|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HARRIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
. |
| CSJ |
0912-72-180 |
| Proj ID |
STP 2012(148) |
| Work Type |
FULL DEPTH REPAIR & BRIDGE REPAIR |
| |
|
0.001 |
1464291.55 |
10500.00 |
1396665.81 |
100.0 |
| Work Order |
01-26-12 |
| Work Began |
04-01-12 |
| Work Completed |
04-18-13 |
| Time Computed |
02-11-12 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
249 |
| Percent Time Used |
97 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-180 MAIN LANE INDUSTRIES, LTD. ( 15.83%) HIGHWAY TECHNOLOGIES, INC. (1.10%) HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP. (8.37%)
|
| Contract # |
12113214 |
|
Totals |
1464291.55 |
10500.00 |
1396665.81 |
100.0 |
|
| County | HARRIS |
| Highway |
VA |
| From |
VAR LOCATIONS IN CENTRAL HOUSTON |
| To |
. |
| CSJ |
0912-72-213 |
| Proj ID |
NH 2012(067) |
| Work Type |
REHAB AND OTHER MISC. WORK |
| |
|
0.001 |
1887399.75 |
0.00 |
1822867.28 |
99.5 |
| Work Order |
11-16-11 |
| Work Began |
01-10-12 |
| Work Completed |
|
| Time Computed |
12-02-11 |
| Contract Working Days |
238 |
| Addl Days Granted |
0 |
| Working Days Charged |
329 |
| Percent Time Used |
138 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-213 HIGHWAY TECHNOLOGIES, INC. (1.67%) MB WESTERN INDUSTRIAL CONTRACTING(1.87%) KOSSMAN CONTRACTING CO., INC.(0.43%) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(1.73%) JASSO"S SAWING & SEALING (1.54%) ROMAR UNLIMITED, INC.(3.05%) EPOXY DESIGN SYSTEMS, INC. (1.00%)
|
| Contract # |
10113010 |
|
Totals |
1887399.75 |
0.00 |
1822867.28 |
99.5 |
|
| County | HARRIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN HOUSTON |
| To |
. |
| CSJ |
0912-72-241 |
| Proj ID |
STP 2013(694) |
| Work Type |
SLOPE REP & CHANNEL STABILIZATION |
| |
|
0.001 |
1883747.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
274 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| NBG CONSTRUCTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-241 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133219 |
|
Totals |
1883747.00 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS ON IH 45, US 59, |
| To |
BW 8 AND FM 525 AND SH 249 |
| CSJ |
0912-72-278 |
| Proj ID |
STP 2012(514) |
| Work Type |
ARMOR JNT, SPALLED JNT & FLANGE REP |
| |
|
0.002 |
789714.28 |
2250.00 |
798964.50 |
100.0 |
| Work Order |
06-21-12 |
| Work Began |
10-29-12 |
| Work Completed |
05-03-13 |
| Time Computed |
07-07-12 |
| Contract Working Days |
54 |
| Addl Days Granted |
0 |
| Working Days Charged |
46 |
| Percent Time Used |
85 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-278 MAIN LANE INDUSTRIES, LTD. ( 55.17%) HIGHWAY TECHNOLOGIES, INC. (1.85%)
|
| Contract # |
05123046 |
|
Totals |
789714.28 |
2250.00 |
798964.50 |
100.0 |
|
| County | HARRIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
US 59,US 90A,IH 610,SH 225 ETCETERA |
| CSJ |
0912-72-287 |
| Proj ID |
STP 2012(515) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
0.001 |
2475888.05 |
185470.65 |
1185788.09 |
47.8 |
| Work Order |
07-25-12 |
