Monthly State Let Construction Report For Houston District As Of Jun 10, 2015 Page 6 Of 12

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTGOMERY
Highway FM 149
From FM 1488
To SS 149
CSJ 0720-02-083
Proj ID STP 2014(741)
Work Type INST LT TN LNS
 
2.466 3762255.55 12391.50 1606862.64 42.7
Work Order 08-29-14
Work Began 10-27-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 25
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-083
THIRD COAST SERVICES LLC (3.68%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
WILLOW CITY SIGN & RAIL, INC.(5.82%)
J & M CONTRACTING, COMPANY ( 11.50%)
EROSION CONTROL, INC.(3.95%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.06%)
Contract # 06143030
Totals 3762255.55 12391.50 1606862.64 42.7

CountyHARRIS
Highway SH 249
From AT VETERANS MEMORIAL DRIVE
To .
CSJ 0720-03-128
Proj ID STP 2014(743)HES
Work Type IMPROVE TS
 
0.404 254036.09 1100.00 111813.86 44.0
Work Order 07-25-14
Work Began 02-10-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 24
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143218
Totals 254036.09 1100.00 111813.86 44.0

CountyFORT BEND
Highway FM 361
From FM 361
To AT FAIRCHILDS CREEK
CSJ 0838-03-023
Proj ID BR 1502(200)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.076 976506.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0838-03-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153024
Totals 976506.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 112026.47 1065319.44 71.8
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 51
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 112026.47 1065319.44 71.8

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 101681.51 23.1
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 58
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 101681.51 23.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 0.00 1232112.93 95.5
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
REGIONAL TRAFFIC SERVICES LLC(0.00%)
VASQUEZ CONCRETE COMPANY (0.38%)
Contract # 04093209
Totals 1289999.25 0.00 1232112.93 95.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 0.00 1600338.38 99.9
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP(5.72%)
ISI CONTRACTING, INC.(6.40%)
VASQUEZ CONCRETE COMPANY (0.32%)
Contract # 09113211
Totals 1515998.78 0.00 1600338.38 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 9866.20 1072592.58 60.0
Work Order 07-19-13
Work Began 10-14-14
Work Completed  
Time Computed 08-04-13
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 23
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.54%)
Contract # 03133016
Totals 1787199.58 9866.20 1072592.58 60.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1196058.08 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1196058.08 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 34310.03 853553.16 58.5
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 19
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 34310.03 853553.16 58.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-417
Proj ID STP 2012(462)
Work Type NEW / UPGRADE TO LED LIGHT ASSEMBLIES
 
0.001 859065.05 6083.23 980962.21 99.9
Work Order 05-09-12
Work Began 12-04-12
Work Completed  
Time Computed 05-25-12
Contract Working Days 220
Addl Days Granted 24
Working Days Charged 187
Percent Time Used 76
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-417
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123026
Totals 859065.05 6083.23 980962.21 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-418
Proj ID STP 2013(321)
Work Type NEW SATELLITE BUILDING POWER SYS
 
0.001 598106.25 0.00 561011.57 93.7
Work Order 03-22-13
Work Began 02-24-14
Work Completed  
Time Computed 04-07-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 312
Percent Time Used 85
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-418
GENERATORS OF HOUSTON, LP( 69.74%)
BEVCO COMPANY, INC.(3.17%)
Contract # 01133028
Totals 598106.25 0.00 561011.57 93.7

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-420
Proj ID STP 2013(322)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1899903.95 0.00 0.00 0.0
Work Order 03-20-13
Work Began 00-00-00
Work Completed  
Time Computed 09-16-13
Contract Working Days 525
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133213
Totals 1899903.95 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-00-424
Proj ID CM 1102(560)
Work Type PED & SIG IMPRVMTS IN AIRLINE DIST
 
1.367 2697458.33 66717.86 1657435.61 62.0
Work Order 01-23-14
Work Began 04-14-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 228
Addl Days Granted 0
Working Days Charged 250
Percent Time Used 109
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03%)
ODUM SERVICES, L.P.(0.35%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 11.47%)
REGIONAL TRAFFIC SERVICES LLC(2.15%)
AGGREGATE TECHNOLOGIES, INC. (5.02%)
SPEEDY PAVING(1.31%)
Contract # 10133027
Totals 2697458.33 66717.86 1657435.61 62.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-440
Proj ID NH 2015(316)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 772662.59 51505.00 186892.04 24.1
Work Order 01-16-15
Work Began 00-00-00
Work Completed  
Time Computed 02-01-15
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 11
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-440
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143019
Totals 772662.59 51505.00 186892.04 24.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-441
Proj ID NH 2014(297)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1210347.90 785.00 1146058.26 94.6
Work Order 03-03-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 500
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 28
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-441
REGIONAL TRAFFIC SERVICES LLC(1.78%)
Contract # 12133223
Totals 1210347.90 785.00 1146058.26 94.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS
To .
CSJ 0912-00-443
Proj ID STP 2014(298)
Work Type INSTALL CCTV
 
0.001 243957.34 0.00 252350.52 100.0
Work Order 01-17-14
Work Began 03-11-14
Work Completed 03-12-15
Time Computed 03-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 98
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-443
AMERICAN CABLE SERVICES, INC.(2.55%)
Contract # 12133020
Totals 243957.34 0.00 252350.52 100.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS ON IH 45
To .
CSJ 0912-00-468
Proj ID IM 0451(341)
Work Type LANDSCAPE DEVELOPMENT
 
52.668 1130845.26 7941.36 1070135.53 94.6
Work Order 05-15-12
Work Began 06-15-12
Work Completed  
Time Computed 07-15-12
Contract Working Days 105
Addl Days Granted 45
Working Days Charged 130
Percent Time Used 86
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-468
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04123018
Totals 1130845.26 7941.36 1070135.53 94.6

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To ALL LOCATIONS ON US 59 & IH 610
CSJ 0912-00-469
Proj ID NH 2012(513)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 778293.17 7210.79 735351.47 94.4
Work Order 06-11-12
Work Began 06-15-12
Work Completed  
Time Computed 06-27-12
Contract Working Days 90
Addl Days Granted 75
Working Days Charged 139
Percent Time Used 84
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-469
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123222
Totals 778293.17 7210.79 735351.47 94.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-484
Proj ID STP 2013(993)
Work Type UPGRADE & MODERNIZE SIGNALS
 
0.001 557849.99 0.00 601002.38 99.9
Work Order 10-30-13
Work Began 05-12-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 109
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-484
PROFESSIONAL TRAFFIC CONTROL, LLC(3.36%)
Contract # 08133263
Totals 557849.99 0.00 601002.38 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12