Monthly State Let Construction Report For Houston District As Of Aug 10, 2015 Page 6 Of 13

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWALLER
Highway FM 362
From AT FM 529
To .
CSJ 0523-02-044
Proj ID STP 2014(486)HES
Work Type INST FLASHING BEACON
 
0.001 109572.50 0.00 108848.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 10-07-14
Work Completed 02-06-15
Time Computed 10-07-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 51
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0523-02-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143031
Totals 109572.50 0.00 108848.50 100.0

CountyMONTGOMERY
Highway FM 1488
From FM 149
To 0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ 0523-10-034
Proj ID C 523-10-34
Work Type CONSTRUCT RR GRADE SEPARATION
 
2.779 27649979.11 23387.39 5255509.84 19.0
Work Order 10-22-13
Work Began 02-16-15
Work Completed  
Time Computed 07-19-14
Contract Working Days 478
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 24
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC(1.11%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67%)
EUBANK EXCAVATION, L.L.C.(0.76%)
BREDA COMPANY, INC.(1.41%)
WILLOW CITY SIGN & RAIL, INC.(0.51%)
GMJ PAVING CO. (5.71%)
RDI FOUNDATION DRILLING(4.28%)
HOUSTON SAWING & DRILLING(0.04%)
TEX OP CONSTRUCTION, LP(0.60%)
SCOTT DERR PAINTING CO (0.13%)
NORTHWEST MATERIALS(0.25%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.13%)
CREACOM, INC.(1.18%)
VALLEY PLACERS, LLC(0.27%)
APCON SERVICES, LLC(0.00%)
FORDE CONSTRUCTION COMPANY, INC. (0.19%)
Contract # 07133003
Totals 27649979.11 23387.39 5255509.84 19.0

CountyFORT BEND
Highway FM 359
From AT US 90A AND UPRR
To .
CSJ 0543-02-055
Proj ID STP 2013(734)RGS
Work Type RR GRADE SEPARATION
 
0.408 27124547.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-22-15
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 482
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153205
Totals 27124547.77 0.00 0.00 0.0

CountyFORT BEND
Highway FM 762
From AT FM 2977
To .
CSJ 0543-03-071
Proj ID STP 2014(927)
Work Type INSTALL TURN LANE & IMPROVE SHLDS
 
0.615 477521.30 0.00 531619.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-04-14
Work Completed 12-18-14
Time Computed 09-04-14
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 80
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-071
INTERSTATE BARRICADES & MARKINGS, INC. (5.36%)
WEST TEXAS RUMBLE STRIP(0.82%)
BAY CITY TRAFFIC (5.41%)
EROSION CONTROL, INC.(2.80%)
JMHP, INC. (0.91%)
R & A TRANSPORT, INC.(3.11%)
Contract # 06143052
Totals 477521.30 0.00 531619.35 100.0

CountyBRAZORIA
Highway SH 288
From CR 56
To .
CSJ 0598-02-106
Proj ID NH 2015(708)
Work Type CONST SB ON - RAMP & NB OFF - RAMP
 
2.908 9196617.23 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-13-15
Work Began 00-00-00
Work Completed  
Time Computed 09-12-15
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-106
WIMMS ENVIRONMENTAL, INC.(5.28%)
Contract # 03153206
Totals 9196617.23 0.00 0.00 0.0

CountyMONTGOMERY
Highway IH 45
From N OF CRIGHTON RD
To LEAGUE LINE ROAD
CSJ 0675-08-071
Proj ID CM 1102(305)
Work Type INST CTMS
 
6.889 1095536.50 0.00 1166135.72 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 12-10-12
Work Completed 09-02-14
Time Computed 03-12-12
Contract Working Days 375
Addl Days Granted 0
Working Days Charged 374
Percent Time Used 99
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08113025
Totals 1095536.50 0.00 1166135.72 100.0

CountyMONTGOMERY
Highway IH 45
From NORTH OF CALVARY
To SOUTH OF FM 830
CSJ 0675-08-084
Proj ID STP 2010(629)ES
Work Type GR, STRS, BASE AND CONC PAVE
 
5.098 57435821.47 0.00 59269218.04 100.0
CountyMONTGOMERY
Highway IH 45
From FM 830
To WALKER COUNTY LINE
CSJ 0675-08-093
Proj ID RW 675-8-93
Work Type ROW ACQ.
 
8.208 181827.00 0.00 90429.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-10
Work Began 05-25-10
Work Completed 03-03-15
Time Computed 05-23-10
Contract Working Days 1,177
Addl Days Granted 30
Working Days Charged 1,205
Percent Time Used 99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-084
JOE VALENCIK, INC. (0.94%)
SCOTT DERR PAINTING CO (0.15%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.38%)
INDUS CONSTRUCTION, L.P. ( 14.55%)
CREATIVE LANDSCAPES OF TEXAS (1.20%)
SMITH & COMPANY( 10.78%)
L.A. UTILITIES, INC. (5.04%)
JET UNDERGROUND UTILITIES(4.78%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
VAQUERO CONSTRUCTION, INC. (0.38%)
D.L. CONDITT (0.35%)
BROOKLYN SWEEPS(0.09%)
HIGHWAY TECHNOLOGIES, INC. (0.01%)
CEN TEX HYDROSEED, INC.(0.01%)
Contract # 03103001
Totals 57617648.47 0.00 59359647.67 100.0

CountyMONTGOMERY
Highway IH 45
From SH 336 SOUTH LOOP
To NORTH LEAGUE LINE ROAD
CSJ 0675-08-107
Proj ID HP 2013(692)
Work Type LANDSCAPE DEVELOPMENT
 
