| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HARRIS |
| Highway |
FM 1960 |
| From |
AT KUYKENDAHL |
| To |
. |
| CSJ |
1685-01-082 |
| Proj ID |
STP 2007(048)MM |
| Work Type |
GRADE SEPARATION |
| |
|
0.334 |
18497065.46 |
333308.68 |
15319974.93 |
80.3 |
| Work Order |
01-08-07 |
| Work Began |
02-26-07 |
| Work Completed |
|
| Time Computed |
01-24-07 |
| Contract Working Days |
564 |
| Addl Days Granted |
0 |
| Working Days Charged |
459 |
| Percent Time Used |
81 |
| Contractor(s) |
HASSELL CONSTRUCTION COMPANY, INC. NBG CONSTRUCTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1685-01-082 GMJ PAVING CO. (3.97%) TRAF-TEX, INC. (2.08%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(1.05%) R & B GROUP, INC.(4.21%) BORING & TUNNELING COMPANY OF AMERICA, INC.(0.86%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.15%) A. H. BECK FOUNDATION CO., INC.(8.55%) HOUSTON SAWING & DRILLING(0.02%) SCOTT DERR PAINTING CO (0.11%) CHAMPIONS HYDROLAWN(0.05%) BECO CONSTRUCTION COMPANY(0.05%) MESA ROD BUSTERS, INC. (0.74%) CHERRY CONCRETE REMOVAL(0.25%) FLORES CURBS (0.04%) BECO CONSTRUCTION COMPANY(0.02%)
|
| Contract # |
10063203 |
|
Totals |
18497065.46 |
333308.68 |
15319974.93 |
80.3 |
|
| County | WALLER |
| Highway |
FM 1736 |
| From |
1076' SOUTH OF HENSON ROAD |
| To |
SH 6 |
| CSJ |
1687-01-014 |
| Proj ID |
C 1687-1-14 |
| Work Type |
BS & SL CT REP |
| |
|
5.056 |
428913.02 |
0.00 |
0.00 |
0.0 |
| Work Order |
11-14-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-30-08 |
| Contract Working Days |
15 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1687-01-014 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083218 |
|
Totals |
428913.02 |
0.00 |
0.00 |
0.0 |
|
| County | FORT BEND |
| Highway |
FM 2234 ETC |
| From |
FM 3345 |
| To |
FM 521 |
| CSJ |
2105-01-043 |
| Proj ID |
STP 2007(623) |
| Work Type |
BS REP & O / L |
| |
|
19.279 |
3381847.58 |
0.00 |
3101678.60 |
92.4 |
| Work Order |
01-03-08 |
| Work Began |
03-04-08 |
| Work Completed |
|
| Time Computed |
01-19-08 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
135 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-043 A TEX-DBE, INC.( 11.36%) INTERSTATE BARRICADES & MARKINGS, INC. (7.91%) TRAF-TEX, INC. (1.07%) SURFACE PREPARATION TECHNOLOGIES, INC. (0.35%) FORDE CONSTRUCTION COMPANY, INC. (1.61%)
|
| Contract # |
12073215 |
|
Totals |
3381847.58 |
0.00 |
3101678.60 |
92.4 |
|
| County | MONTGOMERY |
| Highway |
FM 2978 |
| From |
AT TAMINA ROAD |
| To |
. |
| CSJ |
3050-02-019 |
| Proj ID |
CM 2008(749) |
| Work Type |
ADD LEFT TURN LANE |
| |
|
0.456 |
277188.73 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-03-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
12-19-08 |
| Contract Working Days |
26 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3050-02-019 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083014 |
|
Totals |
277188.73 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
BW 8 |
| From |
S OF BISSONNET |
| To |
N OF BEECHNUT |
| CSJ |
3256-01-083 |
| Proj ID |
NH 2006(073) |
| Work Type |
GR, BS, CRCP & PAV MRKS |
| |
|
1.727 |
4949227.49 |
0.00 |
5407665.58 |
99.9 |
| Work Order |
11-06-06 |
| Work Began |
12-04-06 |
| Work Completed |
|
| Time Computed |
12-04-06 |
| Contract Working Days |
194 |
| Addl Days Granted |
0 |
| Working Days Charged |
206 |
| Percent Time Used |
106 |
| Contractor(s) |
| SOUTH COAST CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-01-083 PEREZ CONSTRUCTION CO. (0.01%) SEAMARCK LANDSCAPE SERVICES, INC (0.53%) MAGNUM TUNNELING, LLC(0.02%) CPAV SPECIALTIES, LP (1.71%) SPECIALTY DRILLING (2.48%) NORTHWEST MATERIALS(0.13%) WORK ZONE PRODUCTS, INC. (1.00%) FLORIDA TRAFFIC CONTROL DEVICES, INC.(0.18%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(2.33%) W.W. WEBBER, LLC (5.96%) MAIN LANE INDUSTRIES, LTD. (0.89%) JMHP, INC. (4.93%) CHERRY CONCRETE REMOVAL(1.38%) SCOTT DERR PAINTING CO (0.69%) DORAN STEEL, INC.(1.50%)
|
| Contract # |
09063208 |
|
Totals |
4949227.49 |
0.00 |
5407665.58 |
99.9 |
|
| County | HARRIS |
| Highway |
BW 8 |
| From |
0.50 MI W. OF US 59 |
| To |
0.75 MI E. OF US 59 |
| CSJ |
3256-02-078 |
| Proj ID |
HP 2007(600) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
3.286 |
617148.12 |
26423.29 |
565641.74 |
91.6 |
| Work Order |
