Monthly State Let Construction Report For Houston District As Of Dec 9, 2016 Page 7 Of 10

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFORT BEND
Highway VA
From VARIOUS LOCATIONS ALONG: US 59,
To SH 6, AND US 90A
CSJ 0912-34-187
Proj ID C 912-34-187
Work Type INSTALLATION OF DMS
 
0.001 992940.68 4035.00 21216.85 2.1
Work Order 04-07-16
Work Began 00-00-00
Work Completed  
Time Computed 05-07-16
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
MAIN LANE INDUSTRIES LTD.( 53.85%)
Contract # 02163213
Totals 992940.68 4035.00 21216.85 2.1

CountyMONTGOMERY
Highway CR
From KUYKENDAHL RD; ALDEN BRIDGE
To CROWNRIDGE DR
CSJ 0912-37-140
Proj ID STP 2002(643)UM
Work Type CONST 2 LANE RDWY
 
0.485 2496548.44 0.00 2560381.62 99.9
Work Order 06-30-14
Work Began 09-02-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 78
Addl Days Granted 59
Working Days Charged 179
Percent Time Used 130
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-140
ABC EROSION CONTROL, INC.(0.66%)
LANDSCAPING CONTRACTING & IRRIGATION (1.93%)
STRIPE-A-LINE, INC.(0.21%)
THIRD COAST SERVICES LLC ( 10.75%)
W. W. FOUNDATION DRILLING, LTD.(4.79%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(1.21%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%)
BREDA COMPANY, INC.(0.70%)
MESA ROD BUSTERS, INC. (0.18%)
HOUSTON SAWING & DRILLING(0.07%)
WILLOW CITY SIGN & RAIL, INC.(0.82%)
APCON SERVICES, LLC(0.73%)
SAND HILL FOUNDATION, LLC(1.21%)
ABC DIRECTIONAL DRILLING, INC. (1.45%)
CPAVE, INC.(0.25%)
COASTAL FOUNDATION DRILLING CO., INC.(0.00%)
TNT CRANE & RIGGING, INC.(0.00%)
Contract # 05143027
Totals 2496548.44 0.00 2560381.62 99.9

CountyHARRIS
Highway CS
From AT ALICE JOHNSON JR HIGH SCHOOL
To .
CSJ 0912-70-067
Proj ID STP 1602(474)SRS
Work Type PEDESTRIAN WAY / SIDEWALKS
 
0.320 582538.50 315688.60 355213.60 60.9
Work Order 09-19-16
Work Began 10-24-16
Work Completed  
Time Computed 11-18-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 55
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163029
Totals 582538.50 315688.60 355213.60 60.9

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 0.00 406205.26 91.0
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 60
Addl Days Granted 25
Working Days Charged 167
Percent Time Used 196
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP( 14.72%)
LANDPRO, INC.(4.34%)
TITAN 360 INDUSTRIAL SERVICES(8.99%)
Contract # 07143054
Totals 499113.96 0.00 406205.26 91.0

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 0.00 2026823.50 78.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 216
Percent Time Used 103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
BIO LANDSCAPE & MAINTENANCE, INC.( 65.42%)
HOGGATT, LP(5.46%)
EVERY SECOND COUNTS (ESC)(5.69%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48%)
MIKELS CONSTRUCTION CO., INC.(2.51%)
PUMPS, MOTORS & CONTROLS (0.04%)
STRIPE LINES, INC. (0.15%)
Contract # 06133013
Totals 2581444.90 0.00 2026823.50 78.7

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 28396.88 801915.34 98.9
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 91
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 28396.88 801915.34 98.9

CountyHARRIS
Highway CS
From WESTERLAND DRIVE; AT HCFCD DITCH
To .
CSJ 0912-70-091
Proj ID BR 2014(555)
Work Type REPL BR & APPR
 
0.163 1844818.40 168608.00 307688.58 16.6
Work Order 08-05-16
Work Began 11-03-16
Work Completed  
Time Computed 09-05-16
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 5
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-091
SPECIALTY DRILLING, LTD. (6.22%)
HIGHWAY 1, LLC (1.64%)
Contract # 04163016
Totals 1844818.40 168608.00 307688.58 16.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS WITHIN CENTRAL
To HOUSTON AREA
CSJ 0912-70-094
Proj ID STP 2015(317)
Work Type BRIDGE MAINTENANCE WORK
 
