Monthly State Let Construction Report For Houston District As Of Apr 10, 2017 Page 9 Of 10

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayBF1960A
FromFM 1960 W OF LEE RD
ToFM 1960 E OF HUMBLE
CSJ1685-07-005
Proj IDC 1685-7-5
Work TypeIMPLEMENT ACCESS MANAGEMENT
 
3.9206976168.046823676.7797.8
CountyHARRIS
HighwayBF1960A
FromLEE ROAD
ToFM 1960(E)
CSJ1685-07-019
Proj IDSTP 2013(994)
Work TypeBS REP, MILL, SC INTERLAYER, OL,ETC
 
4.2006317731.975347298.1086.7
Work Order09-30-14
Work Began11-10-14
Work Completed
Time Computed11-10-14
Contract Working Days270
Addl Days Granted0
Working Days Charged376
Percent Time Used139
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1685-07-005
ANGEL BROTHERS ENTERPRISES, LTD. (27.60)
KOSSMAN CONTRACTING CO., INC. (1.14)
REGIONAL TRAFFIC SERVICES LLC (0.84)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (12.57)
H & E AGGREGATE, LLC (3.50)
SCMU (3.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.48)
AGGREGATE TECHNOLOGIES, INC. (0.39)
SEMARCK LANDSCAPE SERVICES, INC. (1.14)
GULF COAST PAVERS, INC. (0.21)
PEREZ CONSTRUCTION CO. (0.32)
Contract #08133014
Totals13293900.01392972.0012170974.8792.5

CountyMONTGOMERY
HighwayFM 1097
FromEND OF STATE MAINTENANCE
ToFM 149
CSJ1706-03-008
Proj IDSTP 2017(115)
Work TypeBS REPR, OCST, 1.5" OL & ADD SHLDR
 
6.2575759460.111796199.2131.1
Work Order11-15-16
Work Began02-13-17
Work Completed
Time Computed02-13-17
Contract Working Days113
Addl Days Granted0
Working Days Charged33
Percent Time Used29
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1706-03-008
WILLOW CITY SIGN & RAIL, INC. (0.66)
DUSTROL, INC. (2.00)
CEN TEX HYDROSEED, INC. (6.16)
TEXAS LAND CLEARING SERVICE (3.64)
WATERS CONSTRUCTION COMPANY, INC., BOB (3.57)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.73)
J & M CONTRACTING, COMPANY (9.58)
Contract #09163029
Totals5759460.111217655.041796199.2131.1

CountyFORT BEND
HighwayFM 1994
FromSH 36
ToFM 361
CSJ1965-01-006
Proj IDSTP 2017(640)
Work TypeBASE REPAIR AND OVERLAY
 
7.5821774560.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1965-01-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173038
Totals1774560.910.000.000.0

CountyMONTGOMERY
HighwayFM 1314
From0.135 MILES NORTH OF SH 242
To1.088 MILES SOUTH OF SH 242
CSJ1986-01-044
Proj IDC 1986-1-44
Work TypeRESTRIPE ROADWAY FROM 2 TO 4 LANES
 
1.2221385318.821009632.0672.8
Work Order06-20-16
Work Began08-29-16
Work Completed
Time Computed08-19-16
Contract Working Days43
Addl Days Granted0
Working Days Charged43
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1986-01-044
ROADSAFE TRAFFIC SYSTEMS, INC. (4.99)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.80)
CAPSTONE TRUCKING (1.58)
Contract #05163019
Totals1385318.827500.001009632.0672.8

CountyFORT BEND
HighwayFM 2234
FromFORT BEND PARKWAY
ToFM 521
CSJ2105-01-020
Proj IDSTP 1402(122)
Work TypeGR, STRS, BS & SURF
 
4.06831094829.559236518.1029.7
Work Order06-19-15
Work Began08-15-16
Work Completed
Time Computed07-05-15
Contract Working Days506
Addl Days Granted0
Working Days Charged146
Percent Time Used28
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-020
WILLOW CITY SIGN & RAIL, INC. (0.31)
STRIPE-A-LINE, INC. (0.71)
CREACOM, INC. (3.43)
MESA ROD BUSTERS, INC. (6.42)
ROADWAY CONSTRUCTION, LLC (2.94)
EROSION PREVENTION PRODUCTS (0.22)
QUALITY TURF FARMS, LC (2.30)
THELIN RECYCLING COMPANY, L.P. (0.37)
BORTUNCO (0.00)
Contract #05153204
Totals31094829.55319878.359236518.1029.7

