Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway FM 1960
From AT KUYKENDAHL
To .
CSJ 1685-01-082
Proj ID STP 2007(048)MM
Work Type GRADE SEPARATION
 
0.334 18497065.46 6791.59 19146898.18 99.3
Work Order 01-08-07
Work Began 02-26-07
Work Completed  
Time Computed 01-24-07
Contract Working Days 564
Addl Days Granted 89
Working Days Charged 641
Percent Time Used 98
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-082
GMJ PAVING CO. (3.97%)
TRAF-TEX, INC. (2.08%)
UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(1.05%)
R & B GROUP, INC.(4.21%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.86%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15%)
A. H. BECK FOUNDATION CO., INC.(8.55%)
HOUSTON SAWING & DRILLING(0.02%)
SCOTT DERR PAINTING CO (0.11%)
CHAMPIONS HYDROLAWN(0.05%)
BECO CONSTRUCTION, L.L.C.(0.05%)
MESA ROD BUSTERS, INC. (0.74%)
CHERRY CONCRETE REMOVAL(0.25%)
FLORES CURBS (0.04%)
BECO CONSTRUCTION, L.L.C.(0.02%)
Contract # 10063203
Totals 18497065.46 6791.59 19146898.18 99.3

CountyHARRIS
Highway FM 1960
From 0.52 MI WEST OF SH 249
To 0.38 MI WEST OF IH 45
CSJ 1685-01-091
Proj ID STP 2009(882)MM
Work Type IMPLEMENT ACCESS MANAGEMENT TRTMNTS
 
7.670 2049489.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-09
Work Began 00-00-00
Work Completed  
Time Computed 10-30-09
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08093022
Totals 2049489.16 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1314
From 0.212 MI NW OF MILLS ROAD
To 0.126 MI SE OF MILLS ROAD
CSJ 1986-01-059
Proj ID STP 2010(065)ES
Work Type DRAINAGE IMPROVEMENTS
 
0.338 367819.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-06-09
Work Began 00-00-00
Work Completed  
Time Computed 11-22-09
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STONERIDGE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1986-01-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09093048
Totals 367819.89 0.00 0.00 0.0

CountyFORT BEND
Highway FM 2218
From AT POWERLINE ROAD
To .
CSJ 2093-01-024
Proj ID STP 2009(895)SB
Work Type INSTALL LEFT TURN LANE
 
0.224 160983.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 2093-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11093028
Totals 160983.86 0.00 0.00 0.0

CountyBRAZORIA
Highway FM 2004
From SH 288
To BS 288
CSJ 2523-02-030
Proj ID STP 2009(697)ES
Work Type GR, WID STRS, BS & P
 
3.218 18488622.01 1700156.51 1700156.51 9.1
Work Order 09-01-09
Work Began 10-15-09
Work Completed  
Time Computed 09-17-09
Contract Working Days 485
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 2
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2523-02-030
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.00%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (6.33%)
SCOTT DERR PAINTING CO (0.15%)
TREVCON, INC.(3.11%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.14%)
HIGHWAY TECHNOLOGIES, INC. (0.63%)
BATTERSON, L.L.P.(0.60%)
INDUS CONSTRUCTION, L.P. (3.14%)
ATLAS CONCRETE ENTERPRISES, INC. (1.20%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 12.94%)
Contract # 07093202
Totals 18488622.01 1700156.51 1700156.51 9.1

CountyBRAZORIA
Highway FM 2004
From CHOCOLATE BAYOU
To NEW BAYOU
CSJ 2523-02-061
Proj ID STP 2009(269)
Work Type WIDE TO ADD 10 FT SHLDRS
 
25.752 4456457.76 117227.88 5024138.02 99.9
Work Order 04-01-09
Work Began 04-21-09
Work Completed  
Time Computed 04-17-09
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 161
Percent Time Used 130
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 2523-02-061
EROSION CONTROL, INC.(0.22%)
WEST TEXAS RUMBLE STRIP(0.11%)
HIGHWAY TECHNOLOGIES, INC. (0.22%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.94%)
THIRD COAST SERVICES, LLC(0.85%)
INTERSTATE BARRICADES & MARKINGS, INC. (6.42%)
Contract # 02093002
Totals 4456457.76 117227.88 5024138.02 99.9

CountyHARRIS
Highway FM 2978
From MONTGOMERY C/L
To FM 2920
CSJ 3050-03-005
Proj ID STP 2007(510)MM
Work Type GR, STRS, BS & SURF
 
2.288 11581370.88 94209.78 94209.78 0.8
CountyHARRIS
Highway FM 2978
From 0.307 MILES NORTH OF UPRR
To 0.470 MILES SOUTH OF UPRR
CSJ 3050-03-012
Proj ID STP 2007(822)ES
Work Type GR, STRS, BASE & PAVT
 
