Monthly State Let Construction Report For Houston District As Of Apr 12, 2024 Page 10 Of 13

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGALVESTON
HighwayFM 518
FromPALOMINO LANE
ToWILLIAMSPORT STREET
CSJ0976-03-109
Proj IDCM 2023(589)
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
15447120.445163.100.0
Work Order02-15-24
Work Began03-08-24
Work Completed
Time Computed03-16-24
Contract Working Days315
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-109
D. SOLIS TRUCKING, INC. (0.67)
THIRD COAST SERVICES LLC (0.85)
A. SANCHEZ TRUCKING (0.51)
C & C TRAFFIC CONTROL (0.14)
PRV SERVICES, INC. (0.16)
STRIPE LINES, INC. (239.46)
Contract #01243005
Totals15447120.445163.105163.100.0

CountyGALVESTON
HighwayFM 518
FromFM 2351
ToS OF WHISPERING PINES
CSJ0976-03-111
Proj IDSTP 2021(344)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.3752774405.082908317.3299.9
CountyGALVESTON
HighwayFM 518
FromFM 2351
ToS OF WHISPERING PINES
CSJ0976-03-114
Proj IDROW 976-3-111
Work TypeRIGHT OF WAY
 
1.3753570.001200.0033.6
Work Order03-12-21
Work Began07-29-21
Work Completed
Time Computed04-11-21
Contract Working Days180
Addl Days Granted48
Working Days Charged201
Percent Time Used88
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-111
BROCK CONSTRUCTION, LLC (0.87)
CITYLYNX, INC. (42.71)
PBJ CONSTRUCTION (0.00)
LONESTAR TRAFFIC SAFETY, LLC (0.26)
STRIPE LINES, INC. (1.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.09)
W.A. ROBBINS CONSTRUCTION CO., INC. (4.72)
PAVELOC INDUSTRIES LLC (4.09)
TOMMY"S UTILITY SERVICES (2.51)
SELRICO COMMUNICATIONS (0.50)
Contract #02213211
Totals2777975.080.002909517.3299.9

CountyGALVESTON ETC
HighwayFM 518 ETC
FromRIVERSIDE DRIVE
ToEAGLE LAKES DRIVE
CSJ0976-03-116
Proj IDC 976-3-116
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
19.5853312178.67123035.903.7
Work Order07-26-23
Work Began01-30-24
Work Completed
Time Computed08-25-23
Contract Working Days105
Addl Days Granted0
Working Days Charged44
Percent Time Used41
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-116
D. L. MEACHAM CONSTRUCTION CO. (23.83)
ALL ACCESS TRAFFIX LIMITED LIABILITY COMPANY (1.49)
R & A DIRECTIONAL BORING (0.71)
HARDMAN SIGNS, LP (9.33)
FRANK FIFER ENTERPRISES INC. (0.23)
BILL HOUSTON CONCRETE CONSTRUCTION, INC. (0.94)
Contract #06233628
Totals3312178.67121204.10123035.903.7

CountyGALVESTON
HighwaySH 96
FromE OF SH 3
ToSH 146
CSJ0976-07-016
Proj IDC 976-7-16
Work TypeOVERLAY
 
4.4787736540.026414244.4282.9
Work Order03-08-23
Work Began05-15-23
Work Completed
Time Computed05-01-23
Contract Working Days211
Addl Days Granted0
Working Days Charged116
Percent Time Used54
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-07-016
INTERSTATE BARRICADES & MARKINGS, INC. (0.18)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.32)
THIRD COAST SERVICES LLC (1.23)
PROFESSIONAL TRAFFIC CONTROL LLC (0.07)
TRAFFIC SIGNS & LINES, LLC (0.14)
STRIPE LINES, INC. (5.08)
Contract #02233213
Totals7736540.020.006414244.4282.9

CountyGALVESTON
HighwaySH 96 ETC
FromIH 45
ToSH 146
CSJ0976-07-018
Proj IDF 2023(751)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
12.6312212100.331432365.5764.7
Work Order06-14-23
Work Began08-04-23
Work Completed
Time Computed07-14-23
Contract Working Days105
Addl Days Granted0
Working Days Charged94
Percent Time Used89
Contractor(s)
GREEN SAGE SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0976-07-018
R & A DIRECTIONAL BORING (4.14)
TRAFFIC SIGNS & LINES, LLC (0.58)
Contract #05233035
Totals2212100.330.001432365.5764.7