07-09-07 |
| Work Began |
08-06-07 |
| Work Completed |
|
| Time Computed |
07-25-07 |
| Contract Working Days |
75 |
| Addl Days Granted |
0 |
| Working Days Charged |
64 |
| Percent Time Used |
85 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-078 MIKELS CONSTRUCTION CO., INC.(1.86%) SUSTAINABLE GROWTH TEXAS (7.24%) INTERSTATE BARRICADES & MARKINGS, INC. (0.73%)
|
| Contract # |
06073014 |
|
Totals |
617148.12 |
26423.29 |
565641.74 |
91.6 |
|
| County | HARRIS |
| Highway |
BW 8 |
| From |
IH 45 N |
| To |
W OF UPRR |
| CSJ |
3256-02-079 |
| Proj ID |
CM 2007(830) |
| Work Type |
INSTALL CTMS |
| |
|
37.627 |
20754799.00 |
967768.36 |
4900647.36 |
23.6 |
| Work Order |
12-05-07 |
| Work Began |
07-07-08 |
| Work Completed |
|
| Time Computed |
06-02-08 |
| Contract Working Days |
780 |
| Addl Days Granted |
0 |
| Working Days Charged |
131 |
| Percent Time Used |
16 |
| Contractor(s) |
| EAS CONTRACTING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 3256-02-079 WILLOW CITY SIGN & RAIL, INC.(0.40%) INTERSTATE BARRICADES & MARKINGS, INC. (0.15%)
|
| Contract # |
08073008 |
|
Totals |
20754799.00 |
967768.36 |
4900647.36 |
23.6 |
|
| County | WALLER |
| Highway |
FM 3318 |
| From |
FM 1458 |
| To |
END OF MAINTENANCE |
| CSJ |
3506-02-005 |
| Proj ID |
C 3506-2-5 |
| Work Type |
REP BS & SL CT |
| |
|
2.242 |
218649.62 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-18-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
12-04-08 |
| Contract Working Days |
14 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3506-02-005 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083219 |
|
Totals |
218649.62 |
0.00 |
0.00 |
0.0 |
|
| County | FORT BEND |
| Highway |
SH 99 |
| From |
AT US 90A |
| To |
. |
| CSJ |
3510-04-029 |
| Proj ID |
CM 2008(750) |
| Work Type |
ADD 5 TURN LANES |
| |
|
0.670 |
698662.09 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-029 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083010 |
|
Totals |
698662.09 |
0.00 |
0.00 |
0.0 |
|
| County | FORT BEND |
| Highway |
SH 99 |
| From |
BELLAIRE BLVD |
| To |
FM 1093 (SEGMENT D) |
| CSJ |
3510-04-030 |
| Proj ID |
CC 3510-4-30 |
| Work Type |
GR, STRS, BASE AND PAVE |
| |
|
0.694 |
2246392.68 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-030 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12083010 |
|
Totals |
2246392.68 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
SH 99 |
| From |
N OF KATY-FORT BEND ROAD |
| To |
S OF IH 10 |
| CSJ |
3510-05-013 |
| Proj ID |
C 3510-5-13 |
| Work Type |
LANDSCAPING |
| |
|
0.001 |
358343.52 |
7849.39 |
337810.63 |
98.1 |
| Work Order |
08-08-06 |
| Work Began |
08-22-06 |
| Work Completed |
|
| Time Computed |
08-24-06 |
| Contract Working Days |
122 |
| Addl Days Granted |
0 |
| Working Days Charged |
39 |
| Percent Time Used |
31 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 3510-05-013 LONE STAR TRAFFIC SERVICE, INC.(0.76%) MIKELS CONSTRUCTION CO., INC.(0.97%)
|
| Contract # |
07063019 |
|
Totals |
358343.52 |
7849.39 |
337810.63 |
98.1 |
|
| County | HARRIS |
| Highway |
MH |
| From |
IN HOUSTON ON LITTLE YORK RD FROM E |
| To |
HARDY RD TO US 59 |
| CSJ |
8004-12-003 |
| Proj ID |
C 8004-12-3 |
| Work Type |
GR, STRS & SURF |
| |
|
1.920 |
13759609.15 |
322375.24 |
10638748.37 |
81.3 |
| County | HARRIS |
| Highway |
MH |
| From |
IN HOUSTON ON LITTLE YORK RD FROM E |
| To |
HARDY RD TO US 59 |
| CSJ |
8004-12-005 |
| Proj ID |
CC 8004-12-5 |
| Work Type |
UTILITY ADJUSTMENTS |
| |
|
2.000 |
2196138.00 |
7980.00 |
1947550.52 |
93.3 |
| Work Order |
11-02-06 |
| Work Began |
11-27-06 |
| Work Completed |
|
| Time Computed |
11-18-06 |
| Contract Working Days |
337 |
| Addl Days Granted |
0 |
| Working Days Charged |
280 |
| Percent Time Used |
83 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 8004-12-003 WILLOW CITY SIGN & RAIL, INC.(0.25%) WEBBER-BALKE FOUNDATION COMPANY, INC.(0.20%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(0.99%) GMJ PAVING CO. (1.23%) EROSION CONTROL, INC.(0.65%) CREACOM, INC.(6.73%) RODS SURVEYING, INC. (0.15%) KAISER BROTHERS, INC.(0.29%) MICKIE SERVICE, INC. (0.12%) TWO WAY BARRICADE EQUIPMENT, INC.(0.03%) PRIMATE CONSTRUCTION, INC. (0.01%)
|
| Contract # |
07063207 |
|
Totals |
15955747.15 |
330355.24 |
12586298.89 |
83.0 |
|