Monthly State Let Construction Report For Houston District As Of Feb 10, 2017 Page 6 Of 10

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-381
Proj IDSTP 2012(021)
Work TypeUPGRADE/RECONSTRUCT TRAFFIC SIGNALS
 
0.0011787199.581929515.6199.9
Work Order07-19-13
Work Began10-14-14
Work Completed
Time Computed08-04-13
Contract Working Days432
Addl Days Granted0
Working Days Charged382
Percent Time Used88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02)
PROFESSIONAL TRAFFIC CONTROL, LLC (2.54)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.77)
Contract #03133016
Totals1787199.58495.001929515.6199.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-413
Proj IDSTP 2013(542)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011456616.501455332.4399.9
Work Order07-08-13
Work Began11-06-13
Work Completed
Time Computed11-06-13
Contract Working Days417
Addl Days Granted0
Working Days Charged133
Percent Time Used31
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
STRIPE-A-LINE, INC. (0.12)
Contract #04133222
Totals1456616.507488.001455332.4399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-420
Proj IDSTP 2013(322)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011899903.951099921.7257.8
Work Order03-20-13
Work Began09-30-15
Work Completed
Time Computed09-16-13
Contract Working Days525
Addl Days Granted0
Working Days Charged127
Percent Time Used24
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01133213
Totals1899903.95106717.951099921.7257.8

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-00-424
Proj IDCM 1102(560)
Work TypePED & SIG IMPRVMTS IN AIRLINE DIST
 
1.3672697458.332327825.7987.6
Work Order01-23-14
Work Began04-14-14
Work Completed
Time Computed04-14-14
Contract Working Days228
Addl Days Granted0
Working Days Charged273
Percent Time Used119
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03)
ODUM SERVICES, L.P. (0.35)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (11.47)
REGIONAL TRAFFIC SERVICES LLC (2.06)
AGGREGATE TECHNOLOGIES, INC. (5.02)
SPEEDY PAVING (1.31)
AAA ASPHALT PAVING, INC. (0.00)
STRIPES & STOPS COMPANY, INC. (0.06)
PFEIFFER & SON LTD. (0.53)
Contract #10133027
Totals2697458.330.002327825.7987.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-440
Proj IDNH 2015(316)
Work TypeUPGRADE/RECONSTRUCT TRAFFIC SIGNALS
 
0.001772662.59870957.7899.9
Work Order01-16-15
Work Began10-01-15
Work Completed
Time Computed02-01-15
Contract Working Days135
Addl Days Granted0
Working Days Charged129
Percent Time Used95
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-440
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11143019
Totals772662.590.00870957.7899.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-441
Proj IDNH 2014(297)
Work TypeUPGRADE/RECONSTRUCT TRAFFIC SIGNALS
 
0.0011210347.901173894.1396.9
Work Order03-03-14
Work Began06-02-14
Work Completed
Time Computed06-02-14
Contract Working Days500
Addl Days Granted0
Working Days Charged141
Percent Time Used28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC (1.78)
Contract #12133223
Totals1210347.900.001173894.1396.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN MISSOURI CITY
To.
CSJ0912-00-488
Proj IDCM 2015(611)
Work TypeCOMMUNICATIONS/RELIABILITY URGRADE
 
0.0011394256.881360836.7197.6
Work Order11-10-15
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days180
Addl Days Granted0
Working Days Charged142
Percent Time Used78
Contractor(s)
CREACOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-488
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07153067
Totals1394256.8851152.861360836.7197.6

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS WITHIN DISTRICT
To.
CSJ0912-00-489
Proj IDNH 2014(744)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001887550.771829814.6999.9
Work Order08-13-14
Work Began09-22-14
Work Completed
Time Computed09-22-14
Contract Working Days45
Addl Days Granted9
Working Days Charged53
Percent Time Used98
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06143020
Totals887550.77417325.801829814.6999.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-511
Proj IDSTP 2017(158)
Work TypeNEW TRAFFIC SIGNALS
 
0.5081718929.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-511
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163215
Totals1718929.720.000.000.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-513
Proj IDSTP 2017(306)
Work TypeTRAFFIC SIGNAL UPGRADES
 
0.001927576.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-513
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163021
Totals927576.880.000.000.0

CountyBRAZORIA
HighwayCS
FromCR 149 AT MUSTANG BAYOU
To.
CSJ0912-31-203
Proj IDBR 2008(059)
Work TypeREPL BR & APPRS
 
