| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
US 59 N |
| To |
900' S OF GELLHORN |
| CSJ |
0271-14-197 |
| Proj ID |
IM 6107(410) |
| Work Type |
BOND CONC O / L, RECONST ML & BR SLAB |
| |
|
5.347 |
76484640.02 |
778469.77 |
79388327.02 |
99.2 |
| Work Order |
10-13-06 |
| Work Began |
09-07-07 |
| Work Completed |
|
| Time Computed |
10-29-06 |
| Contract Working Days |
1,203 |
| Addl Days Granted |
125 |
| Working Days Charged |
1,266 |
| Percent Time Used |
95 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-197 WILLOW CITY SIGN & RAIL, INC.(0.53%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(2.11%) SCOTT DERR PAINTING CO (0.08%) HOUSTON SAWING & DRILLING(0.04%) BORING & TUNNELING COMPANY OF AMERICA, INC.(0.15%) EROSION CONTROL, INC.(0.39%) INDUS CONSTRUCTION, L.P. (9.95%) JONES HIGHWAY MAINTENANCE(0.00%) FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.02%) SPECIALTY DRILLING (0.51%) SILVA CONTRACTING COMPANY, INC.(1.46%) AMERICAN TRAFFIC CONTROL (0.01%) WEBBER-BALKE FOUNDATION COMPANY, INC.(0.35%) POLY-CARB, INC.(0.38%) EROSION PREVENTION PRODUCTS(0.73%) HASSELL CONSTRUCTION COMPANY, INC. (0.05%) HOLES INCORPORATED (0.00%) ASHTON SAWING AND DRILLING LLC (0.05%) CURB PLANET INC. (0.04%)
|
| Contract # |
08063001 |
|
Totals |
76484640.02 |
778469.77 |
79388327.02 |
99.2 |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
TC JESTER TO N OF IH 10 ON IH 610 |
| To |
AND TO 34TH ST ON US 290 |
| CSJ |
0271-14-217 |
| Proj ID |
STP 2011(998)MM |
| Work Type |
GR, STRS, BASE AND PAVE |
| |
|
5.604 |
151578391.02 |
2859564.92 |
39573913.60 |
26.0 |
| Work Order |
06-15-11 |
| Work Began |
06-20-11 |
| Work Completed |
|
| Time Computed |
07-11-11 |
| Contract Working Days |
1,124 |
| Addl Days Granted |
0 |
| Working Days Charged |
148 |
| Percent Time Used |
13 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-217 INTERSTATE BARRICADES & MARKINGS, INC. (0.54%) FLORIDA TRAFFIC CONTROL DEVICES, INC.(5.43%) ESSARY, HART & MACWILIAM,INC.( 11.06%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.21%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%) SCOTT DERR PAINTING CO (0.58%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.77%) BORTUNCO (0.29%) SPECIALTY DRILLING (0.39%) AMERICAN TRAFFIC CONTROL, INC. (0.01%) TREVCON, INC.(0.09%)
|
| Contract # |
05113015 |
|
Totals |
151578391.02 |
2859564.92 |
39573913.60 |
26.0 |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
EAST OF ELLA |
| To |
IH 45 |
| CSJ |
0271-14-223 |
| Proj ID |
STP 2009(519)ES |
| Work Type |
RECONSTRUCT ROADWAY |
| |
|
2.910 |
28853986.56 |
4405.37 |
30437252.40 |
99.7 |
| Work Order |
09-01-09 |
| Work Began |
09-16-09 |
| Work Completed |
|
| Time Computed |
09-17-09 |
| Contract Working Days |
730 |
| Addl Days Granted |
7 |
| Working Days Charged |
735 |
| Percent Time Used |
99 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-14-223 GIBSON & ASSOCIATES, INC.(2.50%) JTB SERVICES (2.75%) BREDA COMPANY, INC.(1.76%) EL DORADO PAVING COMPANY, INC. (1.57%) WILLOW CITY SIGN & RAIL, INC.(0.66%) NORTHWEST MATERIALS(0.42%) CPAV SPECIALTIES, LP (0.61%) HIGHWAY TECHNOLOGIES, INC. (0.16%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.12%) JOE VALENCIK, INC. (1.60%) EARTH MATERIAL SERVICES, LLC.(3.39%) MCRAY CRANE(0.10%) BATTERSON,LLP(0.94%) SCOTT DERR PAINTING CO (0.35%)
