Monthly State Let Construction Report For Houston District As Of Aug 16, 2016 Page 7 Of 10

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway CR
From CR 48, BROADWAY (FM 518)
To CR 894
CSJ 0912-31-294
Proj ID STP 2015(612)MM
Work Type WIDEN FROM 2 TO 4 - LANE DIVIDED
 
1.944 12154201.39 350920.87 9175353.83 75.4
Work Order 04-10-15
Work Began 06-09-15
Work Completed  
Time Computed 06-09-15
Contract Working Days 357
Addl Days Granted 3
Working Days Charged 241
Percent Time Used 66
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-294
CPAVE, INC.(0.04%)
GEORGE MEEKS LANDPRO, INC. (0.89%)
GMJ PAVING CO. (3.06%)
MESA ROD BUSTERS, INC. (6.36%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41%)
SCOTT DERR PAINTING CO (0.04%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49%)
TEXAS CLEARING AND LEVELING(0.40%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.58%)
W. W. FOUNDATION DRILLING, LTD.(3.10%)
MBN ENTERPRISES LLC(2.49%)
WEBBER BARRIER SERVICES, LLC.(0.22%)
DNA TRUCKING, INC. (0.20%)
CURB PLANET INC. (0.03%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
SOUTHERN CRUSHED CONCRETE LLC(1.11%)
Contract # 02153002
Totals 12154201.39 350920.87 9175353.83 75.4

CountyBRAZORIA
Highway VA
From LOCATIONS IN LAKE JACKSON
To .
CSJ 0912-31-301
Proj ID STP 1602(077)
Work Type LANDSCAPE DEVELOPMENT
 
0.300 920524.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-301
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163041
Totals 920524.00 0.00 0.00 0.0

CountyFORT BEND
Highway CS
From TRAMMEL FRESNO RD, FORT BEND PKWY
To FM 521
CSJ 0912-34-144
Proj ID STP 2010(596)MM
Work Type GR, STR, BASE AND 0AVE
 
3.041 20864455.45 0.00 4788026.65 22.9
Work Order 03-03-15
Work Began 03-24-15
Work Completed  
Time Computed 03-19-15
Contract Working Days 622
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 4
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC.(0.72%)
RICE ENVIRONMENTAL SERVICES(0.24%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(1.96%)
INDUS CONSTRUCTION, L.P. (3.85%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.17%)
BASE CONSTRUCTION, L.L.P.( 23.02%)
KMA CONTRACTORS SERVICES INC.(4.77%)
Contract # 12143003
Totals 20864455.45 0.00 4788026.65 22.9

CountyFORT BEND
Highway CR ETC
From MEYER ROAD AT SNAKE CREEK TRIBUTARY
To .
CSJ 0912-34-176
Proj ID BR 2013(735)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.712 2828589.45 168129.20 2251399.67 79.5
Work Order 08-04-15
Work Began 09-08-15
Work Completed  
Time Computed 09-08-15
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 209
Percent Time Used 65
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55%)
REGIONAL TRAFFIC SERVICES LLC(0.40%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45%)
ODUM SERVICES, L.P.(1.77%)
MESA ROD BUSTERS, INC. (0.19%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.98%)
EROSION PREVENTION PRODUCTS(4.81%)
GARNER PAVING & CONSTRUCTION, LTD. (0.15%)
Contract # 06153027
Totals 2828589.45 168129.20 2251399.67 79.5

CountyFORT BEND
Highway CS
From ON HURRICANE LANE/LAKE OLYMPIA;FROM
To TRAMMEL FRESNO RD TO FT BEND PKWY
CSJ 0912-34-182
Proj ID STP 1302(010)MM
Work Type CONST 2 LN CONC RDWYS
 
1.393 6588849.40 1603299.75 2022702.77 30.6
Work Order 05-11-16
Work Began 06-06-16
Work Completed  
Time Computed 06-06-16
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 14
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-182
PRV SERVICES, INC. (7.89%)
SPRINT SAND AND CLAY, LLC(0.00%)
Contract # 01163030
Totals 6588849.40 1603299.75 2022702.77 30.6

CountyFORT BEND
Highway VA
From VARIOUS LOCATIONS ALONG: US 59,
To SH 6, AND US 90A
CSJ 0912-34-187
Proj ID C 912-34-187
Work Type INSTALLATION OF DMS
 
0.001 992940.68 0.00 9080.00 0.9
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 05-07-16
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163213
Totals 992940.68 0.00 9080.00 0.9

CountyMONTGOMERY
Highway CR
From KUYKENDAHL RD; ALDEN BRIDGE
To CROWNRIDGE DR
CSJ 0912-37-140
Proj ID STP 2002(643)UM
Work Type CONST 2 LANE RDWY
 
0.485 2496548.44 0.00 2501785.32 99.9
Work Order 06-30-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 78
Addl Days Granted 44
Working Days Charged 179
Percent Time Used 146
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-140
ABC EROSION CONTROL, INC.(0.66%)
LANDSCAPING CONTRACTING & IRRIGATION (1.93%)
STRIPE-A-LINE, INC.(0.21%)
THIRD COAST SERVICES LLC ( 10.75%)
W. W. FOUNDATION DRILLING, LTD.(4.79%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(1.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%)
BREDA COMPANY, INC.(0.70%)
MESA ROD BUSTERS, INC. (0.18%)
HOUSTON SAWING & DRILLING(0.07%)
WILLOW CITY SIGN & RAIL, INC.(0.82%)
APCON SERVICES, LLC(0.73%)
SAND HILL FOUNDATION, LLC(1.21%)
ABC DIRECTIONAL DRILLING, INC. (1.45%)
CPAVE, INC.(0.25%)
COASTAL FOUNDATION DRILLING CO., INC.(0.00%)
TNT CRANE & RIGGING, INC.(0.00%)
Contract # 05143027
Totals 2496548.44 0.00 2501785.32 99.9

