Monthly State Let Construction Report For Houston District As Of Apr 10, 2015 Page 10 Of 11

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRIS
Highway FM 1942
From US 90
To CROSBY LYNCHBURG RD
CSJ 1062-05-009
Proj ID STP 2015(614)MM
Work Type WIDEN ROADWAY
 
0.315 3477178.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-05-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153223
Totals 3477178.18 0.00 0.00 0.0

CountyHARRIS
Highway FM 1093
From 3.6 MILES WEST OF IH 610
To 0.25 MILES EAST OF SH 6
CSJ 1258-04-056
Proj ID CM 2013(790)
Work Type IMPLEMENTATION OF ACCESS MGMT
 
7.386 2561914.38 25178.24 2742021.35 99.9
Work Order 11-04-13
Work Began 02-11-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 98
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-056
KOSSMAN CONTRACTING CO., INC.(0.45%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.22%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC( 35.08%)
A TO Z PAVING(0.58%)
Contract # 07133031
Totals 2561914.38 25178.24 2742021.35 99.9

CountyHARRIS
Highway FM 1093
From AT BW 8
To .
CSJ 1258-04-060
Proj ID STP 2015(163)HESG
Work Type IMPROVE TS
 
0.202 493967.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143025
Totals 493967.08 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1097
From FM 149
To IH 45
CSJ 1259-01-039
Proj ID STP 2015(541)
Work Type BASE REPAIR AND ACP O / L
 
13.600 4097441.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 05-13-15
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153217
Totals 4097441.59 0.00 0.00 0.0

CountyMONTGOMERY
Highway FM 1774
From 0.045 MI S OF W. LOST CREEK BLVD
To FM 149
CSJ 1400-04-011
Proj ID STP 1402(182)
Work Type GR, STRS, BS & CONC PAV
 
2.831 18070204.05 0.00 150000.00 0.8
Work Order 11-03-14
Work Began 00-00-00
Work Completed  
Time Computed 11-19-14
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143203
Totals 18070204.05 0.00 150000.00 0.8

CountyMONTGOMERY
Highway FM 1774
From 0.109 MI N OF FM 1488
To 0.045 MI S OF W LOST CREEK BLVD
CSJ 1400-04-035
Proj ID STP 1102(437)
Work Type RECONSTRUCT ROADWAY
 
2.320 11301777.00 185055.22 13601007.62 99.9
Work Order 11-03-11
Work Began 12-06-11
Work Completed  
Time Computed 11-19-11
Contract Working Days 280
Addl Days Granted 302
Working Days Charged 541
Percent Time Used 92
Contractor(s)
HASSELL CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-035
GULF COAST PAVERS, INC.(0.22%)
GMJ PAVING CO. (7.32%)
H & H CURB COMPANY (0.12%)
BREDA COMPANY, INC.(0.89%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.55%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.36%)
BATTERSON,LLP(1.83%)
THIRD COAST SERVICES, LLC(4.26%)
URBAN FORESTERS, LLC (0.44%)
CHAMPIONS HYDRO-LAWN (0.80%)
Contract # 08113209
Totals 11301777.00 185055.22 13601007.62 99.9

CountyBRAZORIA
Highway FM 1462
From AT COUNTY ROAD 185
To .
CSJ 1414-03-039
Proj ID STP 2013(791)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.283 481635.62 0.00 531320.61 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-12-13
Work Began 03-11-14
Work Completed 01-23-15
Time Computed 11-11-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 98
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1414-03-039
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
BATTERSON,LLP(3.54%)
JMHP, INC. (1.34%)
MIKE SORRELL TRUCKING AND MATERIALS, INC.(0.72%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.97%)
Contract # 07133015
Totals 481635.62 0.00 531320.61 100.0

CountyBRAZORIA
Highway SH 332
From FM 521
To FM 2004
CSJ 1524-01-078
Proj ID STP 1502(016)
Work Type PV REP, MILL, BS REP, O / L, PV MKS
 
12.109 3739396.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1524-01-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153207
Totals 3739396.99 0.00 0.00 0.0

CountyGALVESTON
Highway FM 1764
From CENTURY BLVD INT FROM 14TH STREET
To 21ST STREET
CSJ 1607-01-050
Proj ID STP 2011(250)TE
Work Type ENHANCEMENT PROJECT
 
