| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
EAST OF ELLA |
| To |
IH 45 |
| CSJ |
0271-14-223 |
| Proj ID |
STP 2009(519)ES |
| Work Type |
RECONSTRUCT ROADWAY |
| |
|
2.910 |
28853986.56 |
1133185.45 |
3028093.51 |
10.4 |
| Work Order |
09-01-09 |
| Work Began |
09-16-09 |
| Work Completed |
|
| Time Computed |
09-17-09 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
46 |
| Percent Time Used |
6 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-223 CREACOM, INC.(4.18%) GIBSON & ASSOCIATES, INC.(2.50%) JTB SERVICES (2.75%) BREDA COMPANY, INC.(1.76%) EL DORADO PAVING COMPANY, INC. (1.57%) WILLOW CITY SIGN & RAIL, INC.(0.66%) NORTHWEST MATERIALS(0.42%) CPAV SPECIALTIES, LP (0.61%) HIGHWAY TECHNOLOGIES (0.16%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.12%) JOE VALENCIK, INC. (1.60%) EARTH MATERIAL SERVICES, LLC.(3.39%) MCRAY CRANE(0.10%)
|
| Contract # |
07093001 |
|
Totals |
28853986.56 |
1133185.45 |
3028093.51 |
10.4 |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
MARKET STREET |
| To |
PORT OF HOUSTON |
| CSJ |
0271-15-085 |
| Proj ID |
HP 2008(172) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
3.585 |
1255955.07 |
5158.73 |
1283139.51 |
99.9 |
| Work Order |
11-30-07 |
| Work Began |
03-03-08 |
| Work Completed |
|
| Time Computed |
01-29-08 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
88 |
| Percent Time Used |
97 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-15-085 ACE TELECOM, INC.(0.25%) LONE STAR TRAFFIC SERVICE, INC.(0.49%)
|
| Contract # |
11073012 |
|
Totals |
1255955.07 |
5158.73 |
1283139.51 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
BEECHNUT |
| To |
0.5 MI EAST OF FM 865 |
| CSJ |
0271-16-128 |
| Proj ID |
HP 2008(315) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
7.229 |
873509.90 |
9099.73 |
675352.28 |
77.3 |
| Work Order |
04-16-08 |
| Work Began |
10-13-08 |
| Work Completed |
|
| Time Computed |
10-13-08 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
86 |
| Percent Time Used |
95 |
| Contractor(s) |
| BOYER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-128 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03083011 |
|
Totals |
873509.90 |
9099.73 |
675352.28 |
77.3 |
|
| County | GALVESTON |
| Highway |
SH 87 |
| From |
INTERSECTION AT SH 124 |
| To |
2 MILES WEST OF SH 124 |
| CSJ |
0367-02-073 |
| Proj ID |
STP 2009(556)ES |
| Work Type |
REHAB & O / L |
| |
|
21.338 |
6167954.73 |
1603572.12 |
1905946.94 |
30.9 |
| Work Order |
06-02-09 |
| Work Began |
06-18-09 |
| Work Completed |
|
| Time Computed |
06-18-09 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
52 |
| Percent Time Used |
57 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-073 J & M CONTRACTING, COMPANY (2.51%) BATTERSON, L.L.P.(2.79%) WORK ZONE PRODUCTS, INC. (0.20%) DARK HORSE SERVICES, INC.(1.19%) R & A TRANSPORT, INC.(7.79%)
|
| Contract # |
04093602 |
|
Totals |
6167954.73 |
1603572.12 |
1905946.94 |
30.9 |
|
| County | GALVESTON |
| Highway |
SH 87 |
| From |
AT GALVESTON-BOLIVAR FERRY LANDING |
| To |
. |
| CSJ |
0367-05-041 |
| Proj ID |
FT 367-5-41 |
| Work Type |
CONSTRUCT ONE FERRY VESSEL |
| |
|
0.001 |
22512000.00 |
0.00 |
0.00 |
0.0 |
| County | GALVESTON |
| Highway |
US 81 |
| From |
.33 MI NO OF SH 186 |
| To |
.95 MI N OF FM 490 |
