Monthly State Let Construction Report For Houston District As Of Aug 11, 2017 Page 7 Of 10

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFORT BEND
HighwayCS
FromON TRAMMEL FRESNO RD,FROM VICKSBURG
ToFT BEND PKWY
CSJ0912-34-143
Proj IDC 912-34-143
Work TypeGR, STRS, BASE AND PAVE
 
0.6433825527.241833412.8747.9
Work Order03-22-17
Work Began06-07-17
Work Completed
Time Computed05-21-17
Contract Working Days176
Addl Days Granted0
Working Days Charged40
Percent Time Used22
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-143
PRV SERVICES, INC. (0.52)
P&Z LOGISTICS INC. (2.57)
SOUTHERN CRUSHED CONCRETE LLC (0.86)
Contract #02173223
Totals3825527.241009176.691833412.8747.9

CountyFORT BEND
HighwayCS
FromTRAMMEL FRESNO RD, FORT BEND PKWY
ToFM 521
CSJ0912-34-144
Proj IDSTP 2010(596)MM
Work TypeGR, STR, BASE AND 0AVE
 
3.04120864455.456330683.5030.3
Work Order03-03-15
Work Began03-24-15
Work Completed
Time Computed03-19-15
Contract Working Days622
Addl Days Granted0
Working Days Charged68
Percent Time Used10
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC. (0.72)
RICE ENVIRONMENTAL SERVICES (0.24)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.96)
INDUS CONSTRUCTION, L.P. (3.85)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.17)
BASE CONSTRUCTION, L.L.P. (23.02)
KMA CONTRACTORS SERVICES INC. (4.77)
Contract #12143003
Totals20864455.455000.006330683.5030.3

CountyFORT BEND
HighwayCR ETC
FromMEYER ROAD AT SNAKE CREEK TRIBUTARY
To.
CSJ0912-34-176
Proj IDBR 2013(735)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7122828589.452749638.5599.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days321
Addl Days Granted0
Working Days Charged397
Percent Time Used123
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55)
REGIONAL TRAFFIC SERVICES LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45)
ODUM SERVICES, L.P. (1.77)
MESA ROD BUSTERS, INC. (0.19)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.98)
EROSION PREVENTION PRODUCTS (4.81)
GARNER PAVING & CONSTRUCTION, LTD. (0.15)
CROSS TEX CURBS (0.00)
J KRU LAND SERVICES, LLC (0.06)
Contract #06153027
Totals2828589.450.002749638.5599.3

CountyFORT BEND
HighwayCS
FromON HURRICANE LANE/LAKE OLYMPIA;FROM
ToTRAMMEL FRESNO RD TO FT BEND PKWY
CSJ0912-34-182
Proj IDSTP 1302(010)MM
Work TypeCONST 2 LN CONC RDWYS
 
1.3936588849.406570060.0699.7
Work Order05-11-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days245
Addl Days Granted0
Working Days Charged178
Percent Time Used72
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-182
PRV SERVICES, INC. (7.89)
SPRINT SAND AND CLAY, LLC (0.00)
MVA CONSTRUCTION LLC (0.11)
SEMARCK LANDSCAPE SERVICES, INC. (1.54)
CPAVE, INC. (0.33)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (0.49)
HODGES BROTHERS, INC. (0.37)
TRAFFIC SIGNS & LINES, LLC (0.54)
Contract #01163030
Totals6588849.400.006570060.0699.7

CountyFORT BEND
HighwayVA
FromVARIOUS LOCATIONS ALONG: US 59,
ToSH 6, AND US 90A
CSJ0912-34-187
Proj IDC 912-34-187
Work TypeINSTALLATION OF DMS
 
0.001992940.68908511.6191.4
Work Order04-07-16
Work Began02-13-17
Work Completed
Time Computed05-07-16
Contract Working Days91
Addl Days Granted0
Working Days Charged62
Percent Time Used68
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
MAIN LANE INDUSTRIES LTD. (54.26)
INTERSTATE BARRICADES & MARKINGS, INC. (0.98)
Contract #02163213
Totals992940.687523.31908511.6191.4

CountyHARRIS
HighwayCS
FromAT ALICE JOHNSON JR HIGH SCHOOL
To.
CSJ0912-70-067
Proj IDSTP 1602(474)SRS
Work TypePEDESTRIAN WAY/SIDEWALKS
 
0.320582538.50555611.9195.3
Work Order09-19-16
Work Began10-24-16
Work Completed
Time Computed11-18-16
Contract Working Days45
Addl Days Granted15
Working Days Charged60
Percent Time Used100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163029
Totals582538.500.00555611.9195.3

CountyHARRIS
HighwayCS
FromAT BANG ELEMENTARY SCHOOL
To.
CSJ0912-70-068
Proj IDSTP 2014(745)SRS
Work TypeSRTS TRAIL
 