0.2882748072.002729327.4599.9
Work Order09-17-12
Work Began11-26-12
Work Completed
Time Computed11-16-12
Contract Working Days270
Addl Days Granted0
Working Days Charged305
Percent Time Used112
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-203
W. W. FOUNDATION DRILLING, LTD. (9.86)
ENVIRONMENTAL ALLIES, L.P. (0.77)
JUST GROOVING, LTD. (0.03)
WILLOW CITY SIGN & RAIL, INC. (1.01)
GMJ PAVING CO. (5.09)
Contract #07123007
Totals2748072.000.002729327.4599.9

CountyBRAZORIA
HighwayCR
FromCR 48, CR 894
ToSH 6
CSJ0912-31-224
Proj IDSTP 2009(103)MM
Work TypeGR, STRS, BASE AND PAVE
 
3.02214518735.5514738641.3099.9
Work Order10-24-13
Work Began01-06-14
Work Completed
Time Computed12-23-13
Contract Working Days365
Addl Days Granted5
Working Days Charged524
Percent Time Used141
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-224
FLORIDA TRAFFIC CONTROL DEVICES, INC. (3.13)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.74)
VAQUERO CONSTRUCTION, INC. (7.37)
BREDA COMPANY, INC. (8.09)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.43)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.37)
JAMES CONSTRUCTION GROUP, L.L.C. (7.58)
EROSION CONTROL, INC. (0.78)
JMHP, INC. (0.18)
SCOTT DERR PAINTING CO (0.08)
CPAVE, INC. (0.41)
PEREZ CONSTRUCTION CO. (0.18)
SPECIALTY DRILLING, LTD. (0.13)
SCMU (0.27)
Contract #08133009
Totals14518735.550.0014738641.3099.9

CountyBRAZORIA
HighwayCS
FromPEARLAND PKWY FROM W OF OILER DR
ToDIXIE FARM RD
CSJ0912-31-270
Proj IDC 912-31-270
Work TypeCONSTRUCT 4-LN DIVIDED ROADWAY
 
0.0014837804.805021606.3499.9
Work Order12-05-13
Work Began03-17-14
Work Completed
Time Computed03-05-14
Contract Working Days300
Addl Days Granted56
Working Days Charged344
Percent Time Used96
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-270
CPAVE, INC. (0.47)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (6.13)
DNA TRUCKING (1.44)
INTERSTATE BARRICADES & MARKINGS, INC. (0.94)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.56)
JUST GROOVING, LTD. (0.07)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.23)
RDI FOUNDATION DRILLING (2.46)
PEREZ CONSTRUCTION (2.49)
MESA ROD BUSTERS, INC. (1.22)
KOSSMAN CONTRACTING CO., INC. (1.56)
SPEEDY PAVING (1.67)
JMHP, INC. (0.29)
H & E AGGREGATE, LLC (0.26)
CONTRACTORS PAVING SUPPLY, LLP (0.68)
SPECIALTY DRILLING, LTD. (0.23)
WEIMER CONSTRUCTION COMPANY (0.47)
HYDROZONE LANDSCAPE CORPORATION (3.55)
BATTERSON,LLP (0.21)
SEMARCK LANDSCAPE SERVICES, INC. (1.74)
Contract #08133213
Totals4837804.808767.025021606.3499.9

CountyBRAZORIA ETC
HighwayVA ETC
FromVAR LOCATIONS ON SH 288 & SH 332
ToIN LAKE JACKSON
CSJ0912-31-279
Proj IDSTP 2012(516)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0062131009.801648908.3177.3
Work Order09-30-14
Work Began02-24-15
Work Completed
Time Computed11-29-14
Contract Working Days120
Addl Days Granted24
Working Days Charged142
Percent Time Used98
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-279
HOGGATT, LP (5.10)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.02)
APACE SERVICES, INC. (4.11)
SCOTT DERR PAINTING CO (0.59)
CC TREE FARMS, L.L.C. (10.11)
Contract #07143012
Totals2131009.8028347.391648908.3177.3

CountyBRAZORIA
HighwayCR
FromCR 48, BROADWAY (FM 518)
ToCR 894
CSJ0912-31-294
Proj IDSTP 2015(612)MM
Work TypeWIDEN FROM 2 TO 4-LANE DIVIDED
 
