Monthly State Let Construction Report For Houston District As Of Aug 12, 2014 Page 9 Of 10

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGALVESTON
Highway FM 517
From AT FM 146
To .
CSJ 0978-02-071
Proj ID STP 2014(035)HES
Work Type TS IMPRVMT & LT TN LN
 
0.537 959632.80 0.00 0.00 0.0
Work Order 11-22-13
Work Began 00-00-00
Work Completed  
Time Computed 12-08-13
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-071
LONE STAR TRAFFIC SERVICE, INC.(0.28%)
REGIONAL TRAFFIC SERVICES LLC(3.73%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.32%)
Contract # 09133220
Totals 959632.80 0.00 0.00 0.0

CountyBRAZORIA
Highway FM 524
From FM 521
To CR 334
CSJ 1004-01-052
Proj ID STP 2012(519)
Work Type UPGRADE DRAINAGE STRUCTURES
 
3.176 249163.00 0.00 204161.86 92.8
Work Order 07-09-12
Work Began 08-17-12
Work Completed  
Time Computed 07-25-12
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 253
Contractor(s)
NNA FINANCIAL SERVICES CO.
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-052
HIGHWAY TECHNOLOGIES, INC. (1.41%)
Contract # 05123213
Totals 249163.00 0.00 204161.86 92.8

CountyHARRIS
Highway FM 529
From FREEMAN ROAD
To W OF FRY ROAD
CSJ 1006-01-059
Proj ID NH 2012(474)
Work Type GR, STRS, BASE AND SURF
 
1.184 7690213.53 335424.55 3571564.39 46.4
Work Order 01-31-13
Work Began 03-15-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 322
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 45
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-059
HIGHWAY TECHNOLOGIES, INC. (0.79%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.42%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.77%)
ROSALES TRUCKING (1.50%)
BATTERSON,LLP(0.97%)
DURWOOD GREENE CONSTRUCTION CO.(7.49%)
Contract # 10123217
Totals 7690213.53 335424.55 3571564.39 46.4

CountyMONTGOMERY
Highway FM 1485
From SL 494
To HARRIS C/L
CSJ 1062-01-029
Proj ID STP 2014(036)
Work Type BASE REPAIR AND ACP O / L
 
10.852 1568958.32 11013.66 1468355.67 93.5
Work Order 01-17-14
Work Began 03-18-14
Work Completed  
Time Computed 03-18-14
Contract Working Days 35
Addl Days Granted 3
Working Days Charged 35
Percent Time Used 92
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1062-01-029
BATTERSON,LLP(6.09%)
WATERS CONSTRUCTION CO., INC.( 14.63%)
WEST TEXAS RUMBLE STRIP(0.61%)
J & M CONTRACTING, COMPANY (0.25%)
Contract # 10133023
Totals 1568958.32 11013.66 1468355.67 93.5

CountyHARRIS
Highway FM 2100
From FM 1960 (GUY ROAD)
To 0.066 M. S OF HUFFMAN-CLEVELAND RD
CSJ 1062-02-023
Proj ID STP 2013(696)
Work Type MILL & ACP OVERLAY
 
12.426 5966662.66 7163.99 5539421.50 92.8
Work Order 07-31-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 186
Addl Days Granted 3
Working Days Charged 178
Percent Time Used 94
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-023
SIEMENS INDUSTRY, INC. (1.83%)
PROFESSIONAL TRAFFIC CONTROL, LLC(3.07%)
WILLOW CITY SIGN & RAIL, INC.(1.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(2.08%)
SOUTHWEST SIGNAL SUPPLY, INC.(0.35%)
CURB PLANET INC. (0.99%)
Contract # 05133003
Totals 5966662.66 7163.99 5539421.50 92.8

CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MI S. OF FIRST STREET
CSJ 1062-04-047
Proj ID STP 2010(903)RGS
Work Type CONST RR GRADE SEPARATION STR & APP
 
0.870 8537094.26 0.00 11311630.75 99.9
CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MILE SOUTH OF FIRST STREET
CSJ 1062-04-051
Proj ID STP 2011(543)ES
Work Type UTILITY ADJUSTMENT
 
0.870 335846.50 4832.19 575841.86 99.9
Work Order 09-01-10
Work Began 11-28-11
Work Completed  
Time Computed 09-17-10
Contract Working Days 455
Addl Days Granted 101
Working Days Charged 556
Percent Time Used 100
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047
ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%)
BATTERSON,LLP(0.79%)
HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%)
HOUSTON SAWING & DRILLING(0.09%)
JTB SERVICES (0.33%)
KOSSMAN CONTRACTING CO., INC.(0.23%)
REPUBLIC TRAFFIC SAFETY, INC.(0.43%)
SCOTT DERR PAINTING CO, LLC(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%)
MICKIE SERVICE, INC. (0.10%)
SAN JACINTO BORING & TUNNELING, INC. (0.23%)
SOUTHERN CRUSHED CONCRETE LLC(0.31%)
PM CONSTRUCTION & REHAB, LLC (1.62%)
JMHP, INC. (0.52%)
GMJ PAVING CO. (3.78%)
BREDA COMPANY, INC.(0.61%)
H & H CURB COMPANY (0.09%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%)
ENVIRONMENTAL ALLIES, L.P. (0.24%)
DORAN STEEL, INC.(0.18%)
LOPEZ UTILITIES, LLC (0.23%)
R & A BORING COMPANY (0.30%)
Contract # 07103015
Totals 8872940.76 4832.19 11887472.61 99.9

