Monthly State Let Construction Report For Houston District As Of Jun 11, 2013 Page 4 Of 9

Last Update: Tuesday, June 11, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTGOMERY
Highway IH 45
From 1.1 MI SOUTH OF WALKER COUNTY LINE
To NORTH OF CALVARY ROAD
CSJ 0675-08-103
Proj ID NH 2011(372)
Work Type GR, STRS, BASE AND CONC PAVE
 
2.610 24972837.01 37557.89 24475454.05 98.6
Work Order 11-16-10
Work Began 12-06-10
Work Completed  
Time Computed 12-02-10
Contract Working Days 587
Addl Days Granted 0
Working Days Charged 696
Percent Time Used 118
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-103
ROADSAFE TRAFFIC SYSTEMS, INC. (0.08%)
SMITH & COMPANY(8.67%)
ENVIRONMENTAL ALLIES, L.P. (0.05%)
RDI FOUNDATION DRILLING(0.66%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.39%)
EROSION CONTROL, INC.(0.89%)
BATTERSON,LLP(1.08%)
L.A. UTILITIES, INC. (8.15%)
INDUS CONSTRUCTION, L.P. (8.05%)
WILLOW CITY SIGN & RAIL, INC.(0.46%)
VALLEY PLACERS, LLC(0.03%)
WEBBER BARRIER SERVICES, INC.(2.64%)
SOUTHERN CRUSHED CONCRETE INC. (0.77%)
MTAM CORPORATION (0.59%)
BORTUNCO (1.97%)
CREACOM, INC.(4.40%)
MAGNUM TUNNELING, LLC(0.21%)
B & D MAINTENANCE(0.79%)
SPECIALTY DRILLING (0.24%)
SOUTH TEXAS PAINTING COMPANY (0.12%)
Contract # 08103119
Totals 24972837.01 37557.89 24475454.05 98.6

CountyMONTGOMERY
Highway IH 45
From SH 336 SOUTH LOOP
To NORTH LEAGUE LINE ROAD
CSJ 0675-08-107
Proj ID HP 2013(692)
Work Type LANDSCAPE DEVELOPMENT
 
6.300 745136.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133027
Totals 745136.01 0.00 0.00 0.0

CountyHARRIS
Highway SH 249
From AT BOUDREAUX EASTBOUND & WESTBOUND
To .
CSJ 0720-03-126
Proj ID NH 2012(710)
Work Type ADD MEDIAN LNS & REBUILD SIGNALS
 
0.100 322274.27 19152.00 19245.00 5.9
CountyMONTGOMERY
Highway FM 2978
From CONROE HUFFSMITH ROAD
To HARRIS COUNTY LINE
CSJ 3050-02-021
Proj ID STP 2012(107)
Work Type GR, STRS, BASE AND PAVE
 
0.663 743106.43 280013.38 370717.57 49.8
Work Order 10-18-12
Work Began 04-15-13
Work Completed  
Time Computed 02-15-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 31
Contractor(s)
TRIPLE B SERVICES, L.L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-021
BATTERSON,LLP(4.23%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 19.45%)
HODGES BROTHERS, INC.(0.37%)
KOSSMAN CONTRACTING CO., INC.(2.67%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC( 14.86%)
WILLOW CITY SIGN & RAIL, INC.(4.62%)
ENVIRONMENTAL ALLIES, L.P. (0.05%)
Contract # 08123244
Totals 1065380.70 299165.38 389962.57 36.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON SH 6 & FM 1960
To .
CSJ 0912-00-324
Proj ID STP 2012(602)
Work Type INST BATT BACK UP & UPGD POWER METR
 