0.001 1698653.40 100472.00 3278145.12 99.9
Work Order 01-02-15
Work Began 04-25-15
Work Completed  
Time Computed 04-25-15
Contract Working Days 304
Addl Days Granted 16
Working Days Charged 292
Percent Time Used 91
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-094
IOWA BRIDGE & CULVERT, LC( 21.67%)
JTB SERVICES (2.42%)
THIRD COAST SERVICES LLC (2.83%)
TX TINMAN ENTERPRISES, LLC.(5.80%)
AARON CONCRETE CONTRACTORS, L.P. (1.59%)
HOUSTON SAWING & DRILLING(1.05%)
HOLES INCORPORATED (1.58%)
Contract # 11143212
Totals 1698653.40 100472.00 3278145.12 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 0.00 2122734.77 79.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-02-14
Work Began 10-27-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 343
Percent Time Used 140
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
ONE WAY CONCRETE ( 12.07%)
THIRD COAST SERVICES LLC (9.66%)
STRIPE-A-LINE, INC.(2.31%)
AAA TREASURE INTERNATIONAL COMPANY, INC. (6.44%)
GLOBE ELECTRIC SUPPLY COMPANY, INC.(2.65%)
GEORGE MEEKS LANDPRO, INC. (3.02%)
TEXAS CONCRETE AND DEMOLITION, INC.(8.51%)
Contract # 05143031
Totals 2767522.72 0.00 2122734.77 79.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-100
Proj ID STP 2015(613)
Work Type CONST CURB RAMPS
 
0.001 3140223.08 0.00 2691000.42 86.2
Work Order 03-23-15
Work Began 03-07-16
Work Completed  
Time Computed 04-08-15
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 109
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-100
BATTERSON,LLP(4.08%)
A-1 EROSION CONTROL, LLC (0.84%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(9.75%)
STRIPE-A-LINE, INC.(0.00%)
Contract # 02153020
Totals 3140223.08 0.00 2691000.42 86.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To ALONG FM 1960
CSJ 0912-70-101
Proj ID NH 2017(160)
Work Type CONST CURB RAMPS
 
0.001 2708928.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163026
Totals 2708928.95 0.00 0.00 0.0

CountyHARRIS
Highway CS
From MASON PARK PED/BIKE BRG, FROM TIPPS
To ST AT EVERGREEN DR TO 75TH ST
CSJ 0912-70-103
Proj ID STP 2015(559)TE
Work Type CONST PED & BIKE BR
 
0.180 5659268.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163221
Totals 5659268.00 0.00 0.00 0.0

CountyHARRIS
Highway CR
From BRAYS BAYOU, FROM MACGREGOR PARK
To UNIVERISTY OF HOUSTON (WHEELER AVE)
CSJ 0912-70-104
Proj ID STP 2016(352)TE
Work Type CONST BIKE / PED BR
 
0.480 2330231.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163055
Totals 2330231.54 0.00 0.00 0.0

CountyHARRIS
Highway CR
From IH 69 S, FROM HAZARD STREET
To MONTROSE BLVD
CSJ 0912-70-105
Proj ID STP 2014(128)TE
Work Type INST BR LIGHT
 
0.250 3061039.35 861903.20 2768539.36 90.4
Work Order 05-16-16
Work Began 09-12-16
Work Completed  
Time Computed 08-14-16
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 33
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-105
SCOTT DERR PAINTING CO, LLC(0.00%)
BUYERS BARRICADES, INC.(0.80%)
Contract # 02163247
Totals 3061039.35 861903.20 2768539.36 90.4

CountyHARRIS
Highway CS
From CAROLINE STREET;ELGIN STREET
To PIERCE STREET
CSJ 0912-71-003
Proj ID C 912-71-3
Work Type GR, STRS, BASE
 
0.689 11852823.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163207
Totals 11852823.92 0.00 0.00 0.0

CountyHARRIS
Highway CS
From VARIOUS LOCATION IN HARRIS COUNTY
To PRECINCT 1
CSJ 0912-71-046
Proj ID C 912-71-46
Work Type HARRIS COUNTY PRECINCT 1 RCTSS
 
0.001 4241559.87 180717.06 3417638.26 80.5
Work Order 10-28-14
Work Began 11-13-14
Work Completed  
Time Computed 11-13-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 87
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-046
ABC DIRECTIONAL DRILLING, INC. (4.67%)
SCMU ( 11.94%)
STRIPE LINES, INC. (1.41%)
Contract # 08143027
Totals 4241559.87 180717.06 3417638.26 80.5