CountyFORT BEND
HighwayFM 2234
FromFM 3345
ToFORT BEND TOLL ROAD
CSJ2105-01-046
Proj IDC 2105-1-46
Work TypeGR, STRS, BS & SURF
 
1.4588068060.388617334.2599.9
Work Order10-30-13
Work Began01-21-14
Work Completed
Time Computed12-29-13
Contract Working Days215
Addl Days Granted9
Working Days Charged211
Percent Time Used94
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-046
B & D MAINTENANCE (1.89)
CPAVE, INC. (0.31)
SCOTT DERR PAINTING CO, LLC (0.13)
DUSTROL, INC. (1.65)
THIRD COAST SERVICES LLC (8.64)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.89)
BATTERSON,LLP (2.16)
A-1 EROSION CONTROL, LLC (2.12)
BREDA COMPANY, INC. (0.79)
H & E AGGREGATE, LLC (7.21)
SILVA CONSTRUCTION, INC. (3.85)
WILLOW CITY SIGN & RAIL, INC. (0.06)
CURB PLANET INC. (0.09)
Contract #07133218
Totals8068060.387073.848617334.2599.9

CountyHARRIS
HighwayFM 2920
From0.244 MILES EAST OF US 290
ToSH 249
CSJ2941-01-024
Proj IDSTP 1602(487)
Work TypeSEAL COAT, OVERLAY & PV MKS
 
13.9653817766.77294814.857.7
Work Order09-15-16
Work Began00-00-00
Work Completed
Time Computed11-14-16
Contract Working Days70
Addl Days Granted0
Working Days Charged8
Percent Time Used11
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2941-01-024
WEST TEXAS RUMBLE STRIP (0.14)
THIRD COAST SERVICES LLC (4.09)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.37)
Contract #08163229
Totals3817766.77294814.85294814.857.7

CountyHARRIS
HighwayFM 2920
FromBUS 249
ToHOWARD ST
CSJ2941-02-050
Proj IDSTP 1502(020)
Work TypeBS REP,MILL,CR SL,TOM,RADAR,ETC
 
3.1882999793.893051604.1599.9
Work Order08-24-15
Work Began04-29-16
Work Completed
Time Computed10-23-15
Contract Working Days75
Addl Days Granted6
Working Days Charged81
Percent Time Used100
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2941-02-050
REPUBLIC TRAFFIC SAFETY, INC. (6.09)
DUSTROL, INC. (6.38)
SOUTHWEST SIGNAL SUPPLY, INC. (12.48)
BATTERSON,LLP (0.25)
Contract #07153040
Totals2999793.890.003051604.1599.9

CountyMONTGOMERY
HighwayFM 2978
FromFM 1488
ToS OF DRY CREEK
CSJ3050-02-024
Proj IDSTP 2016(119)MM
Work TypeGR, STRS, BASE AND PAVE
 
4.07015788778.29281974.961.7
Work Order04-19-16
Work Began00-00-00
Work Completed
Time Computed06-18-16
Contract Working Days457
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-024
MESA ROD BUSTERS, INC. (0.00)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.00)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.10)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.81)
WILLOW CITY SIGN & RAIL, INC. (0.00)
Contract #02163202
Totals15788778.290.00281974.961.7

CountyMONTGOMERY
HighwayFM 2978
FromS OF DRY CREEK
ToCONROE HUFFSMITH
CSJ3050-02-025
Proj IDC 3050-2-25
Work TypeGR, STRS, BASE AND PAVE
 
2.4628195982.091764539.2621.5
Work Order01-29-16
Work Began03-15-16
Work Completed
Time Computed02-29-16
Contract Working Days276
Addl Days Granted0
Working Days Charged8
Percent Time Used2
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-025
THIRD COAST SERVICES LLC (2.84)
K4 ENVIRONMENTAL LLC (3.19)
LONESTAR TRAFFIC SAFETY, LLC (0.50)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.97)
ROADWAY CONSTRUCTION, LLC (0.30)
Contract #12153035
Totals8195982.097200.001764539.2621.5

CountyMONTGOMERY
HighwayFM 3083
FromAT UPRR
To.
CSJ3158-01-031
Proj IDC 3158-1-31
Work TypeCONSTRUCT GRADE SEPARATION
 
