Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALLER
Highway US 90
From AT FM 359
To .
CSJ 0271-09-021
Proj ID STP 2014(924)
Work Type INSTALL LEFT TURN LANE
 
0.566 671947.83 1350.00 703700.89 100.0
Work Order 09-11-14
Work Began 09-22-14
Work Completed 12-09-15
Time Computed 09-22-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 71
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-09-021
BATTERSON,LLP(5.36%)
THIRD COAST SERVICES LLC ( 17.52%)
EROSION CONTROL, INC.(2.64%)
JMHP, INC. (1.54%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.18%)
Contract # 07143037
Totals 671947.83 1350.00 703700.89 100.0

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-213
Proj ID CM 2013(991)
Work Type GR, STRS, BASE AND PAVE
 
0.198 151543734.14 750238.52 62932560.15 41.3
Work Order 12-11-13
Work Began 12-31-13
Work Completed  
Time Computed 07-07-14
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 16
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-213
CPAVE, INC.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.37%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.75%)
SCOTT DERR PAINTING CO, LLC(0.21%)
HOUSTON SAWING & DRILLING(0.07%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.28%)
ESSARY, HART & MACWILIAM,INC.(9.64%)
BORTUNCO (0.53%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.57%)
RAY"S THREADING AND FAB SHOP (0.39%)
Contract # 11133201
Totals 151543734.14 750238.52 62932560.15 41.3

CountyHARRIS
Highway IH 610
From TC JESTER TO N OF IH 10 ON IH 610
To AND TO 34TH ST ON US 290
CSJ 0271-14-217
Proj ID STP 2011(998)MM
Work Type GR, STRS, BASE AND PAVE
 
5.604 151578391.02 0.00 153061838.42 98.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-11
Work Began 06-20-11
Work Completed  
Time Computed 07-11-11
Contract Working Days 1,124
Addl Days Granted 106
Working Days Charged 1,223
Percent Time Used 99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-217
INTERSTATE BARRICADES & MARKINGS, INC. (0.54%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.43%)
ESSARY, HART & MACWILIAM,INC.( 11.06%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%)
SCOTT DERR PAINTING CO (0.58%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.77%)
BORTUNCO (0.29%)
SPECIALTY DRILLING (0.39%)
AMERICAN TRAFFIC CONTROL, INC. (0.01%)
TREVCON, INC.(0.09%)
BROOKLYN SWEEPS(0.24%)
MAGNOLIA SERVICES INCORPORATED (0.04%)
CHERRY DEMOLITION(0.07%)
PENHALL COMPANY(0.00%)
Contract # 05113015
Totals 151578391.02 0.00 153061838.42 98.4

CountyHARRIS
Highway IH 610
From AT IH 45(N) INTERCHANGE
To .
CSJ 0271-14-224
Proj ID IM 6107(438)
Work Type ACP O / L
 
0.520 1766700.70 0.00 1770732.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-13
Work Began 08-09-14
Work Completed 05-11-15
Time Computed 03-01-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 35
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-224
BATTERSON,LLP(4.84%)
MAIN LANE INDUSTRIES, LTD. ( 18.20%)
Contract # 08133230
Totals 1766700.70 0.00 1770732.57 100.0

CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To ON IH 610
CSJ 0271-14-225
Proj ID RW 271-14-225
Work Type ROW ACQ., UTL. ADJ.; RELOC ASSIST.
 
2.640 1670105.95 0.00 1594268.79 95.4
CountyHARRIS
Highway IH 610
From W OF W 34TH ST ON US 290 (SEG 3)
To N AND S OF US 290 ON IH 610
CSJ 0271-14-228
Proj ID STP 2013(136)MM
Work Type GR, STRS, BASE AND PAVE
 
1.661 105376730.46 2145578.99 78566758.66 74.1
Work Order 11-09-12
Work Began 11-20-12
Work Completed  
Time Computed 02-04-13
Contract Working Days 1,030
Addl Days Granted 0
Working Days Charged 871
Percent Time Used 84
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-228
BATTERSON,LLP(0.69%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.16%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36%)
ESSARY, HART & MACWILIAM,INC.(9.54%)
SCOTT DERR PAINTING CO, LLC(0.23%)
MAGNOLIA SERVICES INCORPORATED (0.17%)
CURB PLANET INC. (0.02%)
EROSION PREVENTION PRODUCTS(0.15%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.74%)
W. W. FOUNDATION DRILLING, LTD.(0.21%)
TEJAS UNDERGROUND UTILITIES, LLC (0.00%)
BROOKLYN SWEEPS(0.23%)
Contract # 10123001
Totals 107046836.41 2145578.99 80161027.45 74.4

CountyHARRIS
Highway IH 610
From US 290
To IH 45
CSJ 0271-14-232
Proj ID HP 1502(446)
Work Type LANDSCAPE DEVELOPMENT
 
6.020 828677.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-232
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153240
Totals 828677.47 0.00 0.00 0.0