|
| Contract # |
07093001 |
|
Totals |
28853986.56 |
4405.37 |
30437252.40 |
99.7 |
|
| County | HARRIS |
| Highway |
IH 610 |
| From |
.122 MILES WST OF SH 35 |
| To |
.228 MILES WEST OF LONG DRIVE |
| CSJ |
0271-16-131 |
| Proj ID |
IM 6107(432) |
| Work Type |
HIGH MAST ILLUMINATION |
| |
|
2.016 |
1018574.45 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-03-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0271-16-131 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12113012 |
|
Totals |
1018574.45 |
0.00 |
0.00 |
0.0 |
|
| County | MONTGOMERY |
| Highway |
SH 105 |
| From |
LP 336W |
| To |
SH 75 |
| CSJ |
0338-03-086 |
| Proj ID |
NH 2012(207) |
| Work Type |
BASE & ASPHALT REPAIR, OCST |
| |
|
5.632 |
2748532.60 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SMITH & COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0338-03-086 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01123024 |
|
Totals |
2748532.60 |
0.00 |
0.00 |
0.0 |
|
| County | GALVESTON |
| Highway |
SH 87 |
| From |
N GALVESTON-BOLIVAR FERRY LANDING |
| To |
S GALVESTON-BOLIVAR FERRY LANDING |
| CSJ |
0367-05-047 |
| Proj ID |
ER 2009(935) |
| Work Type |
REPAIR DAMAGE TO FERRY LANDING |
| |
|
1.750 |
3147777.00 |
0.00 |
3302184.95 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-07-10 |
| Work Began |
01-23-10 |
| Work Completed |
|
| Time Computed |
01-23-10 |
| Contract Working Days |
270 |
| Addl Days Granted |
27 |
| Working Days Charged |
272 |
| Percent Time Used |
91 |
| Contractor(s) |
| TEXAS GULF CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0367-05-047 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12093222 |
|
Totals |
3147777.00 |
0.00 |
3302184.95 |
99.9 |
|
| County | HARRIS |
| Highway |
BS 146E |
| From |
BS 146E WEST BOUND AT GOOSE CREEK |
| To |
. |
| CSJ |
0389-03-035 |
| Proj ID |
BR 2009(734) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.259 |
2543254.76 |
120649.96 |
1970252.07 |
82.9 |
| Work Order |
07-19-10 |
| Work Began |
11-01-10 |
| Work Completed |
|
| Time Computed |
08-04-10 |
| Contract Working Days |
129 |
| Addl Days Granted |
52 |
| Working Days Charged |
355 |
| Percent Time Used |
196 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-03-035 SULLIVAN LAND SERVICES LTD (0.35%) A. H. BECK FOUNDATION CO., INC.( 14.74%) BREDA COMPANY, INC.(2.62%) RIVER CITIES SAWING LLC(0.16%) PROFESSIONAL TRAFFIC CONTROL, LLC(0.51%) AAA ASPHALT PAVING, INC. (8.80%) ROMAR DUMP TRUCK SERVICES(0.08%) TOM-MAC, INC.(5.50%) TURNER BROS. CRANE & RIGGING (0.58%) JUST GROOVING, LTD.(0.14%)
|
| Contract # |
04103207 |
|
Totals |
2543254.76 |
120649.96 |
1970252.07 |
82.9 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
FERRY ROAD |
| To |
CHAMBERS C/L |
| CSJ |
0389-03-036 |
| Proj ID |
NH 1102(107) |
| Work Type |
RBL REP, SL COAT, RBL O / L & PFC |
| |
|
2.660 |
1963261.77 |
0.00 |
2053089.35 |
99.9 |
| Work Order |
07-19-11 |
| Work Began |
08-17-11 |
| Work Completed |
|
| Time Computed |
08-04-11 |
| Contract Working Days |
75 |
| Addl Days Granted |
