Monthly State Let Construction Report For Houston District As Of Jan 11, 2016 Page 7 Of 14

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTGOMERY
Highway FM 149
From FM 1488
To SS 149
CSJ 0720-02-083
Proj ID STP 2014(741)
Work Type INST LT TN LNS
 
2.466 3762255.55 500460.48 3977450.35 99.9
Work Order 08-29-14
Work Began 10-27-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 79
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-083
THIRD COAST SERVICES LLC (3.68%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
WILLOW CITY SIGN & RAIL, INC.(5.82%)
J & M CONTRACTING, COMPANY ( 11.50%)
EROSION CONTROL, INC.(3.95%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.06%)
TEXOP CONSTRUCTION (0.53%)
CEN TEX HYDROSEED, INC.(4.27%)
Contract # 06143030
Totals 3762255.55 500460.48 3977450.35 99.9

CountyMONTGOMERY
Highway FM 149
From FM 1097
To FM 1791
CSJ 0720-02-087
Proj ID STP 1502(606)HES
Work Type BS REPR, OCST, 1.5" OL & ADD SHLDR
 
10.170 10198541.18 0.00 0.00 0.0
Work Order 11-10-15
Work Began 00-00-00
Work Completed  
Time Computed 01-09-16
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-087
J & M CONTRACTING, COMPANY (5.60%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13%)
TEXAS LAND CLEARING, INC.( 18.16%)
WATERS CONSTRUCTION CO., INC.(3.85%)
WILLOW CITY SIGN & RAIL, INC.(1.56%)
Contract # 08153044
Totals 10198541.18 0.00 0.00 0.0

CountyHARRIS
Highway SH 249
From AT VETERANS MEMORIAL DRIVE
To .
CSJ 0720-03-128
Proj ID STP 2014(743)HES
Work Type IMPROVE TS
 
0.404 254036.09 0.00 114013.86 44.8
Work Order 07-25-14
Work Began 02-10-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 24
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143218
Totals 254036.09 0.00 114013.86 44.8

CountyFORT BEND
Highway FM 361
From FM 361
To AT FAIRCHILDS CREEK
CSJ 0838-03-023
Proj ID BR 1502(200)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.076 976506.40 131024.70 772093.72 79.0
Work Order 07-14-15
Work Began 09-14-15
Work Completed  
Time Computed 09-13-15
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 80
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0838-03-023
GMJ PAVING CO. (7.59%)
BATTERSON,LLP(0.64%)
SCOTT DERR PAINTING CO, LLC(0.08%)
WEBER-BALKE FOUNDATION COMPANY, INC(5.07%)
MESA ROD BUSTERS, INC. (0.59%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.19%)
Contract # 05153024
Totals 976506.40 131024.70 772093.72 79.0

CountyBRAZORIA
Highway FM 521
From SH 35
To SH 332
CSJ 0847-03-035
Proj ID STP 2016(061)
Work Type SHOULDER REP AND OVERLAY
 
29.306 7645090.84 0.00 0.00 0.0
Work Order 11-13-15
Work Began 00-00-00
Work Completed  
Time Computed 12-14-15
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0847-03-035
STRIPE A LINE(4.54%)
JMHP, INC. (4.90%)
THIRD COAST SERVICES LLC (1.18%)
Contract # 09153010
Totals 7645090.84 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 0.00 1143341.19 77.1
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 162
Percent Time Used 68
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 0.00 1143341.19 77.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 148701.44 33.7
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 61
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 148701.44 33.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 0.00 1271382.93 98.5
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
REGIONAL TRAFFIC SERVICES LLC(0.00%)
VASQUEZ CONCRETE COMPANY (0.38%)
Contract # 04093209
Totals 1289999.25 0.00 1271382.93 98.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 0.00 1600338.38 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP(5.72%)
ISI CONTRACTING, INC.(6.40%)
VASQUEZ CONCRETE COMPANY (0.32%)
Contract # 09113211
Totals 1515998.78 0.00 1600338.38 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 754.40 1334260.98 74.6
Work Order 07-19-13
Work Began 10-14-14
Work Completed  
Time Computed 08-04-13
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 238
Percent Time Used 55
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.54%)
Contract # 03133016
Totals 1787199.58 754.40 1334260.98 74.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1196058.08 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1196058.08 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 63832.80 1148566.35 78.8
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 23
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 63832.80 1148566.35 78.8

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 0.00 1105336.31 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 24
Working Days Charged 210
Percent Time Used 86
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 0.00 1105336.31 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 0.00 591051.11 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-22-13
Work Began 02-24-14
Work Completed 10-15-15
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 312
Percent Time Used 85
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
GENERATORS OF HOUSTON, LP( 69.74%)
BEVCO COMPANY, INC.(3.17%)
Contract # 01133028
Totals 598106.25 0.00 591051.11 100.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 36816.00 77271.80 4.0
Work Order 03-20-13
Work Began 09-30-15
Work Completed  
Time Computed 09-16-13
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 1
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 36816.00 77271.80 4.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-00-424
Proj ID CM 1102(560)
Work Type PED & SIG IMPRVMTS IN AIRLINE DIST
 
1.367 2697458.33 10000.00 2291483.99 86.2
Work Order 01-23-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 119
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03%)
ODUM SERVICES, L.P.(0.35%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 11.47%)
REGIONAL TRAFFIC SERVICES LLC(2.15%)
AGGREGATE TECHNOLOGIES, INC. (5.02%)
SPEEDY PAVING(1.31%)
AAA ASPHALT PAVING, INC. (0.00%)
Contract # 10133027
Totals 2697458.33 10000.00 2291483.99 86.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-440
Proj ID NH 2015(316)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 772662.59 129193.50 573540.88 74.2
Work Order 01-16-15
Work Began 10-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 48
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-440
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143019
Totals 772662.59 129193.50 573540.88 74.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-441
Proj ID NH 2014(297)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1210347.90 785.00 1169969.13 96.6
Work Order 03-03-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 500
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC(1.78%)
Contract # 12133223
Totals 1210347.90 785.00 1169969.13 96.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-00-443
Proj ID STP 2014(298)
Work Type INSTALL CCTV
 
0.001 243957.34 0.00 252350.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 03-11-14
Work Completed 03-12-15
Time Computed 03-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-443
AMERICAN CABLE SERVICES, INC.(2.55%)
Contract # 12133020
Totals 243957.34 0.00 252350.52 100.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON IH 45
To .
CSJ 0912-00-468
Proj ID IM 0451(341)
Work Type LANDSCAPE DEVELOPMENT
 
52.668 1130845.26 0.00 1126994.45 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-12
Work Began 06-15-12
Work Completed 09-04-15
Time Computed 07-15-12
Contract Working Days 105
Addl Days Granted 45
Working Days Charged 130
Percent Time Used 86
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-468
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123018
Totals 1130845.26 0.00 1126994.45 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13 | page 14