1.94412154201.3912526274.8899.9
Work Order04-10-15
Work Began06-09-15
Work Completed
Time Computed06-09-15
Contract Working Days357
Addl Days Granted5
Working Days Charged333
Percent Time Used91
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-294
CPAVE, INC. (0.04)
GEORGE MEEKS LANDPRO, INC. (0.89)
GMJ PAVING CO. (3.06)
MESA ROD BUSTERS, INC. (6.36)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41)
SCOTT DERR PAINTING CO (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49)
TEXAS CLEARING AND LEVELING (0.40)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.58)
W. W. FOUNDATION DRILLING, LTD. (3.10)
MBN ENTERPRISES LLC (2.49)
WEBBER BARRIER SERVICES, LLC. (0.22)
DNA TRUCKING, INC. (0.20)
CURB PLANET INC. (0.03)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
SOUTHERN CRUSHED CONCRETE LLC (1.11)
Contract #02153002
Totals12154201.3930715.7412526274.8899.9

CountyBRAZORIA
HighwayVA
FromLOCATIONS IN LAKE JACKSON
To.
CSJ0912-31-301
Proj IDSTP 1602(077)
Work TypeLANDSCAPE DEVELOPMENT
 
0.300920524.00271869.1529.5
Work Order08-18-16
Work Began10-24-16
Work Completed
Time Computed10-17-16
Contract Working Days120
Addl Days Granted0
Working Days Charged53
Percent Time Used44
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-301
LONESTAR TRAFFIC SAFETY, LLC (0.92)
Contract #07163041
Totals920524.0015622.70271869.1529.5

CountyFORT BEND
HighwayCS
FromON TRAMMEL FRESNO RD,FROM VICKSBURG
ToFT BEND PKWY
CSJ0912-34-143
Proj IDC 912-34-143
Work TypeGR, STRS, BASE AND PAVE
 
0.6433825527.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days176
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-143
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173223
Totals3825527.240.000.000.0

CountyFORT BEND
HighwayCS
FromTRAMMEL FRESNO RD, FORT BEND PKWY
ToFM 521
CSJ0912-34-144
Proj IDSTP 2010(596)MM
Work TypeGR, STR, BASE AND 0AVE
 
3.04120864455.456203935.3429.7
Work Order03-03-15
Work Began03-24-15
Work Completed
Time Computed03-19-15
Contract Working Days622
Addl Days Granted0
Working Days Charged69
Percent Time Used11
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC. (0.72)
RICE ENVIRONMENTAL SERVICES (0.24)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.96)
INDUS CONSTRUCTION, L.P. (3.85)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.17)
BASE CONSTRUCTION, L.L.P. (23.02)
KMA CONTRACTORS SERVICES INC. (4.77)
Contract #12143003
Totals20864455.455000.006203935.3429.7

CountyFORT BEND
HighwayCR ETC
FromMEYER ROAD AT SNAKE CREEK TRIBUTARY
To.
CSJ0912-34-176
Proj IDBR 2013(735)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7122828589.452429250.5085.8
Work Order08-04-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days321
Addl Days Granted0
Working Days Charged316
Percent Time Used98
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55)
REGIONAL TRAFFIC SERVICES LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45)
ODUM SERVICES, L.P. (1.77)
MESA ROD BUSTERS, INC. (0.19)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.98)
EROSION PREVENTION PRODUCTS (4.81)
GARNER PAVING & CONSTRUCTION, LTD. (0.15)
CROSS TEX CURBS (0.00)
J KRU LAND SERVICES, LLC (0.06)
Contract #06153027
Totals2828589.456271.822429250.5085.8

CountyFORT BEND
HighwayCS
FromON HURRICANE LANE/LAKE OLYMPIA;FROM
ToTRAMMEL FRESNO RD TO FT BEND PKWY
CSJ0912-34-182
Proj IDSTP 1302(010)MM
Work TypeCONST 2 LN CONC RDWYS
 
1.3936588849.406443672.7597.7
Work Order05-11-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days245
Addl Days Granted0
Working Days Charged149
Percent Time Used60
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-182
PRV SERVICES, INC. (7.89)
SPRINT SAND AND CLAY, LLC (0.00)
MVA CONSTRUCTION LLC (0.11)
SEMARCK LANDSCAPE SERVICES, INC. (1.54)
CPAVE, INC. (0.33)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (0.49)
HODGES BROTHERS, INC. (0.37)
TRAFFIC SIGNS & LINES, LLC (0.54)
Contract #01163030
Totals6588849.40165418.726443672.7597.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10