Monthly State Let Construction Report For Houston District As Of Jul 11, 2014 Page 6 Of 10

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBRAZORIA
Highway CS
From NORTH 2ND STREET AT MUSTANG BAYOU
To .
CSJ 0912-31-237
Proj ID BR 2010(723)
Work Type REPLACE BRIDGE
 
0.126 766156.52 0.00 403426.71 52.6
Work Order 08-01-12
Work Began 09-17-12
Work Completed  
Time Computed 09-17-12
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 57
Contractor(s)
TOM-MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-237
REPUBLIC TRAFFIC SAFETY, INC.(0.26%)
KOSSMAN CONTRACTING CO., INC.(2.07%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.05%)
GMJ PAVING CO. (7.38%)
KATY CONSTRUCTION(2.34%)
Contract # 06123205
Totals 766156.52 0.00 403426.71 52.6

CountyBRAZORIA
Highway CR
From CR 210 AT DRAINAGE DITCH
To .
CSJ 0912-31-265
Proj ID BR 2011(708)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.069 448817.82 81190.06 377295.06 84.4
Work Order 01-17-14
Work Began 02-25-14
Work Completed  
Time Computed 02-25-14
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 104
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-265
JMHP, INC. (3.35%)
LONE STAR TRAFFIC SERVICE, INC.(0.49%)
REGIONAL TRAFFIC SERVICES LLC(0.33%)
Contract # 10133205
Totals 448817.82 81190.06 377295.06 84.4

CountyBRAZORIA
Highway CS
From BISSELL RD AT DRAINAGE DITCH
To .
CSJ 0912-31-267
Proj ID BR 2012(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.266 1583872.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-267
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143009
Totals 1583872.56 0.00 0.00 0.0

CountyBRAZORIA
Highway CS
From PEARLAND PKWY FROM W OF OILER DR
To DIXIE FARM RD
CSJ 0912-31-270
Proj ID C 912-31-270
Work Type CONSTRUCT 4 - LN DIVIDED ROADWAY
 
0.001 4837804.80 363839.98 1192338.44 24.6
Work Order 12-05-13
Work Began 03-17-14
Work Completed  
Time Computed 03-05-14
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 26
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-270
CPAVE, INC.(0.47%)
FLORIDA TRAFFIC CONTROL DEVICES, INC.(6.13%)
DNA TRUCKING (1.44%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.94%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.56%)
JUST GROOVING, LTD.(0.07%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.23%)
RDI FOUNDATION DRILLING(2.46%)
PEREZ CONSTRUCTION (2.49%)
MESA ROD BUSTERS, INC. (1.22%)
KOSSMAN CONTRACTING CO., INC.(1.56%)
SPEEDY PAVING(1.67%)
MAINTENANCE TO GO, INC.(3.53%)
JMHP, INC. (0.29%)
H & E AGGREGATE, LLC (0.26%)
CONTRACTORS PAVING SUPPLY, LLP (0.68%)
SPECIALTY DRILLING, LTD. (0.23%)
WEIMER CONSTRUCTION COMPANY(0.47%)
Contract # 08133213
Totals 4837804.80 363839.98 1192338.44 24.6

CountyBRAZORIA
Highway CR
From COUNTY ROAD 220; SH 288
To FM 523
CSJ 0912-31-275
Proj ID STP 2012(711)
Work Type PVMT, GR & STRS
 
3.694 15980617.35 618388.61 15183966.08 95.1
Work Order 03-06-13
Work Began 03-19-13
Work Completed  
Time Computed 03-22-13
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 293
Percent Time Used 108
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-275
LASER EARTH MOVING (0.43%)
SEMARCK LANDSCAPE SERVICES, INC. (0.06%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.03%)
DURWOOD GREENE CONSTRUCTION CO.(8.05%)
W. W. FOUNDATION DRILLING, LTD.(1.03%)
TEXAS CONCRETE ENTERPRISE READY MIX, INC.( 10.72%)
INDUS CONSTRUCTION, L.P. (0.94%)
PRV SERVICES, INC. (1.23%)
WILLOW CITY SIGN & RAIL, INC.(0.49%)
CPAVE, INC.(0.24%)
BUSSELL & SONS, L.L.C. (0.11%)
CURB PLANET INC. (0.01%)
BATTERSON,LLP(1.20%)
WEBBER BARRIER SERVICES, LLC.(0.62%)
Contract # 08123204
Totals 15980617.35 618388.61 15183966.08 95.1

CountyBRAZORIA
Highway VA ETC
From VAR LOCATIONS ON SH 288 & SH 332
To IN LAKE JACKSON
CSJ 0912-31-279
Proj ID STP 2012(516)
Work Type LANDSCAPE DEVELOPMENT
 
0.006 2131009.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-31-279
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143012
Totals 2131009.80 0.00 0.00 0.0

CountyFORT BEND
Highway CS
From WEST AIRPORT - FROM US 59
To 800 FEET WEST OF KIRKWOOD DRIVE
CSJ 0912-34-130
Proj ID HP 2011(793)
Work Type RECONSTRUCTION OF WEST AIRPORT
 
0.695 4192145.17 238124.04 238124.04 5.6
Work Order 03-12-14
Work Began 05-28-14
Work Completed  
Time Computed 05-10-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 7
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-130
CHERRY CRUSHED CONCRETE(0.99%)
REGIONAL TRAFFIC SERVICES LLC(1.27%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(6.68%)
Contract # 01143211
Totals 4192145.17 238124.04 238124.04 5.6

CountyFORT BEND
Highway CR
From WALKER ROAD AT TURKEY CREEK
To .
CSJ 0912-34-159
Proj ID BR 2011(853)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 395576.27 19240.50 362308.52 91.5
Work Order 11-13-13
Work Began 12-05-13
Work Completed  
Time Computed 12-05-13
Contract Working Days 133
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 81
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-159
CENTERLINE TRAFFIC SAFETY, LLC (1.06%)
REGIONAL TRAFFIC SERVICES LLC(1.28%)
A-1 EROSION CONTROL, LLC (1.23%)
KOSSMAN CONTRACTING CO., INC.(0.63%)
JMHP, INC. (2.94%)
GARNER PAVING & CONSTRUCTION, LTD. (1.25%)
Contract # 10133009
Totals 395576.27 19240.50 362308.52 91.5

CountyFORT BEND
Highway CR
From FOSTER SCHOOL @ FAIRCHILDS CRK TRIB
To .
CSJ 0912-34-169
Proj ID BR 2011(989)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.130 978105.55 140965.00 419525.42 42.8
Work Order 03-03-14
Work Began 05-09-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 22
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-169
REGIONAL TRAFFIC SERVICES LLC(1.90%)
LONESTAR TRAFFIC SAFETY, LLC (1.86%)
ODUM SERVICES, L.P.(4.16%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.38%)
ENVIRONMENTAL ALLIES, L.P. (0.49%)
Contract # 01143222
Totals 978105.55 140965.00 419525.42 42.8

CountyFORT BEND
Highway CS
From STAFFORDSHIRE ROAD; 5TH ST
To SCANLIN/LEXINGTON RD
CSJ 0912-34-178
Proj ID STP 2012(734)MM
Work Type GR, STRS, BASE PV W / CURB & GUTTER
 
0.611 3589100.64 4000.00 2799248.88 77.9
Work Order 08-19-13
Work Began 11-16-13
Work Completed  
Time Computed 10-18-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 68
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-34-178
GMJ PAVING CO. (4.70%)
BREDA COMPANY, INC.(3.58%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.29%)
TRAF-TEX, INC. (0.31%)
CPAVE, INC.(0.65%)
EMBARK TREE AND LANDSCAPE SERVICES (0.24%)
CHERRY CONCRETE REMOVAL(0.03%)
CURB PLANET INC. (0.11%)
BATTERSON,LLP(1.63%)
Contract # 05133213
Totals 3589100.64 4000.00 2799248.88 77.9

CountyMONTGOMERY
Highway CR
From KUYKENDAHL RD; ALDEN BRIDGE
To CROWNRIDGE DR
CSJ 0912-37-140
Proj ID STP 2002(643)UM
Work Type CONST 2 LANE RDWY
 
0.485 2496548.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-140
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143027
Totals 2496548.44 0.00 0.00 0.0

CountyMONTGOMERY
Highway CS
From WOODLANDS PKWY, E OF PANTHER CRK DR
To GROGAN'S MILL RD
CSJ 0912-37-199
Proj ID STP 2010(831)MM
Work Type GR, STRS, BASE AND PAVE
 
0.895 2836771.40 165268.73 2040147.64 75.2
Work Order 10-24-12
Work Began 11-26-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 246
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 148
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-199
W. W. FOUNDATION DRILLING, LTD.(3.75%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.86%)
HIGHWAY TECHNOLOGIES, INC. (1.42%)
A BROTHERS MILLING, LLC(0.90%)
CURB PLANET INC. (0.10%)
YORK & YORK FOUNDATION DRILLING, INC.(1.50%)
DAVID GALA DBA GALAXY FENCE(0.54%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.35%)
MESA ROD BUSTERS, INC. (0.14%)
WILLOW CITY SIGN & RAIL, INC.(0.89%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.06%)
HODGES BROTHERS, INC.(0.43%)
CENTRAL CONSTRUCTION SERVICES, INC.(0.22%)
EROSION ABATEMENT, LLC (7.22%)
Contract # 08123031
Totals 2836771.40 165268.73 2040147.64 75.2

CountyMONTGOMERY
Highway CR
From MOUNT MARIAH AT LITTLE CANEY CREEK
To .
CSJ 0912-37-219
Proj ID BR 2011(707)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 454454.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0912-37-219
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143227
Totals 454454.20 0.00 0.00 0.0

CountyHARRIS
Highway CS
From AT BANG ELEMENTARY SCHOOL
To .
CSJ 0912-70-068
Proj ID STP 2014(745)SRS
Work Type SRTS TRAIL
 
1.473 499113.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143054
Totals 499113.96 0.00 0.00 0.0

CountyHARRIS
Highway VA
From BRAYS BAYOU PATH IN E HOUS(75TH ST)
To OLD SPANISH TRAIL
CSJ 0912-70-077
Proj ID STP 2011(254)TE
Work Type ENHANCEMENT PROJECT
 
2.207 1525267.27 136917.58 1143522.82 75.0
Work Order 05-28-13
Work Began 07-15-13
Work Completed  
Time Computed 07-15-13
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 241
Percent Time Used 100
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-077
PROFESSIONAL TRAFFIC CONTROL, LLC(1.10%)
GEORGE MEEKS LANDPRO, INC. (2.83%)
MCDONALD ELECTRIC(4.00%)
KAM CONSTRUCTION, INC. (0.32%)
REGIONAL TRAFFIC SERVICES LLC(0.20%)
Contract # 04133209
Totals 1525267.27 136917.58 1143522.82 75.0

CountyHARRIS
Highway VA
From FANNIN & MN ST ESPLANADES CAMBRIDGE
To MECOM FOUNTAIN
CSJ 0912-70-078
Proj ID STP 2011(255)TE
Work Type ENHANCEMENT PROJECT
 
0.807 2581444.90 179238.03 1914945.78 74.1
Work Order 09-26-13
Work Began 10-21-13
Work Completed  
Time Computed 10-12-13
Contract Working Days 176
Addl Days Granted 32
Working Days Charged 190
Percent Time Used 91
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-078
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
DOWN UNDER CONSTRUCTION(1.83%)
SPECIALTY DRILLING (0.02%)
BUILDER SERVICES CO. (1.50%)
LEXTEX, INC. (7.15%)
Contract # 06133013
Totals 2581444.90 179238.03 1914945.78 74.1

CountyHARRIS
Highway VA
From BW 8, NORTH OF IH 10
To EAST OF SH 249
CSJ 0912-70-080
Proj ID HP 1102(309)
Work Type LANDSCAPE DEVELOPMENT
 
21.348 1437954.68 5525.00 1460298.84 99.9
Work Order 10-07-11
Work Began 11-07-11
Work Completed  
Time Computed 10-23-11
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 100
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-080
ENVIRONMENTAL ALLIES, L.P. (0.80%)
Contract # 08113035
Totals 1437954.68 5525.00 1460298.84 99.9

CountyHARRIS
Highway VA
From BW 8, FROM HOLLISTER
To MESA
CSJ 0912-70-081
Proj ID NH 2012(345)
Work Type LANDSCAPE DEVELOPMENT
 
14.413 1200452.82 3232.00 1042736.70 86.8
Work Order 05-04-12
Work Began 11-01-12
Work Completed  
Time Computed 05-20-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 99
Contractor(s)
BOYER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-081
CONROE WOOD PRODUCTS INC.(0.93%)
CC TREE FARMS, L.L.C.(3.47%)
Contract # 03123012
Totals 1200452.82 3232.00 1042736.70 86.8

CountyHARRIS
Highway VA
From US 59
To IH 10 EAST
CSJ 0912-70-085
Proj ID HP 2013(693)
Work Type LANDSCAPE DEVELOPMENT
 
5.800 810065.64 6871.96 570679.99 70.4
Work Order 11-25-13
Work Began 02-04-14
Work Completed  
Time Computed 01-25-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 82
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133227
Totals 810065.64 6871.96 570679.99 70.4

CountyHARRIS
Highway VA
From VARIOUS LOCATIONS IN HARRIS COUNTY
To .
CSJ 0912-70-099
Proj ID NH 2014(640)
Work Type CONST CURB RAMPS
 
0.001 2767522.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-02-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-70-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143031
Totals 2767522.72 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10