| Work Began |
10-18-12 |
| Work Completed |
|
| Time Computed |
08-10-12 |
| Contract Working Days |
225 |
| Addl Days Granted |
0 |
| Working Days Charged |
167 |
| Percent Time Used |
74 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-287 THIRD COAST SERVICES LLC ( 10.39%) PROFESSIONAL TRAFFIC CONTROL, LLC(5.01%) AQUALAWN HYDROMULCH & EROSION CONTROL(1.27%)
|
| Contract # |
05123225 |
|
Totals |
2475888.05 |
185470.65 |
1185788.09 |
47.8 |
|
| County | HARRIS |
| Highway |
VA |
| From |
AT VARIOUS LOCATIONS ALONG IH 45 |
| To |
AT SH 288 IN HARRIS COUNTY |
| CSJ |
0912-72-288 |
| Proj ID |
STP 2013(460) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
0.001 |
1189354.45 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
195 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-288 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133217 |
|
Totals |
1189354.45 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
CS |
| From |
ON HEMPSTEAD, FROM WEST OF MANGUM |
| To |
BRITTMOORE RD |
| CSJ |
0912-72-293 |
| Proj ID |
C 912-72-293 |
| Work Type |
BS REP, PLANING, 2" O / L & PV_MRKS |
| |
|
8.394 |
3559738.01 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-17-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
135 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-293 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133005 |
|
Totals |
3559738.01 |
0.00 |
0.00 |
0.0 |
|
| County | GALVESTON |
| Highway |
CS |
| From |
SEAWOLF PKWY AT PELICAN ISLAND CHNL |
| To |
. |
| CSJ |
0912-73-117 |
| Proj ID |
BR 2007(366) |
| Work Type |
REHABILITATE BRIDGE |
| |
|
0.612 |
3439504.50 |
0.00 |
3968543.71 |
99.9 |
| Work Order |
05-18-11 |
| Work Began |
08-03-11 |
| Work Completed |
|
| Time Computed |
06-03-11 |
| Contract Working Days |
301 |
| Addl Days Granted |
0 |
| Working Days Charged |
287 |
| Percent Time Used |
95 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-117 ORION CONSTRUCTION, L.P. (6.38%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%) INTECH CONTRACTING LLC ( 74.13%) BRIDGES R US PAINTING CO., INC.( 36.05%)
|
| Contract # |
04113207 |
|
Totals |
3439504.50 |
0.00 |
3968543.71 |
99.9 |
|
| County | GALVESTON |
| Highway |
VA |
| From |
VARIOUS LOCATIONS |
| To |
IN GALVESTON COUNTY |
| CSJ |
0912-73-180 |
| Proj ID |
STP 1102(311) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
3.842 |
3284825.97 |
199693.65 |
1665914.18 |
51.2 |
| Work Order |
10-21-11 |
| Work Began |
11-06-11 |
| Work Completed |
|
| Time Computed |
11-06-11 |
| Contract Working Days |
254 |
| Addl Days Granted |
0 |
| Working Days Charged |
277 |
| Percent Time Used |
109 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-180 THIRD COAST SERVICES, LLC( 11.29%) WORK ZONE PRODUCTS, INC. (5.46%) KOSSMAN CONTRACTING COMPANY(1.91%) SUPERIOR LIGHTING(0.43%)
|
| Contract # |
08113036 |
|
Totals |
3284825.97 |
199693.65 |
1665914.18 |
51.2 |
|
| County | HARRIS |
| Highway |
FM 865 |
| From |
SOUTH OF BW 8 |
| To |
BRAZORIA COUNTY LINE(CLEAR CREEK) |
| CSJ |
0976-01-035 |
| Proj ID |
STP 1102(436) |
| Work Type |
