERO CONSTRUCTION, INC. (0.32%) QUALITY TURF GRASS (0.25%)
|
| Contract # |
06043001 |
|
Totals |
152570259.98 |
20267.10 |
147613625.18 |
97.1 |
|
| County | HARRIS |
| Highway |
US 59 |
| From |
BELL ST |
| To |
S SHEPHERD |
| CSJ |
0027-13-162 |
| Proj ID |
CM 2007(769) |
| Work Type |
INST CTMS |
| |
|
3.604 |
1894460.36 |
0.00 |
1970460.27 |
99.9 |
| Work Order |
10-03-07 |
| Work Began |
10-22-07 |
| Work Completed |
|
| Time Computed |
10-19-07 |
| Contract Working Days |
312 |
| Addl Days Granted |
0 |
| Working Days Charged |
276 |
| Percent Time Used |
88 |
| Contractor(s) |
| FLORIDA TRAFFIC CONTROL DEVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-13-162 RNS CONSTRUCTION, LLC(3.16%)
|
| Contract # |
08073212 |
|
Totals |
1894460.36 |
0.00 |
1970460.27 |
99.9 |
|
| County | HARRIS |
| Highway |
US 59 |
| From |
AT IH 45 |
| To |
. |
| CSJ |
0027-13-198 |
| Proj ID |
NH 2010(049) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
0.454 |
305747.82 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-06-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-22-09 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0027-13-198 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09093018 |
|
Totals |
305747.82 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
US 90 |
| From |
0.40 MILES WEST OF NORMANDY ST. |
| To |
0.48 MILES EAST OF NORMANDY ST. |
| CSJ |
0028-02-044 |
| Proj ID |
HP 2006(708) |
| Work Type |
GR STRS SURF |
| |
|
3.129 |
45844448.40 |
21760.33 |
37744248.42 |
82.3 |
| Work Order |
08-02-06 |
| Work Began |
08-07-06 |
| Work Completed |
|
| Time Computed |
08-18-06 |
| Contract Working Days |
917 |
| Addl Days Granted |
33 |
| Working Days Charged |
491 |
| Percent Time Used |
55 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-044 ESSARY, HART & MACWILIAM,INC.(9.03%) SCOTT DERR PAINTING CO (0.09%) EROSION CONTROL, INC.(0.36%) VAQUERO CONSTRUCTION, INC. (1.73%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%) BORTUNCO (0.01%) WILLOW CITY SIGN & RAIL, INC.(0.47%) BATTERSON, L.L.P.(0.41%) FLORIDA TRAFFIC CONTROL DEVICES, INC.(4.73%) SPECIALTY DRILLING (0.23%)
|
| Contract # |
07063002 |
|
Totals |
45844448.40 |
21760.33 |
37744248.42 |
82.3 |
|
| County | HARRIS |
| Highway |
US 90 |
| From |
0.62 MI E OF HUNTING BAYOU |
| To |
0.590 MI. E. OF WALLISVILLE |
| CSJ |
0028-02-054 |
| Proj ID |
HP 2006(669) |
| Work Type |
GR, STRS & SURF |
| |
|
2.763 |
67299167.03 |
1618.66 |
55646334.10 |
82.6 |
| Work Order |
08-02-06 |
| Work Began |
08-07-06 |
| Work Completed |
|
| Time Computed |
08-18-06 |
| Contract Working Days |
1,176 |
| Addl Days Granted |
199 |
| Working Days Charged |
980 |
| Percent Time Used |
71 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-054 ESSARY, HART & MACWILIAM,INC.(9.63%) EROSION CONTROL, INC.(0.70%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.29%) VAQUERO CONSTRUCTION, INC. (0.58%) SCOTT DERR PAINTING CO (0.11%) ODUM SERVICES, L.P.(0.19%) PFEIFFER & SON LTD.(5.42%) L.A. UTILITIES, INC. (9.13%) BATTERSON, L.L.P.(0.81%) THE ANCHOR GROUP, INC. (0.03%) ODUM SERVICES, L.P.(0.09%) BORTUNCO (0.29%) SPECIALTY DRILLING (0.36%)
|
| Contract # |
07063201 |
|
Totals |
67299167.03 |
1618.66 |
55646334.10 |
82.6 |
|
| County | HARRIS |
| Highway |
US 90 |
| From |
BW 8 |
| To |
FM 2100 (IN SECTIONS) |
| CSJ |
0028-02-084 |
| Proj ID |
NH 2010(069) |
| Work Type |
FULL DPTH & SPALL REPR IN CONC PAV |
| |
|
9.026 |
498721.60 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-14-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-30-09 |
| Contract Working Days |
58 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
3 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-084 ROADSAFE TRAFFIC SYSTEMS, INC. (2.15%) HOLES INCORPORATED (7.29%)
|
| Contract # |
09093041 |
|
Totals |
498721.60 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
US 90 |
| From |
W OF KRENEK |
| To |
E OF RUNNEBURG |
| CSJ |
0028-02-087 |
| Proj ID |
STP 2009(557)ES |
| Work Type |
MILL, BASE REPAIR, SEAL COAT AND OV |
| |
|
2.072 |
1241291.35 |
34482.05 |
1103187.31 |
88.8 |
| Work Order |
06-08-09 |
| Work Began |
07-06-09 |
| Work Completed |
|
| Time Computed |
06-24-09 |
| Contract Working Days |
55 |
| Addl Days Granted |
0 |
| Working Days Charged |
48 |
| Percent Time Used |
87 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0028-02-087 BATTERSON, L.L.P.(4.92%) CROSS STONES RENTALS (0.14%) DARK HORSE SERVICES, INC.(2.57%)
|
| Contract # |
04093444 |
|