1.200 704750.96 3842.93 705039.26 99.9
Work Order 09-05-13
Work Began 10-22-13
Work Completed  
Time Computed 10-22-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 102
Contractor(s)
BIO LANDSCAPE & MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1607-01-050
CC TREE FARMS, L.L.C.(0.93%)
ENVIRONMENTAL ALLIES, L.P. (0.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.35%)
VACA UNDERGROUND UTILITIES INC (1.38%)
PFEIFFER & SON LTD.( 30.86%)
RANGEL CONSTRUCTION(5.95%)
Contract # 06133212
Totals 704750.96 3842.93 705039.26 99.9

CountyHARRIS
Highway FM 1960
From IH 45
To 6.5 MI E OF IH 45 (HUMBLE BYPASS)
CSJ 1685-02-049
Proj ID NH 2013(064)
Work Type PAVEMENT MARKINGS
 
14.553 546380.10 0.00 390018.83 80.6
Work Order 10-18-12
Work Began 11-18-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 203
Percent Time Used 169
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-02-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123024
Totals 546380.10 0.00 390018.83 80.6

CountyHARRIS
Highway FM 1960
From AT LEE ROAD
To .
CSJ 1685-03-092
Proj ID STP 2014(585)HES
Work Type IMPROVE TS
 
0.606 732234.51 126656.50 449699.44 61.4
Work Order 06-05-14
Work Began 03-03-15
Work Completed  
Time Computed 12-02-14
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 45
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1685-03-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143011
Totals 732234.51 126656.50 449699.44 61.4

CountyHARRIS
Highway SH 6
From IH 10 W.
To US 290
CSJ 1685-05-104
Proj ID NH 2014(300)
Work Type ACCESS MANAGEMENT
 
12.205 3853845.41 422380.98 2580092.15 66.9
Work Order 04-17-14
Work Began 07-10-14
Work Completed  
Time Computed 06-16-14
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 96
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 1685-05-104
CURB PLANET INC. (2.25%)
GMJ PAVING CO. (1.69%)
HOLES INCORPORATED (3.23%)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC(6.74%)
SPEEDY PAVING(9.48%)
BILL MURFF TURF FARM, INC. (0.68%)
BATTERSON,LLP(5.84%)
CHAMPIONS HYDRO-LAWN (0.05%)
CHERRY CRUSHED CONCRETE(0.76%)
SILT SOLUTIONS, INC. (0.11%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.96%)
WEBBER BARRIER SERVICES, LLC.(4.46%)
STRIPES & STOPS COMPANY, INC.(1.05%)
Contract # 02143213
Totals 3853845.41 422380.98 2580092.15 66.9

CountyHARRIS
Highway BF1960A
From FM 1960 W OF LEE RD
To FM 1960 E OF HUMBLE
CSJ 1685-07-005
Proj ID C 1685-7-5
Work Type IMPLEMENT ACCESS MANAGEMENT
 
3.920 6976168.04 176.00 1104742.87 15.8
CountyHARRIS
Highway BF1960A
From LEE ROAD
To FM 1960(E)
CSJ 1685-07-019
Proj ID STP 2013(994)
Work Type BS REP, MILL, SC INTERLAYER, OL, ETC
 
4.200 6317731.97 6664.30 51248.40 0.8
Work Order 09-30-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 15
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1685-07-019
ANGEL BROTHERS ENTERPRISES, LTD. ( 27.60%)
KOSSMAN CONTRACTING CO., INC.(1.14%)
REGIONAL TRAFFIC SERVICES LLC(0.84%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.49%)
TRAFFIC SYSTEMS CONSTRUCTION, INC. ( 12.57%)
H & E AGGREGATE, LLC (3.50%)
Contract # 08133014
Totals 13293900.01 6840.30 1155991.27 8.6

CountyHARRIS
Highway FM 1942
From AT N MAIN STREET
To .
CSJ 1812-01-021
Proj ID STP 2015(542)
Work Type CONSTRUCT LEFT TURN LANE
 
0.532 948590.00 0.00 50087.50 5.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 30
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1812-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153212
Totals 948590.00 0.00 50087.50 5.2

CountyFORT BEND
Highway FM 2234
From FM 3345
To FORT BEND TOLL ROAD
CSJ 2105-01-046
Proj ID C 2105-1-46
Work Type GR, STRS, BS & SURF
 
