Monthly State Let Construction Report For Houston District As Of Apr 10, 2017 Page 7 Of 10

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayVA
FromFANNIN & MN ST ESPLANADES CAMBRIDGE
ToMECOM FOUNTAIN
CSJ0912-70-078
Proj IDSTP 2011(255)TE
Work TypeENHANCEMENT PROJECT
 
0.8072581444.902026823.5078.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-13
Work Began10-21-13
Work Completed
Time Computed10-12-13
Contract Working Days176
Addl Days Granted32
Working Days Charged216
Percent Time Used103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88)
DOWN UNDER CONSTRUCTION (1.83)
SPECIALTY DRILLING (0.02)
BUILDER SERVICES CO. (1.50)
LEXTEX, INC. (7.15)
BIO LANDSCAPE & MAINTENANCE, INC. (65.42)
HOGGATT, LP (5.46)
EVERY SECOND COUNTS (ESC) (5.69)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48)
MIKELS CONSTRUCTION CO., INC. (2.51)
PUMPS, MOTORS & CONTROLS (0.04)
STRIPE LINES, INC. (0.15)
Contract #06133013
Totals2581444.900.002026823.5078.7

CountyHARRIS
HighwayCS
FromWESTERLAND DRIVE; AT HCFCD DITCH
To.
CSJ0912-70-091
Proj IDBR 2014(555)
Work TypeREPL BR & APPR
 
0.1631844818.401231913.7466.7
Work Order08-05-16
Work Began11-03-16
Work Completed
Time Computed09-05-16
Contract Working Days254
Addl Days Granted0
Working Days Charged94
Percent Time Used37
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
SPECIALTY DRILLING, LTD. (6.22)
HIGHWAY 1, LLC (1.64)
Contract #04163016
Totals1844818.40296235.041231913.7466.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS WITHIN CENTRAL
ToHOUSTON AREA
CSJ0912-70-094
Proj IDSTP 2015(317)
Work TypeBRIDGE MAINTENANCE WORK
 
0.0011698653.403347701.5799.9
Work Order01-02-15
Work Began04-25-15
Work Completed
Time Computed04-25-15
Contract Working Days304
Addl Days Granted16
Working Days Charged292
Percent Time Used91
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
IOWA BRIDGE & CULVERT, LC (21.67)
JTB SERVICES (2.42)
THIRD COAST SERVICES LLC (2.83)
TX TINMAN ENTERPRISES, LLC. (5.80)
AARON CONCRETE CONTRACTORS, L.P. (1.59)
HOUSTON SAWING & DRILLING (1.05)
HOLES INCORPORATED (1.58)
Contract #11143212
Totals1698653.4027978.673347701.5799.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-70-099
Proj IDNH 2014(640)
Work TypeCONST CURB RAMPS
 
0.0012767522.722122734.7779.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-14
Work Began10-27-14
Work Completed
Time Computed08-31-14
Contract Working Days244
Addl Days Granted0
Working Days Charged343
Percent Time Used140
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE (12.07)
THIRD COAST SERVICES LLC (9.66)
STRIPE-A-LINE, INC. (2.31)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44)
GLOBE ELECTRIC SUPPLY COMPANY, INC. (2.65)
GEORGE MEEKS LANDPRO, INC. (3.02)
TEXAS CONCRETE AND DEMOLITION, INC. (8.51)
Contract #05143031
Totals2767522.720.002122734.7779.5

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-70-100
Proj IDSTP 2015(613)
Work TypeCONST CURB RAMPS
 
0.0013140223.082720750.4287.2
Work Order03-23-15
Work Began03-07-16
Work Completed
Time Computed04-08-15
Contract Working Days203
Addl Days Granted0
Working Days Charged222
Percent Time Used109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-100
BATTERSON,LLP (4.08)
A-1 EROSION CONTROL, LLC (0.84)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (9.75)
STRIPE-A-LINE, INC. (0.00)
Contract #02153020
Totals3140223.080.002720750.4287.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToALONG FM 1960
CSJ0912-70-101
Proj IDNH 2017(160)
Work TypeCONST CURB RAMPS
 
0.0012708928.950.000.0
Work Order12-12-16
Work Began00-00-00
Work Completed
Time Computed01-11-17
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163026
Totals2708928.950.000.000.0

CountyHARRIS
HighwayCS
FromMASON PARK PED/BIKE BRG, FROM TIPPS
ToST AT EVERGREEN DR TO 75TH ST
CSJ0912-70-103
Proj IDSTP 2015(559)TE
Work TypeCONST PED & BIKE BR
 
0.1805659268.00204959.883.6
Work Order12-15-16
Work Began00-00-00
Work Completed
Time Computed02-13-17
Contract Working Days228
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163221
Totals5659268.0079235.40204959.883.6