0.70513080676.414404051.5733.6
Work Order09-11-15
Work Began07-05-16
Work Completed
Time Computed06-07-16
Contract Working Days378
Addl Days Granted0
Working Days Charged154
Percent Time Used40
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3158-01-031
ROADSAFE TRAFFIC SYSTEMS, INC. (0.33)
J & M CONTRACTING, COMPANY (6.16)
WILLOW CITY SIGN & RAIL, INC. (0.94)
CENTEX HYDROSEED (1.70)
EROSION PREVENTION PRODUCTS (0.48)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.51)
MESA ROD BUSTERS, INC. (0.34)
Contract #07143209
Totals13080676.41191103.944404051.5733.6

CountyHARRIS
HighwaySH 99
FromBS 146 EAST (SEGMENT 1-2)
ToCHAMBERS COUNTY LINE
CSJ3187-01-005
Proj IDC 3187-1-5
Work TypeCONSTRUCT TWO 2-LN FRONTAGE ROADS
 
3.10135161387.5421369340.2660.7
Work Order10-17-14
Work Began08-31-15
Work Completed
Time Computed11-02-14
Contract Working Days486
Addl Days Granted0
Working Days Charged408
Percent Time Used83
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3187-01-005
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.38)
TEXAS ENVIRONMENTAL MANAGEMENT, INC (2.19)
SOUTHERN CRUSHED CONCRETE LLC (1.13)
WILLOW CITY SIGN & RAIL, INC. (1.28)
PRIMATE CONSTRUCTION, INC. (0.19)
WEBBER BARRIER SERVICES, LLC. (0.28)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.87)
CHOCTAW ERECTORS, INC. (2.04)
MESA ROD BUSTERS, INC. (0.78)
MBN ENTERPRISES LLC (1.64)
SCOTT DERR PAINTING CO, LLC (0.20)
GMJ PAVING CO. (4.60)
A. H. BECK FOUNDATION CO., INC. (2.29)
JCF BRIDGE & CONCRETE, INC. (2.18)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.41)
TEXAS FENCE, INC. (0.09)
TROY ATKINSON (0.04)
Contract #07143003
Totals35161387.54665988.9121369340.2660.7

CountyHARRIS
HighwaySL 8
FromWEST AIRPORT BLVD
ToWESTPARK
CSJ3256-01-106
Proj IDHP 1502(450)
Work TypeLANDSCAPE DEVELOPMENT
 
5.660875730.77776503.8788.6
Work Order11-02-15
Work Began06-20-16
Work Completed
Time Computed01-31-16
Contract Working Days90
Addl Days Granted0
Working Days Charged85
Percent Time Used94
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-106
R & A BORING COMPANY (1.41)
MICKIE SERVICE, INC. (2.11)
Contract #07153020
Totals875730.770.00776503.8788.6

CountyHARRIS
HighwaySL 8
FromIH 45 NORTH
ToUS 59 NORTH
CSJ3256-02-089
Proj IDNH 2016(448)
Work TypeTRANSPORTATION MANAGEMENT SYSTEM
 
3.08726822716.0915412939.2557.4
Work Order03-24-16
Work Began06-22-16
Work Completed
Time Computed06-22-16
Contract Working Days536
Addl Days Granted0
Working Days Charged216
Percent Time Used40
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-089
SCMU (3.33)
CREACOM, INC. (4.64)
SOUTHERN CRUSHED CONCRETE LLC (1.34)
SCOTT DERR PAINTING CO (0.24)
WEBBER BARRIER SERVICES, LLC. (2.25)
PRIMATE CONSTRUCTION, INC. (0.20)
WILLOW CITY SIGN & RAIL, INC. (1.31)
SCR CONSTRUCTION CO., INC. (0.16)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.46)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.82)
MESA ROD BUSTERS, INC. (3.42)
FARR FOUNDATION, INC. (1.40)
LONESTAR TRAFFIC SAFETY, LLC (0.19)
RDI FOUNDATION DRILLING (4.00)
GMJ PAVING CO. (1.37)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
RAY"S THREADING AND FAB SHOP (0.06)
STEEL EFFECTS (0.00)
LILLEY INDUSTRIAL CONSTRUCTION (0.14)
STEEL EFFECTS (0.09)
BUYERS BARRICADES, INC. (0.01)
PENHALL COMPANY (0.01)
VALLEY PLACERS, LLC (0.19)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.04)
Contract #11153003
Totals26822716.091794384.9115412939.2557.4

