Monthly State Let Construction Report For Houston District As Of Dec 10, 2014 Page 9 Of 11

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGALVESTON
Highway VA
From AT THE GALVESTON FERRY LANDING
To .
CSJ 0912-73-193
Proj ID FT 912-73-193
Work Type CONSTRUCT NEW BOAT LIFT
 
0.001 305695.00 8253.77 264426.18 86.5
Work Order 05-08-14
Work Began 08-13-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 37
Working Days Charged 130
Percent Time Used 82
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-193
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143230
Totals 305695.00 8253.77 264426.18 86.5

CountyGALVESTON
Highway VA
From AT GALV AND BOLIVAR FERRY LANDING
To .
CSJ 0912-73-194
Proj ID C 912-73-194
Work Type CONSTRUCT NEW SCREENING CANOPIES
 
0.001 731490.00 43279.40 579418.32 79.2
Work Order 05-08-14
Work Began 05-27-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 120
Addl Days Granted 11
Working Days Charged 132
Percent Time Used 100
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-194
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143231
Totals 731490.00 43279.40 579418.32 79.2

CountyHARRIS
Highway FM 865
From ALMEDA-GENOA
To BW 8
CSJ 0976-01-019
Proj ID C 976-1-19
Work Type GR, BS & SURF
 
1.272 13285921.44 0.00 309823.10 2.3
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 11-09-14
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133025
Totals 13285921.44 0.00 309823.10 2.3

CountyHARRIS
Highway FM 865
From SOUTH OF BW 8
To BRAZORIA COUNTY LINE(CLEAR CREEK)
CSJ 0976-01-035
Proj ID STP 1102(436)
Work Type CR, BS & SURF
 
1.106 9266318.15 0.00 9267159.36 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-11
Work Began 11-29-11
Work Completed 09-09-14
Time Computed 11-12-11
Contract Working Days 410
Addl Days Granted 0
Working Days Charged 410
Percent Time Used 100
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-035
EMBARK TREE AND LANDSCAPE SERVICES (0.35%)
URBAN FORESTERS, LLC (0.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(4.74%)
GMJ PAVING CO. (2.40%)
BREDA COMPANY, INC.(0.58%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
BATTERSON,LLP(1.10%)
CHAMPIONS HYDROLAWN(0.33%)
JMHP, INC. (0.05%)
H & H CURB COMPANY (0.11%)
NBG CONSTRUCTORS, INC. ( 22.94%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.39%)
MESA ROD BUSTERS, INC. (0.00%)
CHERRY CONCRETE REMOVAL(0.26%)
DORAN STEEL, INC.(0.04%)
WALLACE CONCRETE SAWING(0.06%)
Contract # 08113207
Totals 9266318.15 0.00 9267159.36 100.0

CountyGALVESTON
Highway FM 518
From BAY AREA BLVD
To FM 2094
CSJ 0976-03-100
Proj ID C 976-3-100
Work Type ACCESS MANAGEMENT IMPROVEMENTS
 
0.668 1295137.47 0.00 1105297.00 90.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-13
Work Began 02-12-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 221
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-100
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 25.48%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.48%)
AGGREGATE TECHNOLOGIES, INC. (1.99%)
SPEEDY PAVING(1.62%)
Contract # 08133223
Totals 1295137.47 0.00 1105297.00 90.2

CountyGALVESTON
Highway FM 646
From GRAND AVE
To FM 517
CSJ 0978-02-054
Proj ID STP 2007(404)
Work Type INST CULV, ADJ DRWAYS & RESTORE DRNG
 
3.700 5827858.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143223
Totals 5827858.98 0.00 0.00 0.0

CountyGALVESTON
Highway FM 517
From AT FM 3436
To .
CSJ 0978-02-069
Proj ID STP 2014(570)HES
Work Type INST INTERSECTION FLASHING BEACON
 
0.404 246122.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-069
ISI CONTRACTING, INC.( 17.44%)
STRIPES & STOPS COMPANY, INC.(1.45%)
Contract # 04143029
Totals 246122.55 0.00 0.00 0.0

CountyGALVESTON
Highway FM 517
From AT FM 146
To .
CSJ 0978-02-071
Proj ID STP 2014(035)HES
Work Type TS IMPRVMT & LT TN LN
 
0.537 959632.80 0.00 0.00 0.0
Work Order 11-22-13
Work Began 11-24-14
Work Completed  
Time Computed 12-08-13
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-071
LONE STAR TRAFFIC SERVICE, INC.(0.28%)
REGIONAL TRAFFIC SERVICES LLC(3.73%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.32%)
Contract # 09133220
Totals 959632.80 0.00 0.00 0.0

