|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | GALVESTON |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
IN GALVESTON COUNTY |
| CSJ |
0912-73-180 |
| Proj ID |
STP 1102(311) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
3.842 |
3284825.97 |
102880.18 |
118227.49 |
3.5 |
| Work Order |
10-21-11 |
| Work Began |
11-06-11 |
| Work Completed |
|
| Time Computed |
11-06-11 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
25 |
| Percent Time Used |
9 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-180 THIRD COAST SERVICES, LLC( 11.29%) WORK ZONE PRODUCTS, INC. (5.46%) KOSSMAN CONTRACTING COMPANY(1.91%) SUPERIOR LIGHTING(0.43%)
|
| Contract # |
08113036 |
|
Totals |
3284825.97 |
102880.18 |
118227.49 |
3.5 |
|
| County | HARRIS |
| Highway |
FM 865 |
| From |
SOUTH OF BW 8 |
| To |
BRAZORIA COUNTY LINE(CLEAR CREEK) |
| CSJ |
0976-01-035 |
| Proj ID |
STP 1102(436) |
| Work Type |
CR, BS & SURF |
| |
|
1.106 |
9266318.15 |
551192.15 |
1203651.45 |
12.9 |
| Work Order |
10-27-11 |
| Work Began |
11-29-11 |
| Work Completed |
|
| Time Computed |
11-12-11 |
| Contract Working Days |
410 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
5 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-035 EMBARK TREE AND LANDSCAPE SERVICES (0.35%) URBAN FORESTERS, LLC (0.34%) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(4.74%) GMJ PAVING CO. (2.40%) BREDA COMPANY, INC.(0.35%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%) BATTERSON,LLP(1.10%) CHAMPIONS HYDROLAWN(0.33%) JMHP, INC. (0.05%) H & H CURB COMPANY (0.11%) NBG CONSTRUCTORS, INC. ( 22.94%)
|
| Contract # |
08113207 |
|
Totals |
9266318.15 |
551192.15 |
1203651.45 |
12.9 |
|
| County | BRAZORIA |
| Highway |
FM 865 |
| From |
SOUTH OF HARRIS COUNTY LINE |
| To |
FM 518 |
| CSJ |
0976-02-085 |
| Proj ID |
STP 2009(283) |
| Work Type |
GR, BS & SURF |
| |
|
1.915 |
13267224.77 |
42923.54 |
12372466.76 |
94.4 |
| County | BRAZORIA |
| Highway |
FM 865 |
| From |
SOUTH OF HARRIS COUNTY LINE |
| To |
FM 518 |
| CSJ |
0976-02-087 |
| Proj ID |
RW 976-2-87 |
| Work Type |
ROW ACQ. AND UTL. ADJ. |
| |
|
0.001 |
394560.47 |
0.00 |
294380.05 |
74.6 |
| Work Order |
04-09-09 |
| Work Began |
05-05-09 |
| Work Completed |
|
| Time Computed |
04-25-09 |
| Contract Working Days |
459 |
| Addl Days Granted |
0 |
| Working Days Charged |
562 |
| Percent Time Used |
122 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0976-02-085 HIGHWAY TECHNOLOGIES, INC. (1.51%) GMJ PAVING CO. (4.67%) PROTECTIVE ENVIRONMENTAL STRATEGIES, INC.(0.70%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27%) CREACOM, INC.(6.36%) CHERRY CRUSHED CONCRETE(4.42%) SPECIALTY DRILLING (0.58%) SCOTT DERR PAINTING CO (0.00%) BECO CONSTRUCTION, L.L.C.(0.21%) NBG CONSTRUCTORS, INC. ( 17.22%) MAGNUM TUNNELING, LLC(0.10%) MICKIE SERVICE, INC. (0.01%) BECO CONSTRUCTION, L.L.C.(4.69%) OATES INDUSTRIES, INC. (0.20%) FLORES CURBS (0.10%)
|
| Contract # |
02093201 |
|
Totals |
13661785.24 |
42923.54 |
12666846.81 |
93.9 |
|
| County | HARRIS |
| Highway |
NASA 1 |
| From |
IH 45 |
| To |
SH 146 |
| CSJ |
0981-01-102 |
| Proj ID |
CM 2008(837) |
| Work Type |
INSTALL CTMS |
| |
|
7.964 |
3356949.75 |
0.00 |
3034059.40 |
90.3 |
| Work Order |
11-06-09 |
| Work Began |
01-04-10 |
| Work Completed |
|
| Time Computed |
11-22-09 |
| Contract Working Days |
375 |
| Addl Days Granted |
0 |
| Working Days Charged |
372 |
| Percent Time Used |