| CSJ |
3487-02-010 |
| Proj ID |
STP 2009(679)ES |
| Work Type |
ASPHALTIC CONCRETE PAVEMENT OVERLAY |
| |
|
6.808 |
0.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-30-07 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
540 |
| Addl Days Granted |
0 |
| Working Days Charged |
429 |
| Percent Time Used |
79 |
| Contractor(s) |
| CONRAD SHIPYARD, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0367-05-041 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07073205 |
|
Totals |
22512000.00 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
AT BNSF RR/PORT ROAD |
| To |
. |
| CSJ |
0389-05-105 |
| Proj ID |
HP 2009(817) |
| Work Type |
CONSTRUCT DIRECT CONNECTORS |
| |
|
3.213 |
41949338.29 |
2308884.06 |
2308884.06 |
5.5 |
| Work Order |
10-14-09 |
| Work Began |
10-26-09 |
| Work Completed |
|
| Time Computed |
10-30-09 |
| Contract Working Days |
931 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
0 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-105 CURB PLANET INC. (0.03%) SCOTT DERR PAINTING CO (0.30%) ANGEL BROTHERS ENTERPRISES, LTD. (6.73%) CRAVENS PARTNERS, LTD. (7.03%) TRAF-TEX, INC. (6.18%) JOE VALENCIK, INC. (0.55%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%) EROSION CONTROL, INC.(1.26%) INDUS CONSTRUCTION, L.P. (5.55%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.51%)
|
| Contract # |
08093202 |
|
Totals |
41949338.29 |
2308884.06 |
2308884.06 |
5.5 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
AT SPUR 330 |
| To |
. |
| CSJ |
0389-13-040 |
| Proj ID |
CM 2007(829) |
| Work Type |
CONST DIRECT CONN & BRAID RAMP |
| |
|
0.001 |
16205858.39 |
0.00 |
16227139.52 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-25-08 |
| Work Began |
02-11-08 |
| Work Completed |
|
| Time Computed |
02-10-08 |
| Contract Working Days |
420 |
| Addl Days Granted |
1 |
| Working Days Charged |
412 |
| Percent Time Used |
98 |
| Contractor(s) |
| SOUTH COAST CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-040 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.49%) BATTERSON, L.L.P.(0.42%) BECO CONSTRUCTION COMPANY(6.73%) RDI FOUNDATION DRILLING(2.39%) PRIMATE CONSTRUCTION, INC. (0.20%) MAGNUM TUNNELING, LLC(0.01%) NORTHWEST MATERIALS(0.03%) S & S BRIDGE PAINTING, INC.(0.05%) PFEIFFER & SON LTD.(1.52%) TRIUMPH PARKING LOT MAINTENANCE, INC.(0.06%) PEREZ CONSTRUCTION CO. (0.00%) ODUM SERVICES, L.P.(0.04%)
|
| Contract # |
12073202 |
|
Totals |
16205858.39 |
0.00 |
16227139.52 |
99.9 |
|
| County | HARRIS |
| Highway |
BS 146D |
| From |
AT LITTLE CEDAR BAYOU |
| To |
. |
| CSJ |
0389-15-014 |
| Proj ID |
BR 2008(747) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.267 |
3059787.12 |
156019.88 |
2606804.35 |
87.3 |
| Work Order |
10-27-08 |
| Work Began |
12-01-08 |
| Work Completed |
|
| Time Computed |
11-12-08 |
| Contract Working Days |
229 |
| Addl Days Granted |
0 |
| Working Days Charged |
311 |
| Percent Time Used |
135 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-15-014 STRIPES & STOPS COMPANY, INC.(0.77%) SCOTT DERR PAINTING CO (0.05%) CURB PLANET INC. (0.02%) CHERRY CONCRETE REMOVAL(0.58%) JUST GROOVING, LTD.(0.17%) ENVIRONMENTAL ALLIES, L.P. (0.88%) GMJ PAVING CO. (2.26%) HOLES INCORPORATED (0.47%) CPAV SPECIALTIES, LP (0.18%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.01%) INDUS CONSTRUCTION, L.P. (0.82%) BREDA COMPANY, INC.(0.21%) AAA ASPHALT PAVING, INC. (0.14%)