CR, BS & SURF |
| |
|
1.106 |
9266318.15 |
182237.88 |
9071920.11 |
97.9 |
| Work Order |
10-27-11 |
| Work Began |
11-29-11 |
| Work Completed |
|
| Time Computed |
11-12-11 |
| Contract Working Days |
410 |
| Addl Days Granted |
0 |
| Working Days Charged |
410 |
| Percent Time Used |
100 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-035 EMBARK TREE AND LANDSCAPE SERVICES (0.35%) URBAN FORESTERS, LLC (0.34%) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(4.74%) GMJ PAVING CO. (2.40%) BREDA COMPANY, INC.(0.58%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%) BATTERSON,LLP(1.10%) CHAMPIONS HYDROLAWN(0.33%) JMHP, INC. (0.05%) H & H CURB COMPANY (0.11%) NBG CONSTRUCTORS, INC. ( 22.94%) WEBBER-BALKE FOUNDATION COMPANY, INC.(2.39%) MESA ROD BUSTERS, INC. (0.00%) CHERRY CONCRETE REMOVAL(0.26%) DORAN STEEL, INC.(0.04%) WALLACE CONCRETE SAWING(0.06%)
|
| Contract # |
08113207 |
|
Totals |
9266318.15 |
182237.88 |
9071920.11 |
97.9 |
|
| County | BRAZORIA |
| Highway |
FM 865 |
| From |
SOUTH OF HARRIS COUNTY LINE |
| To |
FM 518 |
| CSJ |
0976-02-085 |
| Proj ID |
STP 2009(283) |
| Work Type |
GR, BS & SURF |
| |
|
1.915 |
13267224.77 |
164800.00 |
12695564.86 |
95.6 |
| County | BRAZORIA |
| Highway |
FM 865 |
| From |
SOUTH OF HARRIS COUNTY LINE |
| To |
FM 518 |
| CSJ |
0976-02-087 |
| Proj ID |
RW 976-2-87 |
| Work Type |
ROW ACQ. AND UTL. ADJ. |
| |
|
0.001 |
394560.47 |
0.00 |
303926.38 |
77.0 |
| Work Order |
04-09-09 |
| Work Began |
05-05-09 |
| Work Completed |
|
| Time Computed |
04-25-09 |
| Contract Working Days |
459 |
| Addl Days Granted |
146 |
| Working Days Charged |
562 |
| Percent Time Used |
92 |
| Contractor(s) |
| HASSELL CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0976-02-085 HIGHWAY TECHNOLOGIES, INC. (1.51%) GMJ PAVING CO. (4.67%) PROTECTIVE ENVIRONMENTAL STRATEGIES, INC.(0.70%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27%) CREACOM, INC.(6.36%) CHERRY CRUSHED CONCRETE(4.42%) SPECIALTY DRILLING (0.58%) SCOTT DERR PAINTING CO (0.00%) BECO CONSTRUCTION, L.L.C.(0.21%) NBG CONSTRUCTORS, INC. ( 17.22%) MAGNUM TUNNELING, LLC(0.10%) MICKIE SERVICE, INC. (0.01%) BECO CONSTRUCTION, L.L.C.(4.69%) OATES INDUSTRIES, INC. (0.20%) FLORES CURBS (0.10%)
|
| Contract # |
02093201 |
|
Totals |
13661785.24 |
164800.00 |
12999491.24 |
95.1 |
|
| County | GALVESTON |
| Highway |
FM 646 |
| From |
GRAND AVE |
| To |
9TH STREET |
| CSJ |
0978-02-068 |
| Proj ID |
STP 2013(544) |
| Work Type |
BS REPR, PLAN & ACP O / L |
| |
|
3.685 |
847434.15 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DURWOOD GREENE CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-068 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04133017 |
|
Totals |
847434.15 |
0.00 |
0.00 |
0.0 |
|
| County | BRAZORIA |
| Highway |
FM 523 |
| From |
AT CR 226/STRATTON RIDGE NB & SB |
| To |
AND AT CR 792/SUGGS SB |
| CSJ |
1003-01-090 |
| Proj ID |
STP 2013(244)MM |
| Work Type |
INSTALL LEFT TURN LANES |
| |
|
0.582 |
481934.13 |
0.00 |
424245.20 |
88.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-08-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
