Monthly State Let Construction Report For Houston District As Of May 11, 2017 Page 6 Of 10

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-413
Proj IDSTP 2013(542)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011456616.501506293.4399.9
Work Order07-08-13
Work Began11-06-13
Work Completed
Time Computed11-06-13
Contract Working Days417
Addl Days Granted0
Working Days Charged135
Percent Time Used32
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-413
STRIPE-A-LINE, INC. (0.12)
Contract #04133222
Totals1456616.500.001506293.4399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-420
Proj IDSTP 2013(322)
Work TypeNEW TRAFFIC SIGNALS
 
0.0011899903.951222939.9264.3
Work Order03-20-13
Work Began09-30-15
Work Completed
Time Computed09-16-13
Contract Working Days525
Addl Days Granted0
Working Days Charged134
Percent Time Used25
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-420
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01133213
Totals1899903.9591459.001222939.9264.3

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN HARRIS COUNTY
To.
CSJ0912-00-424
Proj IDCM 1102(560)
Work TypePED & SIG IMPRVMTS IN AIRLINE DIST
 
1.3672697458.332332487.2487.7
Work Order01-23-14
Work Began04-14-14
Work Completed
Time Computed04-14-14
Contract Working Days228
Addl Days Granted0
Working Days Charged273
Percent Time Used119
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-424
GEORGE MEEKS LANDPRO, INC. (7.03)
ODUM SERVICES, L.P. (0.35)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (11.47)
REGIONAL TRAFFIC SERVICES LLC (2.06)
AGGREGATE TECHNOLOGIES, INC. (5.02)
SPEEDY PAVING (1.31)
AAA ASPHALT PAVING, INC. (0.00)
STRIPES & STOPS COMPANY, INC. (0.06)
PFEIFFER & SON LTD. (0.53)
Contract #10133027
Totals2697458.331258.272332487.2487.7

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS IN MISSOURI CITY
To.
CSJ0912-00-488
Proj IDCM 2015(611)
Work TypeCOMMUNICATIONS/RELIABILITY URGRADE
 
0.0011394256.881427001.1599.9
Work Order11-10-15
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days180
Addl Days Granted0
Working Days Charged151
Percent Time Used83
Contractor(s)
CREACOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-488
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07153067
Totals1394256.880.001427001.1599.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS WITHIN DISTRICT
To.
CSJ0912-00-489
Proj IDNH 2014(744)
Work TypeLANDSCAPE DEVELOPMENT
 
0.001887550.772085919.7399.9
Work Order08-13-14
Work Began09-22-14
Work Completed
Time Computed09-22-14
Contract Working Days45
Addl Days Granted9
Working Days Charged53
Percent Time Used98
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-489
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06143020
Totals887550.77129748.162085919.7399.9

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-511
Proj IDSTP 2017(158)
Work TypeNEW TRAFFIC SIGNALS
 
0.5081718929.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-511
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163215
Totals1718929.720.000.000.0

CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0912-00-513
Proj IDSTP 2017(306)
Work TypeTRAFFIC SIGNAL UPGRADES
 
0.001927576.88170432.7018.3
Work Order01-17-17
Work Began03-20-17
Work Completed
Time Computed02-16-17
Contract Working Days119
Addl Days Granted0
Working Days Charged27
Percent Time Used22
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-00-513
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163021
Totals927576.88169262.85170432.7018.3

CountyBRAZORIA
HighwayCS
FromCR 149 AT MUSTANG BAYOU
To.
CSJ0912-31-203
Proj IDBR 2008(059)
Work TypeREPL BR & APPRS
 
0.2882748072.002729327.4599.9
Work Order09-17-12
Work Began11-26-12
Work Completed
Time Computed11-16-12
Contract Working Days270
Addl Days Granted0
Working Days Charged305
Percent Time Used112
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-203
W. W. FOUNDATION DRILLING, LTD. (9.86)
ENVIRONMENTAL ALLIES, L.P. (0.77)
JUST GROOVING, LTD. (0.03)
WILLOW CITY SIGN & RAIL, INC. (1.01)
GMJ PAVING CO. (5.09)
Contract #07123007
Totals2748072.000.002729327.4599.9

CountyBRAZORIA
HighwayCR
FromCR 48, CR 894
ToSH 6
CSJ0912-31-224
Proj IDSTP 2009(103)MM
Work TypeGR, STRS, BASE AND PAVE
 