0 |
| Working Days Charged |
63 |
| Percent Time Used |
84 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-03-036 HIGHWAY TECHNOLOGIES, INC. (5.62%) SCR CONSTRUCTION CO., INC. (0.70%)
|
| Contract # |
06113021 |
|
Totals |
1963261.77 |
0.00 |
2053089.35 |
99.9 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
AT BNSF RR/PORT ROAD |
| To |
. |
| CSJ |
0389-05-105 |
| Proj ID |
HP 2009(817) |
| Work Type |
CONSTRUCT DIRECT CONNECTORS |
| |
|
3.213 |
41949338.29 |
626986.72 |
31032950.41 |
73.9 |
| Work Order |
10-14-09 |
| Work Began |
10-26-09 |
| Work Completed |
|
| Time Computed |
10-30-09 |
| Contract Working Days |
931 |
| Addl Days Granted |
1 |
| Working Days Charged |
659 |
| Percent Time Used |
70 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-05-105 CURB PLANET INC. (0.03%) SCOTT DERR PAINTING CO (0.49%) ANGEL BROTHERS ENTERPRISES, LTD. (6.73%) CRAVENS PARTNERS, LTD. (7.03%) TRAF-TEX, INC. (6.18%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19%) EROSION CONTROL, INC.(1.26%) INDUS CONSTRUCTION, L.P. (5.92%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.51%) BATTERSON, L.L.P.(0.55%) BSP CONSTRUCTION (5.20%) KATY CONSTRUCTION(0.09%) SPECIALTY DRILLING (0.07%) DIXIE DRILLING COMPANY, INC. (0.05%) VAQUERO CONSTRUCTION, INC. (0.95%)
|
| Contract # |
08093202 |
|
Totals |
41949338.29 |
626986.72 |
31032950.41 |
73.9 |
|
| County | GALVESTON |
| Highway |
SH 146 |
| From |
N OF LOOP 197 |
| To |
S OF LOOP 197 |
| CSJ |
0389-06-098 |
| Proj ID |
STP 2011(032)MM |
| Work Type |
CONSTRUCT SB GRADE SEPARATION |
| |
|
1.231 |
7825859.49 |
116872.16 |
7801755.12 |
99.7 |
| Work Order |
09-01-10 |
| Work Began |
09-16-10 |
| Work Completed |
|
| Time Computed |
09-17-10 |
| Contract Working Days |
180 |
| Addl Days Granted |
12 |
| Working Days Charged |
197 |
| Percent Time Used |
102 |
| Contractor(s) |
| LONE STAR ROAD CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-06-098 BATTERSON,LLP(0.42%) MAIN LANE INDUSTRIES, LTD. (3.76%) NORTHWEST MATERIALS(0.11%) PENNTEX MILLING, LLC (0.22%) PROTECTIVE ENVIRONMENTAL STRATEGIES, INC.(0.25%) RDI FOUNDATION DRILLING( 12.72%) STRIPES & STOPS COMPANY, INC.(0.22%) WEST TEXAS RUMBLE STRIP(0.04%) SOUTH TEXAS PAINTING COMPANY (0.12%) JMHP, INC. (0.16%) MESA ROD BUSTERS, INC. (4.50%) DORAN STEEL, INC.(0.63%) EROSION CONTROL, INC.(0.36%) TRAF-TEX, INC. (0.19%) CURB PLANET INC. (0.01%) KOSSMAN CONTRACTING COMPANY(0.43%)
|
| Contract # |
07103064 |
|
Totals |
7825859.49 |
116872.16 |
7801755.12 |
99.7 |
|
| County | GALVESTON |
| Highway |
SH 146 |
| From |
AT FM 1765 |
| To |
. |
| CSJ |
0389-07-035 |
| Proj ID |
STP 1102(303)HESG |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.001 |
154993.60 |
0.00 |
74201.00 |
47.8 |
| Work Order |
09-14-11 |
| Work Began |
10-03-11 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
43 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
53 |
| Contractor(s) |
| TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-07-035 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08113015 |
|
Totals |
154993.60 |
0.00 |
74201.00 |
47.8 |
|
| County | HARRIS |
| Highway |
SH 146 |
| From |
AT BS 146E |
| To |
. |
| CSJ |