99 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0981-01-102 VACA UNDERGOUND UTILITIES INC(1.34%) ODUM SERVICES, L.P.(0.59%) SUPERIOR GROUTING SERVICES, INC. (0.60%)
|
| Contract # |
09093210 |
|
Totals |
3356949.75 |
0.00 |
3034059.40 |
90.3 |
|
| County | BRAZORIA |
| Highway |
FM 523 |
| From |
0.261 MI SE OF SH 35 |
| To |
SH 332 |
| CSJ |
1003-01-089 |
| Proj ID |
STP 1102(312)HES |
| Work Type |
RUMBLE STRIPS |
| |
|
66.958 |
1083224.24 |
148367.35 |
627249.17 |
57.9 |
| Work Order |
09-13-11 |
| Work Began |
09-29-11 |
| Work Completed |
|
| Time Computed |
09-29-11 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
28 |
| Percent Time Used |
62 |
| Contractor(s) |
| HIGHWAY TECHNOLOGIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1003-01-089 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08113048 |
|
Totals |
1083224.24 |
148367.35 |
627249.17 |
57.9 |
|
| County | BRAZORIA |
| Highway |
FM 524 |
| From |
0.19 MILES NORTH OF CR 360 |
| To |
SH 35 |
| CSJ |
1004-01-040 |
| Proj ID |
CC 1004-1-40 |
| Work Type |
GR, STRS, LTS, CSB & ACP |
| |
|
2.092 |
5344886.63 |
28766.43 |
5463776.22 |
99.9 |
| Work Order |
01-10-11 |
| Work Began |
01-26-11 |
| Work Completed |
|
| Time Computed |
01-26-11 |
| Contract Working Days |
215 |
| Addl Days Granted |
0 |
| Working Days Charged |
213 |
| Percent Time Used |
99 |
| Contractor(s) |
| TRIPLE B SERVICES, L.L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-040 CHAMPIONS HYDROLAWN(0.08%) CHERRY CONCRETE REMOVAL(0.25%) ENVIRONMENTAL ALLIES, L.P. (0.28%) HIGHWAY TECHNOLOGIES, INC. (0.15%) JAVELINA CONSTRUCTION SOUTH, INC.(0.62%) MIKE SORRELL TRUCKING(0.48%) RICE ENVIRONMENTAL SERVICES(0.76%) SILVA CONTRACTING COMPANY, INC.( 17.84%) STRIPES & STOPS COMPANY, INC.(1.06%) THIRD COAST SERVICES, LLC(2.84%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.61%) WEST TEXAS RUMBLE STRIP(0.04%) VAQUERO CONSTRUCTION, INC. (6.05%)
|
| Contract # |
12103010 |
|
Totals |
5344886.63 |
28766.43 |
5463776.22 |
99.9 |
|
| County | HARRIS |
| Highway |
FM 529 |
| From |
GREEN HOUSE ROAD |
| To |
FRY ROAD |
| CSJ |
1006-01-058 |
| Proj ID |
STP 2009(671)MM |
| Work Type |
GR, STRS, BASE AND SURF |
| |
|
1.485 |
8936871.99 |
49466.58 |
5504556.05 |
61.5 |
| Work Order |
10-16-09 |
| Work Began |
08-05-10 |
| Work Completed |
|
| Time Computed |
04-14-10 |
| Contract Working Days |
516 |
| Addl Days Granted |
0 |
| Working Days Charged |
379 |
| Percent Time Used |
73 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-058 GMJ PAVING CO. (4.27%) BECO CONSTRUCTION, L.L.C.(6.90%) CREACOM, INC.(4.13%) CURB PLANET INC. (0.08%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.42%) TOM-MAC, INC.(0.42%) BATTERSON, L.L.P.(1.45%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.16%) BREDA COMPANY, INC.(7.12%) W. W. FOUNDATION DRILLING, LTD.(1.13%) VALLEY PLACERS, LLC(0.06%) SOUTH TEXAS PAINTING COMPANY (0.08%)
|
| Contract # |
08093007 |
|
Totals |
8936871.99 |
49466.58 |
5504556.05 |
61.5 |
|
| County | HARRIS |
| Highway |
FM 529 |
| From |
GREEN HOUSE ROAD |
| To |
FRY ROAD |
| CSJ |
1006-01-061 |
| Proj ID |
NH 2010(988) |
| Work Type |
2 DETENTION PONDS |
| |
|
1.250 |
411110.10 |
1186.75 |
393773.78 |
95.7 |
| Work Order |
09-15-10 |
| Work Began |
02-14-11 |
| Work Completed |
|
| Time Computed |
10-01-10 |
| Contract Working Days |
63 |
| Addl Days Granted |
0 |
| Working Days Charged |
60 |
| Percent Time Used |