CountyHARRIS
Highway CS
From MARKET ST EB AT HUNTING BAYOU
To HOUSTON
CSJ 0912-71-078
Proj ID BR 99(271)
Work Type REPLACE BRIDGE
 
0.158 1687687.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10163015
Totals 1687687.90 0.00 0.00 0.0

CountyHARRIS
Highway VA
From KEEGANS BAYOU TRAIL: GESSNER
To KIRKWOOD
CSJ 0912-71-631
Proj ID CM 99(567)
Work Type HIKE AND BIKE TRAIL
 
4.034 5688316.22 104535.45 6681754.65 99.9
Work Order 10-18-12
Work Began 09-16-13
Work Completed  
Time Computed 01-16-13
Contract Working Days 368
Addl Days Granted 0
Working Days Charged 362
Percent Time Used 98
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-631
CARMA CONSTRUCTION, LLC( 16.32%)
HIGHWAY TECHNOLOGIES, INC. (0.18%)
REGIONAL TRAFFIC SERVICES LLC(0.15%)
THIRD COAST SERVICES LLC (3.37%)
GEORGE MEEKS LANDPRO, INC. (4.04%)
SPECIALTY DRILLING, LTD. (0.53%)
ENVIRONMENTAL ALLIES, L.P. (0.94%)
Contract # 08123008
Totals 5688316.22 104535.45 6681754.65 99.9

CountyHARRIS
Highway CS
From ON SOUTH SHAVER FROM GULF FRWY
To SH 3
CSJ 0912-71-688
Proj ID STP 99(751)MM
Work Type WIDEN TO 6 LANE DIVIDED
 
1.138 13480682.20 2165.00 13372552.50 99.1
Work Order 04-23-13
Work Began 06-24-13
Work Completed  
Time Computed 06-22-13
Contract Working Days 404
Addl Days Granted 0
Working Days Charged 402
Percent Time Used 99
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-688
CPAVE, INC.(0.54%)
WILLOW CITY SIGN & RAIL, INC.(0.17%)
INDUS CONSTRUCTION, L.P. (0.73%)
APCON SERVICES, LLC(6.16%)
GMJ PAVING CO. (5.12%)
THIRD COAST SERVICES LLC (1.85%)
EAGLE CONSTRUCTION AND ENVIRONMENTAL SERVICES, L.P.(0.70%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.01%)
DUSTROL, INC.(0.54%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.03%)
STRIPES & STOPS COMPANY, INC.(0.97%)
ENVIRONMENTAL ALLIES, L.P. (0.30%)
H & E AGGREGATE, LLC (2.77%)
MCNORTON DEWATERING, INC.(0.06%)
FIRST KATY CONSTRUCTION(1.32%)
MICKIE SERVICE, INC. (0.03%)
CURB PLANET INC. (0.02%)
A1 EROSION CONTROL (1.07%)
Contract # 02133203
Totals 13480682.20 2165.00 13372552.50 99.1

CountyHARRIS
Highway CR
From BEAMER RD; W OF TALL SHIPS LN
To WEST BAY AREA BOULEVARD
CSJ 0912-71-894
Proj ID C 912-71-894
Work Type CONSTRUCT 4 - LANE BOULEVARD
 
1.343 10341416.18 25811.41 9914668.77 96.6
Work Order 01-05-15
Work Began 05-04-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 316
Percent Time Used 126
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-71-894
THIRD COAST SERVICES LLC (3.79%)
PEREZ CONSTRUCTION CO. (1.69%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.56%)
MESA ROD BUSTERS, INC. (0.69%)
DOUBLE OAK CONSTRUCTION, INC.(1.05%)
BUYERS BARRICADES, INC.(0.28%)
ENVIRONMENTAL ALLIES, L.P. (0.92%)
CONTRACTORS PAVING SUPPLY, LLP (0.42%)
ROSALES TRUCKING (0.00%)
WILLOW CITY SIGN & RAIL, INC.(0.17%)
DURWOOD GREENE CONSTRUCTION CO.(2.93%)
ROSALES TRUCKING (2.45%)
CPAVE, INC.(0.19%)
PROFESSIONAL TRAFFIC CONTROL, LLC(0.42%)
SEMARCK LANDSCAPE SERVICES, INC. (0.33%)
VALLEY PLACERS, LLC(0.01%)
SCOTT DERR PAINTING CO (0.09%)
Contract # 07143225
Totals 10341416.18 25811.41 9914668.77 96.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10