CountyHARRIS
HighwayCR
FromBRAYS BAYOU, FROM MACGREGOR PARK
ToUNIVERISTY OF HOUSTON (WHEELER AVE)
CSJ0912-70-104
Proj IDSTP 2016(352)TE
Work TypeCONST BIKE/PED BR
 
0.4802330231.54440458.5318.9
Work Order09-16-16
Work Began01-23-17
Work Completed
Time Computed12-15-16
Contract Working Days150
Addl Days Granted0
Working Days Charged30
Percent Time Used20
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-104
HOUSTON BARRICADES AND SUPPLY, LLC (0.39)
GROUND HOG FOUNDATION DRILLING (1.79)
HI-TECH CONCREE PUMPING SERVICES (0.32)
SPECIALTY DRILLING, LTD. (2.22)
Contract #08163055
Totals2330231.54101450.90440458.5318.9

CountyHARRIS
HighwayCR
FromIH 69 S, FROM HAZARD STREET
ToMONTROSE BLVD
CSJ0912-70-105
Proj IDSTP 2014(128)TE
Work TypeINST BR LIGHT
 
0.2503061039.353395463.8599.9
Work Order05-16-16
Work Began09-12-16
Work Completed
Time Computed08-14-16
Contract Working Days157
Addl Days Granted0
Working Days Charged125
Percent Time Used79
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
SCOTT DERR PAINTING CO, LLC (0.00)
BUYERS BARRICADES, INC. (0.80)
Contract #02163247
Totals3061039.353800.003395463.8599.9

CountyHARRIS
HighwayCS
FromCAROLINE STREET;ELGIN STREET
ToPIERCE STREET
CSJ0912-71-003
Proj IDC 912-71-3
Work TypeGR, STRS, BASE
 
0.68912380276.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173038
Totals12380276.540.000.000.0

CountyHARRIS
HighwayCS
FromVARIOUS LOCATION IN HARRIS COUNTY
ToPRECINCT 1
CSJ0912-71-046
Proj IDC 912-71-46
Work TypeHARRIS COUNTY PRECINCT 1 RCTSS
 
0.0014241559.873709755.0587.4
Work Order10-28-14
Work Began11-13-14
Work Completed
Time Computed11-13-14
Contract Working Days300
Addl Days Granted0
Working Days Charged263
Percent Time Used87
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
ABC DIRECTIONAL DRILLING, INC. (4.67)
SCMU (11.94)
STRIPE LINES, INC. (1.41)
Contract #08143027
Totals4241559.8730703.213709755.0587.4

CountyHARRIS
HighwayCS
FromMARKET ST EB AT HUNTING BAYOU
ToHOUSTON
CSJ0912-71-078
Proj IDBR 99(271)
Work TypeREPLACE BRIDGE
 
0.1581687687.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days148
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-078
GMJ PAVING CO. (0.78)
STRIPE LINES, INC. (0.85)
FIRST KATY CONSTRUCTION (11.43)
JMHP, INC. (0.73)
Contract #10163015
Totals1687687.900.000.000.0

CountyHARRIS
HighwayVA
FromKEEGANS BAYOU TRAIL: GESSNER
ToKIRKWOOD
CSJ0912-71-631
Proj IDCM 99(567)
Work TypeHIKE AND BIKE TRAIL
 
4.0345688316.226933081.6399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-18-12
Work Began09-16-13
Work Completed
Time Computed01-16-13
Contract Working Days368
Addl Days Granted0
Working Days Charged362
Percent Time Used98
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-631
CARMA CONSTRUCTION, LLC (16.32)
HIGHWAY TECHNOLOGIES, INC. (0.18)
REGIONAL TRAFFIC SERVICES LLC (0.15)
THIRD COAST SERVICES LLC (3.37)
GEORGE MEEKS LANDPRO, INC. (4.04)
SPECIALTY DRILLING, LTD. (0.53)
ENVIRONMENTAL ALLIES, L.P. (0.94)
Contract #08123008
Totals5688316.220.006933081.6399.9

CountyHARRIS
HighwayCS
FromON SOUTH SHAVER FROM GULF FRWY
ToSH 3
CSJ0912-71-688
Proj IDSTP 99(751)MM
Work TypeWIDEN TO 6 LANE DIVIDED
 
