Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway VA
From VAR LOCATIONS OUTSIDE HARRIS COUNTY
To .
CSJ 0912-00-384
Proj ID STP 2010(741)
Work Type PAVEMENT MARKINGS
 
0.001 783351.77 0.00 789528.01 99.9
Work Order 05-18-10
Work Began 07-13-10
Work Completed  
Time Computed 06-03-10
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 220
Percent Time Used 100
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-384
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04103022
Totals 783351.77 0.00 789528.01 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 45355.30 117673.70 12.9
Work Order 02-10-11
Work Began 00-00-00
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 5
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 45355.30 117673.70 12.9

CountyHARRIS
Highway VA
From VAR LOCATIONS OUTSIDE HARRIS COUNTY
To .
CSJ 0912-00-386
Proj ID STP 2011(715)G
Work Type PAVEMENT MARKINGS
 
0.001 2213307.80 106850.71 1617842.05 73.0
Work Order 01-06-11
Work Began 03-22-11
Work Completed  
Time Computed 01-22-11
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 85
Contractor(s)
BATTERSON,LLP
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-386
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103203
Totals 2213307.80 106850.71 1617842.05 73.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-397
Proj ID STP 2009(706)ES
Work Type ITS IMPLEMENTATION
 
0.001 4068749.00 14750.00 1988899.10 48.8
Work Order 05-13-10
Work Began 00-00-00
Work Completed  
Time Computed 05-29-10
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 38
Contractor(s)
REPUBLIC INTELLIGENT TRANSPORTATION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-397
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03103006
Totals 4068749.00 14750.00 1988899.10 48.8

CountyHARRIS
Highway VA
From ON SH 6; IH 10
To VOSS ROAD (FORT BEND & HARRIS CO.)
CSJ 0912-00-399
Proj ID NH 1102(307)
Work Type ACCESS MGT IMPRVMTS
 
9.000 3134199.14 89980.13 470534.91 15.0
Work Order 09-30-11
Work Began 10-31-11
Work Completed  
Time Computed 10-16-11
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 27
Contractor(s)
ROZCO CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-399
BATTERSON,LLP(8.48%)
SILVA CONTRACTING COMPANY, INC.(8.00%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.72%)
MAGNUM TUNNELING, LLC(0.53%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (8.01%)
CURB PLANET INC. (4.67%)
CPAVE, INC.(0.30%)
Contract # 08113249
Totals 3134199.14 89980.13 470534.91 15.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-00-404
Proj ID STP 2012(106)
Work Type REPAIR OF BRIDGE APPROACHES
 
0.001 1680068.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-12
Work Began 00-00-00
Work Completed  
Time Computed 01-19-12
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
URETEK USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-404
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11113213
Totals 1680068.00 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-455
Proj ID NH 1102(144)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 1441141.70 11790.24 467481.92 32.4
Work Order 09-06-11
Work Began 09-22-11
Work Completed  
Time Computed 09-22-11
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-455
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07113215
Totals 1441141.70 11790.24 467481.92 32.4

CountyBRAZORIA
Highway CS
From DIXIE FARM RD FROM SH 35
To 1500 FT S OF FM 518
CSJ 0912-31-108
Proj ID STP 99(546)MM
Work Type WIDEN TO 4 LANES
 
2.173 12512243.81 -6905.02 12229153.28 98.8
CountyBRAZORIA
Highway CS
From DIXIE FARM ROAD FROM HARRIS COUNTY
To SH 35
CSJ 0912-31-144
Proj ID STP 2004(215)MM
Work Type ACQUISITION AND UTILITIES
 
3.800 124811.82 0.00 133719.32 99.9
Work Order 04-09-09
Work Began 04-25-09
Work Completed  
Time Computed 04-25-09
Contract Working Days 489
Addl Days Granted 0
Working Days Charged 574
Percent Time Used 117
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-108
HIGHWAY TECHNOLOGIES, INC. (1.54%)
NBG CONSTRUCTORS, INC. (7.22%)
SCOTT DERR PAINTING CO (0.00%)
TOM-MAC, INC.(0.66%)
REDDICO CONSTRUCTION CO., INC. (8.86%)
PROTECTIVE ENVIRONMENTAL STRATEGIES, INC.(3.50%)
GMJ PAVING CO. (5.61%)
HUBCO, INC.(1.83%)
CREACOM, INC.(3.60%)
BECO CONSTRUCTION, L.L.C.(7.05%)
FLORES CURBS (0.15%)
OATES INDUSTRIES, INC. (0.11%)
SPECIALTY DRILLING (0.17%)
GULF COAST PAVERS, INC.(1.08%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%)
JMHP, INC. (0.12%)
BIO LANDSCAPE & MAINTENANCE, INC.(1.08%)
Contract # 02093202
Totals 12637055.63 6905.02 12362872.60 98.9

