|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | GALVESTON |
| Highway |
SH 146 |
| From |
AT FM 1764 |
| To |
. |
| CSJ |
0389-06-101 |
| Proj ID |
STP 2012(512)HES |
| Work Type |
LEFT TURN LANE |
| |
|
0.133 |
98934.92 |
0.00 |
160303.98 |
99.9 |
| Work Order |
07-12-12 |
| Work Began |
08-13-12 |
| Work Completed |
|
| Time Computed |
07-28-12 |
| Contract Working Days |
30 |
| Addl Days Granted |
9 |
| Working Days Charged |
42 |
| Percent Time Used |
107 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-101 HIGHWAY TECHNOLOGIES, INC. (4.95%) KEY-SCAPE LANDSCAPE CONSTRUCTION ( 11.72%) HOLES INCORPORATED (0.51%) CURB PLANET INC. (0.93%) HOUSTON SAWING & DRILLING(1.82%)
|
| Contract # |
05123012 |
|
Totals |
98934.92 |
0.00 |
160303.98 |
99.9 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
AT SPUR 330 |
| To |
. |
| CSJ |
0389-13-056 |
| Proj ID |
DMO 2013(178) |
| Work Type |
CONSTRUCT DIRECT CONNECTOR |
| |
|
0.020 |
6585237.93 |
423659.20 |
468785.46 |
7.1 |
| Work Order |
01-15-13 |
| Work Began |
02-14-13 |
| Work Completed |
|
| Time Computed |
01-31-13 |
| Contract Working Days |
195 |
| Addl Days Granted |
0 |
| Working Days Charged |
53 |
| Percent Time Used |
27 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-056 SCOTT DERR PAINTING CO, LLC(0.30%) WEBBER-BALKE FOUNDATION COMPANY, INC.( 13.91%) HIGHWAY TECHNOLOGIES, INC. (0.46%) HOUSTON SAWING & DRILLING(0.13%) KOSSMAN CONTRACTING CO., INC.(0.19%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36%) MESA ROD BUSTERS, INC. (5.19%) PROFESSIONAL TRAFFIC CONTROL, LLC(0.62%) AQUALAWN HYDROMULCH & EROSION CONTROL(0.49%)
|
| Contract # |
11123215 |
|
Totals |
6585237.93 |
423659.20 |
468785.46 |
7.1 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
0.4808 MILES SOUTH OF EL DORADO |
| To |
SOUTH OF MEDICAL CENTER DRIVE |
| CSJ |
0500-03-042 |
| Proj ID |
NH 2013(163) |
| Work Type |
GR, WIDEN STRS & RECONSTR PV |
| |
|
2.180 |
92660504.64 |
677569.41 |
18490058.16 |
19.9 |
| County | HARRIS |
| Highway |
IH 45 |
| From |
0.4808 MILES SOUTH OF EL DORADO |
| To |
MEDICAL CENTER DRIVE |
| CSJ |
0500-03-546 |
| Proj ID |
RW 500-3-546 |
| Work Type |
ROW ACQUISITION, RELO & UTILITIES |
| |
|
5.530 |
627780.60 |
0.00 |
0.00 |
0.0 |
| Work Order |
12-12-12 |
| Work Began |
12-17-12 |
| Work Completed |
|
| Time Computed |
12-17-12 |
| Contract Working Days |
1,125 |
| Addl Days Granted |
0 |
| Working Days Charged |
45 |
| Percent Time Used |
4 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-042 SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.64%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59%) ESSARY, HART & MACWILIAM,INC.(8.94%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%) SCOTT DERR PAINTING CO, LLC(0.03%) INTERSTATE BARRICADES & MARKINGS, INC. (0.78%) CREACOM, INC.(4.12%) BASE CONSTRUCTION, L.L.P.( 12.36%)
|
| Contract # |
11123001 |
|
Totals |
93288285.24 |
677569.41 |
18490058.16 |
19.8 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
NYACK ROAD |
| To |
0.7881 MILES SOUTH OF FM 1959 |
| CSJ |
0500-03-462 |
| Proj ID |
C 500-3-462 |
| Work Type |
GR, STRS, BASE, AND PAVE |
| |
|
5.188 |
77483150.88 |
1752880.83 |
34589144.41 |
44.0 |