0.001 555317.00 30612.00 583804.50 99.9
Work Order 07-12-12
Work Began 01-25-13
Work Completed  
Time Computed 07-28-12
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 54
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-324
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06123020
Totals 555317.00 30612.00 583804.50 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 0.00 953292.97 64.2
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 43
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 0.00 953292.97 64.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-335
Proj ID STP 2010(057)ES
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 898349.73 44.00 927416.91 99.9
Work Order 11-16-09
Work Began 08-17-10
Work Completed  
Time Computed 08-02-10
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 76
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-335
SPRING CREEK CONSTRUCTION, INC.(3.85%)
BATTERSON,LLP(1.16%)
Contract # 09093012
Totals 898349.73 44.00 927416.91 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 101681.51 23.1
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 58
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 101681.51 23.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 9823.66 487373.51 37.7
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 48
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
Contract # 04093209
Totals 1289999.25 9823.66 487373.51 37.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 13107.34 234189.06 15.4
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 10
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09113211
Totals 1515998.78 13107.34 234189.06 15.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133016
Totals 1787199.58 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-383
Proj ID STP 2010(058)ES
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 946870.85 76833.12 808239.05 85.3
Work Order 10-30-09
Work Began 01-25-11
Work Completed  
Time Computed 11-15-09
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 30
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-383
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.00%)
YORK & YORK FOUNDATION DRILLING, INC.(0.11%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.19%)
THOMPSON CONSTRUCTION(3.27%)
BELL BOTTOM FOUNDATION CO. (0.63%)
ENERGY ELECTRICAL SUPPLY,INC.(0.84%)
VACA UNDERGROUND UTILITIES INC (0.91%)
Contract # 09093011
Totals 946870.85 76833.12 808239.05 85.3

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1020950.13 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 146
Percent Time Used 54
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1020950.13 99.9

CountyHARRIS
Highway VA
From ON SH 6; IH 10
To VOSS ROAD (FORT BEND & HARRIS CO.)
CSJ 0912-00-399
Proj ID NH 1102(307)
Work Type ACCESS MGT IMPRVMTS
 
9.000 3134199.14 60.02 2848091.90 91.4
Work Order 09-30-11
Work Began 10-31-11
Work Completed  
Time Computed 10-16-11
Contract Working Days 176
Addl Days Granted 2
Working Days Charged 199
Percent Time Used 111
Contractor(s)
ROZCO CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-399
BATTERSON,LLP(8.48%)
SILVA CONTRACTING COMPANY, INC.(8.00%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.72%)
MAGNUM TUNNELING, LLC(0.53%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (8.01%)
CURB PLANET INC. (4.67%)
CPAVE, INC.(0.30%)
CROSSROADS DECORATIVE PAVEMENT ( 19.21%)
Contract # 08113249
Totals 3134199.14 60.02 2848091.90 91.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 1000.00 570394.80 66.3
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 38
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 1000.00 570394.80 66.3

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 0.00 0.00 0.0
Work Order 03-22-13
Work Began 00-00-00
Work Completed  
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133028
Totals 598106.25 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-455
Proj ID NH 1102(144)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 1441141.70 9409.63 984987.06 68.3
Work Order 09-06-11
Work Began 09-22-11
Work Completed  
Time Computed 09-22-11
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-455
CONROE WOOD PRODUCTS INC.(1.76%)
ENVIRONMENTAL ALLIES, L.P. (0.87%)
LOPEZ BROTHERS ENTERPRISES, INC. (1.48%)
Contract # 07113215
Totals 1441141.70 9409.63 984987.06 68.3

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON IH 45
To .
CSJ 0912-00-468
Proj ID IM 0451(341)
Work Type LANDSCAPE DEVELOPMENT
 
52.668 1130845.26 2435.61 751065.07 66.4
Work Order 05-15-12
Work Began 06-15-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 105
Addl Days Granted 45
Working Days Charged 130
Percent Time Used 86
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-468
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123018
Totals 1130845.26 2435.61 751065.07 66.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To ALL LOCATIONS ON US 59 & IH 610
CSJ 0912-00-469
Proj ID NH 2012(513)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 778293.17 760.67 458217.62 58.8
Work Order 06-11-12
Work Began 06-15-12
Work Completed  
Time Computed 06-27-12
Contract Working Days 90
Addl Days Granted 75
Working Days Charged 139
Percent Time Used 84
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-469
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123222
Totals 778293.17 760.67 458217.62 58.8