CountyBRAZORIA
Highway CR
From CR 54 AT CHOC BYU WATER CO CANAL
To .
CSJ 0912-31-164
Proj ID BR 2006(322)
Work Type REPLACE BRIDGE
 
0.208 815348.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 171
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-164
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01123207
Totals 815348.60 0.00 0.00 0.0

CountyBRAZORIA
Highway CR
From CR 128 AT DRAINAGE DITCH
To .
CSJ 0912-31-169
Proj ID BR 2006(327)
Work Type REPLACE BRIDGE
 
0.179 1076463.26 0.00 800174.06 74.3
Work Order 09-23-10
Work Began 01-04-11
Work Completed  
Time Computed 10-09-10
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 77
Contractor(s)
ROZCO CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-169
HIGHWAY TECHNOLOGIES, INC. (0.75%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.82%)
REGIONAL TRAFFIC SERVICES, LLC (0.41%)
SHINN & GREGORY, INC.(5.69%)
AAA ASPHALT PAVING, INC. (9.08%)
Contract # 08103244
Totals 1076463.26 0.00 800174.06 74.3

CountyBRAZORIA
Highway CR
From CR 541 AT CHIGGER CREEK
To .
CSJ 0912-31-171
Proj ID BR 2006(329)
Work Type REPLACE BRIDGE
 
0.183 789069.67 3598.75 343916.08 43.5
Work Order 08-10-11
Work Began 09-19-11
Work Completed  
Time Computed 08-26-11
Contract Working Days 179
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 22
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-171
HIGHWAY TECHNOLOGIES, INC. (0.82%)
REGIONAL TRAFFIC SERVICES, LLC (0.55%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.64%)
W. W. FOUNDATION DRILLING, LTD.(2.28%)
Contract # 07113005
Totals 789069.67 3598.75 343916.08 43.5

CountyBRAZORIA
Highway CS
From CR 105 (ROY RD) AT HICKORY SLOUGH
To .
CSJ 0912-31-197
Proj ID BR 2007(202)
Work Type REPLACE BRIDGE
 
0.135 649949.93 105102.20 310705.19 47.8
Work Order 04-15-11
Work Began 10-10-11
Work Completed  
Time Computed 10-10-11
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 62
Contractor(s)
ROZCO CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-197
REPUBLIC TRAFFIC SAFETY, INC.(0.67%)
SPECIALTY DRILLING (5.44%)
HOUSTON SAWING & DRILLING(0.35%)
KELLYSTONE, INC(3.07%)
PREMIER CONCRETE PRODUCTS,INC. (3.90%)
RICE ENVIRONMENTAL SERVICES(4.30%)
YORK & YORK FOUNDATION DRILLING, INC.(3.74%)
W. W. FOUNDATION DRILLING, LTD.(7.43%)
Contract # 03113003
Totals 649949.93 105102.20 310705.19 47.8

CountyBRAZORIA
Highway CS
From MILLER RANCH RD AT HICKORY SLOUGH
To .
CSJ 0912-31-207
Proj ID BR 2007(205)
Work Type REPLACE BRIDGE
 
0.130 483525.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-207
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01123005
Totals 483525.75 0.00 0.00 0.0

CountyBRAZORIA
Highway VA
From VARIOUS LOCATIONS BRAZORIA COUNTY
To .
CSJ 0912-31-227
Proj ID STP 2012(022)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 114114.14 0.00 0.00 0.0
Work Order 10-13-11
Work Began 00-00-00
Work Completed  
Time Computed 10-29-11
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JERDON ENTERPRISE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-227
HEWITT ELECTRIC( 14.45%)
B & R MASONRY( 18.00%)
Contract # 09113009
Totals 114114.14 0.00 0.00 0.0

CountyBRAZORIA
Highway VA
From VARIOUS LOCATIONS BRAZORIA COUNTY
To .
CSJ 0912-31-228
Proj ID NH 2009(830)
Work Type LANDSCAPE DEVELOPMENT
 
0.003 308543.60 4000.00 321963.62 99.9
Work Order 08-10-09
Work Began 08-26-09
Work Completed  
Time Computed 08-26-09
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 80
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-228
LONE STAR TRAFFIC SERVICE, INC.(1.45%)
TALL GRASS ENVIRONMENTAL SOLUTIONS, LLC(7.89%)
Contract # 07093213
Totals 308543.60 4000.00 321963.62 99.9

CountyFORT BEND
Highway CS
From STAFFORD/STAFFORDSHIRE,HARRIS C/L
To 5TH STREET
CSJ 0912-34-126
Proj ID STP 2009(792)ES
Work Type WIDEN TO 4 LANES CURB & GUTTER
 
2.210 8870686.85 259153.75 9898104.32 99.9
CountyFORT BEND
Highway CS
From STAFFORD/STAFFORDSHIRE RD,HARRIS C/
To 5TH STREET
CSJ 0912-34-168
Proj ID CC 912-34-168
Work Type ROW UTL. ADJ. IN CST. CONTRACT
 