| Work Order |
06-15-11 |
| Work Began |
06-17-11 |
| Work Completed |
|
| Time Computed |
06-17-11 |
| Contract Working Days |
1,135 |
| Addl Days Granted |
25 |
| Working Days Charged |
464 |
| Percent Time Used |
40 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-462 BASE CONSTRUCTION, L.L.P.( 11.55%) DORAN STEEL, INC.( 11.03%) INTERSTATE BARRICADES & MARKINGS, INC. (1.06%) CREACOM, INC.(4.33%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.59%) WEST TEXAS RUMBLE STRIP(0.00%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.58%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%) SCOTT DERR PAINTING CO (0.23%) MAGNUM TUNNELING, LLC(0.05%) FOSTER FENCE, LTD. (0.00%)
|
| Contract # |
05113210 |
|
Totals |
77483150.88 |
1752880.83 |
34589144.41 |
44.0 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
AT PARKER AND LITTLE YORK ROAD |
| To |
. |
| CSJ |
0500-03-553 |
| Proj ID |
IM 0451(338) |
| Work Type |
ARMOR JNT & WIDE FLNG BM REPR |
| |
|
0.130 |
364992.00 |
0.00 |
367025.76 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-10-11 |
| Work Began |
01-13-12 |
| Work Completed |
|
| Time Computed |
06-26-11 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
45 |
| Percent Time Used |
125 |
| Contractor(s) |
| SPRING EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-553 TEXAS STERLING CONSTRUCTION CO.( 47.35%) HOLES INCORPORATED (1.08%) BATTERSON,LLP(1.74%) CPAVE, INC.(3.06%)
|
| Contract # |
05113014 |
|
Totals |
364992.00 |
0.00 |
367025.76 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
HOUSTON CITY STREETS (AT TELLESPEN |
| To |
UNDERPASS) |
| CSJ |
0500-03-563 |
| Proj ID |
DMO 2006(885) |
| Work Type |
FLOOD / DRAINAGE IMPROVEMENTS |
| |
|
0.549 |
3069254.60 |
21000.00 |
3228292.01 |
100.0 |
| County | HARRIS |
| Highway |
IH 45 |
| From |
HOUSTON CITY STREETS (AT TELLESPEN |
| To |
UNDERPASS) |
| CSJ |
0500-03-568 |
| Proj ID |
IM 0451(337) |
| Work Type |
ROW UTL. ADJ. |
| |
|
0.001 |
0.00 |
0.00 |
0.00 |
0.0 |
| Work Order |
01-06-11 |
| Work Began |
06-28-11 |
| Work Completed |
04-19-13 |
| Time Computed |
03-06-11 |
| Contract Working Days |
391 |
| Addl Days Granted |
0 |
| Working Days Charged |
277 |
| Percent Time Used |
70 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-563 BATTERSON,LLP(1.28%) PFEIFFER & SON LTD.(0.22%) ENVIRONMENTAL ALLIES, L.P. (0.54%) EL DORADO PAVING COMPANY, INC. (1.22%) T & C CONSTRUCTION, INC. ( 17.91%) CHERRY CONCRETE REMOVAL(0.32%) MAGNUM TUNNELING, LLC(1.09%) PEREZ CONSTRUCTION CO. (0.10%) FOSTER FENCE, LTD. (0.42%) WILLOW CITY SIGN & RAIL, INC.(0.12%) MESA ROD BUSTERS, INC. (0.24%)
|
| Contract # |
10103023 |
|
Totals |
3069254.60 |
21000.00 |
3228292.01 |
100.0 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
AT SHEPHERD |
| To |
. |
| CSJ |
0500-03-577 |
| Proj ID |
C 500-3-577 |
| Work Type |
TMS IMPRVMTS CONT NB & SB DCS |
| |
|
4.549 |
24847758.29 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
449 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-577 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133201 |
|
Totals |
24847758.29 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SH 225 |
| From |
WAFER STREET |
| To |
BW 8 |
| CSJ |
