Monthly State Let Construction Report For Houston District As Of May 10, 2016 Page 7 Of 10

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway CR
From CR 48, BROADWAY (FM 518)
To CR 894
CSJ 0912-31-294
Proj ID STP 2015(612)MM
Work Type WIDEN FROM 2 TO 4 - LANE DIVIDED
 
1.944 12154201.39 315551.40 8130408.60 66.8
Work Order 04-10-15
Work Began 06-09-15
Work Completed  
Time Computed 06-09-15
Contract Working Days 357
Addl Days Granted 3
Working Days Charged 187
Percent Time Used 51
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-294
CPAVE, INC.(0.04%)
GEORGE MEEKS LANDPRO, INC. (0.89%)
GMJ PAVING CO. (3.06%)
MESA ROD BUSTERS, INC. (6.36%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41%)
SCOTT DERR PAINTING CO (0.04%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49%)
TEXAS CLEARING AND LEVELING(0.40%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.58%)
W. W. FOUNDATION DRILLING, LTD.(3.10%)
MBN ENTERPRISES LLC(2.49%)
WEBBER BARRIER SERVICES, LLC.(0.22%)
DNA TRUCKING, INC. (0.20%)
CURB PLANET INC. (0.03%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
SOUTHERN CRUSHED CONCRETE LLC(1.11%)
Contract # 02153002
Totals 12154201.39 315551.40 8130408.60 66.8

CountyBRAZORIA
Highway VA
From LOCATIONS IN LAKE JACKSON
To .
CSJ 0912-31-301
Proj ID STP 1602(077)
Work Type LANDSCAPE DEVELOPMENT
 
0.500 1098524.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-301
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163227
Totals 1098524.00 0.00 0.00 0.0

CountyFORT BEND
Highway CS
From WEST AIRPORT - FROM US 59
To 800 FEET WEST OF KIRKWOOD DRIVE
CSJ 0912-34-130
Proj ID HP 2011(793)
Work Type RECONSTRUCTION OF WEST AIRPORT
 
0.695 4192145.17 0.00 3967302.61 95.5
Work Order 03-12-14
Work Began 05-28-14
Work Completed  
Time Computed 05-10-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 117
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-130
CHERRY CRUSHED CONCRETE(0.99%)
REGIONAL TRAFFIC SERVICES LLC(1.27%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(6.68%)
ABLE PAVING(0.52%)
HODGES BROTHERS, INC.(0.81%)
DORAN STEEL, INC.(0.19%)
CURB PLANET INC. (0.15%)
JASSO"S SAWING & SEALING (0.10%)
KOSSMAN CONTRACTING CO., INC.(0.35%)
A-1 EROSION CONTROL, LLC (0.38%)
MICKIE SERVICE, INC. (0.33%)
Contract # 01143211
Totals 4192145.17 0.00 3967302.61 95.5

CountyFORT BEND
Highway CS
From TRAMMEL FRESNO RD, FORT BEND PKWY
To FM 521
CSJ 0912-34-144
Proj ID STP 2010(596)MM
Work Type GR, STR, BASE AND 0AVE
 
3.041 20864455.45 5000.00 4070902.46 19.5
Work Order 03-03-15
Work Began 03-24-15
Work Completed  
Time Computed 03-19-15
Contract Working Days 622
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 4
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC.(0.72%)
RICE ENVIRONMENTAL SERVICES(0.24%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(1.96%)
INDUS CONSTRUCTION, L.P. (3.85%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.17%)
BASE CONSTRUCTION, L.L.P.( 23.02%)
KMA CONTRACTORS SERVICES INC.(4.77%)
Contract # 12143003
Totals 20864455.45 5000.00 4070902.46 19.5

CountyFORT BEND
Highway CR ETC
From MEYER ROAD AT SNAKE CREEK TRIBUTARY
To .
CSJ 0912-34-176
Proj ID BR 2013(735)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.712 2828589.45 80898.00 1958917.06 69.2
Work Order 08-04-15
Work Began 09-08-15
Work Completed  
Time Computed 09-08-15
Contract Working Days 321
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 46
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55%)
REGIONAL TRAFFIC SERVICES LLC(0.40%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45%)
ODUM SERVICES, L.P.(1.77%)
MESA ROD BUSTERS, INC. (0.19%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.98%)
EROSION PREVENTION PRODUCTS(4.81%)
Contract # 06153027
Totals 2828589.45 80898.00 1958917.06 69.2