Totals |
1241291.35 |
34482.05 |
1103187.31 |
88.8 |
|
| County | HARRIS |
| Highway |
US 290 |
| From |
FM 529 |
| To |
200' NW OF TIDWELL'S CENTERLINE |
| CSJ |
0050-09-059 |
| Proj ID |
NH 2008(375) |
| Work Type |
TSM IMPROVEMENTS |
| |
|
1.193 |
2526731.50 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
99 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROZCO CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0050-09-059 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10093015 |
|
Totals |
2526731.50 |
0.00 |
0.00 |
0.0 |
|
| County | GALVESTON |
| Highway |
SH 3 |
| From |
AT CLEAR CREEK BRIDGE |
| To |
. |
| CSJ |
0051-03-097 |
| Proj ID |
NH 2010(050) |
| Work Type |
REPLC TR, FOUNDATION & REP RET WALL |
| |
|
0.159 |
234443.33 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-14-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-30-09 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-097 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09093228 |
|
Totals |
234443.33 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SH 3 |
| From |
IH 45 |
| To |
RICHEY STREET |
| CSJ |
0051-06-017 |
| Proj ID |
NH 2009(030) |
| Work Type |
FULL DEPTH CONC REP, PLANING & O / L |
| |
|
1.210 |
762505.69 |
0.00 |
691838.43 |
92.0 |
| Work Order |
03-12-09 |
| Work Began |
07-06-09 |
| Work Completed |
|
| Time Computed |
03-28-09 |
| Contract Working Days |
31 |
| Addl Days Granted |
0 |
| Working Days Charged |
51 |
| Percent Time Used |
164 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0051-06-017 MAIN LANE INDUSTRIES, LTD. (4.18%) HIGHWAY TECHNOLOGIES (6.35%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.47%) HOLES INCORPORATED (0.43%)
|
| Contract # |
02093224 |
|
Totals |
762505.69 |
0.00 |
691838.43 |
92.0 |
|
| County | GALVESTON |
| Highway |
FM 3005 |
| From |
SAN LUIS PASS TOLL BRIDGE |
| To |
WEST END OF GALVESTON'S SEAWALL |
| CSJ |
0051-09-023 |
| Proj ID |
STP 2010(051)ES |
| Work Type |
RAISE RDWY & BS REPR (PH 1) |
| |
|
18.273 |
3866866.75 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-02-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-18-09 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0051-09-023 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09093222 |
|
Totals |
3866866.75 |
0.00 |
0.00 |
0.0 |
|
| County | FORT BEND |
| Highway |
US 59 |
| From |
US 59 SB |
| To |
AT SNAKE CREEK AND TURKEY CREEK |
| CSJ |
0089-09-072 |
| Proj ID |
BR 2010(052) |
| Work Type |
REPLACE 2 BRIDGES |
| |
|
0.410 |
1999760.18 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-06-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-22-09 |
| Contract Working Days |
150 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LONE STAR ROAD CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-072 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09093220 |
|
Totals |
1999760.18 |
0.00 |
0.00 |
0.0 |
|
| County | MONTGOMERY |
| Highway |
SH 75 |
| From |
AT ESPERANZA |
| To |
. |
| CSJ |
0110-02-021 |
| Proj ID |
STP 2010(143)SB |
| Work Type |
INSTALL LEFT TURN LANE |
| |
|
1.126 |
529307.31 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0110-02-021 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10093228 |
|
Totals |
529307.31 |
0.00 |
0.00 |
0.0 |
|
| County | MONTGOMERY |
| Highway |
IH 45 |
| From |
FM 1488 |
| To |
NORTH OF CREIGHTON ROAD |
| CSJ |
0110-04-181 |
| Proj ID |
CM 2008(835) |
| Work Type |
INSTALL CTMS |
| |
|
2.584 |
296099.02 |
71205.12 |
141506.05 |
47.7 |
| Work Order |
06-16-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
07-02-09 |
| Contract Working Days |
312 |
| Addl Days Granted |
0 |
| Working Days Charged |
95 |
| Percent Time Used |
30 |
| Contractor(s) |
| TRANSCORE ITS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-181 TEXAS FIBER FUSION ( 15.59%) SPECIALTY DRILLING (3.56%)
|
| Contract # |
05093211 |
|
Totals |
296099.02 |
71205.12 |
141506.05 |
47.7 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
CYPRESSWOOD DRIVE |
| To |
MONTGOMERY COUNTY LINE |
| CSJ |
0110-05-115 |
| Proj ID |
IM 0451(335) |
| Work Type |
PAVEMENT MARKINGS |
| |
|
4.037 |
157164.75 |
0.00 |
0.00 |
0.0 |
| Work Order |
10-14-09 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
10-30-09 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HIGHWAY TECHNOLOGIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0110-05-115 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09093215 |
|
Totals |
157164.75 |
0.00 |
0.00 |
0.0 |
|