95 |
| Contractor(s) |
| ROZCO CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-061 BOYER, INC.( 29.84%)
|
| Contract # |
08103062 |
|
Totals |
411110.10 |
1186.75 |
393773.78 |
95.7 |
|
| County | MONTGOMERY |
| Highway |
FM 1485 |
| From |
SH 242 |
| To |
KIDD CEMETERY ROAD |
| CSJ |
1062-03-046 |
| Proj ID |
STP 2012(331) |
| Work Type |
BASE REPAIR, O / L & RUMBLE STRIPS |
| |
|
16.171 |
3754449.19 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1062-03-046 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01123017 |
|
Totals |
3754449.19 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
FM 2100 |
| From |
DIAMONDHEAD BLVD. |
| To |
0.14 MI S. OF FIRST STREET |
| CSJ |
1062-04-047 |
| Proj ID |
STP 2010(903)RGS |
| Work Type |
CONST RR GRADE SEPARATION STR & APP |
| |
|
0.870 |
8537094.26 |
1484169.82 |
1484169.82 |
17.3 |
| County | HARRIS |
| Highway |
FM 2100 |
| From |
DIAMONDHEAD BLVD. |
| To |
0.14 MILE SOUTH OF FIRST STREET |
| CSJ |
1062-04-051 |
| Proj ID |
STP 2011(543)ES |
| Work Type |
UTILITY ADJUSTMENT |
| |
|
0.870 |
335846.50 |
21634.00 |
21634.00 |
6.4 |
| Work Order |
09-01-10 |
| Work Began |
11-28-11 |
| Work Completed |
|
| Time Computed |
09-17-10 |
| Contract Working Days |
455 |
| Addl Days Granted |
0 |
| Working Days Charged |
22 |
| Percent Time Used |
4 |
| Contractor(s) |
| NBG CONSTRUCTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047 ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%) BATTERSON,LLP(0.79%) HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%) HOUSTON SAWING & DRILLING(0.09%) JTB SERVICES (0.33%) KOSSMAN CONTRACTING COMPANY(0.23%) REPUBLIC TRAFFIC SAFETY, INC.(0.43%) SCOTT DERR PAINTING CO, LLC(0.26%) WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%) MICKIE SERVICE, INC. (0.10%) SAN JACINTO BORING & TUNNELING, INC. (0.23%) SOUTHERN CRUSHED CONCRETE LLC(0.31%) PM CONSTRUCTION & REHAB, LLC (1.62%) JMHP, INC. (0.52%) GMJ PAVING CO. (3.78%) BREDA COMPANY, INC.(0.61%) H & H CURB COMPANY (0.09%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%)
|
| Contract # |
07103015 |
|
Totals |
8872940.76 |
1505803.82 |
1505803.82 |
16.9 |
|
| County | HARRIS |
| Highway |
FM 1093 |
| From |
AT SHADOWBRIAR DRIVE |
| To |
. |
| CSJ |
1258-04-059 |
| Proj ID |
STP 1102(313)HESG |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.001 |
146421.50 |
0.00 |
10200.00 |
6.9 |
| Work Order |
09-14-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THIRD COAST SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-059 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08113053 |
|
Totals |
146421.50 |
0.00 |
10200.00 |
6.9 |
|
| County | MONTGOMERY |
| Highway |
FM 1774 |
| From |
0.109 MI N OF FM 1488 |
| To |
0.045 MI S OF W LOST CREEK BLVD |
| CSJ |
1400-04-035 |
| Proj ID |
STP 1102(437) |
| Work Type |
RECONSTRUCT ROADWAY |
| |
|
2.320 |
11301777.00 |
798871.82 |
849871.82 |
7.5 |
| Work Order |
11-03-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-19-11 |
| Contract Working Days |
280 |
| Addl Days Granted |
0 |
| Working Days Charged |
11 |
| Percent Time Used |
3 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-035 GULF COAST PAVERS, INC.(0.22%) GMJ PAVING CO. (7.32%) H & H CURB COMPANY (0.12%) BREDA COMPANY, INC.(0.89%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.36%) BATTERSON,LLP(1.83%) THIRD COAST SERVICES, LLC(4.26%) URBAN FORESTERS, LLC (0.44%)
|
| Contract # |