CountyFORT BEND
Highway CS
From ON HURRICANE LANE/LAKE OLYMPIA;FROM
To TRAMMEL FRESNO RD TO FT BEND PKWY
CSJ 0912-34-182
Proj ID STP 1302(010)MM
Work Type CONST 2 LN CONC RDWYS
 
1.393 6588849.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-182
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163030
Totals 6588849.40 0.00 0.00 0.0

CountyFORT BEND
Highway VA
From VARIOUS LOCATIONS ALONG: US 59,
To SH 6, AND US 90A
CSJ 0912-34-187
Proj ID C 912-34-187
Work Type INSTALLATION OF DMS
 
0.001 992940.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163213
Totals 992940.68 0.00 0.00 0.0

CountyMONTGOMERY
Highway CR
From KUYKENDAHL RD; ALDEN BRIDGE
To CROWNRIDGE DR
CSJ 0912-37-140
Proj ID STP 2002(643)UM
Work Type CONST 2 LANE RDWY
 
0.485 2496548.44 0.00 2475985.32 99.9
Work Order 06-30-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 78
Addl Days Granted 44
Working Days Charged 179
Percent Time Used 146
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-140
ABC EROSION CONTROL, INC.(0.66%)
LANDSCAPING CONTRACTING & IRRIGATION (1.93%)
STRIPE-A-LINE, INC.(0.21%)
THIRD COAST SERVICES LLC ( 10.75%)
W. W. FOUNDATION DRILLING, LTD.(4.79%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(1.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%)
BREDA COMPANY, INC.(0.70%)
MESA ROD BUSTERS, INC. (0.18%)
HOUSTON SAWING & DRILLING(0.07%)
WILLOW CITY SIGN & RAIL, INC.(0.82%)
APCON SERVICES, LLC(0.73%)
SAND HILL FOUNDATION, LLC(1.21%)
ABC DIRECTIONAL DRILLING, INC. (1.45%)
CPAVE, INC.(0.25%)
COASTAL FOUNDATION DRILLING CO., INC.(0.00%)
TNT CRANE & RIGGING, INC.(0.00%)
Contract # 05143027
Totals 2496548.44 0.00 2475985.32 99.9

CountyMONTGOMERY
Highway VA
From VARIOUS LOCATIONS ON IH 45 & SH 105
To .
CSJ 0912-37-226
Proj ID STP 2016(472)
Work Type BASE REPAIR AND PAVEMENT LEVELING
 
0.053 766066.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTEX CONCRETE LIFT & STABILIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-226
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163211
Totals 766066.00 0.00 0.00 0.0

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 0.00 406205.26 91.0
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 60
Addl Days Granted 25
Working Days Charged 167
Percent Time Used 196
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP( 14.72%)
LANDPRO, INC.(4.34%)
TITAN 360 INDUSTRIAL SERVICES(8.99%)
Contract # 07143054
Totals 499113.96 0.00 406205.26 91.0

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 0.00 2026823.50 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 216
Percent Time Used 103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
BIO LANDSCAPE & MAINTENANCE, INC.( 65.42%)
HOGGATT, LP(5.46%)
EVERY SECOND COUNTS (ESC)(5.69%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48%)
MIKELS CONSTRUCTION CO., INC.(2.51%)
PUMPS, MOTORS & CONTROLS (0.04%)
STRIPE LINES, INC. (0.15%)
Contract # 06133013
Totals 2581444.90 0.00 2026823.50 78.7

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 4715.10 745227.86 91.9
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 91
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 4715.10 745227.86 91.9

CountyHARRIS
Highway CS
From WESTERLAND DRIVE; AT HCFCD DITCH
To .
CSJ 0912-70-091
Proj ID BR 2014(555)
Work Type REPL BR & APPR
 
0.163 1844818.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163016
Totals 1844818.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN CENTRAL
To HOUSTON AREA
CSJ 0912-70-094
Proj ID STP 2015(317)
Work Type BRIDGE MAINTENANCE WORK
 
