Monthly State Let Construction Report For Houston District As Of Apr 11, 2014 Page 7 Of 9

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway CS
From SOUTH JENSEN DR AT BUFFALO BAYOU
To .
CSJ 0912-72-050
Proj ID BR 2006(741)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.129 1384264.10 31975.00 1447929.89 99.9
Work Order 10-18-12
Work Began 02-25-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 84
Addl Days Granted 68
Working Days Charged 152
Percent Time Used 100
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-050
S & S BRIDGE PAINTING, INC.( 55.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.16%)
ISI CONTRACTING, INC.(5.32%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.71%)
Contract # 09123217
Totals 1384264.10 31975.00 1447929.89 99.9

CountyHARRIS
Highway CR
From HOUSE-HAHL RD AT BIG CYPRESS CREEK
To .
CSJ 0912-72-061
Proj ID BR 2006(446)
Work Type REPLACE BRIDGE
 
0.123 736542.36 8708.04 79309.16 10.7
Work Order 09-23-13
Work Began 00-00-00
Work Completed  
Time Computed 11-22-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133228
Totals 736542.36 8708.04 79309.16 10.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-72-084
Proj ID CM 2008(894)
Work Type TRAFFIC SIGNAL INTERCONNECT
 
0.002 1924706.58 0.00 2479190.67 99.9
Work Order 09-23-10
Work Began 10-14-10
Work Completed  
Time Computed 10-09-10
Contract Working Days 312
Addl Days Granted 190
Working Days Charged 481
Percent Time Used 95
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-084
THE L.E. MYERS CO. (7.02%)
B&M TELECOM, INC.(5.66%)
Contract # 08103011
Totals 1924706.58 0.00 2479190.67 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-72-088
Proj ID CM 2008(054)
Work Type TRAFFIC SIGNAL
 
0.001 1462321.41 0.00 3060112.21 99.9
Work Order 09-25-07
Work Began 12-07-07
Work Completed  
Time Computed 11-24-07
Contract Working Days 388
Addl Days Granted 0
Working Days Charged 377
Percent Time Used 97
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-088
HIGHWAY TECHNOLOGIES, INC. (6.50%)
TEAM WORK CONSTRUCTION SERVICES( 14.35%)
Contract # 08073044
Totals 1462321.41 0.00 3060112.21 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-72-089
Proj ID CM 2011(101)
Work Type TRAFFIC SIGNAL INTERCONNECT
 
0.002 4497940.86 2877.12 4761583.66 99.9
Work Order 09-23-10
Work Began 03-08-11
Work Completed  
Time Computed 10-09-10
Contract Working Days 468
Addl Days Granted 259
Working Days Charged 716
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-089
L.E. MYERS CO. (2.24%)
B&M TELECOM, INC.(7.15%)
FORDE CONSTRUCTION COMPANY, INC. (1.97%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.00%)
Contract # 08103208
Totals 4497940.86 2877.12 4761583.66 99.9

CountyHARRIS
Highway VA
From MIDTOWN/DOWNTOWN HOUSTON
To .
CSJ 0912-72-141
Proj ID CM 1102(006)
Work Type CBD COMMUNICATIONS SYSTEM
 
0.001 1453930.00 52826.37 1306091.75 89.8
Work Order 10-18-11
Work Began 07-16-12
Work Completed  
Time Computed 11-03-11
Contract Working Days 186
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 76
Contractor(s)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-141
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07113213
Totals 1453930.00 52826.37 1306091.75 89.8

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To PRECINCT 4
CSJ 0912-72-199
Proj ID CM 2013(989)
Work Type HARRIS COUNTY PRECINCT 4 RCTSS
 
0.001 2561452.60 45093.00 45093.00 1.7
Work Order 11-22-13
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 2
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-199
VERSALINK MEDIA(6.77%)
Contract # 08133042
Totals 2561452.60 45093.00 45093.00 1.7

CountyHARRIS
Highway CS
From ALDINE WESTFIELD AT HCFCD DITCH
To .
CSJ 0912-72-229
Proj ID BR 1102(481)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.069 600781.75 100663.42 558844.70 93.2
Work Order 09-04-13
Work Began 11-18-13
Work Completed  
Time Computed 11-03-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 102
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-229
ROADSAFE TRAFFIC SYSTEMS, INC. (1.02%)
Contract # 07133017
Totals 600781.75 100663.42 558844.70 93.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HOUSTON
To .
CSJ 0912-72-241
Proj ID STP 2013(694)
Work Type SLOPE REP & CHANNEL STABILIZATION
 
0.001 1883747.00 88238.00 1484865.51 78.8
Work Order 06-28-13
Work Began 07-25-13
Work Completed  
Time Computed 07-25-13
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 87
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-241
ENVIRONMENTAL SAFETY SERVICES, INC.(4.58%)
KOSSMAN CONTRACTING CO., INC.(0.87%)
FOSTER FENCE, LTD. (1.54%)
TOM-MAC, INC.(8.26%)
Contract # 05133219
Totals 1883747.00 88238.00 1484865.51 78.8

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To US 59,US 90A,IH 610,SH 225 ETCETERA
CSJ 0912-72-287
Proj ID STP 2012(515)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2475888.05 8160.00 2033029.52 83.2
Work Order 07-25-12
Work Began 10-18-12
Work Completed  
Time Computed 08-10-12
Contract Working Days 225
Addl Days Granted 48
Working Days Charged 310
Percent Time Used 113
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-287
THIRD COAST SERVICES LLC ( 10.39%)
PROFESSIONAL TRAFFIC CONTROL, LLC(5.01%)
AQUALAWN HYDROMULCH & EROSION CONTROL(1.27%)
Contract # 05123225
Totals 2475888.05 8160.00 2033029.52 83.2