1.13813480682.2013408805.0999.4
Work Order04-23-13
Work Began06-24-13
Work Completed
Time Computed06-22-13
Contract Working Days404
Addl Days Granted0
Working Days Charged402
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-688
CPAVE, INC. (0.54)
WILLOW CITY SIGN & RAIL, INC. (0.17)
INDUS CONSTRUCTION, L.P. (0.73)
APCON SERVICES, LLC (6.16)
GMJ PAVING CO. (5.12)
THIRD COAST SERVICES LLC (1.85)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P. (0.70)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.01)
DUSTROL, INC. (0.54)
BORING & TUNNELING COMPANY OF AMERICA, INC. (0.03)
STRIPES & STOPS COMPANY, INC. (0.97)
ENVIRONMENTAL ALLIES, L.P. (0.30)
H & E AGGREGATE, LLC (2.77)
MCNORTON DEWATERING, INC. (0.06)
FIRST KATY CONSTRUCTION (1.32)
MICKIE SERVICE, INC. (0.03)
CURB PLANET INC. (0.02)
A1 EROSION CONTROL (1.07)
Contract #02133203
Totals13480682.200.0013408805.0999.4

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToPRECINCT 2
CSJ0912-72-190
Proj IDC 912-72-190
Work TypeHARRIS COUNTY PRECINCT 2 RCTSS
 
0.0011906720.281586966.6083.2
Work Order10-28-14
Work Began11-13-15
Work Completed
Time Computed11-13-14
Contract Working Days220
Addl Days Granted0
Working Days Charged188
Percent Time Used85
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-190
SCMU (12.11)
ABC DIRECTIONAL DRILLING, INC. (4.29)
WALLACE CONCRETE SAWING (0.68)
BAY CITY TRAFFIC (1.68)
Contract #08143011
Totals1906720.2891555.111586966.6083.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToPRECINCT 4
CSJ0912-72-199
Proj IDCM 2013(989)
Work TypeHARRIS COUNTY PRECINCT 4 RCTSS
 
0.0012561452.602980953.1599.9
Work Order11-22-13
Work Began03-21-14
Work Completed
Time Computed03-21-14
Contract Working Days305
Addl Days Granted0
Working Days Charged289
Percent Time Used94
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-199
VERSALINK MEDIA (6.77)
SPRING CREEK CONSTRUCTION, INC. (17.27)
Contract #08133042
Totals2561452.6045780.002980953.1599.9

CountyHARRIS
HighwayCS
FromYALE ST AT WHITE OAK BAYOU
To.
CSJ0912-72-230
Proj IDBR 2013(801)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0912825133.253278908.3699.9
Work Order11-24-15
Work Began04-25-16
Work Completed
Time Computed02-22-16
Contract Working Days401
Addl Days Granted0
Working Days Charged239
Percent Time Used59
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-230
THIRD COAST SERVICES LLC (2.17)
W. W. FOUNDATION DRILLING, LTD. (8.29)
SCOTT DERR PAINTING CO, LLC (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.99)
MESA ROD BUSTERS, INC. (2.76)
GMJ PAVING CO. (2.75)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.74)
SOUTHERN CRUSHED CONCRETE LLC (3.21)
AGGREGATE TECHNOLOGIES, INC. (0.10)
HOUSTON SAWING & DRILLING (0.08)
Contract #09153017
Totals2825133.2519081.233278908.3699.9

CountyHARRIS
HighwayCS
FromHEMPSTEAD RD, FROM E OF LONG POINT
ToWEST OF WEST LITTLE YORK ROAD
CSJ0912-72-296
Proj IDSTP 2017(440)
Work TypeINTERSECTION IMPROVEMENTS
 
1.3164496496.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-296
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163220
Totals4496496.000.000.000.0

CountyHARRIS
HighwayVA
FromON FM 270 FROM NASA ROAD 1
ToHENDERSON ROAD
CSJ0912-72-302
Proj IDSTP 2014(138)TE
Work TypeSHARED USE PATH
 
1.9021755575.5015637.280.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-06-15
Work Began00-00-00
Work Completed
Time Computed10-05-15
Contract Working Days150
Addl Days Granted0
Working Days Charged36
Percent Time Used24
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-302
BATTERSON,LLP (2.94)
GEORGE MEEKS LANDPRO, INC. (3.12)
J KRU LAND SERVICES, LLC (0.78)
CURB PLANET INC. (0.11)
Contract #05153226
Totals1755575.500.0015637.280.8

CountyHARRIS
HighwayVA
FromFALLS STREET
ToLOCKWOOD DRIVE
CSJ0912-72-315
Proj IDSTP 2014(142)TE
Work TypeCONSTRUCT MULTI-USE PATH
 
0.8671323726.00594328.8044.8
Work Order06-22-16
Work Began08-10-16
Work Completed
Time Computed07-22-16
Contract Working Days136
Addl Days Granted0
Working Days Charged22
Percent Time Used16
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-315
SPECIALTY DRILLING, LTD. (1.17)
Contract #04163021
Totals1323726.0031117.51594328.8044.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10