1.458 8068060.38 214827.21 7632865.23 94.6
Work Order 10-30-13
Work Began 01-21-14
Work Completed  
Time Computed 12-29-13
Contract Working Days 215
Addl Days Granted 9
Working Days Charged 211
Percent Time Used 94
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-046
B & D MAINTENANCE(1.89%)
CPAVE, INC.(0.31%)
SCOTT DERR PAINTING CO, LLC(0.13%)
DUSTROL, INC.(1.65%)
THIRD COAST SERVICES LLC (8.64%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.89%)
BATTERSON,LLP(2.16%)
A-1 EROSION CONTROL, LLC (2.12%)
BREDA COMPANY, INC.(0.79%)
H & E AGGREGATE, LLC (7.21%)
SILVA CONSTRUCTION, INC. (3.85%)
Contract # 07133218
Totals 8068060.38 214827.21 7632865.23 94.6

CountyFORT BEND
Highway FM 2234
From US 90A
To TURTLE CREEK DR
CSJ 2105-01-047
Proj ID STP 2013(698)MM
Work Type INTERSECTION IMPROVEMENTS
 
0.314 1659983.68 0.00 1682037.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 02-19-14
Work Completed 01-12-15
Time Computed 10-01-13
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 98
Contractor(s)
MAIN LANE INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2105-01-047
TRAF-TEX, INC. ( 55.72%)
REGIONAL TRAFFIC SERVICES LLC(1.70%)
KOSSMAN CONTRACTING CO., INC.(0.22%)
ENERGY ELECTRIC SUPPLY, INC. (5.96%)
TEXAS REEXCAVATION (1.32%)
Contract # 05133015
Totals 1659983.68 0.00 1682037.39 100.0

CountyMONTGOMERY
Highway FM 2432
From AT TEXAS NATIONAL BOULEVARD
To .
CSJ 2325-01-016
Proj ID STP 2014(597)
Work Type INSTALL LEFT TURN LANE
 
0.256 399448.91 4154.68 405673.32 100.0
Work Order 07-22-14
Work Began 08-07-14
Work Completed 11-03-14
Time Computed 08-07-14
Contract Working Days 30
Addl Days Granted 2
Working Days Charged 22
Percent Time Used 68
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2325-01-016
DUSTROL, INC.(1.25%)
J & M CONTRACTING, COMPANY ( 12.20%)
LONESTAR TRAFFIC SAFETY, LLC (0.36%)
STRIPE-A-LINE, INC.(0.80%)
A-1 EROSION CONTROL, LLC (6.25%)
WILLOW CITY SIGN & RAIL, INC.(0.62%)
Contract # 06143062
Totals 399448.91 4154.68 405673.32 100.0

CountyBRAZORIA
Highway FM 2004
From AT CHOCOLATE BAYOU
To .
CSJ 2523-02-067
Proj ID STP 2015(417)
Work Type BR JT REP
 
0.409 262610.50 116845.48 185978.28 70.8
Work Order 01-13-15
Work Began 02-26-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 34
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2523-02-067
LONE STAR TRAFFIC SERVICE, INC.(0.74%)
Contract # 12143207
Totals 262610.50 116845.48 185978.28 70.8

CountyMONTGOMERY
Highway FM 2854
From AT O'GRADY
To .
CSJ 2744-01-030
Proj ID STP 1402(104)
Work Type INST LT TN LN
 
0.183 298966.25 0.00 293108.70 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 11-10-14
Work Completed 02-11-15
Time Computed 11-08-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 96
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2744-01-030
BIO LANDSCAPE & MAINTENANCE, INC.(4.50%)
LONESTAR TRAFFIC SAFETY, LLC (0.59%)
AQUALAWN HYDROMULCH & EROSION CONTROL(6.41%)
STRIPE-A-LINE, INC.(1.33%)
WILLOW CITY SIGN & RAIL, INC.(2.80%)
Contract # 08143235
Totals 298966.25 0.00 293108.70 100.0

CountyHARRIS
Highway FM 2920
From AT ROBERTS CEMETERY, LOBLOLLY,
To BINFORD & MUESCHKE
CSJ 2941-01-021
Proj ID STP 2013(462)
Work Type INTERSECTION IMPROVEMENTS
 
10.795 3074858.55 0.00 2572860.53 83.6
Work Order 08-30-13
Work Began 11-11-13
Work Completed  
Time Computed 10-29-13
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 46
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 2941-01-021
BATTERSON,LLP(0.95%)
EROSION CONTROL, INC.(3.00%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.07%)
JMHP, INC. (3.79%)
THIRD COAST SERVICES LLC (6.87%)
Contract # 07133021
Totals 3074858.55 0.00 2572860.53 83.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11