CountyHARRIS
Highway IH 610
From AT IH 10 (E) INTERCHANGE
To .
CSJ 0271-15-086
Proj ID NH 2015(239)
Work Type SLDR REP, PV REP, FULL DEPTH REP, ETC
 
3.793 4114146.51 11696.05 3214053.44 78.1
Work Order 01-05-15
Work Began 04-27-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 177
Percent Time Used 84
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0271-15-086
BATTERSON,LLP(2.23%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(1.52%)
COX PAVING COMPANY, L.P. (4.18%)
ISI CONTRACTING, INC.( 36.12%)
R & A TRANSPORT, INC.(5.02%)
Contract # 10143008
Totals 4114146.51 11696.05 3214053.44 78.1

CountyHARRIS
Highway IH 610
From .228 MILES WEST OF LONG DRIVE
To .241 MILES EAST OF SH 288
CSJ 0271-16-130
Proj ID IM 6107(440)
Work Type HIGH MAST ILLUMINATION
 
3.237 1733013.17 0.00 1752079.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-13
Work Began 12-27-13
Work Completed 02-03-15
Time Computed 12-27-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 104
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-130
VACA UNDERGROUND UTILITIES INC (4.27%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.49%)
INTERSTATE STEEL (BIG SPRING)(1.31%)
THOMPSON CONSTRUCTION(0.80%)
RICE ENVIRONMENTAL SERVICES(1.99%)
BAY CITY TRAFFIC (2.42%)
Contract # 07133231
Totals 1733013.17 0.00 1752079.10 100.0

CountyHARRIS
Highway IH 610
From AT CRESTMONT STREET
To .
CSJ 0271-16-134
Proj ID STP 2014(484)HES
Work Type IMPROVE TS
 
0.404 699002.00 0.00 733673.32 99.9
Work Order 05-01-14
Work Began 10-28-14
Work Completed  
Time Computed 10-28-14
Contract Working Days 123
Addl Days Granted 19
Working Days Charged 145
Percent Time Used 102
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-134
KAM CONSTRUCTION, INC. ( 10.17%)
REGIONAL TRAFFIC SERVICES LLC(3.05%)
VASQUEZ CONCRETE COMPANY (6.43%)
Contract # 03143016
Totals 699002.00 0.00 733673.32 99.9

CountyMONTGOMERY
Highway SH 105
From 0.25 MI W OF GRIMES C/L
To PLANTERSVILLE RD
CSJ 0338-02-041
Proj ID NH 2015(157)
Work Type BASE REPAIR AND ACP O / L
 
7.085 2574451.88 0.00 2607405.83 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-14
Work Began 10-31-14
Work Completed 07-22-15
Time Computed 10-31-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 180
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0338-02-041
STRIPE-A-LINE, INC.(3.86%)
J & M CONTRACTING, COMPANY (2.95%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (4.35%)
Contract # 09143227
Totals 2574451.88 0.00 2607405.83 100.0

CountyMONTGOMERY
Highway SH 105
From WALDEN ROAD
To OLD RIVER ROAD
CSJ 0338-03-087
Proj ID NH 2012(372)
Work Type WIDEN WB FROM 2 TO 3 LANES
 
0.870 1127783.80 0.00 1459612.29 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-21-13
Work Began 01-02-14
Work Completed 07-01-15
Time Computed 11-19-13
Contract Working Days 45
Addl Days Granted 21
Working Days Charged 65
Percent Time Used 98
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-087
BATTERSON,LLP(4.36%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 16.28%)
GMJ PAVING CO. (3.87%)
CPAVE, INC.(2.84%)
CHERRY CONCRETE REMOVAL(0.95%)
Contract # 06133019
Totals 1127783.80 0.00 1459612.29 100.0

CountyMONTGOMERY
Highway LP 336
From FM 2854
To IH 45
CSJ 0338-11-051
Proj ID STP 2013(992)
Work Type WIDEN TO 4 LANES
 
3.826 7593341.62 0.00 8227495.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-15-13
Work Began 11-18-13
Work Completed 09-18-15
Time Computed 10-31-13
Contract Working Days 143
Addl Days Granted 104
Working Days Charged 256
Percent Time Used 103
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-051
CPAVE, INC.(0.79%)
J & M CONTRACTING, COMPANY ( 35.90%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
SIEMENS INDUSTRY, INC. (2.74%)
WEST TEXAS RUMBLE STRIP(0.18%)
WILLOW CITY SIGN & RAIL, INC.(1.37%)
BORTUNCO (0.41%)
CEN TEX HYDROSEED, INC.(4.21%)
HEMPHILL PILE DRIVING CO., A CORP. (1.91%)
THIRD COAST SERVICES LLC (2.82%)
BELKNAP CONCRETE, CUTTING & DRILLING, INC. (0.67%)
TOM-MAC, INC.(0.68%)
PRIMATE CONSTRUCTION, INC. (0.19%)
WEBBER BARRIER SERVICES, LLC.(0.34%)
HASSELL CONSTRUCTION COMPANY, INC. (1.18%)
Contract # 08133245
Totals 7593341.62 0.00 8227495.50 100.0