29 |
| Percent Time Used |
85 |
| Contractor(s) |
| FORDE CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1003-01-090 HIGHWAY TECHNOLOGIES, INC. (5.74%) RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(7.06%) JMHP, INC. (0.95%) AQUALAWN HYDROMULCH & EROSION CONTROL(2.81%)
|
| Contract # |
12123208 |
|
Totals |
481934.13 |
0.00 |
424245.20 |
88.0 |
|
| County | BRAZORIA |
| Highway |
FM 524 |
| From |
FM 521 |
| To |
CR 334 |
| CSJ |
1004-01-052 |
| Proj ID |
STP 2012(519) |
| Work Type |
UPGRADE DRAINAGE STRUCTURES |
| |
|
3.176 |
249163.00 |
0.00 |
196910.46 |
89.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-09-12 |
| Work Began |
08-17-12 |
| Work Completed |
|
| Time Computed |
07-25-12 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
75 |
| Percent Time Used |
250 |
| Contractor(s) |
| NNA FINANCIAL SERVICES CO. |
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-052 HIGHWAY TECHNOLOGIES, INC. (1.41%)
|
| Contract # |
05123213 |
|
Totals |
249163.00 |
0.00 |
196910.46 |
89.6 |
|
| County | HARRIS |
| Highway |
FM 525 |
| From |
AT HARDY ROAD |
| To |
. |
| CSJ |
1005-01-041 |
| Proj ID |
STP 2012(520)HES |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.001 |
213760.65 |
25290.30 |
25290.30 |
11.8 |
| Work Order |
06-18-12 |
| Work Began |
04-13-13 |
| Work Completed |
|
| Time Computed |
07-04-12 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
1 |
| Percent Time Used |
3 |
| Contractor(s) |
| SIEMENS INDUSTRY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1005-01-041 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05123236 |
|
Totals |
213760.65 |
25290.30 |
25290.30 |
11.8 |
|
| County | HARRIS |
| Highway |
FM 529 |
| From |
FREEMAN ROAD |
| To |
W OF FRY ROAD |
| CSJ |
1006-01-059 |
| Proj ID |
NH 2012(474) |
| Work Type |
GR, STRS, BASE AND SURF |
| |
|
1.184 |
7690213.53 |
1000.00 |
1048640.12 |
13.6 |
| Work Order |
01-31-13 |
| Work Began |
03-15-13 |
| Work Completed |
|
| Time Computed |
02-16-13 |
| Contract Working Days |
322 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-059 HIGHWAY TECHNOLOGIES, INC. (0.79%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.96%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.42%) TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.77%)
|
| Contract # |
10123217 |
|
Totals |
7690213.53 |
1000.00 |
1048640.12 |
13.6 |
|
| County | HARRIS |
| Highway |
FM 529 |
| From |
GREENHOUSE RD |
| To |
US 290 |
| CSJ |
1006-01-068 |
| Proj ID |
C 1006-1-68 |
| Work Type |
ACCESS MANAGEMENT |
| |
|
8.050 |
1457279.03 |
54050.47 |
1402200.16 |
97.3 |
| Work Order |
09-24-12 |
| Work Began |
11-19-12 |
| Work Completed |
|
| Time Computed |
10-10-12 |
| Contract Working Days |
88 |
| Addl Days Granted |
0 |
| Working Days Charged |
112 |
| Percent Time Used |
127 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-068 A-1 HYDRO-MULCHING OF TEXAS, INC.(0.60%) AMCO LANDSCAPING & IRRIGATION, INC.(1.02%) CURBS, INC.(3.16%) HIGHWAY TECHNOLOGIES, INC. ( 22.32%) HOLES INCORPORATED (6.14%) SPEEDY PAVING( 10.93%) THIRD COAST SERVICES LLC (0.34%) RANDY"S ROAD BOARING (0.58%) CURB BUILDERS, LLC (3.16%)