|
| Contract # |
07083014 |
|
Totals |
3059787.12 |
156019.88 |
2606804.35 |
87.3 |
|
| County | GALVESTON |
| Highway |
IH 45 |
| From |
AT GALVESTON ISLAND CAUSEWAY |
| To |
. |
| CSJ |
0500-01-117 |
| Proj ID |
HP 993(1) |
| Work Type |
REPLACE BRIDGES |
| |
|
2.377 |
135328791.08 |
1964.00 |
167351291.21 |
99.9 |
| County | GALVESTON |
| Highway |
IH 45 |
| From |
AT GALVESTON ISLAND CAUSEWAY |
| To |
. |
| CSJ |
0500-01-126 |
| Proj ID |
BR 2002(869) |
| Work Type |
UTILITIES |
| |
|
0.001 |
604929.60 |
0.00 |
588703.60 |
97.3 |
| Work Order |
07-22-03 |
| Work Began |
10-13-03 |
| Work Completed |
|
| Time Computed |
08-07-03 |
| Contract Working Days |
1,376 |
| Addl Days Granted |
141 |
| Working Days Charged |
1,502 |
| Percent Time Used |
99 |
| Contractor(s) |
| TRAYLOR BROS., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-01-117 A & G EBERHARDT ENTERPRISES, INC.(3.91%) SCOTT DERR PAINTING CO.(0.06%) JMHP, INC. (0.22%) APPLIED FOUNDATION TESTING, INC. (0.00%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.16%) EAGLE GROOVING & GRINDING CONTRACTORS(0.13%) JOE VALENCIK, INC. (0.34%) D&D HELPING OTHERS, INC. (0.00%) SOUTHERN CRUSHED CONCRETE INC. (0.11%) DORSETT BROTHERS (9.36%) CREACOM, INC.(0.32%) HUBCO, INC.(2.91%) NICHOLSON CONSTRUCTION COMPANY (0.71%) CSC STEEL SERVICES, INC. (1.61%) A. H. BECK FOUNDATION CO., INC.(0.02%) BOOTHE BROTHERS PAVING COMPANY, INC. (0.03%) BLUEGRASS BIT COMPANY, INC.(0.00%) T & T MARINE SALVAGE, INC. (0.02%) A. H. BECK FOUNDATION CO., INC.(0.09%) AGGREGATE TECHNOLOGIES, INC. (0.00%) BIO LANDSCAPE & MAINTENANCE, INC.(0.10%) ENGINEERED EXPLOSIVE SERVICES(0.23%) HOUSTON CURB COMPANY, INC. (0.00%) ROAD TRAC, INC.(0.00%) HOUSTON SAWING & DRILLING(0.02%) ORION CONSTRUCTION, L.P. (0.16%) DORAN STEEL, INC.(0.08%) W.W. WEBBER, LLC (0.01%) RAMPART HYDRO SERVICES (0.02%) WEBBER-BALKE FOUNDATION COMPANY, INC.(0.05%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%) PANTHER CONCRETE REPAIR SPECIALIST, INC. (0.00%)
|
| Contract # |
06033001 |
|
Totals |
135933720.68 |
1964.00 |
167939994.81 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
MEDICAL CENTER |
| To |
0.48 MILES SOUTH OF EXISTING NASA 1 |
| CSJ |
0500-03-544 |
| Proj ID |
NH 2007(507) |
| Work Type |
GR, STRS, BASE AND CONC PAVEMENT |
| |
|
0.974 |
35966334.02 |
1866567.99 |
29724469.43 |
81.5 |
| County | HARRIS |
| Highway |
IH 45 |
| From |
MEDICAL CENTER |
| To |
0.48 MILES SOUTH OF EXISTING NASA 1 |
| CSJ |
0500-03-548 |
| Proj ID |
NH 2006(803) |
| Work Type |
ROW ACQUISITION AND UTILITIES |
| |
|
0.974 |
220487.50 |
-5208.00 |
173824.50 |
78.8 |
| Work Order |
06-26-07 |
| Work Began |
11-05-07 |
| Work Completed |
|
| Time Computed |
09-24-07 |
| Contract Working Days |
562 |
| Addl Days Granted |
100 |
| Working Days Charged |
594 |
| Percent Time Used |
89 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-544 FLORIDA TRAFFIC CONTROL DEVICES, INC.(4.63%) SPECIALTY DRILLING (0.18%) BATTERSON, L.L.P.(0.64%) BREDA COMPANY, INC.(1.02%) BORING & TUNNELING COMPANY OF AMERICA, INC.(0.02%) J. T. B. SERVICES, INC.(0.40%) EL DORADO PAVING COMPANY, INC. (0.64%) KELLYSTONE, INC(0.70%) NORTHWEST MATERIALS(0.24%) PRIMATE CONSTRUCTION, INC. (0.31%) SCOTT DERR PAINTING CO (0.18%) STOMPER DEMOLITION (0.36%) WILLOW CITY SIGN & RAIL, INC.(0.23%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.39%) TREVCON, INC.(0.19%) HOUSTON SAWING & DRILLING(0.01%)
