Monthly State Let Construction Report For Houston District As Of Mar 13, 2017 Page 10 Of 10

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayFM 270
FromHENDERSON ST
ToHARRIS COUNTY LINE
CSJ3312-01-008
Proj IDCM 2013(571)
Work TypeBICYCLE/PEDESTRIAN IMPROVEMENTS
 
1.1363845442.262425187.2963.0
Work Order01-08-16
Work Began05-09-16
Work Completed
Time Computed05-07-16
Contract Working Days225
Addl Days Granted0
Working Days Charged164
Percent Time Used72
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 3312-01-008
REBAR SUPPLY COMPANY, LTD. (3.29)
BATTERSON,LLP (0.97)
BELL BOTTOM FOUNDATION CO. (6.42)
JE CASEY, LLC (1.02)
KOSSMAN CONTRACTING CO., INC. (1.18)
NEW WORLD_CONTRACTING LLC (1.63)
ROSALES TRUCKING (2.44)
SCOTT DERR PAINTING CO, LLC (0.02)
TOM-MAC, INC. (3.91)
DORAN STEEL, INC. (0.48)
ENVIRONMENTAL ALLIES, L.P. (0.46)
INDUS CONSTRUCTION, L.P. (0.54)
SCMU (0.52)
Contract #08153027
Totals3845442.26130273.502425187.2963.0

CountyGALVESTON
HighwayFM 270
FromFM 518/FM 2094
ToFM 270
CSJ3312-02-014
Proj IDC 3312-2-14
Work TypeREALIGN ROADWAY
 
0.5022299180.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3312-02-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173254
Totals2299180.800.000.000.0

CountyFORT BEND
HighwaySH 99
FromAT HARLEM ROAD
ToSH 99 AT HARLEM ROAD, NB & SB
CSJ3510-04-053
Proj IDNH 2017(247)
Work TypeADD UTN, LT TN LNS & REBUILD SIGNAL
 
0.5512240983.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days147
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAR-CON SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3510-04-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163012
Totals2240983.050.000.000.0

CountyMONTGOMERY
HighwaySH 242
FromAT FM 1485
To.
CSJ3538-01-044
Proj IDSTP 2016(722)HES
Work TypeTS IMPRVMTS
 
0.500275772.88100034.4036.2
Work Order03-08-16
Work Began07-27-16
Work Completed
Time Computed07-06-16
Contract Working Days38
Addl Days Granted0
Working Days Charged28
Percent Time Used73
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 3538-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02163036
Totals275772.880.00100034.4036.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10