1.473499113.96465081.5199.9
Work Order10-02-14
Work Began12-01-14
Work Completed
Time Computed12-01-14
Contract Working Days60
Addl Days Granted25
Working Days Charged167
Percent Time Used196
Contractor(s)
INSURORS INDEMNITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP (14.72)
LANDPRO, INC. (4.34)
TITAN 360 INDUSTRIAL SERVICES (8.99)
Contract #07143054
Totals499113.960.00465081.5199.9

CountyHARRIS
HighwayVA
FromFANNIN & MN ST ESPLANADES CAMBRIDGE
ToMECOM FOUNTAIN
CSJ0912-70-078
Proj IDSTP 2011(255)TE
Work TypeENHANCEMENT PROJECT
 
0.8072581444.902026823.5078.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-13
Work Began10-21-13
Work Completed
Time Computed10-12-13
Contract Working Days176
Addl Days Granted32
Working Days Charged216
Percent Time Used103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88)
DOWN UNDER CONSTRUCTION (1.83)
SPECIALTY DRILLING (0.02)
BUILDER SERVICES CO. (1.50)
LEXTEX, INC. (7.15)
BIO LANDSCAPE & MAINTENANCE, INC. (65.42)
HOGGATT, LP (5.46)
EVERY SECOND COUNTS (ESC) (5.69)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48)
MIKELS CONSTRUCTION CO., INC. (2.51)
PUMPS, MOTORS & CONTROLS (0.04)
STRIPE LINES, INC. (0.15)
Contract #06133013
Totals2581444.900.002026823.5078.7

CountyHARRIS
HighwayCS
FromWESTERLAND DRIVE; AT HCFCD DITCH
To.
CSJ0912-70-091
Proj IDBR 2014(555)
Work TypeREPL BR & APPR
 
0.1631844818.401616263.8987.6
Work Order08-05-16
Work Began11-03-16
Work Completed
Time Computed09-05-16
Contract Working Days254
Addl Days Granted0
Working Days Charged179
Percent Time Used70
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
SPECIALTY DRILLING, LTD. (6.22)
HIGHWAY 1, LLC (1.64)
Contract #04163016
Totals1844818.4062287.501616263.8987.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS WITHIN CENTRAL
ToHOUSTON AREA
CSJ0912-70-094
Proj IDSTP 2015(317)
Work TypeBRIDGE MAINTENANCE WORK
 
0.0011698653.403593398.9099.9
Work Order01-02-15
Work Began04-25-15
Work Completed
Time Computed04-25-15
Contract Working Days304
Addl Days Granted16
Working Days Charged292
Percent Time Used91
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
IOWA BRIDGE & CULVERT, LC (21.67)
JTB SERVICES (2.42)
THIRD COAST SERVICES LLC (2.83)
TX TINMAN ENTERPRISES, LLC. (5.80)
AARON CONCRETE CONTRACTORS, L.P. (1.59)
HOUSTON SAWING & DRILLING (1.05)
HOLES INCORPORATED (1.58)
Contract #11143212
Totals1698653.4024245.073593398.9099.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-70-099
Proj IDNH 2014(640)
Work TypeCONST CURB RAMPS
 
0.0012767522.722122734.7779.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-14
Work Began10-27-14
Work Completed
Time Computed08-31-14
Contract Working Days244
Addl Days Granted0
Working Days Charged343
Percent Time Used140
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE (12.07)
THIRD COAST SERVICES LLC (9.66)
STRIPE-A-LINE, INC. (2.31)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44)
GLOBE ELECTRIC SUPPLY COMPANY, INC. (2.65)
GEORGE MEEKS LANDPRO, INC. (3.02)
TEXAS CONCRETE AND DEMOLITION, INC. (8.51)
Contract #05143031
Totals2767522.720.002122734.7779.5

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-70-100
Proj IDSTP 2015(613)
Work TypeCONST CURB RAMPS
 
0.0013140223.082720750.4287.2
Work Order03-23-15
Work Began03-07-16
Work Completed
Time Computed04-08-15
Contract Working Days203
Addl Days Granted0
Working Days Charged222
Percent Time Used109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-100
BATTERSON,LLP (4.08)
A-1 EROSION CONTROL, LLC (0.84)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (9.75)
STRIPE-A-LINE, INC. (0.00)
Contract #02153020
Totals3140223.080.002720750.4287.2

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
ToALONG FM 1960
CSJ0912-70-101
Proj IDNH 2017(160)
Work TypeCONST CURB RAMPS
 
0.0012708928.95379885.6714.0
Work Order12-12-16
Work Began04-19-17
Work Completed
Time Computed01-11-17
Contract Working Days200
Addl Days Granted0
Working Days Charged63
Percent Time Used31
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-101
STRIPE LINES, INC. (2.40)
TRAF-TEX, INC. (11.23)
BUYERS BARRICADES HOUSTON, LLC. (0.68)
Contract #10163026
Totals2708928.95282206.75379885.6714.0