0502-01-206 |
| Proj ID |
NH 2012(669) |
| Work Type |
HIGH MAST ILLUMINATION |
| |
|
3.484 |
1874035.37 |
89924.28 |
1506736.17 |
80.4 |
| Work Order |
08-16-12 |
| Work Began |
11-26-12 |
| Work Completed |
|
| Time Computed |
09-01-12 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
106 |
| Percent Time Used |
48 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-206 WILLOW CITY SIGN & RAIL, INC.(4.79%) W. W. FOUNDATION DRILLING, LTD.( 10.34%)
|
| Contract # |
07123228 |
|
Totals |
1874035.37 |
89924.28 |
1506736.17 |
80.4 |
|
| County | HARRIS |
| Highway |
SH 225 |
| From |
GOODYEAR ROAD |
| To |
RED BLUFF |
| CSJ |
0502-01-208 |
| Proj ID |
NH 2012(709) |
| Work Type |
ACP O / L, BS REP |
| |
|
3.450 |
2342263.41 |
1400.00 |
1400.00 |
0.0 |
| Work Order |
09-24-12 |
| Work Began |
04-28-13 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
84 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-208 ROADSAFE TRAFFIC SYSTEMS, INC. (2.56%) MAIN LANE INDUSTRIES, LTD. (7.69%) HOLES INCORPORATED (1.33%)
|
| Contract # |
08123017 |
|
Totals |
2342263.41 |
1400.00 |
1400.00 |
0.0 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
AT WAYSIDE |
| To |
. |
| CSJ |
0508-01-331 |
| Proj ID |
IM 0107(429) |
| Work Type |
INSTALL U - TURNS |
| |
|
0.208 |
1550849.21 |
1605.60 |
1507939.92 |
99.9 |
| Work Order |
11-03-11 |
| Work Began |
03-15-12 |
| Work Completed |
|
| Time Computed |
11-19-11 |
| Contract Working Days |
115 |
| Addl Days Granted |
0 |
| Working Days Charged |
196 |
| Percent Time Used |
170 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-331 FLORIDA TRAFFIC CONTROL DEVICES, INC.( 31.27%) HIGHWAY TECHNOLOGIES, INC. (1.74%) CRAIG & HEIDT, INC.(1.42%) CHERRY CONCRETE REMOVAL(0.52%) GULF COAST PAVERS, INC.(2.21%) SCOTT DERR PAINTING CO, LLC(0.33%) TREVCON, INC.( 12.89%) ROMAR UNLIMITED, INC.(0.73%) SCR CONSTRUCTION CO., INC. (1.79%) AQUALAWN HYDROMULCH & EROSION CONTROL(0.13%)
|
| Contract # |
09113029 |
|
Totals |
1550849.21 |
1605.60 |
1507939.92 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
MERCURY |
| To |
CLOVERLEAF ST |
| CSJ |
0508-01-332 |
| Proj ID |
IM 0107(435) |
| Work Type |
HIGH MAST ILLUMINATION |
| |
|
4.100 |
2460155.34 |
0.00 |
0.00 |
0.0 |
| Work Order |
04-03-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-19-13 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CREACOM, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-332 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01133221 |
|
Totals |
2460155.34 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
ON IH 10, FROM N. WAYSIDE TO BW 8 & |
| To |
ON IH 610 AT MCCARTY |
| CSJ |
0508-01-335 |
| Proj ID |
C 508-1-335 |
| Work Type |
INTERSECTION IMPROVEMENTS |
| |
|
1.150 |
1650456.27 |
0.00 |
0.00 |
0.0 |
| Work Order |
11-14-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-30-12 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
22 |
| Percent Time Used |
34 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-335 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10123027 |
|
Totals |
1650456.27 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SP 330 |
| From |
EAST OF OAKLAND AVE(EB FRONTAGE RD) |
| To |
BAYWAY DR |