|
| Contract # |
05073001 |
|
Totals |
36186821.52 |
1861359.99 |
29898293.93 |
81.5 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
US 59 |
| To |
BW 8 SOUTH |
| CSJ |
0500-03-555 |
| Proj ID |
HP 2009(331) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
13.443 |
423082.94 |
3653.20 |
81037.86 |
19.1 |
| Work Order |
02-12-09 |
| Work Began |
03-04-09 |
| Work Completed |
|
| Time Computed |
02-28-09 |
| Contract Working Days |
780 |
| Addl Days Granted |
0 |
| Working Days Charged |
173 |
| Percent Time Used |
22 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-555 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01093021 |
|
Totals |
423082.94 |
3653.20 |
81037.86 |
19.1 |
|
| County | GALVESTON |
| Highway |
IH 45 |
| From |
AT SH 96 |
| To |
. |
| CSJ |
0500-04-118 |
| Proj ID |
NH 2007(228) |
| Work Type |
CONSTR OVERPASS |
| |
|
1.864 |
20774061.50 |
1049664.52 |
17762546.83 |
85.5 |
| County | GALVESTON |
| Highway |
IH 45 |
| From |
AT SH 96 |
| To |
. |
| CSJ |
0500-04-119 |
| Proj ID |
NH 2006(725) |
| Work Type |
ROW ACQUISITION |
| |
|
0.100 |
707410.00 |
0.00 |
695494.63 |
98.3 |
| Work Order |
08-23-07 |
| Work Began |
02-07-08 |
| Work Completed |
|
| Time Computed |
12-21-07 |
| Contract Working Days |
563 |
| Addl Days Granted |
6 |
| Working Days Charged |
484 |
| Percent Time Used |
86 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-118 RDI FOUNDATION DRILLING(1.52%) HIGHWAY TECHNOLOGIES (0.63%) HIGHWAY TECHNOLOGIES (0.11%) SOUTHERN CRUSHED CONCRETE INC. (0.34%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.10%) HAYWARD BAKER, INC.(2.80%) ANCHOR FENCE (0.07%) CREACOM, INC.(6.26%) SILVA CONTRACTING COMPANY, INC.(1.57%) SCOTT DERR PAINTING CO (0.18%) INDUS CONSTRUCTION, L.P. (0.94%) ENVIRONMENTAL ALLIES, L.P. (0.13%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%) WILLOW CITY SIGN & RAIL, INC.(0.35%) THOMAS TRACTOR WORKS, INC. (0.23%) PENNTEX MILLING, LLC (0.05%) HUBCO, INC.(0.10%) BATTEN DRILLING(0.33%) INDUS CONSTRUCTION, L.P. (0.06%) MAGNUM TUNNELING, LLC(0.12%) EZ CURB(0.04%) A & G EBERHARDT ENTERPRISES, INC.(0.08%) MAGNUM TUNNELING, LLC(1.51%) ENVIRONMENTAL DEWATERING, INC(0.26%) HY-TECH WELDING AND FABRICATING(0.06%) MICKIE SERVICE, INC. (0.00%) MAIN LANE INDUSTRIES, LTD. (0.02%) FORDE CONSTRUCTION COMPANY, INC. (0.18%) SPECIALTY DRILLING (0.22%)
|
| Contract # |
07073016 |
|
Totals |
21481471.50 |
1049664.52 |
18458041.46 |
85.9 |
|
| County | HARRIS |
| Highway |
SH 225 |
| From |
SHELL OVERPASS |
| To |
MILLER CUTOFF ROAD |
| CSJ |
0502-01-203 |
| Proj ID |
STP 2009(542)ES |
| Work Type |
FULL DPTH & SPALL REPR IN CONC PAV |
| |
|
4.397 |
882735.48 |
44248.53 |
111081.01 |
12.5 |
| Work Order |
06-29-09 |
| Work Began |
07-30-09 |
| Work Completed |
|
| Time Computed |
07-15-09 |
| Contract Working Days |
123 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
29 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-203 WEBBER BARRIER SERVICES, INC.(3.61%) KOSSMAN CONTRACTING COMPANY(0.08%) HOLES INCORPORATED (2.88%) CROSS STONES RENTALS (0.47%) HIGHWAY TECHNOLOGIES ( 11.94%) C.M. NUNEZ TRUCKING COMPANY(4.88%)