6.300 745136.01 3916.67 637023.62 85.4
Work Order 08-26-13
Work Began 10-14-13
Work Completed  
Time Computed 10-14-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 100
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0675-08-107
CC TREE FARMS, L.L.C.(1.89%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.96%)
Contract # 05133027
Totals 745136.01 3916.67 637023.62 85.4

CountyGALVESTON
Highway FM 1765
From AT 33RD STREET S
To .
CSJ 0686-01-046
Proj ID STP 2015(315)HES
Work Type FLASHING BEACON AND TURN LANE
 
0.186 481773.82 45744.58 409581.42 85.0
Work Order 01-02-15
Work Began 04-29-15
Work Completed  
Time Computed 03-03-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 95
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0686-01-046
AQUALAWN HYDROMULCH & EROSION CONTROL(1.33%)
STRIPE-A-LINE, INC.(2.44%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 14.21%)
Contract # 11143208
Totals 481773.82 45744.58 409581.42 85.0

CountyMONTGOMERY
Highway FM 149
From FM 1488
To SS 149
CSJ 0720-02-083
Proj ID STP 2014(741)
Work Type INST LT TN LNS
 
2.466 3762255.55 563012.31 2170474.95 57.6
Work Order 08-29-14
Work Began 10-27-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 39
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-083
THIRD COAST SERVICES LLC (3.68%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
WILLOW CITY SIGN & RAIL, INC.(5.82%)
J & M CONTRACTING, COMPANY ( 11.50%)
EROSION CONTROL, INC.(3.95%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.06%)
TEXOP CONSTRUCTION (0.53%)
Contract # 06143030
Totals 3762255.55 563012.31 2170474.95 57.6

CountyMONTGOMERY
Highway FM 149
From FM 1097
To FM 1791
CSJ 0720-02-087
Proj ID STP 1502(606)HES
Work Type BS REPR, OCST, 1.5" OL & ADD SHLDR
 
10.170 10198541.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-02-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153044
Totals 10198541.18 0.00 0.00 0.0

CountyHARRIS
Highway SH 249
From AT VETERANS MEMORIAL DRIVE
To .
CSJ 0720-03-128
Proj ID STP 2014(743)HES
Work Type IMPROVE TS
 
0.404 254036.09 1100.00 114013.86 44.8
Work Order 07-25-14
Work Began 02-10-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 24
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0720-03-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143218
Totals 254036.09 1100.00 114013.86 44.8

CountyFORT BEND
Highway FM 361
From FM 361
To AT FAIRCHILDS CREEK
CSJ 0838-03-023
Proj ID BR 1502(200)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.076 976506.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-14-15
Work Began 00-00-00
Work Completed  
Time Computed 09-13-15
Contract Working Days 81
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0838-03-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153024
Totals 976506.40 0.00 0.00 0.0

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-331
Proj ID CM 2008(055)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1482581.45 500.00 1071433.67 72.2
Work Order 09-11-07
Work Began 04-04-08
Work Completed  
Time Computed 09-27-07
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 56
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-331
BATTERSON, L.L.P.(1.04%)
SPRING CREEK CONSTRUCTION, INC.(4.49%)
Contract # 08073244
Totals 1482581.45 500.00 1071433.67 72.2

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-336
Proj ID STP 2011(578)G
Work Type INSTALL VIVDS AND INSTALL LOOPS
 
0.003 439963.75 0.00 101681.51 23.1
Work Order 01-06-11
Work Began 04-09-12
Work Completed  
Time Computed 01-22-11
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 58
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-336
CURB PLANET INC. (0.11%)
Contract # 12103011
Totals 439963.75 0.00 101681.51 23.1

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-350
Proj ID CM 2009(364)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1289999.25 0.00 1232112.93 95.5
Work Order 06-02-09
Work Began 08-12-12
Work Completed  
Time Computed 06-18-09
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 198
Percent Time Used 88
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-350
CREACOM, INC.(0.04%)
SPRING CREEK CONSTRUCTION, INC.(3.15%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
KAM CONSTRUCTION, INC. (0.86%)
WALLACE CONCRETE SAWING(0.14%)
REGIONAL TRAFFIC SERVICES LLC(0.00%)
VASQUEZ CONCRETE COMPANY (0.38%)
Contract # 04093209
Totals 1289999.25 0.00 1232112.93 95.5

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-380
Proj ID STP 2012(020)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1515998.78 0.00 1600338.38 99.9
Work Order 11-16-11
Work Began 02-13-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 437
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 62
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-380
BATTERSON,LLP(5.72%)
ISI CONTRACTING, INC.(6.40%)
VASQUEZ CONCRETE COMPANY (0.32%)
Contract # 09113211
Totals 1515998.78 0.00 1600338.38 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-381
Proj ID STP 2012(021)
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 1787199.58 68130.18 1151286.91 64.4
Work Order 07-19-13
Work Began 10-14-14
Work Completed  
Time Computed 08-04-13
Contract Working Days 432
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 32
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-381
AAA ASPHALT PAVING, INC. (3.02%)
PROFESSIONAL TRAFFIC CONTROL, LLC(2.54%)
Contract # 03133016
Totals 1787199.58 68130.18 1151286.91 64.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-385
Proj ID STP 2011(714)G
Work Type UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
 
0.001 911168.15 0.00 1196058.08 99.9
Work Order 02-10-11
Work Began 11-01-11
Work Completed  
Time Computed 02-26-11
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 182
Percent Time Used 67
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-385
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12103230
Totals 911168.15 0.00 1196058.08 99.9

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0912-00-413
Proj ID STP 2013(542)
Work Type NEW TRAFFIC SIGNALS
 
0.001 1456616.50 85409.64 939542.80 64.5
Work Order 07-08-13
Work Began 11-06-13
Work Completed  
Time Computed 11-06-13
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 20
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133222
Totals 1456616.50 85409.64 939542.80 64.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13