0.001 1698653.40 2310.17 2218493.35 99.9
Work Order 01-02-15
Work Began 04-25-15
Work Completed  
Time Computed 04-25-15
Contract Working Days 304
Addl Days Granted 16
Working Days Charged 217
Percent Time Used 67
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
IOWA BRIDGE & CULVERT, LC( 21.67%)
JTB SERVICES (2.42%)
THIRD COAST SERVICES LLC (2.83%)
TX TINMAN ENTERPRISES, LLC.(5.80%)
AARON CONCRETE CONTRACTORS, L.P. (1.59%)
HOUSTON SAWING & DRILLING(1.05%)
HOLES INCORPORATED (1.58%)
Contract # 11143212
Totals 1698653.40 2310.17 2218493.35 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 25476.03 2122734.77 79.5
Work Order 07-02-14
Work Began 10-27-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 343
Percent Time Used 140
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE ( 12.07%)
THIRD COAST SERVICES LLC (9.66%)
STRIPE-A-LINE, INC.(2.31%)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44%)
GLOBE ELECTRIC SUPPLY COMPANY, INC.(2.65%)
GEORGE MEEKS LANDPRO, INC. (3.02%)
TEXAS CONCRETE AND DEMOLITION, INC.(8.51%)
Contract # 05143031
Totals 2767522.72 25476.03 2122734.77 79.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-100
Proj ID STP 2015(613)
Work Type CONST CURB RAMPS
 
0.001 3140223.08 190632.08 2136593.13 68.6
Work Order 03-23-15
Work Began 03-07-16
Work Completed  
Time Computed 04-08-15
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-100
BATTERSON,LLP(4.08%)
A-1 EROSION CONTROL, LLC (0.84%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.75%)
STRIPE-A-LINE, INC.(0.00%)
Contract # 02153020
Totals 3140223.08 190632.08 2136593.13 68.6

CountyHARRIS
Highway CR
From IH 69 S, FROM HAZARD STREET
To MONTROSE BLVD
CSJ 0912-70-105
Proj ID STP 2014(128)TE
Work Type INST BR LIGHT
 
0.250 3061039.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163247
Totals 3061039.35 0.00 0.00 0.0

CountyHARRIS
Highway CS
From VARIOUS LOCATION IN HARRIS COUNTY
To PRECINCT 1
CSJ 0912-71-046
Proj ID C 912-71-46
Work Type HARRIS COUNTY PRECINCT 1 RCTSS
 
0.001 4241559.87 248618.55 1995570.46 47.0
Work Order 10-28-14
Work Began 11-13-14
Work Completed  
Time Computed 11-13-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 55
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
ABC DIRECTIONAL DRILLING, INC. (4.67%)
SCMU ( 11.94%)
Contract # 08143027
Totals 4241559.87 248618.55 1995570.46 47.0

CountyHARRIS
Highway VA
From VARIOUS
To .
CSJ 0912-71-627
Proj ID CM 99(570)
Work Type RCTSS PGM - IMPR TRAF CNTL DEV
 
0.001 2119996.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 285
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-627
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153034
Totals 2119996.95 0.00 0.00 0.0

CountyHARRIS
Highway VA
From KEEGANS BAYOU TRAIL: GESSNER
To KIRKWOOD
CSJ 0912-71-631
Proj ID CM 99(567)
Work Type HIKE AND BIKE TRAIL
 
4.034 5688316.22 2260.50 4862173.36 85.4
Work Order 10-18-12
Work Began 09-16-13
Work Completed  
Time Computed 01-16-13
Contract Working Days 368
Addl Days Granted 0
Working Days Charged 321
Percent Time Used 87
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-631
CARMA CONSTRUCTION, LLC( 16.32%)
HIGHWAY TECHNOLOGIES, INC. (0.18%)
REGIONAL TRAFFIC SERVICES LLC(0.15%)
THIRD COAST SERVICES LLC (3.37%)
GEORGE MEEKS LANDPRO, INC. (4.04%)
SPECIALTY DRILLING, LTD. (0.53%)
ENVIRONMENTAL ALLIES, L.P. (0.94%)
Contract # 08123008
Totals 5688316.22 2260.50 4862173.36 85.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10