CountyMONTGOMERY
Highway LP 336
From SH 105 SOUTH
To 0.473 MILES NORTH OF FM 2854
CSJ 0338-11-055
Proj ID NH 2014(638)
Work Type INSTALL CTWLTL
 
0.489 1161105.76 0.00 1266789.84 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-29-14
Work Began 08-01-14
Work Completed 02-18-15
Time Computed 07-28-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 82
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0338-11-055
LONESTAR TRAFFIC SAFETY, LLC (0.54%)
CEN TEX HYDROSEED, INC.(2.76%)
BATTERSON,LLP(2.21%)
J & M CONTRACTING, COMPANY (6.65%)
CPAVE, INC.(0.64%)
Contract # 04143239
Totals 1161105.76 0.00 1266789.84 100.0

CountyGALVESTON
Highway SH 124
From SH 87
To CHAMBERS COUNTY LINE
CSJ 0367-02-077
Proj ID STP 2014(459)
Work Type ACP O / L
 
2.982 1685779.05 0.00 1629867.45 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-14
Work Began 06-09-14
Work Completed 11-12-14
Time Computed 06-09-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-077
ROADSAFE TRAFFIC SYSTEMS, INC. (3.67%)
JMHP, INC. ( 10.08%)
Contract # 04143222
Totals 1685779.05 0.00 1629867.45 100.0

CountyGALVESTON
Highway SH 124
From AT INTRACOASTAL CANAL
To .
CSJ 0367-02-081
Proj ID BR 1502(603)
Work Type CLEAN / PAINT WEATHERING STEEL
 
0.001 1137775.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-16-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OLYMPUS PAINTING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0367-02-081
ACCESS RIGGING LLC ( 24.16%)
ODUM SERVICES, L.P.(1.15%)
Contract # 08153023
Totals 1137775.00 0.00 0.00 0.0

CountyHARRIS
Highway SH 146
From AT BNSF RR/PORT ROAD
To .
CSJ 0389-05-119
Proj ID HP 2012(220)
Work Type CONSTRUCT DIRECT CONNECTOR
 
0.540 11747790.36 42288.02 11907479.02 99.9
Work Order 07-16-12
Work Began 07-24-12
Work Completed  
Time Computed 07-24-12
Contract Working Days 273
Addl Days Granted 5
Working Days Charged 197
Percent Time Used 70
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-119
MESA ROD BUSTERS, INC. (7.06%)
BATTERSON,LLP(0.23%)
JMHP, INC. (0.47%)
BASE CONSTRUCTION, L.L.P.(1.57%)
ROADWAY CONSTRUCTION, INC. (7.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08%)
KOSSMAN CONTRACTING CO., INC.(0.31%)
TRAF-TEX, INC. (1.10%)
SCOTT DERR PAINTING CO, LLC(0.03%)
Contract # 06123227
Totals 11747790.36 42288.02 11907479.02 99.9

CountyHARRIS
Highway SH 146
From VARIOUS LOCATIONS
To .
CSJ 0389-05-123
Proj ID NH 1502(604)
Work Type LANDSCAPE DEVELOPMENT
 
10.159 1376457.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153014
Totals 1376457.70 0.00 0.00 0.0

CountyGALVESTON
Highway SH 146
From AT FM 646
To .
CSJ 0389-06-103
Proj ID STP 2015(244)HES
Work Type IMPROVE TS
 
0.652 369995.94 0.00 365777.30 98.8
Work Order 11-10-14
Work Began 05-14-15
Work Completed  
Time Computed 05-09-15
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 98
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-103
STRIPES & STOPS COMPANY, INC.(1.24%)
Contract # 10143005
Totals 369995.94 0.00 365777.30 98.8

CountyHARRIS
Highway SH 146
From AT FRED HARTMAN BRIDGE
To .
CSJ 0389-12-090
Proj ID NH 1402(100)
Work Type STAY CABLE MAINTENANCE
 
0.001 5139060.00 278271.31 6204579.30 99.9
Work Order 09-22-14
Work Began 12-01-14
Work Completed  
Time Computed 11-21-14
Contract Working Days 225
Addl Days Granted 12
Working Days Charged 237
Percent Time Used 100
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0389-12-090
LONESTAR TRAFFIC SAFETY, LLC (0.46%)
ALPIN TECHNIK UND INGENIEURSERVICE GMBH( 62.87%)
PURE TECHNOLOGIES(1.51%)
Contract # 08143030
Totals 5139060.00 278271.31 6204579.30 99.9

CountyHARRIS
Highway SH 146
From 0.19 MILES SOUTH OF WEST MAIN
To 0.37 MILES SOUTH OF WEST TEXAS
CSJ 0389-13-057
Proj ID NH 2015(158)
Work Type MILL & O / L
 
1.130 224351.11 0.00 199296.84 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-14
Work Began 05-20-15
Work Completed 08-10-15
Time Computed 12-13-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 83
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-057
LONESTAR TRAFFIC SAFETY, LLC (1.00%)
BATTERSON,LLP( 17.29%)
Contract # 09143010
Totals 224351.11 0.00 199296.84 100.0