3.02214518735.5514739265.0199.9
Work Order10-24-13
Work Began01-06-14
Work Completed
Time Computed12-23-13
Contract Working Days365
Addl Days Granted5
Working Days Charged524
Percent Time Used141
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-224
FLORIDA TRAFFIC CONTROL DEVICES, INC. (3.13)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.74)
VAQUERO CONSTRUCTION, INC. (7.37)
BREDA COMPANY, INC. (8.09)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.43)
WEBBER-BALKE FOUNDATION COMPANY, INC. (1.37)
JAMES CONSTRUCTION GROUP, L.L.C. (7.58)
EROSION CONTROL, INC. (0.78)
JMHP, INC. (0.18)
SCOTT DERR PAINTING CO (0.08)
CPAVE, INC. (0.41)
PEREZ CONSTRUCTION CO. (0.18)
SPECIALTY DRILLING, LTD. (0.13)
SCMU (0.27)
Contract #08133009
Totals14518735.550.0014739265.0199.9

CountyBRAZORIA ETC
HighwayVA ETC
FromVAR LOCATIONS ON SH 288 & SH 332
ToIN LAKE JACKSON
CSJ0912-31-279
Proj IDSTP 2012(516)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0062131009.801691429.4179.3
Work Order09-30-14
Work Began02-24-15
Work Completed
Time Computed11-29-14
Contract Working Days120
Addl Days Granted24
Working Days Charged142
Percent Time Used98
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-279
HOGGATT, LP (5.10)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.02)
APACE SERVICES, INC. (4.11)
SCOTT DERR PAINTING CO (0.59)
CC TREE FARMS, L.L.C. (10.11)
Contract #07143012
Totals2131009.8014173.701691429.4179.3

CountyBRAZORIA
HighwayCR
FromCR 48, BROADWAY (FM 518)
ToCR 894
CSJ0912-31-294
Proj IDSTP 2015(612)MM
Work TypeWIDEN FROM 2 TO 4-LANE DIVIDED
 
1.94412154201.3912540218.1599.9
Work Order04-10-15
Work Began06-09-15
Work Completed
Time Computed06-09-15
Contract Working Days357
Addl Days Granted5
Working Days Charged333
Percent Time Used91
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-294
CPAVE, INC. (0.04)
GEORGE MEEKS LANDPRO, INC. (0.89)
GMJ PAVING CO. (3.06)
MESA ROD BUSTERS, INC. (6.36)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.41)
SCOTT DERR PAINTING CO (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49)
TEXAS CLEARING AND LEVELING (0.40)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.58)
W. W. FOUNDATION DRILLING, LTD. (3.10)
MBN ENTERPRISES LLC (2.49)
WEBBER BARRIER SERVICES, LLC. (0.22)
DNA TRUCKING, INC. (0.20)
CURB PLANET INC. (0.03)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
SOUTHERN CRUSHED CONCRETE LLC (1.11)
Contract #02153002
Totals12154201.397317.1512540218.1599.9

CountyBRAZORIA
HighwayVA
FromLOCATIONS IN LAKE JACKSON
To.
CSJ0912-31-301
Proj IDSTP 1602(077)
Work TypeLANDSCAPE DEVELOPMENT
 
0.300920524.00834390.6590.6
Work Order08-18-16
Work Began10-24-16
Work Completed
Time Computed10-17-16
Contract Working Days120
Addl Days Granted0
Working Days Charged97
Percent Time Used80
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-301
LONESTAR TRAFFIC SAFETY, LLC (0.92)
Contract #07163041
Totals920524.0088200.00834390.6590.6

CountyFORT BEND
HighwayCS
FromON TRAMMEL FRESNO RD,FROM VICKSBURG
ToFT BEND PKWY
CSJ0912-34-143
Proj IDC 912-34-143
Work TypeGR, STRS, BASE AND PAVE
 
0.6433825527.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days176
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-143
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173223
Totals3825527.240.000.000.0

CountyFORT BEND
HighwayCS
FromTRAMMEL FRESNO RD, FORT BEND PKWY
ToFM 521
CSJ0912-34-144
Proj IDSTP 2010(596)MM
Work TypeGR, STR, BASE AND 0AVE
 
3.04120864455.456315683.5030.2
Work Order03-03-15
Work Began03-24-15
Work Completed
Time Computed03-19-15
Contract Working Days622
Addl Days Granted0
Working Days Charged68
Percent Time Used10
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-144
STRIPE-A-LINE, INC. (0.72)
RICE ENVIRONMENTAL SERVICES (0.24)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (1.96)
INDUS CONSTRUCTION, L.P. (3.85)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.17)
BASE CONSTRUCTION, L.L.P. (23.02)
KMA CONTRACTORS SERVICES INC. (4.77)
Contract #12143003
Totals20864455.459666.206315683.5030.2