|
| Contract # |
04093654 |
|
Totals |
882735.48 |
44248.53 |
111081.01 |
12.5 |
|
| County | HARRIS |
| Highway |
SH 225 |
| From |
IH 610 |
| To |
RICHEY ROAD |
| CSJ |
0502-01-204 |
| Proj ID |
NH 2008(282) |
| Work Type |
INSTALL HIGH MAST ILLUMINATION |
| |
|
1.998 |
1239354.80 |
0.00 |
1284259.47 |
99.9 |
| Work Order |
02-11-08 |
| Work Began |
08-04-08 |
| Work Completed |
|
| Time Computed |
02-27-08 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
87 |
| Percent Time Used |
96 |
| Contractor(s) |
| STATEWIDE TRAFFIC SIGNAL COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-204 SPECIALTY DRILLING ( 12.49%) MCRAY CRANE(0.00%) ISI INFRASTRUCTURE, INC. (3.37%)
|
| Contract # |
01083013 |
|
Totals |
1239354.80 |
0.00 |
1284259.47 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
GELLHORN |
| To |
MERCURY DR. |
| CSJ |
0508-01-166 |
| Proj ID |
IM 0107(245) |
| Work Type |
GR, STRS, BASE 7 PAVT |
| |
|
1.836 |
44622238.45 |
12218.21 |
42187944.44 |
94.5 |
| Work Order |
10-13-06 |
| Work Began |
10-20-06 |
| Work Completed |
|
| Time Computed |
10-29-06 |
| Contract Working Days |
705 |
| Addl Days Granted |
248 |
| Working Days Charged |
815 |
| Percent Time Used |
85 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-166 ESSARY, HART & MACWILIAM,INC.(7.23%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20%) VAQUERO CONSTRUCTION, INC. (1.18%) EROSION CONTROL, INC.(1.71%) SCOTT DERR PAINTING CO (0.14%) BORTUNCO (0.00%) MICA CORPORATION (4.57%) ODUM SERVICES, L.P.(0.75%) JOE VALENCIK, INC. (1.48%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.71%)
|
| Contract # |
09063201 |
|
Totals |
44622238.45 |
12218.21 |
42187944.44 |
94.5 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
0.1 MI EAST OF MAGNOLIA STREET |
| To |
0.14 MI EAST OF SPUR 330 |
| CSJ |
0508-01-292 |
| Proj ID |
IM 0107(413) |
| Work Type |
REPLC EXISTING PAVEMENT & PV MRKS |
| |
|
2.592 |
20207782.85 |
6789.00 |
21172338.35 |
99.9 |
| Work Order |
03-13-08 |
| Work Began |
08-11-08 |
| Work Completed |
|
| Time Computed |
03-29-08 |
| Contract Working Days |
352 |
| Addl Days Granted |
0 |
| Working Days Charged |
350 |
| Percent Time Used |
99 |
| Contractor(s) |
| PACE SERVICES, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-292 FLORIDA TRAFFIC CONTROL DEVICES, INC.(4.62%) MESA ROD BUSTERS, INC. ( 14.48%) W. W. FOUNDATION DRILLING, LTD.(2.54%) INDUS CONSTRUCTION, L.P. (0.07%) ODUM SERVICES, L.P.(0.45%) HIGHWAY TECHNOLOGIES (1.84%) CENTURY ASPHALT MATERIALS(0.00%) HUBCO, INC.(0.04%) SILT SOLUTIONS, INC. (0.07%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.39%) INTERSTATE SAFETY SYSTEMS, INC.(1.52%) AMERICAN REMEDIATION OPTIONS, INC. (0.25%)
|
| Contract # |
12073002 |
|
Totals |
20207782.85 |
6789.00 |
21172338.35 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
US 59 |
| To |
E OF LOCKWOOD (E OF SPRR) |
| CSJ |
0508-01-294 |
| Proj ID |
IM 10-7(390) |
| Work Type |
CONC O / L & RECONSTR |
| |
|
1.575 |
12742133.74 |
0.00 |
11865226.51 |
95.0 |
| County | HARRIS |
| Highway |
IH 10 |
| From |
SAN JACINTO STREET |
| To |
LOCKWOOD |
| CSJ |
0508-01-299 |
| Proj ID |
IM 10-7(390) |
| Work Type |
RECONSTR & GRIND EXST PV & THIN BOND O / L |