0.777 6909231.46 10400.00 10400.00 0.1
Work Order 10-14-09
Work Began 10-19-09
Work Completed  
Time Computed 10-19-09
Contract Working Days 507
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 1
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3050-03-005
A & G EBERHARDT ENTERPRISES, INC.(1.16%)
A. H. BECK FOUNDATION CO., INC.(0.06%)
EROSION CONTROL, INC.(1.05%)
HIGHWAY TECHNOLOGIES, INC. (0.05%)
SCOTT DERR PAINTING CO (0.08%)
TEXAS LAND CLEARING SERVICE(0.06%)
WEBBER BARRIER SERVICES, INC.(1.46%)
WILLOW CITY SIGN & RAIL, INC.(0.63%)
CRAVENS SERVICES, INC. ( 21.57%)
BATTERSON, L.L.P.(0.60%)
Contract # 08093206
Totals 18490602.34 104609.78 104609.78 0.5

CountyHARRIS
Highway BW 8
From S OF BISSONNET
To N OF BEECHNUT
CSJ 3256-01-083
Proj ID NH 2006(073)
Work Type GR, BS, CRCP & PAV MRKS
 
1.727 4949227.49 0.00 5407665.58 99.9
Work Order 11-06-06
Work Began 12-04-06
Work Completed  
Time Computed 12-04-06
Contract Working Days 194
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 106
Contractor(s)
SOUTH COAST CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-083
PEREZ CONSTRUCTION CO. (0.01%)
SEAMARCK LANDSCAPE SERVICES, INC (0.53%)
MAGNUM TUNNELING, LLC(0.02%)
CPAV SPECIALTIES, LP (1.71%)
SPECIALTY DRILLING (2.48%)
NORTHWEST MATERIALS(0.13%)
WORK ZONE PRODUCTS, INC. (1.00%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(0.18%)
UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(2.33%)
W.W. WEBBER, LLC (5.96%)
MAIN LANE INDUSTRIES, LTD. (0.89%)
JMHP, INC. (4.93%)
CHERRY CONCRETE REMOVAL(1.38%)
SCOTT DERR PAINTING CO (0.69%)
DORAN STEEL, INC.(1.50%)
Contract # 09063208
Totals 4949227.49 0.00 5407665.58 99.9

CountyHARRIS
Highway BW 8
From AT WHITE OAK BAYOU
To .
CSJ 3256-01-094
Proj ID STP 2010(066)ES
Work Type EMERGENCY RELIEF REPAIRS
 
0.034 106335.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-04-09
Work Began 00-00-00
Work Completed  
Time Computed 11-20-09
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAS CONTRACTORS, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09093259
Totals 106335.60 0.00 0.00 0.0

CountyHARRIS
Highway BW 8
From WEST OF GREENSPOINT DR.
To WEST HARDY ROAD
CSJ 3256-02-061
Proj ID CM 2008(838)
Work Type GR, STRS, BASE AND PAVE
 
2.451 15013244.15 0.00 0.00 0.0
CountyHARRIS
Highway BW 8
From IH 45N
To HARDY TOLL ROAD
CSJ 3256-02-070
Proj ID CM 2006(382)
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
1.553 390857.00 0.00 0.00 0.0
Work Order 05-22-09
Work Began 09-05-09
Work Completed  
Time Computed 09-05-09
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 4
Contractor(s)
SOUTH COAST CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03093228
Totals 15404101.15 0.00 0.00 0.0

CountyHARRIS
Highway BW 8
From AT US 59 NORTH
To .
CSJ 3256-02-074
Proj ID STP 2009(658)ES
Work Type CONSTRUCT 4 DCS
 
1.624 29595089.52 2437673.43 2437673.43 8.2
Work Order 10-06-09
Work Began 10-15-09
Work Completed  
Time Computed 10-22-09
Contract Working Days 478
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 1
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-074
INDUS CONSTRUCTION, L.P. (5.92%)
EROSION CONTROL, INC.(0.10%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
JOE VALENCIK, INC. (0.12%)
CREACOM, INC.(1.36%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.76%)
SCOTT DERR PAINTING CO (1.67%)
Contract # 08093001
Totals 29595089.52 2437673.43 2437673.43 8.2

CountyHARRIS
Highway BW 8
From 0.50 MI W. OF US 59
To 0.75 MI E. OF US 59
CSJ 3256-02-078
Proj ID HP 2007(600)
Work Type LANDSCAPE DEVELOPMENT
 
3.286 617148.12 1297.42 600391.31 97.2
Work Order 07-09-07
Work Began 08-06-07
Work Completed  
Time Computed 07-25-07
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 85
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-078
MIKELS CONSTRUCTION CO., INC.(1.86%)
SUSTAINABLE GROWTH TEXAS (7.24%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.73%)
Contract # 06073014
Totals 617148.12 1297.42 600391.31 97.2

CountyHARRIS
Highway BW 8
From IH 45 N
To W OF UPRR
CSJ 3256-02-079
Proj ID CM 2007(830)
Work Type INSTALL CTMS
 