CountyHARRIS
HighwayBW 8
FromAT MYKAWA AND SFRR
To.
CSJ3256-04-061
Proj IDNH 1402(198)
Work TypeSTRS, GR, BASE AND PAVEMENT
 
1.04010329185.5010513824.7699.9
Work Order10-17-14
Work Began03-17-15
Work Completed
Time Computed11-02-14
Contract Working Days282
Addl Days Granted5
Working Days Charged306
Percent Time Used106
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3256-04-061
LONE STAR TRAFFIC SERVICE, INC. (0.16)
BELL BOTTOM FOUNDATION CO. (4.88)
SCOTT DERR PAINTING CO, LLC (0.39)
A-1 EROSION CONTROL, LLC (0.66)
MESA ROD BUSTERS, INC. (3.41)
FOSTER FENCE, LTD. (0.41)
PRIMATE CONSTRUCTION, INC. (0.34)
WILLOW CITY SIGN & RAIL, INC. (1.67)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.97)
STORM WATER SOLUTIONS, LP (0.01)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.42)
GMJ PAVING CO. (0.65)
DORAN STEEL, INC. (0.47)
LONESTAR TRAFFIC SAFETY, LLC (0.16)
Contract #08143037
Totals10329185.5069604.7410513824.7699.9

CountyHARRIS
HighwayFM 270
FromHENDERSON ST
ToHARRIS COUNTY LINE
CSJ3312-01-008
Proj IDCM 2013(571)
Work TypeBICYCLE/PEDESTRIAN IMPROVEMENTS
 
1.1363845442.262610764.6967.8
Work Order01-08-16
Work Began05-09-16
Work Completed
Time Computed05-07-16
Contract Working Days225
Addl Days Granted0
Working Days Charged183
Percent Time Used81
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 3312-01-008
REBAR SUPPLY COMPANY, LTD. (3.29)
BATTERSON,LLP (0.97)
BELL BOTTOM FOUNDATION CO. (6.42)
JE CASEY, LLC (1.02)
KOSSMAN CONTRACTING CO., INC. (1.18)
NEW WORLD_CONTRACTING LLC (1.63)
ROSALES TRUCKING (2.44)
SCOTT DERR PAINTING CO, LLC (0.02)
TOM-MAC, INC. (3.91)
DORAN STEEL, INC. (0.48)
ENVIRONMENTAL ALLIES, L.P. (0.46)
INDUS CONSTRUCTION, L.P. (0.54)
SCMU (0.52)
Contract #08153027
Totals3845442.26185577.402610764.6967.8

CountyGALVESTON
HighwayFM 270
FromFM 518/FM 2094
ToFM 270
CSJ3312-02-014
Proj IDC 3312-2-14
Work TypeREALIGN ROADWAY
 
0.5022299180.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3312-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173254
Totals2299180.800.000.000.0

CountyFORT BEND
HighwayPR 72
FromIN BRAZOS BEND STATE PARK
To.
CSJ3422-01-011
Proj IDC 3422-1-11
Work TypeOVERLAY
 
1.858563996.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3422-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173006
Totals563996.220.000.000.0

CountyFORT BEND
HighwaySH 99
FromAT HARLEM ROAD
ToSH 99 AT HARLEM ROAD, NB & SB
CSJ3510-04-053
Proj IDNH 2017(247)
Work TypeADD UTN, LT TN LNS & REBUILD SIGNAL
 
0.5512240983.05314583.7314.0
Work Order01-17-17
Work Began03-20-17
Work Completed
Time Computed03-18-17
Contract Working Days147
Addl Days Granted0
Working Days Charged6
Percent Time Used4
Contractor(s)
MAR-CON SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-053
GEORGE MEEKS LANDPRO, INC. (0.77)
THIRD COAST SERVICES LLC (19.88)
GMJ PAVING CO. (3.22)
PROFESSIONAL TRAFFIC CONTROL, LLC (2.33)
Contract #11163012
Totals2240983.05314583.73314583.7314.0

CountyMONTGOMERY
HighwaySH 242
FromAT FM 1485
To.
CSJ3538-01-044
Proj IDSTP 2016(722)HES
Work TypeTS IMPRVMTS
 
0.500275772.88100034.4036.2
Work Order03-08-16
Work Began07-27-16
Work Completed
Time Computed07-06-16
Contract Working Days38
Addl Days Granted0
Working Days Charged28
Percent Time Used73
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 3538-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02163036
Totals275772.880.00100034.4036.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10