| |
|
1.825 |
2732225.60 |
0.00 |
2749060.47 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-06-03 |
| Work Began |
05-13-03 |
| Work Completed |
|
| Time Computed |
02-22-03 |
| Contract Working Days |
527 |
| Addl Days Granted |
242 |
| Working Days Charged |
775 |
| Percent Time Used |
100 |
| Contractor(s) |
| ST. PAUL FIRE AND MARINE INSURANCE COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-294 GMJ PAVING CO. (3.47%) KENMOR ELECTRIC COMPANY, L.P.(0.25%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.55%) RUDY BREDA RODBUSTERS COMPANY, INC.(7.09%) BATTERSON, L.L.P.(2.40%) AGGREGATE TECHNOLOGIES, INC. (2.46%) FORDE CONSTRUCTION COMPANY, INC. (1.06%) J.A. GAMEZ TRUCKING SERVICES (1.31%) RAYMOND PAINTING, INC. (0.02%) TREVCON(3.70%) K. G. TRUCKING, INC. (0.39%) FLORES CURBS (0.09%) WALKER CONSTRUCTION(0.55%) STRAIGHT LINE(0.10%)
|
| Contract # |
12023202 |
|
Totals |
15474359.34 |
0.00 |
14614286.98 |
96.4 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
HOLLAND |
| To |
FEDERAL ROAD |
| CSJ |
0508-01-298 |
| Proj ID |
IM 0107(412) |
| Work Type |
GR, BS, CONC PVMT & PV MKS |
| |
|
6.482 |
19270603.40 |
1187239.35 |
10747215.73 |
53.5 |
| Work Order |
01-10-08 |
| Work Began |
07-07-08 |
| Work Completed |
|
| Time Computed |
04-09-08 |
| Contract Working Days |
433 |
| Addl Days Granted |
0 |
| Working Days Charged |
121 |
| Percent Time Used |
27 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-298 BATTERSON, L.L.P.(2.68%) SEMARCK LANDSCAPE SERVICES, INC. (0.72%) WILLOW CITY SIGN & RAIL, INC.(0.70%) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(2.02%) DYNAMIC VISION CO., INC. (1.10%) LONE STAR ROAD CONSTRUCTION, LTD.(9.21%) ENVIRONMENTAL ALLIES, L.P. (0.30%) CPAV SPECIALTIES, LP (0.05%) J & M CONTRACTING, COMPANY (2.45%) AGGREGATE TECHNOLOGIES, INC. (1.32%) CURB PLANET INC. (0.00%)
|
| Contract # |
11073202 |
|
Totals |
19270603.40 |
1187239.35 |
10747215.73 |
53.5 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
AT SAN JACINTO RIVER |
| To |
. |
| CSJ |
0508-01-309 |
| Proj ID |
BR 2008(079) |
| Work Type |
FNDR SYS & SUPPORT COLUMN PROTECTIO |
| |
|
0.001 |
3468680.00 |
243509.51 |
3056031.22 |
88.1 |
| Work Order |
11-01-07 |
| Work Began |
03-03-08 |
| Work Completed |
|
| Time Computed |
11-17-07 |
| Contract Working Days |
116 |
| Addl Days Granted |
7 |
| Working Days Charged |
68 |
| Percent Time Used |
55 |
| Contractor(s) |
| ORION CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-309 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10073218 |
|
Totals |
3468680.00 |
243509.51 |
3056031.22 |
88.1 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
US 59 |
| To |
GELLHORN |
| CSJ |
0508-01-322 |
| Proj ID |
HP 2008(173) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
4.000 |
1045496.65 |
7815.52 |
967274.90 |
92.5 |
| Work Order |
11-28-07 |
| Work Began |
02-06-08 |
| Work Completed |
|
| Time Computed |
01-27-08 |
| Contract Working Days |
90 |
| Addl Days Granted |
31 |
| Working Days Charged |
121 |
| Percent Time Used |
100 |
| Contractor(s) |
| TEXAS TREE & LANDSCAPE, LTD |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-322 SUSTAINABLE GROWTH TEXAS ( 11.22%)
|
| Contract # |
11073212 |
|
Totals |
1045496.65 |
7815.52 |
967274.90 |
92.5 |
|