CountyFORT BEND
HighwayCR ETC
FromMEYER ROAD AT SNAKE CREEK TRIBUTARY
To.
CSJ0912-34-176
Proj IDBR 2013(735)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7122828589.452658514.1495.4
Work Order08-04-15
Work Began09-08-15
Work Completed
Time Computed09-08-15
Contract Working Days321
Addl Days Granted0
Working Days Charged374
Percent Time Used116
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-176
LONESTAR TRAFFIC SAFETY, LLC (0.55)
REGIONAL TRAFFIC SERVICES LLC (0.40)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.45)
ODUM SERVICES, L.P. (1.77)
MESA ROD BUSTERS, INC. (0.19)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.98)
EROSION PREVENTION PRODUCTS (4.81)
GARNER PAVING & CONSTRUCTION, LTD. (0.15)
CROSS TEX CURBS (0.00)
J KRU LAND SERVICES, LLC (0.06)
Contract #06153027
Totals2828589.4563592.812658514.1495.4

CountyFORT BEND
HighwayCS
FromON HURRICANE LANE/LAKE OLYMPIA;FROM
ToTRAMMEL FRESNO RD TO FT BEND PKWY
CSJ0912-34-182
Proj IDSTP 1302(010)MM
Work TypeCONST 2 LN CONC RDWYS
 
1.3936588849.406528907.2199.0
Work Order05-11-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days245
Addl Days Granted0
Working Days Charged178
Percent Time Used72
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-182
PRV SERVICES, INC. (7.89)
SPRINT SAND AND CLAY, LLC (0.00)
MVA CONSTRUCTION LLC (0.11)
SEMARCK LANDSCAPE SERVICES, INC. (1.54)
CPAVE, INC. (0.33)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (0.49)
HODGES BROTHERS, INC. (0.37)
TRAFFIC SIGNS & LINES, LLC (0.54)
Contract #01163030
Totals6588849.4010586.896528907.2199.0

CountyFORT BEND
HighwayVA
FromVARIOUS LOCATIONS ALONG: US 59,
ToSH 6, AND US 90A
CSJ0912-34-187
Proj IDC 912-34-187
Work TypeINSTALLATION OF DMS
 
0.001992940.68623290.3662.7
Work Order04-07-16
Work Began02-13-17
Work Completed
Time Computed05-07-16
Contract Working Days91
Addl Days Granted0
Working Days Charged39
Percent Time Used42
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-187
MAIN LANE INDUSTRIES LTD. (54.26)
INTERSTATE BARRICADES & MARKINGS, INC. (0.98)
Contract #02163213
Totals992940.68189591.67623290.3662.7

CountyHARRIS
HighwayCS
FromAT ALICE JOHNSON JR HIGH SCHOOL
To.
CSJ0912-70-067
Proj IDSTP 1602(474)SRS
Work TypePEDESTRIAN WAY/SIDEWALKS
 
0.320582538.50544381.9195.0
Work Order09-19-16
Work Began10-24-16
Work Completed
Time Computed11-18-16
Contract Working Days45
Addl Days Granted0
Working Days Charged60
Percent Time Used133
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163029
Totals582538.503270.00544381.9195.0

CountyHARRIS
HighwayCS
FromAT BANG ELEMENTARY SCHOOL
To.
CSJ0912-70-068
Proj IDSTP 2014(745)SRS
Work TypeSRTS TRAIL
 
1.473499113.96406205.2691.0
Work Order10-02-14
Work Began12-01-14
Work Completed
Time Computed12-01-14
Contract Working Days60
Addl Days Granted25
Working Days Charged167
Percent Time Used196
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
BATTERSON,LLP (14.72)
LANDPRO, INC. (4.34)
TITAN 360 INDUSTRIAL SERVICES (8.99)
Contract #07143054
Totals499113.960.00406205.2691.0

CountyHARRIS
HighwayVA
FromFANNIN & MN ST ESPLANADES CAMBRIDGE
ToMECOM FOUNTAIN
CSJ0912-70-078
Proj IDSTP 2011(255)TE
Work TypeENHANCEMENT PROJECT
 
0.8072581444.902026823.5078.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-13
Work Began10-21-13
Work Completed
Time Computed10-12-13
Contract Working Days176
Addl Days Granted32
Working Days Charged216
Percent Time Used103
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88)
DOWN UNDER CONSTRUCTION (1.83)
SPECIALTY DRILLING (0.02)
BUILDER SERVICES CO. (1.50)
LEXTEX, INC. (7.15)
BIO LANDSCAPE & MAINTENANCE, INC. (65.42)
HOGGATT, LP (5.46)
EVERY SECOND COUNTS (ESC) (5.69)
HIGHWAY BARRICADES AND SERVICES, LLC (0.48)
MIKELS CONSTRUCTION CO., INC. (2.51)
PUMPS, MOTORS & CONTROLS (0.04)
STRIPE LINES, INC. (0.15)
Contract #06133013
Totals2581444.900.002026823.5078.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10