08113209 |
|
Totals |
11301777.00 |
798871.82 |
849871.82 |
7.5 |
|
| County | BRAZORIA |
| Highway |
FM 1462 |
| From |
AT CHOCOLATE BAYOU |
| To |
(STR #10) |
| CSJ |
1414-03-034 |
| Proj ID |
BR 1102(314) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.169 |
1489044.36 |
150736.32 |
342087.32 |
22.9 |
| Work Order |
10-13-11 |
| Work Began |
11-07-11 |
| Work Completed |
|
| Time Computed |
10-29-11 |
| Contract Working Days |
114 |
| Addl Days Granted |
0 |
| Working Days Charged |
29 |
| Percent Time Used |
25 |
| Contractor(s) |
| LONE STAR ROAD CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1414-03-034 CHERRY CRUSHED CONCRETE(0.64%) ENVIRONMENTAL ALLIES, L.P. (0.81%) HIGHWAY TECHNOLOGIES, INC. (0.28%) KOSSMAN CONTRACTING COMPANY(0.98%) REGIONAL TRAFFIC SERVICES, LLC (0.89%) SCOTT DERR PAINTING CO, LLC(0.21%) THIRD COAST SERVICES, LLC(0.94%) VALLEY PLACERS, LLC(0.52%) HOUSTON SAWING & DRILLING(0.21%) GMJ PAVING CO. (7.76%) JMHP, INC. (1.01%) CPAVE, INC.(0.08%)
|
| Contract # |
08113055 |
|
Totals |
1489044.36 |
150736.32 |
342087.32 |
22.9 |
|
| County | FORT BEND |
| Highway |
FM 1464 |
| From |
SHILOH LAKES DR |
| To |
SH 99 |
| CSJ |
1415-02-040 |
| Proj ID |
STP 2009(703)ES |
| Work Type |
GR, STRS BASE & SURF |
| |
|
2.724 |
13611377.00 |
821134.25 |
11374762.62 |
83.5 |
| Work Order |
04-14-10 |
| Work Began |
06-14-10 |
| Work Completed |
|
| Time Computed |
04-30-10 |
| Contract Working Days |
393 |
| Addl Days Granted |
85 |
| Working Days Charged |
456 |
| Percent Time Used |
95 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1415-02-040 EMBARK (0.21%) BATTERSON, L.L.P.(1.71%) CHAMPIONS HYDROLAWN(0.93%) NBG CONSTRUCTORS, INC. ( 16.22%) SEMARCK LANDSCAPE SERVICES, INC. (0.21%) RDI FOUNDATION DRILLING(0.68%) CHERRY DEMOLITION(0.09%) ORP CONSTRUCTION (0.41%) BREDA COMPANY, INC.(0.77%) CURB PLANET INC. (0.20%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.90%) GMJ PAVING CO. (8.33%) JMHP, INC. (0.18%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.45%) SCOTT DERR PAINTING CO (0.02%) HOUSTON SAWING & DRILLING(0.02%) SAN JACINTO BORING & TUNNELING, INC. (0.15%) MICKIE SERVICE, INC. (0.07%) EROSION PREVENTION PRODUCTS(0.23%)
|
| Contract # |
02103203 |
|
Totals |
13611377.00 |
821134.25 |
11374762.62 |
83.5 |
|
| County | BRAZORIA |
| Highway |
SH 332 |
| From |
0.373 MI N OF THIS WAY STREET |
| To |
0.196 MI S OF THIS WAY STREET |
| CSJ |
1524-01-041 |
| Proj ID |
NH 2009(399) |
| Work Type |
GR, STRS, LTS, CSB & CONC PAVT |
| |
|
4.735 |
63360228.52 |
1009580.98 |
57388698.35 |
90.5 |
| Work Order |
05-06-09 |
| Work Began |
06-22-09 |
| Work Completed |
|
| Time Computed |
05-22-09 |
| Contract Working Days |
963 |
| Addl Days Granted |
0 |
| Working Days Charged |
766 |
| Percent Time Used |
79 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1524-01-041 VAQUERO CONSTRUCTION, INC. (0.65%) CURB PLANET INC. (0.07%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.96%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.39%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.69%) EROSION CONTROL, INC.(0.72%) SCOTT DERR PAINTING CO (0.61%) JOE VALENCIK, INC. (0.41%) INDUS CONSTRUCTION, L.P. ( 10.64%) TREVCON, INC.(0.51%) BATTERSON,LLP(0.42%)
|
| Contract # |
03093226 |
|
Totals |
63360228.52 |
1009580.98 |
57388698.35 |
90.5 |
|
| County | GALVESTON |
| Highway |
FM 1764 |
| From |
SH 146 |
| To |
14TH STREET |
| CSJ |