CountyHARRIS
HighwayCS
FromMASON PARK PED/BIKE BRG, FROM TIPPS
ToST AT EVERGREEN DR TO 75TH ST
CSJ0912-70-103
Proj IDSTP 2015(559)TE
Work TypeCONST PED & BIKE BR
 
0.1805659268.001497694.5626.4
Work Order12-15-16
Work Began04-10-17
Work Completed
Time Computed02-13-17
Contract Working Days228
Addl Days Granted0
Working Days Charged45
Percent Time Used19
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-103
DORAN STEEL, INC. (0.75)
GEORGE MEEKS LANDPRO, INC. (4.41)
PFEIFFER & SON LTD. (5.13)
TAYLOR LIGHTNING PROTECTION (0.18)
LONESTAR TRAFFIC SAFETY, LLC (0.09)
CLODFELTER BRIDGE & STRUCTURES INTERNATIONAL, INC. (8.61)
Contract #06163221
Totals5659268.00544174.901497694.5626.4

CountyHARRIS
HighwayCR
FromBRAYS BAYOU, FROM MACGREGOR PARK
ToUNIVERISTY OF HOUSTON (WHEELER AVE)
CSJ0912-70-104
Proj IDSTP 2016(352)TE
Work TypeCONST BIKE/PED BR
 
0.4802330231.54907808.9238.9
Work Order09-16-16
Work Began01-23-17
Work Completed
Time Computed12-15-16
Contract Working Days150
Addl Days Granted0
Working Days Charged102
Percent Time Used68
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-104
HOUSTON BARRICADES AND SUPPLY, LLC (0.39)
GROUND HOG FOUNDATION DRILLING (1.79)
HI-TECH CONCREE PUMPING SERVICES (0.32)
SPECIALTY DRILLING, LTD. (2.22)
LANDPRO, INC. (8.01)
COASTAL FOUNDATION DRILLING CO., INC. (1.28)
Contract #08163055
Totals2330231.54131565.64907808.9238.9

CountyHARRIS
HighwayCR
FromIH 69 S, FROM HAZARD STREET
ToMONTROSE BLVD
CSJ0912-70-105
Proj IDSTP 2014(128)TE
Work TypeINST BR LIGHT
 
0.2503061039.353446875.2899.9
Work Order05-16-16
Work Began09-12-16
Work Completed
Time Computed08-14-16
Contract Working Days157
Addl Days Granted0
Working Days Charged143
Percent Time Used91
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
SCOTT DERR PAINTING CO, LLC (0.00)
BUYERS BARRICADES, INC. (0.80)
Contract #02163247
Totals3061039.351311.433446875.2899.9

CountyHARRIS
HighwayCS
FromCAROLINE STREET;ELGIN STREET
ToPIERCE STREET
CSJ0912-71-003
Proj IDC 912-71-3
Work TypeGR, STRS, BASE
 
0.68912380276.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-29-17
Work Began00-00-00
Work Completed
Time Computed08-28-17
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173038
Totals12380276.540.000.000.0

CountyHARRIS
HighwayCS
FromVARIOUS LOCATION IN HARRIS COUNTY
ToPRECINCT 1
CSJ0912-71-046
Proj IDC 912-71-46
Work TypeHARRIS COUNTY PRECINCT 1 RCTSS
 
0.0014241559.873825817.6590.1
Work Order10-28-14
Work Began11-13-14
Work Completed
Time Computed11-13-14
Contract Working Days300
Addl Days Granted0
Working Days Charged263
Percent Time Used87
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
ABC DIRECTIONAL DRILLING, INC. (4.67)
SCMU (11.94)
STRIPE LINES, INC. (1.41)
Contract #08143027
Totals4241559.87116062.603825817.6590.1

CountyHARRIS
HighwayCS
FromMARKET ST EB AT HUNTING BAYOU
ToHOUSTON
CSJ0912-71-078
Proj IDBR 99(271)
Work TypeREPLACE BRIDGE
 
0.1581687687.90320110.3918.9
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed03-20-17
Contract Working Days148
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-078
GMJ PAVING CO. (0.78)
STRIPE LINES, INC. (0.85)
FIRST KATY CONSTRUCTION (11.43)
JMHP, INC. (0.73)
CHERRY CRUSHED CONCRETE (2.67)
Contract #10163015
Totals1687687.902000.00320110.3918.9

CountyHARRIS
HighwayMH
FromAIRPORT BLVD FROM HIRAM CLARKE ROAD
ToFM 521
CSJ0912-71-386
Proj IDHP 1702(559)
Work TypeGR, STRS & SURF
 
2.49817962352.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days396
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-386
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173003
Totals17962352.180.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10