0389-13-055 |
| Proj ID |
STP 1102(142)HES |
| Work Type |
TRAFFIC SIGNAL |
| |
|
0.001 |
244341.77 |
0.00 |
0.00 |
0.0 |
| Work Order |
08-16-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-01-11 |
| Contract Working Days |
69 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CREACOM, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0389-13-055 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07113226 |
|
Totals |
244341.77 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
NYACK ROAD |
| To |
0.7881 MILES SOUTH OF FM 1959 |
| CSJ |
0500-03-462 |
| Proj ID |
C 500-3-462 |
| Work Type |
GR, STRS, BASE, AND PAVE |
| |
|
5.188 |
77483150.88 |
1932556.73 |
16047005.24 |
20.7 |
| Work Order |
06-15-11 |
| Work Began |
06-17-11 |
| Work Completed |
|
| Time Computed |
06-17-11 |
| Contract Working Days |
1,135 |
| Addl Days Granted |
0 |
| Working Days Charged |
155 |
| Percent Time Used |
13 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-462 BASE CONSTRUCTION, L.L.P.( 11.55%) DORAN STEEL, INC.( 11.03%) INTERSTATE BARRICADES & MARKINGS, INC. (1.06%) CREACOM, INC.(4.33%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.59%) WEST TEXAS RUMBLE STRIP(0.00%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.58%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33%) SCOTT DERR PAINTING CO (0.23%)
|
| Contract # |
05113210 |
|
Totals |
77483150.88 |
1932556.73 |
16047005.24 |
20.7 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
AT PARKER AND LITTLE YORK ROAD |
| To |
. |
| CSJ |
0500-03-553 |
| Proj ID |
IM 0451(338) |
| Work Type |
ARMOR JNT & WIDE FLNG BM REPR |
| |
|
0.130 |
364992.00 |
0.00 |
0.00 |
0.0 |
| Work Order |
06-10-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-26-11 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
31 |
| Percent Time Used |
86 |
| Contractor(s) |
| SPRING EQUIPMENT CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-553 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05113014 |
|
Totals |
364992.00 |
0.00 |
0.00 |
0.0 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
US 59 |
| To |
BW 8 SOUTH |
| CSJ |
0500-03-555 |
| Proj ID |
HP 2009(331) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
13.443 |
423082.94 |
3653.20 |
432675.59 |
99.9 |
| Work Order |
02-12-09 |
| Work Began |
03-04-09 |
| Work Completed |
|
| Time Computed |
02-28-09 |
| Contract Working Days |
780 |
| Addl Days Granted |
0 |
| Working Days Charged |
726 |
| Percent Time Used |
93 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-555 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01093021 |
|
Totals |
423082.94 |
3653.20 |
432675.59 |
99.9 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
HOUSTON CITY STREETS (AT TELLESPEN |
| To |
UNDERPASS) |
| CSJ |
0500-03-563 |
| Proj ID |
DMO 2006(885) |
| Work Type |
FLOOD / DRAINAGE IMPROVEMENTS |
| |
|
0.549 |
3069254.60 |
250365.94 |
1483926.90 |
48.3 |
| County | HARRIS |
| Highway |
IH 45 |
| From |
HOUSTON CITY STREETS (AT TELLESPEN |
| To |
UNDERPASS) |
| CSJ |
0500-03-568 |
| Proj ID |
IM 0451(337) |
| Work Type |
ROW UTL. ADJ. |
| |
|
0.001 |
0.00 |
0.00 |
0.00 |
0.0 |
| Work Order |
01-06-11 |
| Work Began |
06-28-11 |