CountyMONTGOMERY
Highway VA
From VARIOUS LOCATIONS ON IH 45 & SH 105
To .
CSJ 0912-37-226
Proj ID STP 2016(472)
Work Type BASE REPAIR AND PAVEMENT LEVELING
 
0.053 766066.00 20000.00 26500.00 3.4
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 05-30-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 10
Contractor(s)
NORTEX CONCRETE LIFT & STABILIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-226
ROAD SAFE(5.69%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 21.98%)
Contract # 01163211
Totals 766066.00 20000.00 26500.00 3.4

CountyHARRIS
Highway CS
From AT ALICE JOHNSON JR HIGH SCHOOL
To .
CSJ 0912-70-067
Proj ID STP 1602(474)SRS
Work Type PEDESTRIAN WAY / SIDEWALKS
 
0.320 582538.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163029
Totals 582538.50 0.00 0.00 0.0

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 0.00 406205.26 91.0
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 60
Addl Days Granted 25
Working Days Charged 167
Percent Time Used 196
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP( 14.72%)
LANDPRO, INC.(4.34%)
TITAN 360 INDUSTRIAL SERVICES(8.99%)
Contract # 07143054
Totals 499113.96 0.00 406205.26 91.0

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 0.00 2026823.50 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 216
Percent Time Used 103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
BIO LANDSCAPE & MAINTENANCE, INC.( 65.42%)
HOGGATT, LP(5.46%)
EVERY SECOND COUNTS (ESC)(5.69%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48%)
MIKELS CONSTRUCTION CO., INC.(2.51%)
PUMPS, MOTORS & CONTROLS (0.04%)
STRIPE LINES, INC. (0.15%)
Contract # 06133013
Totals 2581444.90 0.00 2026823.50 78.7

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 4715.10 759373.16 93.7
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 91
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 4715.10 759373.16 93.7

CountyHARRIS
Highway CS
From WESTERLAND DRIVE; AT HCFCD DITCH
To .
CSJ 0912-70-091
Proj ID BR 2014(555)
Work Type REPL BR & APPR
 
0.163 1844818.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-05-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163016
Totals 1844818.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN CENTRAL
To HOUSTON AREA
CSJ 0912-70-094
Proj ID STP 2015(317)
Work Type BRIDGE MAINTENANCE WORK
 
0.001 1698653.40 632757.29 3022908.49 99.9
Work Order 01-02-15
Work Began 04-25-15
Work Completed  
Time Computed 04-25-15
Contract Working Days 304
Addl Days Granted 16
Working Days Charged 289
Percent Time Used 90
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
IOWA BRIDGE & CULVERT, LC( 21.67%)
JTB SERVICES (2.42%)
THIRD COAST SERVICES LLC (2.83%)
TX TINMAN ENTERPRISES, LLC.(5.80%)
AARON CONCRETE CONTRACTORS, L.P. (1.59%)
HOUSTON SAWING & DRILLING(1.05%)
HOLES INCORPORATED (1.58%)
Contract # 11143212
Totals 1698653.40 632757.29 3022908.49 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 0.00 2122734.77 79.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-02-14
Work Began 10-27-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 343
Percent Time Used 140
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE ( 12.07%)
THIRD COAST SERVICES LLC (9.66%)
STRIPE-A-LINE, INC.(2.31%)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44%)
GLOBE ELECTRIC SUPPLY COMPANY, INC.(2.65%)
GEORGE MEEKS LANDPRO, INC. (3.02%)
TEXAS CONCRETE AND DEMOLITION, INC.(8.51%)
Contract # 05143031
Totals 2767522.72 0.00 2122734.77 79.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-100
Proj ID STP 2015(613)
Work Type CONST CURB RAMPS
 
0.001 3140223.08 95897.80 2451948.53 78.6
Work Order 03-23-15
Work Began 03-07-16
Work Completed  
Time Computed 04-08-15
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-100
BATTERSON,LLP(4.08%)
A-1 EROSION CONTROL, LLC (0.84%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.75%)
STRIPE-A-LINE, INC.(0.00%)
Contract # 02153020
Totals 3140223.08 95897.80 2451948.53 78.6

CountyHARRIS
Highway CS
From MASON PARK PED/BIKE BRG, FROM TIPPS
To ST AT EVERGREEN DR TO 75TH ST
CSJ 0912-70-103
Proj ID STP 2015(559)TE
Work Type CONST PED & BIKE BR
 
0.180 5659268.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163221
Totals 5659268.00 0.00 0.00 0.0

CountyHARRIS
Highway CR
From BRAYS BAYOU, FROM MACGREGOR PARK
To UNIVERISTY OF HOUSTON (WHEELER AVE)
CSJ 0912-70-104
Proj ID STP 2016(352)TE
Work Type CONST BIKE / PED BR
 
0.480 2330231.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163055
Totals 2330231.54 0.00 0.00 0.0

CountyHARRIS
Highway CR
From IH 69 S, FROM HAZARD STREET
To MONTROSE BLVD
CSJ 0912-70-105
Proj ID STP 2014(128)TE
Work Type INST BR LIGHT
 
0.250 3061039.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163247
Totals 3061039.35 0.00 0.00 0.0

CountyHARRIS
Highway CS
From CAROLINE STREET;ELGIN STREET
To PIERCE STREET
CSJ 0912-71-003
Proj ID C 912-71-3
Work Type GR, STRS, BASE
 
0.689 11852823.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163207
Totals 11852823.92 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10