CountyBRAZORIA
Highway FM 524
From FM 521
To CR 334
CSJ 1004-01-052
Proj ID STP 2012(519)
Work Type UPGRADE DRAINAGE STRUCTURES
 
3.176 249163.00 10400.00 216661.86 100.0
Work Order 07-09-12
Work Began 08-17-12
Work Completed 09-10-14
Time Computed 07-25-12
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 253
Contractor(s)
NNA FINANCIAL SERVICES CO.
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-052
HIGHWAY TECHNOLOGIES, INC. (1.41%)
Contract # 05123213
Totals 249163.00 10400.00 216661.86 100.0

CountyHARRIS
Highway FM 529
From FREEMAN ROAD
To W OF FRY ROAD
CSJ 1006-01-059
Proj ID NH 2012(474)
Work Type GR, STRS, BASE AND SURF
 
1.184 7690213.53 102805.24 5680766.05 73.8
Work Order 01-31-13
Work Began 03-15-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 322
Addl Days Granted 0
Working Days Charged 234
Percent Time Used 72
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-059
HIGHWAY TECHNOLOGIES, INC. (0.79%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.96%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.42%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.77%)
ROSALES TRUCKING (1.50%)
BATTERSON,LLP(0.97%)
DURWOOD GREENE CONSTRUCTION CO.(7.49%)
EL DORADO PAVING COMPANY, INC. (0.49%)
TEX OP CONSTRUCTION, LP(1.02%)
CPAV SPECIALTIES, LP (0.60%)
INDUS CONSTRUCTION, L.P. (2.66%)
MASTER CURB, LLC (0.10%)
Contract # 10123217
Totals 7690213.53 102805.24 5680766.05 73.8

CountyHARRIS
Highway FM 2100
From FM 1960 (GUY ROAD)
To 0.066 M. S OF HUFFMAN-CLEVELAND RD
CSJ 1062-02-023
Proj ID STP 2013(696)
Work Type MILL & ACP OVERLAY
 
12.426 5966662.66 0.00 5657563.44 94.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 09-24-13
Work Completed  
Time Computed 09-24-13
Contract Working Days 186
Addl Days Granted 3
Working Days Charged 198
Percent Time Used 104
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-023
SIEMENS INDUSTRY, INC. (1.83%)
PROFESSIONAL TRAFFIC CONTROL, LLC(3.07%)
WILLOW CITY SIGN & RAIL, INC.(1.34%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(2.08%)
SOUTHWEST SIGNAL SUPPLY, INC.(0.35%)
CURB PLANET INC. (0.99%)
Contract # 05133003
Totals 5966662.66 0.00 5657563.44 94.9

CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MI S. OF FIRST STREET
CSJ 1062-04-047
Proj ID STP 2010(903)RGS
Work Type CONST RR GRADE SEPARATION STR & APP
 
0.870 8537094.26 70000.00 11381687.75 100.0
CountyHARRIS
Highway FM 2100
From DIAMONDHEAD BLVD.
To 0.14 MILE SOUTH OF FIRST STREET
CSJ 1062-04-051
Proj ID STP 2011(543)ES
Work Type UTILITY ADJUSTMENT
 
0.870 335846.50 0.00 575841.86 100.0
Work Order 09-01-10
Work Began 11-28-11
Work Completed 11-21-14
Time Computed 09-17-10
Contract Working Days 455
Addl Days Granted 101
Working Days Charged 556
Percent Time Used 100
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047
ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%)
BATTERSON,LLP(0.79%)
HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%)
HOUSTON SAWING & DRILLING(0.09%)
JTB SERVICES (0.33%)
KOSSMAN CONTRACTING CO., INC.(0.23%)
REPUBLIC TRAFFIC SAFETY, INC.(0.43%)
SCOTT DERR PAINTING CO, LLC(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%)
MICKIE SERVICE, INC. (0.10%)
SAN JACINTO BORING & TUNNELING, INC. (0.23%)
SOUTHERN CRUSHED CONCRETE LLC(0.31%)
PM CONSTRUCTION & REHAB, LLC (1.62%)
JMHP, INC. (0.52%)
GMJ PAVING CO. (3.78%)
BREDA COMPANY, INC.(0.61%)
H & H CURB COMPANY (0.09%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%)
ENVIRONMENTAL ALLIES, L.P. (0.24%)
DORAN STEEL, INC.(0.18%)
LOPEZ UTILITIES, LLC (0.23%)
R & A BORING COMPANY (0.30%)
Contract # 07103015
Totals 8872940.76 70000.00 11957529.61 100.0