37.627 20754799.00 276878.80 19285690.69 92.9
Work Order 12-05-07
Work Began 07-07-08
Work Completed  
Time Computed 06-02-08
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 412
Percent Time Used 52
Contractor(s)
EAS CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-079
WILLOW CITY SIGN & RAIL, INC.(0.40%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.15%)
W. W. FOUNDATION DRILLING, LTD.(1.15%)
ANCHOR FENCE (0.10%)
DEVOLVE CORP (0.52%)
SUPERIOR GROUTING SERVICES, INC. (1.16%)
LONE STAR PRESTRESS(1.19%)
CONDUIT CONSTRUCTORS (1.28%)
Contract # 08073008
Totals 20754799.00 276878.80 19285690.69 92.9

CountyHARRIS
Highway BW 8
From IH 45 NORTH
To US 59 NORTH
CSJ 3256-02-080
Proj ID NH 2009(644)
Work Type PAVEMENT MARKINGS
 
6.959 236777.97 0.00 0.00 0.0
Work Order 10-14-09
Work Began 00-00-00
Work Completed  
Time Computed 10-30-09
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09093213
Totals 236777.97 0.00 0.00 0.0

CountyHARRIS
Highway BW 8
From AT VISTA,SPENCER,PASADENA BLVD_&
To RED BLUFF
CSJ 3256-03-072
Proj ID CM 2007(854)ES
Work Type TURN RADIUS IMPROVEMENTS
 
0.360 2349189.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-09
Work Began 00-00-00
Work Completed  
Time Computed 11-18-09
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 3256-03-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09093006
Totals 2349189.33 0.00 0.00 0.0

CountyHARRIS
Highway BW 8
From SABO/HUGHES
To SH 3
CSJ 3256-03-083
Proj ID HP 2009(334)
Work Type LANDSCAPE DEVELOPMENT
 
1.900 705933.07 24007.64 443953.81 62.8
Work Order 04-03-09
Work Began 04-30-09
Work Completed  
Time Computed 04-30-09
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 58
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-03-083
TREES OF DELTA II, LLC (4.11%)
Contract # 01093222
Totals 705933.07 24007.64 443953.81 62.8

CountyFORT BEND
Highway SH 99
From AT US 90A
To .
CSJ 3510-04-029
Proj ID CM 2008(750)
Work Type ADD 5 TURN LANES
 
0.670 698662.09 5555.45 691853.82 99.0
Work Order 01-05-09
Work Began 02-20-09
Work Completed  
Time Computed 01-21-09
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-029
EROSION CONTROL, INC.(0.57%)
HIGHWAY TECHNOLOGIES, INC. (6.03%)
THIRD COAST SERVICES, LLC(8.00%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.72%)
A TEX-DBE, INC.(4.29%)
CENTRAL CONSTRUCTION SERVICES, INC.(3.51%)
CLEARWATER UTILITIES, INC. ( 12.90%)
CURB PLANET INC. (0.21%)
URETEK USA, INC. (1.10%)
CLEANSERVE, INC. (0.81%)
Contract # 11083010
Totals 698662.09 5555.45 691853.82 99.0

CountyFORT BEND
Highway SH 99
From BELLAIRE BLVD
To FM 1093 (SEGMENT D)
CSJ 3510-04-030
Proj ID CC 3510-4-30
Work Type GR, STRS, BASE AND PAVE
 
0.694 2246392.68 0.00 2029164.38 90.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-12-09
Work Began 02-16-09
Work Completed  
Time Computed 01-28-09
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 133
Percent Time Used 73
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-030
THIRD COAST SERVICES, LLC(1.35%)
CRAWFORD YANT(4.29%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.94%)
BATTERSON, L.L.P.(0.69%)
CROSS STONES RENTALS (0.29%)
Contract # 12083010
Totals 2246392.68 0.00 2029164.38 90.3

CountyHARRIS
Highway MH
From IN HOUSTON ON LITTLE YORK RD FROM E
To HARDY RD TO US 59
CSJ 8004-12-003
Proj ID C 8004-12-3
Work Type GR, STRS & SURF
 
1.920 13759609.15 0.00 13301831.95 99.9
CountyHARRIS
Highway MH
From IN HOUSTON ON LITTLE YORK RD FROM E
To HARDY RD TO US 59
CSJ 8004-12-005
Proj ID CC 8004-12-5
Work Type UTILITY ADJUSTMENTS
 
2.000 2196138.00 0.00 1983322.92 95.0
Work Order 11-02-06
Work Began 11-27-06
Work Completed  
Time Computed 11-18-06
Contract Working Days 337
Addl Days Granted 0
Working Days Charged 337
Percent Time Used 100
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 8004-12-003
WILLOW CITY SIGN & RAIL, INC.(0.25%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.20%)
UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(0.99%)
GMJ PAVING CO. (1.23%)
EROSION CONTROL, INC.(0.65%)
CREACOM, INC.(6.73%)
RODS SURVEYING, INC. (0.15%)
KAISER BROTHERS, INC.(0.29%)
MICKIE SERVICE, INC. (0.12%)
TWO WAY BARRICADE EQUIPMENT, INC.(0.03%)
PRIMATE CONSTRUCTION, INC. (0.01%)
Contract # 07063207
Totals 15955747.15 0.00 15285154.87 99.9