CountyHARRIS
Highway VA
From AT VARIOUS LOCATIONS ALONG IH 45
To AT SH 288 IN HARRIS COUNTY
CSJ 0912-72-288
Proj ID STP 2013(460)
Work Type CONSTRUCT CURB RAMPS
 
0.001 1189354.45 239234.65 899016.30 75.5
Work Order 06-03-13
Work Began 08-12-13
Work Completed  
Time Computed 06-19-13
Contract Working Days 195
Addl Days Granted 0
Working Days Charged 179
Percent Time Used 91
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-288
PROFESSIONAL TRAFFIC CONTROL, LLC(4.72%)
THIRD COAST SERVICES LLC (5.32%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.27%)
Contract # 03133217
Totals 1189354.45 239234.65 899016.30 75.5

CountyHARRIS
Highway CS
From ON HEMPSTEAD, FROM WEST OF MANGUM
To BRITTMOORE RD
CSJ 0912-72-293
Proj ID C 912-72-293
Work Type BS REP, PLANING, 2" O / L & PV_MRKS
 
8.394 3559738.01 15833.00 3836177.10 99.9
Work Order 04-17-13
Work Began 08-13-13
Work Completed  
Time Computed 06-17-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 82
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-293
INTERSTATE BARRICADES & MARKINGS, INC. (5.51%)
ISI CONTRACTING, INC.(2.43%)
Contract # 02133005
Totals 3559738.01 15833.00 3836177.10 99.9

CountyGALVESTON
Highway CS
From SEAWOLF PKWY AT PELICAN ISLAND CHNL
To .
CSJ 0912-73-117
Proj ID BR 2007(366)
Work Type REHABILITATE BRIDGE
 
0.612 3439504.50 356115.35 6124015.63 99.9
Work Order 05-18-11
Work Began 08-03-11
Work Completed  
Time Computed 06-03-11
Contract Working Days 301
Addl Days Granted 396
Working Days Charged 437
Percent Time Used 62
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-117
ORION CONSTRUCTION, L.P. (6.38%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
INTECH CONTRACTING LLC ( 74.13%)
BRIDGES R US PAINTING CO., INC.( 36.05%)
TIME MARINE, INC.(130.15%)
GENERAL METAL FABRICATING, INC.( 38.58%)
Contract # 04113207
Totals 3439504.50 356115.35 6124015.63 99.9

CountyGALVESTON
Highway CR
From MCFARLAND ROAD AT DICKINSON BAYOU
To .
CSJ 0912-73-120
Proj ID BR 2008(624)
Work Type REPLACE BRIDGE
 
0.076 550633.62 22720.00 446484.55 81.0
Work Order 10-24-13
Work Began 12-09-13
Work Completed  
Time Computed 12-09-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 69
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-120
CENTERLINE TRAFFIC SAFETY, LLC (1.26%)
REGIONAL TRAFFIC SERVICES LLC(0.37%)
JMHP, INC. (7.62%)
Contract # 08133034
Totals 550633.62 22720.00 446484.55 81.0

CountyGALVESTON
Highway VA
From VARIOUS LOCATIONS
To IN GALVESTON COUNTY
CSJ 0912-73-180
Proj ID STP 1102(311)
Work Type CONSTRUCT CURB RAMPS
 
3.842 3284825.97 0.00 2590236.73 81.4
Work Order 10-21-11
Work Began 11-06-11
Work Completed  
Time Computed 11-06-11
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 361
Percent Time Used 142
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-180
THIRD COAST SERVICES, LLC( 11.29%)
WORK ZONE PRODUCTS, INC. (5.46%)
KOSSMAN CONTRACTING COMPANY(1.91%)
SUPERIOR LIGHTING(0.43%)
Contract # 08113036
Totals 3284825.97 0.00 2590236.73 81.4

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-189
Proj ID FT 912-73-189
Work Type REHAB BILGE WATER TREATMENT SYSTEMS
 
0.001 629425.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 00-00-00
Work Completed  
Time Computed 04-18-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-189
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143202
Totals 629425.00 0.00 0.00 0.0

CountyGALVESTON
Highway VA
From AT GALVESTON FERRY OFFICE
To .
CSJ 0912-73-190
Proj ID C 912-73-190
Work Type RENOVATION OF SHOP RESTROOMS
 
0.001 357800.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.C. LEWIS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-190
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143232
Totals 357800.00 0.00 0.00 0.0

CountyGALVESTON
Highway VA
From AT THE GALVESTON FERRY LANDING
To .
CSJ 0912-73-193
Proj ID FT 912-73-193
Work Type CONSTRUCT NEW BOAT LIFT
 
0.001 305695.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-193
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143230
Totals 305695.00 0.00 0.00 0.0

CountyGALVESTON
Highway VA
From AT GALV AND BOLIVAR FERRY LANDING
To .
CSJ 0912-73-194
Proj ID C 912-73-194
Work Type CONSTRUCT NEW SCREENING CANOPIES
 
0.001 731490.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-194
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143231
Totals 731490.00 0.00 0.00 0.0

CountyHARRIS
Highway FM 865
From ALMEDA-GENOA
To BW 8
CSJ 0976-01-019
Proj ID C 976-1-19
Work Type GR, BS & SURF
 
1.272 13285921.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 305
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133025
Totals 13285921.44 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9