CountyHARRIS
Highway FM 1093
From 3.6 MILES WEST OF IH 610
To 0.25 MILES EAST OF SH 6
CSJ 1258-04-056
Proj ID CM 2013(790)
Work Type IMPLEMENTATION OF ACCESS MGMT
 
7.386 2561914.38 130301.72 1598607.66 62.3
Work Order 11-04-13
Work Began 02-11-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 81
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-056
KOSSMAN CONTRACTING CO., INC.(0.45%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.22%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC( 35.08%)
Contract # 07133031
Totals 2561914.38 130301.72 1598607.66 62.3

CountyMONTGOMERY
Highway FM 1774
From 0.045 MI S OF W. LOST CREEK BLVD
To FM 149
CSJ 1400-04-011
Proj ID STP 1402(182)
Work Type GR, STRS, BS & CONC PAV
 
2.831 18070204.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143203
Totals 18070204.05 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.109 MI N OF FM 1488
To 0.045 MI S OF W LOST CREEK BLVD
CSJ 1400-04-035
Proj ID STP 1102(437)
Work Type RECONSTRUCT ROADWAY
 
2.320 11301777.00 1565082.54 10484788.07 92.7
Work Order 11-03-11
Work Began 12-06-11
Work Completed  
Time Computed 11-19-11
Contract Working Days 280
Addl Days Granted 287
Working Days Charged 421
Percent Time Used 74
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-035
GULF COAST PAVERS, INC.(0.22%)
GMJ PAVING CO. (7.32%)
H & H CURB COMPANY (0.12%)
BREDA COMPANY, INC.(0.89%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.36%)
BATTERSON,LLP(1.83%)
THIRD COAST SERVICES, LLC(4.26%)
URBAN FORESTERS, LLC (0.44%)
CHAMPIONS HYDRO-LAWN (0.80%)
Contract # 08113209
Totals 11301777.00 1565082.54 10484788.07 92.7

CountyBRAZORIA
Highway FM 1462
From AT COUNTY ROAD 185
To .
CSJ 1414-03-039
Proj ID STP 2013(791)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.283 481635.62 24081.08 77981.08 16.1
Work Order 09-12-13
Work Began 03-11-14
Work Completed  
Time Computed 11-11-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 38
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1414-03-039
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
BATTERSON,LLP(3.54%)
JMHP, INC. (1.34%)
MIKE SORRELL TRUCKING AND MATERIALS, INC.(0.72%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.97%)
Contract # 07133015
Totals 481635.62 24081.08 77981.08 16.1

CountyFORT BEND
Highway FM 1464
From AT PUMPKIN LAKE
To .
CSJ 1415-02-045
Proj ID STP 2013(848)
Work Type DETENTION POND
 
0.100 495924.72 86478.29 535008.32 99.9
Work Order 02-12-14
Work Began 03-31-14
Work Completed  
Time Computed 03-31-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 92
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 1415-02-045
SILT SOLUTIONS, INC. (0.16%)
BILL MURFF TURF FARMS, INC.(6.05%)
CHAMPIONS HYDRO-LAWN (2.70%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.89%)
LONESTAR TRAFFIC SAFETY, LLC (0.35%)
CANALES TRUCKING INC.( 11.09%)
SOUTHLAND FENCE COMPANY(4.59%)
Contract # 01143010
Totals 495924.72 86478.29 535008.32 99.9

CountyGALVESTON
Highway FM 1764
From CENTURY BLVD INT FROM 14TH STREET
To 21ST STREET
CSJ 1607-01-050
Proj ID STP 2011(250)TE
Work Type ENHANCEMENT PROJECT
 
1.200 704750.96 56931.28 323660.61 45.9
Work Order 09-05-13
Work Began 10-22-13
Work Completed  
Time Computed 10-22-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 77
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1607-01-050
CC TREE FARMS, L.L.C.(0.93%)
ENVIRONMENTAL ALLIES, L.P. (0.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.35%)
VACA UNDERGROUND UTILITIES INC (1.38%)
PFEIFFER & SON LTD.( 30.86%)
RANGEL CONSTRUCTION(5.95%)
Contract # 06133212
Totals 704750.96 56931.28 323660.61 45.9

CountyHARRIS
Highway FM 1960
From IH 45
To 6.5 MI E OF IH 45 (HUMBLE BYPASS)
CSJ 1685-02-049
Proj ID NH 2013(064)
Work Type PAVEMENT MARKINGS
 
14.553 546380.10 0.00 390018.83 80.6
Work Order 10-18-12
Work Began 11-18-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 169
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123024
Totals 546380.10 0.00 390018.83 80.6