| CSJ |
0508-07-281 |
| Proj ID |
NH 2013(390) |
| Work Type |
BS REP, MILLING, & ACP OVERLAY |
| |
|
2.347 |
1510503.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-26-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-07-281 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133027 |
|
Totals |
1510503.00 |
0.00 |
0.00 |
0.0 |
|
| County | WALLER |
| Highway |
FM 362 |
| From |
NB AT FM 529 AND NB AT ROYAL ST |
| To |
. |
| CSJ |
0523-02-043 |
| Proj ID |
STP 2012(601)MM |
| Work Type |
INSTALL LEFT TURN LANES |
| |
|
0.710 |
763184.54 |
6120.24 |
812339.38 |
99.9 |
| Work Order |
10-12-12 |
| Work Began |
11-27-12 |
| Work Completed |
|
| Time Computed |
10-28-12 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
57 |
| Percent Time Used |
95 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-043 COX PAVING COMPANY, L.P. (4.21%) CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.11%) BATTERSON,LLP(5.03%) JMHP, INC. (3.38%) EROSION CONTROL, INC.(2.43%)
|
| Contract # |
08123041 |
|
Totals |
763184.54 |
6120.24 |
812339.38 |
99.9 |
|
| County | FORT BEND |
| Highway |
FM 359 |
| From |
W OF FARMER ROAD |
| To |
US 90A |
| CSJ |
0543-02-047 |
| Proj ID |
STP 2009(701)ES |
| Work Type |
GR, STR, BASE, & CONC |
| |
|
2.424 |
11784812.25 |
0.00 |
11802417.77 |
99.9 |
| Work Order |
04-01-10 |
| Work Began |
04-19-10 |
| Work Completed |
|
| Time Computed |
04-17-10 |
| Contract Working Days |
468 |
| Addl Days Granted |
118 |
| Working Days Charged |
728 |
| Percent Time Used |
124 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-047 BATTERSON, L.L.P.(2.04%) SEMARCK LANDSCAPE SERVICES, INC. (0.04%) GMJ PAVING CO. ( 15.60%) CHAMPIONS HYDROLAWN(0.66%) ORP CONSTRUCTION (0.57%) BREDA COMPANY, INC.(0.72%) HOLES INCORPORATED (0.02%) CHERRY DEMOLITION(0.06%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%) H & H CURB COMPANY (0.20%) JMHP, INC. (0.03%) GULF COAST PAVERS, INC.(0.11%) THIRD COAST SERVICES, LLC(3.04%)
|
| Contract # |
02103003 |
|
Totals |
11784812.25 |
0.00 |
11802417.77 |
99.9 |
|
| County | BRAZORIA |
| Highway |
SH 332 |
| From |
FM 523 |
| To |
SURFSIDE |
| CSJ |
0586-01-064 |
| Proj ID |
STP 2013(320) |
| Work Type |
ACP OVERLAY |
| |
|
2.665 |
684632.05 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-06-13 |
| Work Began |
05-02-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
33 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0586-01-064 CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.93%) HIGHWAY TECHNOLOGIES, INC. (0.30%) STRIPES & STOPS COMPANY, INC.(3.50%) THIRD COAST SERVICES LLC (1.97%) WEST TEXAS RUMBLE STRIP(0.82%)
|
| Contract # |
01133209 |
|
Totals |
684632.05 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SH 288 |
| From |
AT IH 610 |
| To |
. |
| CSJ |
0598-01-094 |
| Proj ID |
C 598-1-94 |
| Work Type |
INTERSECTION IMPROVEMENTS |
| |
|
0.288 |
953842.72 |
51920.02 |
859807.06 |
91.2 |
| Work Order |
09-24-12 |
| Work Began |
11-12-12 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
68 |
| Addl Days Granted |
0 |
| Working Days Charged |
85 |
| Percent Time Used |