1607-01-049 |
| Proj ID |
STP 1102(326) |
| Work Type |
MILL, CAM, O / L, CURB REP |
| |
|
1.990 |
1219291.07 |
0.00 |
0.00 |
0.0 |
| Work Order |
09-14-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1607-01-049 HIGHWAY TECHNOLOGIES, INC. (6.59%) THIRD COAST SERVICES, LLC(5.09%)
|
| Contract # |
08113259 |
|
Totals |
1219291.07 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
FM 1960 |
| From |
AT E DENTON |
| To |
. |
| CSJ |
1685-03-090 |
| Proj ID |
STP 1102(145)HES |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.002 |
332396.25 |
400.00 |
251333.75 |
75.6 |
| Work Order |
08-16-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-01-11 |
| Contract Working Days |
98 |
| Addl Days Granted |
0 |
| Working Days Charged |
54 |
| Percent Time Used |
55 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1685-03-090 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07113006 |
|
Totals |
332396.25 |
400.00 |
251333.75 |
75.6 |
|
| County | HARRIS |
| Highway |
SH 6 |
| From |
BELLAIRE BLVD FROM 900 FT W OF SH 6 |
| To |
595 FT E OF SH 6 |
| CSJ |
1685-05-089 |
| Proj ID |
CM 1102(066) |
| Work Type |
INT IMPRUMTS |
| |
|
0.284 |
1308626.44 |
189362.90 |
1309625.34 |
99.9 |
| Work Order |
08-25-11 |
| Work Began |
09-26-11 |
| Work Completed |
|
| Time Computed |
09-10-11 |
| Contract Working Days |
49 |
| Addl Days Granted |
0 |
| Working Days Charged |
49 |
| Percent Time Used |
100 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-089 REGIONAL TRAFFIC SERVICES, LLC (4.33%) THIRD COAST SERVICES, LLC(3.50%) CHERRY CONCRETE REMOVAL(1.36%) GMJ PAVING CO. ( 11.51%) HIGHWAY PAVEMENT SPECIALTIES, INC. (1.00%) HOUSTON TREE FARM(0.11%) H & H CURB COMPANY (0.15%) CHAMPIONS HYDRO-LAWN (0.38%)
|
| Contract # |
06113040 |
|
Totals |
1308626.44 |
189362.90 |
1309625.34 |
99.9 |
|
| County | HARRIS |
| Highway |
SH 6 |
| From |
AT PIPING ROCK |
| To |
. |
| CSJ |
1685-05-101 |
| Proj ID |
STP 1102(315)HESG |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.002 |
256046.10 |
0.00 |
10727.05 |
4.1 |
| Work Order |
09-13-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-29-11 |
| Contract Working Days |
81 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STATEWIDE TRAFFIC SIGNAL COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-101 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08113261 |
|
Totals |
256046.10 |
0.00 |
10727.05 |
4.1 |
|
| County | FORT BEND |
| Highway |
FM 2218 |
| From |
US 59 |
| To |
FM 1640 |
| CSJ |
2093-01-009 |
| Proj ID |
STP 2008(050)MM |
| Work Type |
GR, STRS, BASE & SURF |
| |
|
2.310 |
14284407.38 |
838718.48 |
9239253.51 |
64.6 |
| Work Order |
07-22-10 |
| Work Began |
10-11-10 |
| Work Completed |
|
| Time Computed |
09-20-10 |
| Contract Working Days |
552 |
| Addl Days Granted |
0 |
| Working Days Charged |
377 |
| Percent Time Used |
68 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2093-01-009 HURTADO CONSTRUCTION COMPANY ( 13.80%) BATTERSON,LLP(1.84%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.36%) BREDA COMPANY, INC.(0.70%) GMJ PAVING CO. (6.95%) FLORIDA TRAFFIC CONTROL DEVICES, INC.(9.09%) H & H CURB COMPANY (0.15%) CHAMPIONS HYDROLAWN(0.84%) JMHP, INC. (0.07%) R & A BORING COMPANY (1.10%) EROSION PREVENTION PRODUCTS(0.23%) CHERRY CONCRETE REMOVAL(0.11%) WEBBER-BALKE FOUNDATION COMPANY, INC.(0.30%)
|
| Contract # |
05103002 |
|
Totals |
14284407.38 |
838718.48 |
9239253.51 |
64.6 |
|