CountyHARRIS
Highway FM 1960
From AT LEE ROAD
To .
CSJ 1685-03-092
Proj ID STP 2014(585)HES
Work Type IMPROVE TS
 
0.606 732234.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1685-03-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143011
Totals 732234.51 0.00 0.00 0.0

CountyHARRIS
Highway SH 6
From IH 10 W.
To US 290
CSJ 1685-05-104
Proj ID NH 2014(300)
Work Type ACCESS MANAGEMENT
 
12.205 3853845.41 165735.67 165735.67 4.3
Work Order 04-17-14
Work Began 07-10-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 8
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-104
CURB PLANET INC. (2.25%)
GMJ PAVING CO. (1.69%)
HOLES INCORPORATED (3.23%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(6.74%)
SPEEDY PAVING(9.48%)
BILL MURFF TURF FARM, INC. (0.68%)
BATTERSON,LLP(5.84%)
CHAMPIONS HYDRO-LAWN (0.05%)
CHERRY CRUSHED CONCRETE(0.76%)
SILT SOLUTIONS, INC. (0.11%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.96%)
WEBBER BARRIER SERVICES, LLC.(4.46%)
Contract # 02143213
Totals 3853845.41 165735.67 165735.67 4.3

CountyHARRIS
Highway BF1960A
From FM 1960 W OF LEE RD
To FM 1960 E OF HUMBLE
CSJ 1685-07-005
Proj ID C 1685-7-5
Work Type IMPLEMENT ACCESS MANAGEMENT
 
3.920 6976168.04 0.00 0.00 0.0
CountyHARRIS
Highway BF1960A
From LEE ROAD
To FM 1960(E)
CSJ 1685-07-019
Proj ID STP 2013(994)
Work Type BS REP, MILL, SC INTERLAYER, OL, ETC
 
4.200 6317731.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1685-07-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133014
Totals 13293900.01 0.00 0.00 0.0

CountyWALLER
Highway FM 1887
From SH 159
To FM 359
CSJ 1745-01-019
Proj ID STP 2013(545)
Work Type BS REPR, SC, LVL UP, ACP O / L & PAV MRK
 
13.729 5083865.74 94026.32 5172096.88 100.0
Work Order 07-01-13
Work Began 10-10-13
Work Completed 07-09-14
Time Computed 09-29-13
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 87
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1745-01-019
PROFESSIONAL TRAFFIC CONTROL, LLC(3.48%)
SEAMARCK LANDSCAPE SERVICES, INC (0.18%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.03%)
Contract # 04133228
Totals 5083865.74 94026.32 5172096.88 100.0

CountyFORT BEND
Highway FM 2234
From FM 3345
To FORT BEND TOLL ROAD
CSJ 2105-01-046
Proj ID C 2105-1-46
Work Type GR, STRS, BS & SURF
 
1.458 8068060.38 700946.79 4509796.20 55.8
Work Order 10-30-13
Work Began 01-21-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 49
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-046
B & D MAINTENANCE(1.89%)
CPAVE, INC.(0.31%)
SCOTT DERR PAINTING CO, LLC(0.13%)
DUSTROL, INC.(1.65%)
THIRD COAST SERVICES LLC (8.64%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.89%)
BATTERSON,LLP(2.16%)
A-1 EROSION CONTROL, LLC (2.12%)
BREDA COMPANY, INC.(0.79%)
H & E AGGREGATE, LLC (7.21%)
SILVA CONSTRUCTION, INC. (3.85%)
Contract # 07133218
Totals 8068060.38 700946.79 4509796.20 55.8

CountyFORT BEND
Highway FM 2234
From US 90A
To TURTLE CREEK DR
CSJ 2105-01-047
Proj ID STP 2013(698)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.314 1659983.68 24764.63 1633884.57 98.4
Work Order 08-02-13
Work Began 02-19-14
Work Completed  
Time Computed 10-01-13
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 98
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-047
TRAF-TEX, INC. ( 55.72%)
REGIONAL TRAFFIC SERVICES LLC(1.70%)
KOSSMAN CONTRACTING CO., INC.(0.22%)
ENERGY ELECTRIC SUPPLY, INC. (5.96%)
TEXAS REEXCAVATION (1.32%)
Contract # 05133015
Totals 1659983.68 24764.63 1633884.57 98.4

CountyMONTGOMERY
Highway FM 2432
From AT TEXAS NATIONAL BOULEVARD
To .
CSJ 2325-01-016
Proj ID STP 2014(597)
Work Type INSTALL LEFT TURN LANE
 
0.256 399448.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-14
Work Began 00-00-00
Work Completed  
Time Computed 08-07-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2325-01-016
DUSTROL, INC.(1.25%)
J & M CONTRACTING, COMPANY ( 12.20%)
LONESTAR TRAFFIC SAFETY, LLC (0.36%)
STRIPE-A-LINE, INC.(0.73%)
A-1 EROSION CONTROL, LLC (6.25%)
WILLOW CITY SIGN & RAIL, INC.(0.62%)
Contract # 06143062
Totals 399448.91 0.00 0.00 0.0