125 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0598-01-094 TRAFFIC SYSTEMS CONSTRUCTION, INC. (9.11%) REGIONAL TRAFFIC SERVICES LLC(2.04%) CRAIG & HEIDT, INC.(4.69%) COASTAL CRUSHED CONCRETE, LLC(1.36%) AQUA LAWN(2.07%) BREDA COMPANY, INC.(0.96%) W. W. FOUNDATION DRILLING, LTD.(2.83%)
|
| Contract # |
08123013 |
|
Totals |
953842.72 |
51920.02 |
859807.06 |
91.2 |
|
| County | BRAZORIA |
| Highway |
SH 288 |
| From |
AT SH 6 |
| To |
. |
| CSJ |
0598-02-094 |
| Proj ID |
NH 2012(361) |
| Work Type |
TURNAROUND AND RIGHT TURN LN |
| |
|
0.132 |
489302.55 |
210231.58 |
423621.09 |
86.5 |
| Work Order |
05-22-12 |
| Work Began |
08-14-12 |
| Work Completed |
|
| Time Computed |
07-21-12 |
| Contract Working Days |
82 |
| Addl Days Granted |
0 |
| Working Days Charged |
81 |
| Percent Time Used |
98 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-094 HOUSTON SAWING & DRILLING(1.13%) THIRD COAST SERVICES LLC ( 40.51%) NORTHWEST MATERIALS(0.30%) ENVIRONMENTAL ALLIES, L.P. (0.93%) HIGHWAY TECHNOLOGIES, INC. (3.04%)
|
| Contract # |
04123205 |
|
Totals |
489302.55 |
210231.58 |
423621.09 |
86.5 |
|
| County | BRAZORIA |
| Highway |
SH 288 |
| From |
AT SH 35 |
| To |
. |
| CSJ |
0598-04-025 |
| Proj ID |
NH 2013(124) |
| Work Type |
CONSTR TURNAROUND |
| |
|
0.087 |
216059.82 |
0.00 |
0.00 |
0.0 |
| Work Order |
11-14-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
01-13-13 |
| Contract Working Days |
63 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
57 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0598-04-025 KOSSMAN CONTRACTING CO., INC.(3.16%) HIGHWAY TECHNOLOGIES, INC. (2.74%) REGIONAL TRAFFIC SERVICES LLC(1.16%)
|
| Contract # |
10123008 |
|
Totals |
216059.82 |
0.00 |
0.00 |
0.0 |
|
| County | MONTGOMERY |
| Highway |
IH 45 |
| From |
0.717 MI NORTH OF NORTH LOOP 336 |
| To |
0.118 MI NORTH OF SOUTH LOOP 336 |
| CSJ |
0675-08-052 |
| Proj ID |
NH 2007(813) |
| Work Type |
GR, STRS, BASE & CONC PAVE |
| |
|
4.489 |
168445217.29 |
0.00 |
169644622.95 |
100.0 |
| County | MONTGOMERY |
| Highway |
IH 45 |
| From |
0.60 MI NORTH OF NORTH LOOP 336 |
| To |
0.043 MI NORTH OF SOUTH LOOP 336 |
| CSJ |
0675-08-089 |
| Proj ID |
NH 2007(211) |
| Work Type |
UTILITIES |
| |
|
4.489 |
7079517.00 |
0.00 |
7031011.02 |
100.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-28-07 |
| Work Began |
09-04-07 |
| Work Completed |
05-10-13 |
| Time Computed |
09-13-07 |
| Contract Working Days |
1,196 |
| Addl Days Granted |
157 |
| Working Days Charged |
1,353 |
| Percent Time Used |
100 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-052 ESSARY, HART & MACWILIAM,INC.( 10.92%) JOE VALENCIK, INC. (0.41%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.38%) PRIMATE CONSTRUCTION, INC. (0.04%) SCOTT DERR PAINTING CO (0.19%) VAQUERO CONSTRUCTION, INC. (0.50%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%) EROSION CONTROL, INC.(0.46%) NILEX CONSTRUCTION LLC (0.38%) WILLOW CITY SIGN & RAIL, INC.(0.24%) BORTUNCO (1.20%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.62%) VICON SERVICES, INC. (0.01%) INTERSTATE BARRICADES & MARKINGS, INC. (0.34%) W. W. FOUNDATION DRILLING, LTD.(0.09%) BROOKLYN SWEEPS(0.01%) MAXIMUM EROSION SOLUTIONS(0.31%)
|
| Contract # |
08073001 |
|
Totals |
175524734.29 |
0.00 |
176675633.97 |
100.0 |
|