CountyHARRIS
Highway FM 1093
From 3.6 MILES WEST OF IH 610
To 0.25 MILES EAST OF SH 6
CSJ 1258-04-056
Proj ID CM 2013(790)
Work Type IMPLEMENTATION OF ACCESS MGMT
 
7.386 2561914.38 139827.16 2224138.99 86.8
Work Order 11-04-13
Work Began 02-11-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 98
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-056
KOSSMAN CONTRACTING CO., INC.(0.45%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.22%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC( 35.08%)
Contract # 07133031
Totals 2561914.38 139827.16 2224138.99 86.8

CountyHARRIS
Highway FM 1093
From AT BW 8
To .
CSJ 1258-04-060
Proj ID STP 2015(163)HESG
Work Type IMPROVE TS
 
0.202 493967.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143025
Totals 493967.08 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.045 MI S OF W. LOST CREEK BLVD
To FM 149
CSJ 1400-04-011
Proj ID STP 1402(182)
Work Type GR, STRS, BS & CONC PAV
 
2.831 18070204.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143203
Totals 18070204.05 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.109 MI N OF FM 1488
To 0.045 MI S OF W LOST CREEK BLVD
CSJ 1400-04-035
Proj ID STP 1102(437)
Work Type RECONSTRUCT ROADWAY
 
2.320 11301777.00 483061.45 12795928.89 99.9
Work Order 11-03-11
Work Began 12-06-11
Work Completed  
Time Computed 11-19-11
Contract Working Days 280
Addl Days Granted 288
Working Days Charged 477
Percent Time Used 83
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-035
GULF COAST PAVERS, INC.(0.22%)
GMJ PAVING CO. (7.32%)
H & H CURB COMPANY (0.12%)
BREDA COMPANY, INC.(0.89%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.36%)
BATTERSON,LLP(1.83%)
THIRD COAST SERVICES, LLC(4.26%)
URBAN FORESTERS, LLC (0.44%)
CHAMPIONS HYDRO-LAWN (0.80%)
Contract # 08113209
Totals 11301777.00 483061.45 12795928.89 99.9

CountyBRAZORIA
Highway FM 1462
From AT COUNTY ROAD 185
To .
CSJ 1414-03-039
Proj ID STP 2013(791)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.283 481635.62 0.00 529220.61 99.9
Work Order 09-12-13
Work Began 03-11-14
Work Completed  
Time Computed 11-11-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 98
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1414-03-039
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
BATTERSON,LLP(3.54%)
JMHP, INC. (1.34%)
MIKE SORRELL TRUCKING AND MATERIALS, INC.(0.72%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.97%)
Contract # 07133015
Totals 481635.62 0.00 529220.61 99.9

CountyFORT BEND
Highway FM 1464
From AT PUMPKIN LAKE
To .
CSJ 1415-02-045
Proj ID STP 2013(848)
Work Type DETENTION POND
 
0.100 495924.72 0.00 537787.58 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 03-31-14
Work Completed 10-06-14
Time Computed 03-31-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 92
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 1415-02-045
SILT SOLUTIONS, INC. (0.16%)
BILL MURFF TURF FARMS, INC.(6.05%)
CHAMPIONS HYDRO-LAWN (2.70%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.89%)
LONESTAR TRAFFIC SAFETY, LLC (0.35%)
CANALES TRUCKING INC.( 11.09%)
SOUTHLAND FENCE COMPANY(4.59%)
Contract # 01143010
Totals 495924.72 0.00 537787.58 100.0

CountyGALVESTON
Highway FM 1764
From CENTURY BLVD INT FROM 14TH STREET
To 21ST STREET
CSJ 1607-01-050
Proj ID STP 2011(250)TE
Work Type ENHANCEMENT PROJECT
 
1.200 704750.96 10348.85 687404.38 97.7
Work Order 09-05-13
Work Began 10-22-13
Work Completed  
Time Computed 10-22-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 102
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1607-01-050
CC TREE FARMS, L.L.C.(0.93%)
ENVIRONMENTAL ALLIES, L.P. (0.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.35%)
VACA UNDERGROUND UTILITIES INC (1.38%)
PFEIFFER & SON LTD.( 30.86%)
RANGEL CONSTRUCTION(5.95%)
Contract # 06133212
Totals 704750.96 10348.85 687404.38 97.7

CountyHARRIS
Highway FM 1960
From IH 45
To 6.5 MI E OF IH 45 (HUMBLE BYPASS)
CSJ 1685-02-049
Proj ID NH 2013(064)
Work Type PAVEMENT MARKINGS
 
14.553 546380.10 0.00 390018.83 80.6
Work Order 10-18-12
Work Began 11-18-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 169
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123024
Totals 546380.10 0.00 390018.83 80.6