|
| Contract # |
08123233 |
|
Totals |
1457279.03 |
54050.47 |
1402200.16 |
97.3 |
|
| County | HARRIS |
| Highway |
FM 2100 |
| From |
FM 1960 (GUY ROAD) |
| To |
0.066 M. S OF HUFFMAN-CLEVELAND RD |
| CSJ |
1062-02-023 |
| Proj ID |
STP 2013(696) |
| Work Type |
MILL & ACP OVERLAY |
| |
|
12.426 |
5966662.66 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
186 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-023 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133003 |
|
Totals |
5966662.66 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
FM 1485 |
| From |
AT HUFFMAN NEW CANEY RD WESTBOUND |
| To |
. |
| CSJ |
1062-02-024 |
| Proj ID |
STP 2012(604)MM |
| Work Type |
ADD LT TN LN |
| |
|
1.139 |
987119.10 |
14829.08 |
974242.52 |
99.9 |
| Work Order |
10-12-12 |
| Work Began |
11-06-12 |
| Work Completed |
|
| Time Computed |
10-28-12 |
| Contract Working Days |
80 |
| Addl Days Granted |
0 |
| Working Days Charged |
104 |
| Percent Time Used |
130 |
| Contractor(s) |
| MAIN LANE INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-024 COWBELL TRAFFIC SERVICES, INC. (0.42%) REGIONAL TRAFFIC SERVICES LLC(4.39%) ROADSAFE TRAFFIC SYSTEMS, INC. (0.54%) ENVIRONMENTAL ALLIES, L.P. (2.55%) NORTHWEST MATERIALS(0.42%) JMHP, INC. (1.40%)
|
| Contract # |
06123210 |
|
Totals |
987119.10 |
14829.08 |
974242.52 |
99.9 |
|
| County | HARRIS |
| Highway |
FM 2100 |
| From |
DIAMONDHEAD BLVD. |
| To |
0.14 MI S. OF FIRST STREET |
| CSJ |
1062-04-047 |
| Proj ID |
STP 2010(903)RGS |
| Work Type |
CONST RR GRADE SEPARATION STR & APP |
| |
|
0.870 |
8537094.26 |
457241.27 |
8243299.26 |
96.5 |
| County | HARRIS |
| Highway |
FM 2100 |
| From |
DIAMONDHEAD BLVD. |
| To |
0.14 MILE SOUTH OF FIRST STREET |
| CSJ |
1062-04-051 |
| Proj ID |
STP 2011(543)ES |
| Work Type |
UTILITY ADJUSTMENT |
| |
|
0.870 |
335846.50 |
0.00 |
564880.47 |
99.9 |
| Work Order |
09-01-10 |
| Work Began |
11-28-11 |
| Work Completed |
|
| Time Computed |
09-17-10 |
| Contract Working Days |
455 |
| Addl Days Granted |
0 |
| Working Days Charged |
412 |
| Percent Time Used |
90 |
| Contractor(s) |
| NBG CONSTRUCTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-047 ALLSTATE SIGNAL & CONSTRUCTION, LLC(2.70%) BATTERSON,LLP(0.79%) HASSELL CONSTRUCTION COMPANY, INC. ( 48.33%) HOUSTON SAWING & DRILLING(0.09%) JTB SERVICES (0.33%) KOSSMAN CONTRACTING CO., INC.(0.23%) REPUBLIC TRAFFIC SAFETY, INC.(0.43%) SCOTT DERR PAINTING CO, LLC(0.26%) WEBBER-BALKE FOUNDATION COMPANY, INC.(2.70%) MICKIE SERVICE, INC. (0.10%) SAN JACINTO BORING & TUNNELING, INC. (0.23%) SOUTHERN CRUSHED CONCRETE LLC(0.31%) PM CONSTRUCTION & REHAB, LLC (1.62%) JMHP, INC. (0.52%) GMJ PAVING CO. (3.78%) BREDA COMPANY, INC.(0.61%) H & H CURB COMPANY (0.09%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.31%) ENVIRONMENTAL ALLIES, L.P. (0.24%) DORAN STEEL, INC.(0.18%) LOPEZ UTILITIES, LLC (0.23%) R & A BORING COMPANY (0.30%)
|
| Contract # |
07103015 |
|
Totals |
8872940.76 |
457241.27 |
8808179.73 |
99.2 |
|