| Work Completed |
|
| Time Computed |
03-06-11 |
| Contract Working Days |
391 |
| Addl Days Granted |
0 |
| Working Days Charged |
163 |
| Percent Time Used |
41 |
| Contractor(s) |
| TEXAS STERLING CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-563 BATTERSON,LLP(1.28%) PFEIFFER & SON LTD.(0.22%) ENVIRONMENTAL ALLIES, L.P. (0.54%) EL DORADO PAVING COMPANY, INC. (1.22%) T & C CONSTRUCTION, INC. ( 17.91%) CHERRY CONCRETE REMOVAL(0.32%) MAGNUM TUNNELING, LLC(1.09%)
|
| Contract # |
10103023 |
|
Totals |
3069254.60 |
250365.94 |
1483926.90 |
48.3 |
|
| County | HARRIS |
| Highway |
IH 45 |
| From |
NORTH OF HB&T RR |
| To |
NORTH OF AIRLINE |
| CSJ |
0500-03-564 |
| Proj ID |
IM 0451(340) |
| Work Type |
MILL, SC, RBL, PFC & PAV MARKS |
| |
|
1.230 |
1984915.07 |
0.00 |
1873280.11 |
94.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-16-11 |
| Work Began |
10-10-11 |
| Work Completed |
|
| Time Computed |
09-01-11 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
26 |
| Percent Time Used |
81 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-564 BATTERSON,LLP(3.16%)
|
| Contract # |
07113058 |
|
Totals |
1984915.07 |
0.00 |
1873280.11 |
94.3 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
MEADOW ROAD |
| To |
W OF BW 8 AT UPS RR (IN SECTIONS) |
| CSJ |
0508-01-323 |
| Proj ID |
HP 2011(167) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
10.931 |
855313.31 |
6810.47 |
740050.09 |
86.5 |
| Work Order |
10-04-10 |
| Work Began |
10-22-10 |
| Work Completed |
|
| Time Computed |
10-20-10 |
| Contract Working Days |
89 |
| Addl Days Granted |
0 |
| Working Days Charged |
81 |
| Percent Time Used |
91 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-323 XELLENT SERVICES (5.26%)
|
| Contract # |
08103018 |
|
Totals |
855313.31 |
6810.47 |
740050.09 |
86.5 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
AT UNION PACIFIC RAILROAD |
| To |
SPRING BAYOU |
| CSJ |
0508-01-324 |
| Proj ID |
HP 2011(168) |
| Work Type |
LANDSCAPE DEVELOPMENT |
| |
|
8.406 |
650522.13 |
7692.18 |
531487.70 |
81.7 |
| Work Order |
09-27-10 |
| Work Began |
10-18-10 |
| Work Completed |
|
| Time Computed |
10-13-10 |
| Contract Working Days |
90 |
| Addl Days Granted |
0 |
| Working Days Charged |
87 |
| Percent Time Used |
96 |
| Contractor(s) |
| BIO LANDSCAPE & MAINTENANCE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-324 XELLENT SERVICES (4.22%)
|
| Contract # |
08103218 |
|
Totals |
650522.13 |
7692.18 |
531487.70 |
81.7 |
|
| County | HARRIS |
| Highway |
IH 10 |
| From |
AT WAYSIDE |
| To |
. |
| CSJ |
0508-01-331 |
| Proj ID |
IM 0107(429) |
| Work Type |
INSTALL U - TURNS |
| |
|
0.208 |
1550849.21 |
0.00 |
0.00 |
0.0 |
| Work Order |
11-03-11 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-19-11 |
| Contract Working Days |
115 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ISI CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-331 FLORIDA TRAFFIC CONTROL DEVICES, INC.( 31.27%) HIGHWAY TECHNOLOGIES, INC. (1.74%) CRAIG & HEIDT, INC.(1.42%) CHERRY CONCRETE REMOVAL(0.52%) GULF COAST PAVERS, INC.(2.21%) SCOTT DERR PAINTING CO, LLC(0.33%)
|
| Contract # |
09113029 |
|
Totals |
1550849.21 |
0.00 |
0.00 |
0.0 |
|