2.210 1557289.00 0.00 1627193.26 99.9
CountyHARRIS
Highway CS
From STAFFORD/STAFFORDSHIRE RD, BW 8
To FORT BEND COUNTY LINE
CSJ 0912-72-246
Proj ID CC 912-72-246
Work Type WIDEN TO 4 LANES CURB & GUTTER
 
0.574 2053028.90 2093.99 2086554.62 99.9
CountyHARRIS
Highway CS
From STAFFORD/STAFFORDSHIRE RD, BW 8
To FORT BEND COUNTY LINE
CSJ 0912-72-262
Proj ID CC 912-72-262
Work Type ROW UTL. ADJ. IN CST. CONTRACT
 
0.574 63887.00 6310.00 61303.00 95.9
Work Order 05-11-10
Work Began 06-07-10
Work Completed  
Time Computed 05-27-10
Contract Working Days 360
Addl Days Granted 90
Working Days Charged 446
Percent Time Used 99
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-126
JMHP, INC. (0.03%)
CURB PLANET INC. (0.23%)
EROSION CONTROL, INC.(0.83%)
HIGHWAY TECHNOLOGIES, INC. (0.27%)
BATTERSON, L.L.P.(1.05%)
THIRD COAST SERVICES, LLC(2.08%)
L.A. UTILITIES, INC. ( 40.41%)
ASPLUNDH COMPANY (0.05%)
BORTUNCO (0.29%)
DORAN STEEL, INC.(0.52%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.97%)
CLEARWATER UTILITIES, INC. (4.54%)
R & A BORING COMPANY (0.02%)
HUNTER WELLPOINT, INC. (0.04%)
SIREN STEEL, INC.(0.36%)
Contract # 03103003
Totals 12544891.75 267557.74 13673155.20 99.9

CountyFORT BEND
Highway VA
From VARIOUS LOCATIONS ON US 59
To .
CSJ 0912-34-148
Proj ID STP 2010(059)ESTE
Work Type LANDSCAPE DEVELOPMENT
 
0.001 232761.67 3437.17 219106.84 94.1
Work Order 11-16-09
Work Began 12-18-09
Work Completed  
Time Computed 12-02-09
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 93
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-148
R & A DIRECTIONAL BORING (2.14%)
XELLENT SERVICES (4.19%)
Contract # 09093020
Totals 232761.67 3437.17 219106.84 94.1

CountyFORT BEND
Highway VA
From VARIOUS LOCATIONS IN MISSOURI CITY
To .
CSJ 0912-34-150
Proj ID STP 2010(303)ES
Work Type ITS
 
0.001 2778094.72 0.00 2401246.00 86.4
Work Order 04-30-10
Work Began 07-01-10
Work Completed  
Time Computed 05-16-10
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 91
Contractor(s)
TRANSCORE ITS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-150
BATTERSON, L.L.P.(0.29%)
APMS TELECOM, LLC(9.71%)
KAM CONSTRUCTION, INC. ( 11.25%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.07%)
ADEPT GENERAL CONSTRUCTION, INC. (7.88%)
Contract # 03103210
Totals 2778094.72 0.00 2401246.00 86.4

CountyMONTGOMERY
Highway VA
From IH 45, HARRIS/MONTGOMERY C/L
To LOOP 336 SOUTH
CSJ 0912-37-201
Proj ID HP 2009(333)
Work Type LANDSCAPE DEVELOPMENT
 
11.862 738493.25 35644.96 678868.99 91.9
Work Order 03-20-09
Work Began 04-10-09
Work Completed  
Time Computed 04-05-09
Contract Working Days 780
Addl Days Granted 0
Working Days Charged 698
Percent Time Used 89
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-201
XELLENT SERVICES (5.30%)
Contract # 01093221
Totals 738493.25 35644.96 678868.99 91.9

CountyHARRIS
Highway CS
From FARTHER POINT AT BUFFALO BAYOU
To .
CSJ 0912-70-002
Proj ID BR 2007(834)
Work Type REPLACE BRIDGE
 
0.097 1509342.80 17138.74 1517048.52 99.9
Work Order 10-07-10
Work Began 04-04-11
Work Completed  
Time Computed 10-23-10
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 97
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-002
BATTERSON,LLP(0.28%)
DORAN STEEL, INC.(0.87%)
ODUM SERVICES, L.P.(2.91%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.60%)
W. W. FOUNDATION DRILLING, LTD.(9.83%)
SOUTH TEXAS PAINTING COMPANY (0.09%)
GEO-GLEN ENTERPRISES, INC. (0.53%)
MESA ROD BUSTERS, INC. (0.43%)
CURB PLANET INC. (0.06%)
Contract # 08103243
Totals 1509342.80 17138.74 1517048.52 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8
 
spacer spacer
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts