Monthly State Let Construction Report For Houston District As Of Jun 12, 2017 Page 2 Of 10

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayUS 290 ETC
FromWEST OF FM 529
ToE OF W LITTLE YORK (SEGMENT 6)
CSJ0050-09-071
Proj IDNH 2013(082)
Work TypeGR, STRS, BASE AND PAVE
 
6.056110414015.10109944201.9995.8
Work Order02-13-13
Work Began02-27-13
Work Completed
Time Computed02-01-13
Contract Working Days1,170
Addl Days Granted0
Working Days Charged1,169
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-09-071
ARANDA BROTHERS CONSTRUCTION, INC. (0.68)
BATTERSON,LLP (0.75)
ENVIRONMENTAL ALLIES, L.P. (0.10)
BORCO OF TEXAS, INC. (1.07)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.23)
CURB PLANET INC. (0.03)
D G MEDINA CONSTRUCTION, LLC (0.22)
FARR FOUNDATION, INC. (0.20)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
HOUSTON SAWING & DRILLING (0.03)
INDUS CONSTRUCTION, L.P. (0.90)
J.H. PAINTING COMPANY (0.27)
KELLYSTONE, INC (0.03)
KOSSMAN CONTRACTING CO., INC. (0.08)
RDI FOUNDATION DRILLING (2.38)
R K STEPHENS CONSTRUCTION, LLC (1.04)
SPEEDY PAVING (0.25)
T & C CONSTRUCTION, INC. (3.02)
WILLOW CITY SIGN & RAIL, INC. (0.47)
LAZER CONSTRUCTION COMPANY, INC. (0.82)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.07)
STEEL EFFECTS (0.13)
NORTHWEST MATERIALS (0.08)
SPRINT SAND AND CLAY, LLC (1.47)
SOUTHERN CRUSHED CONCRETE LLC (1.42)
MAGNOLIA SERVICES INCORPORATED (0.17)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (5.96)
MEDCALF FABRICATION, INC. (0.09)
C & B REBAR CONSTRUCTION, INC. (0.01)
(OLD PRIME)BORING & TUNNELING COMPANY OF AMERICA, INC. (0.13)
PFEIFFER & SON LTD. (0.58)
BRUNDAGE-BONE (0.07)
VALLEY PLACERS, LLC (0.10)
BATTEN DRILLING, INC. (0.21)
WEBBER BARRIER SERVICES, LLC. (1.29)
S & S MASONRY,INC. (0.02)
AAR INCORPORATED (0.01)
CPAVE, INC. (0.02)
H & S COMPANY (0.01)
MBN ENTERPRISES LLC (1.11)
AGGREGATE TECHNOLOGIES, INC. (0.01)
NATIONAL FENCE CO. (0.00)
D.H. GRIFFIN OF TEXAS, INC. (0.08)
INTERSTATE IMPROVEMENT, INC. (0.90)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.31)
CHANCE CONTRACTING (0.00)
Contract #09123202
Totals110414015.101038701.54109944201.9995.8

CountyHARRIS
HighwaySH 3
FromAT FM 2351 AND AT SOUTH SHAVER ROAD
To.
CSJ0051-02-079
Proj IDNH 2013(541)
Work TypeADD RT LN, RR WORK, W/SIGNALS
 
0.5481755643.651310830.0874.6
Work Order10-30-14
Work Began08-06-15
Work Completed
Time Computed04-28-15
Contract Working Days132
Addl Days Granted0
Working Days Charged104
Percent Time Used78
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-079
ROADSAFE TRAFFIC SYSTEMS, INC. (3.39)
CHAMPIONS HYDRO LAWN, INC. (0.22)
CENTRAL CONSTRUCTION SERVICES, INC. (0.05)
DUSTROL, INC. (3.66)
AGGREGATE TECHNOLOGIES, INC. (0.63)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (11.12)
SILT SOLUTIONS, INC. (0.31)
BADGER DAYLIGHTING CORP. (0.37)
CANALES TRUCKING INC. (0.85)
WILLOW CITY SIGN & RAIL, INC. (2.07)
SCMU (2.99)
GMJ PAVING CO. (25.75)
CURB PLANET INC. (2.52)
Contract #08133232
Totals1755643.6567393.411310830.0874.6

CountyGALVESTON
HighwaySH 3
FromAT SH 96
To.
CSJ0051-03-106
Proj IDSTP 1502(247)HES
Work TypeTS IMPRVMTS
 
0.750609218.50564783.8192.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-15
Work Began12-07-15
Work Completed
Time Computed11-14-15
Contract Working Days103
Addl Days Granted0
Working Days Charged102
Percent Time Used99
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-106
BAY CITY TRAFFIC (4.85)
Contract #06153226
Totals609218.500.00564783.8192.7

CountyGALVESTON
HighwaySH 87
FromAT 21ST STREET
To.
CSJ0051-04-063
Proj IDSTP 2016(045)HES
Work TypeTS IMPRVMTS
 
0.120699482.62871212.8299.9
Work Order12-21-15
Work Began05-24-16
Work Completed
Time Computed04-19-16
Contract Working Days139
Addl Days Granted0
Working Days Charged92
Percent Time Used66
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0051-04-063
STRIPE-A-LINE, INC. (0.74)
LONESTAR TRAFFIC SAFETY, LLC (1.19)
ISI CONTRACTING, INC. (11.73)
Contract #11153211
Totals699482.62807.52871212.8299.9

CountyGALVESTON
HighwaySS 342
FromIH 45
ToSEAWALL BLVD
CSJ0051-08-017
Proj IDNH 1602(169)
Work TypeMILL, BASE REP, OVERLAY & STRIPING
 
1.6451738923.022148202.8399.9
Work Order07-28-16
Work Began09-06-16
Work Completed
Time Computed08-27-16
Contract Working Days45
Addl Days Granted0
Working Days Charged36
Percent Time Used80
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0051-08-017
(USE 26488)STRIPE A LINE (4.08)
THIRD COAST SERVICES LLC (9.40)
MAIN LANE INDUSTRIES LTD. (4.29)
Contract #06163014
Totals1738923.0210277.282148202.8399.9

CountyFORT BEND
HighwayUS 59
FromWEST OF HAMLINK ROAD
ToWEST OF SPUR 10
CSJ0089-09-058
Proj IDC 89-9-58
Work TypeGR, STRS, BS & SURF
 
8.004100144090.3244701570.4244.6
Work Order01-06-16
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days919
Addl Days Granted0
Working Days Charged409
Percent Time Used44
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-058
BASE CONSTRUCTION (9.99)
CPAVE, INC. (0.24)
CREACOM, INC. (3.26)
ESSARY, HART & MACWILIAM,INC. (6.93)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INTERSTATE BARRICADES & MARKINGS, INC. (0.96)
QUALITY TURF FARMS, LC (2.08)
SCOTT DERR PAINTING CO, LLC (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.13)
BORTUNCO (0.23)
WASTE PARTNERS OF TEXAS, INC (0.07)
Contract #12153001
Totals100144090.321086674.9744701570.4244.6

CountyFORT BEND
HighwayUS 59
FromWHARTON COUNTY LINE
ToW OF DARST RD
CSJ0089-09-067
Proj IDC 89-9-67
Work TypeGR, STRS, BS & SURF
 
2.77137743798.5511872877.3331.4
Work Order08-12-16
Work Began08-29-16
Work Completed
Time Computed08-29-16
Contract Working Days1,208
Addl Days Granted0
Working Days Charged220
Percent Time Used18
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-067
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.94)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.69)
WILLOW CITY SIGN & RAIL, INC. (2.12)
SCOTT DERR PAINTING CO (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24)
EROSION PREVENTION PRODUCTS (0.50)
QUALITY TURF FARMS, LC (0.88)
DORAN STEEL, INC. (7.47)
WASTE PARTNERS OF TEXAS, INC (0.32)
Contract #07163001
Totals37743798.55445017.7111872877.3331.4

CountyMONTGOMERY ETC
HighwayIH 45
FromMONTGOMERY COUNTY LINE
ToLOOP 336 SOUTH
CSJ0110-04-195
Proj IDNH 1502(618)
Work TypeLANDSCAPE DEVELOPMENT
 
47.4543256878.262327132.6671.4
Work Order12-04-15
Work Began03-29-16
Work Completed
Time Computed01-04-16
Contract Working Days120
Addl Days Granted6
Working Days Charged127
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-195
G & A BORING (0.15)
Contract #08153238
Totals3256878.2671018.752327132.6671.4

CountyHARRIS
HighwayIH 45
FromAT FM 525
To.
CSJ0110-06-136
Proj IDSTP 1502(120)HES
Work TypeIMPROVE TS
 
0.001279667.05314000.1099.9
Work Order11-12-15
Work Began05-23-16
Work Completed
Time Computed05-10-16
Contract Working Days60
Addl Days Granted0
Working Days Charged56
Percent Time Used93
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-06-136
PRECISE SERVICES, INC. (12.65)
SELRICO COMMUNICATIONS (0.54)
STRIPE LINES, INC. (4.58)
Contract #08153226
Totals279667.050.00314000.1099.9

CountyBRAZORIA
HighwayBS 288B
FromCEMETERY ROAD
ToBASTROP BAYOU
CSJ0111-07-048
Proj IDSTP 2017(633)
Work TypePV REP & ACP O/L
 
10.1515258450.721629349.8830.9
Work Order03-08-17
Work Began04-17-17
Work Completed
Time Computed04-07-17
Contract Working Days151
Addl Days Granted0
Working Days Charged34
Percent Time Used22
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-07-048
THIRD COAST SERVICES LLC (7.52)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.30)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.62)
BATTERSON,LLP (4.06)
MAIN LANE INDUSTRIES LTD. (2.24)
HOLES INCORPORATED (0.29)
Contract #02173211
Totals5258450.721170436.281629349.8830.9

CountyWALLER
HighwayUS 290
FromOLD HOWTH ROAD
ToJONES ROAD
CSJ0114-11-076
Proj IDSTP 2017(634)HES
Work TypeTS IMPRVMTS
 
0.311181056.63198911.4099.9
Work Order02-09-17
Work Began04-17-17
Work Completed
Time Computed04-10-17
Contract Working Days23
Addl Days Granted0
Working Days Charged8
Percent Time Used34
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-076
PROFFESSIONAL TRAFFIC CONTROL, LLC. (12.24)
TRAF-TEX, INC. (18.33)
Contract #01173257
Totals181056.6324573.34198911.4099.9

CountyHARRIS
HighwayUS 290
FromFM 2920
ToBADTKE ROAD (SEGMENT 12)
CSJ0114-12-007
Proj IDNH 2013(733)
Work TypeGR, STRS, BASE AND PAVE
 
6.52660092663.9645117663.2875.0
Work Order07-22-15
Work Began07-27-15
Work Completed
Time Computed10-21-15
Contract Working Days536
Addl Days Granted38
Working Days Charged452
Percent Time Used78
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-007
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.87)
MESA ROD BUSTERS, INC. (6.67)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.43)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.00)
BASE CONSTRUCTION (3.36)
QUALITY TURF FARMS, LC (2.53)
BAY CITY TRAFFIC (0.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.34)
SCOTT DERR PAINTING CO (0.01)
CEN-TEX IRRIGATION SYSTEMS, INC. (0.14)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (0.20)
ROADWAY CONSTRUCTION, LLC (0.85)
Contract #06153201
Totals60092663.961192138.8645117663.2875.0

CountyMONTGOMERY
HighwayIH 69
FromN. OF FM 2090
ToS. OF EAST RIVER
CSJ0177-05-093
Proj IDC 177-5-93
Work TypeGR, BASE AND PVT
 
1.4577416768.137782027.5699.9
Work Order12-01-15
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days248
Addl Days Granted0
Working Days Charged238
Percent Time Used95
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-093
CPAVE, INC. (0.58)
GMJ PAVING CO. (4.27)
MESA ROD BUSTERS, INC. (1.14)
SOUTHERN CRUSHED CONCRETE LLC (1.02)
STRIPE-A-LINE, INC. (0.59)
TEX OP CONSTRUCTION, LP (0.42)
THIRD COAST SERVICES LLC (2.74)
WILLOW CITY SIGN & RAIL, INC. (0.60)
A-1 EROSION CONTROL, LLC (0.09)
SILT SOLUTIONS, INC. (3.11)
LONESTAR TRAFFIC SAFETY, LLC (0.17)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.14)
SCOTT DERR PAINTING CO, LLC (0.02)
Contract #05153038
Totals7416768.135500.007782027.5699.9

CountyMONTGOMERY
HighwayIH 69
FromHARRIS COUNTY
ToLIBERTY COUNTY LINE
CSJ0177-05-110
Proj IDNH 1402(089)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0021838258.201661196.6090.4
Work Order11-03-14
Work Began01-14-15
Work Completed
Time Computed01-02-15
Contract Working Days90
Addl Days Granted0
Working Days Charged91
Percent Time Used101
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-110
G & A BORING (56.49)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
Contract #08143233
Totals1838258.209355.441661196.6090.4

CountyBRAZORIA
HighwaySH 35
FromAT INDUSTRIAL DR
To.
CSJ0178-02-088
Proj IDNH 2017(483)
Work TypeADD LEFT TURN LANE
 
0.278261915.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0178-02-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173206
Totals261915.900.000.000.0

CountyFORT BEND
HighwaySS 10
FromUS 59 SOUTH
ToSH 36
CSJ0187-05-048
Proj IDSTP 1602(587)MM
Work TypeGR, STRS, BASE & SURF
 
4.82511736891.345753573.4149.0
Work Order09-15-16
Work Began09-26-16
Work Completed
Time Computed11-14-16
Contract Working Days219
Addl Days Granted0
Working Days Charged150
Percent Time Used68
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-048
SCOTT DERR PAINTING CO (0.00)
QUALITY TURF FARMS, LC (3.34)
MESA ROD BUSTERS, INC. (1.27)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.45)
WILLOW CITY SIGN & RAIL, INC. (0.72)
BATTERSON,LLP (1.90)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (13.32)
Contract #08163006
Totals11736891.34708634.455753573.4149.0

CountyFORT BEND
HighwaySH 36
FromSP 10
ToAUSTIN C/L
CSJ0187-05-060
Proj IDNH 1602(074)
Work TypeBASE REP AND OVERLAY
 
34.9794918131.865235028.0699.9
Work Order11-29-16
Work Began01-25-17
Work Completed
Time Computed01-28-17
Contract Working Days120
Addl Days Granted0
Working Days Charged80
Percent Time Used66
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-060
MARTIN ASPHALT COMPANY (1.02)
ROADSAFE TRAFFIC SYSTEMS, INC. (5.55)
THIRD COAST SERVICES LLC (0.31)
TROUT TRUCKING_COMPANY INC. (0.05)
WEST TEXAS RUMBLE STRIP (0.38)
Contract #05163013
Totals4918131.861653175.745235028.0699.9

CountyBRAZORIA
HighwaySH 35
FromSH 36
To17TH ST
CSJ0188-07-005
Proj IDCM 2016(268)
Work TypeCONSTRUCT SIDEWALKS
 
0.589741699.95632606.8691.8
Work Order05-09-16
Work Began07-12-16
Work Completed
Time Computed07-08-16
Contract Working Days71
Addl Days Granted19
Working Days Charged170
Percent Time Used188
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0188-07-005
LONESTAR TRAFFIC SAFETY, LLC (0.46)
CENTEX HYDROSEED (1.75)
REPUBLIC TRAFFIC SAFETY, INC. (0.32)
Contract #11153011
Totals741699.9517279.25632606.8691.8

CountyBRAZORIA
HighwaySH 6
FromFORT BEND COUNTY LINE
ToBS 35-C
CSJ0192-02-050
Proj IDCM 1602(269)
Work TypeACCESS MANAGEMENT IMPROVEMENTS
 
17.9164942808.252733812.2255.3
Work Order08-29-16
Work Began01-03-17
Work Completed
Time Computed11-27-16
Contract Working Days237
Addl Days Granted0
Working Days Charged124
Percent Time Used52
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0192-02-050
GMJ PAVING CO. (2.51)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.22)
THIRD COAST SERVICES LLC (15.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.65)
CHERRY CRUSHED CONCRETE (0.14)
BATTERSON,LLP (12.75)
SPEEDY PAVING (4.83)
CURB PLANET INC. (0.43)
SPECIALTY DRILLING, LTD. (0.33)
Contract #07163038
Totals4942808.25766308.262733812.2255.3

CountyWALLER
HighwayIH 10
FromBRAZOS RIVER
ToFM 359
CSJ0271-04-071
Proj IDNH 1702(007)
Work TypeCONST 1 MORE ML EACH DIRECTION
 
5.820141496478.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,391
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0271-04-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173201
Totals141496478.120.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10