CountyGALVESTON
HighwayFM 517
FromFM 646
ToIH 45
CSJ0978-01-039
Proj IDC 978-1-39
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.880519798.14408196.6378.5
Work Order01-04-24
Work Began00-00-00
Work Completed
Time Computed02-03-24
Contract Working Days120
Addl Days Granted0
Working Days Charged41
Percent Time Used34
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-01-039
CURB PLANET INC. (1.43)
PROFESSIONAL TRAFFIC CONTROL LLC (10.13)
AWP SAFETY (0.97)
Contract #12233212
Totals519798.1465028.26408196.6378.5

CountyBRAZORIA
HighwayFM 521
FromAT CR 461
To.
CSJ1004-01-065
Proj IDSTP 2023(522)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
532257.18613461.5499.9
Work Order04-19-23
Work Began09-05-23
Work Completed
Time Computed05-19-23
Contract Working Days27
Addl Days Granted0
Working Days Charged21
Percent Time Used77
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-065
LONESTAR TRAFFIC SAFETY, LLC (0.39)
HIGHWAY 1 LLC (5.57)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (7.12)
QUALITY TURF FARMS, L.C. (1.98)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (3.62)
Contract #03233242
Totals532257.180.00613461.5499.9

CountyHARRIS
HighwayFM 529
FromAT KATY HOCKLEY RD
To.
CSJ1006-01-080
Proj IDC 1006-1-80
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.211355217.20353276.0899.4
Work Order03-15-23
Work Began04-11-23
Work Completed
Time Computed04-14-23
Contract Working Days30
Addl Days Granted0
Working Days Charged24
Percent Time Used80
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1006-01-080
STRIPE LINES, INC. (3.94)
THIRD COAST SERVICES LLC (33.37)
Contract #02233241
Totals355217.200.00353276.0899.4

CountyHARRIS
HighwayFM 2100
FromHUFFMAN-CLEVELAND RD (NORTH)
ToFM 1960
CSJ1062-02-009
Proj IDF 2021(840)
Work TypeWIDEN NON-FREEWAY
 
4.42854799229.7830737111.7956.0
Work Order09-16-21
Work Began02-07-22
Work Completed
Time Computed12-15-21
Contract Working Days651
Addl Days Granted0
Working Days Charged551
Percent Time Used84
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-009
BUYERS BARRICADES, INC. (0.00)
WILLIAMS ROAD, LLC (0.20)
CITYLYNX, INC. (1.63)
GMJ PAVING COMPANY LLC (2.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.45)
GMJ PAVING CO. (2.05)
PROFESSIONAL TRAFFIC CONTROL LLC (0.32)
BUYERS BARRICADES HOUSTON, LLC (0.04)
CURB PLANET INC. (0.11)
SCOTT DERR PAINTING CO, LLC (0.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.25)
WASTE PARTNERS OF TEXAS, INC (0.05)
HERMANOS STEEL, LLC (5.00)
HB FARMER FOUNDATION, LLC (3.64)
PRIMATE CONSTRUCTION, LP (0.15)
JB PINNACLE GROUP, LLC (2.43)
BTM SERVICES, LLC (0.29)
Contract #08213203
Totals54799229.78746097.3030737111.7956.0

CountyHARRIS
HighwayFM 2100
From0.23 MI S OF ANTELOPE DR
ToFM 1960
CSJ1062-04-058
Proj IDNH 1902(182)
Work TypeWNF
 
2.94925495057.2629970964.5099.9
Work Order10-25-19
Work Began01-13-20
Work Completed
Time Computed01-23-20
Contract Working Days331
Addl Days Granted0
Working Days Charged273
Percent Time Used82
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1062-04-058
CLEARVIEW CLEARING & SITE SERVICE, INC (0.37)
GMJ PAVING CO. (4.35)
PRV SERVICES, INC. (0.19)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.67)
D. SOLIS TRUCKING, INC. (0.09)
PROFESSIONAL TRAFFIC CONTROL LLC (1.18)
MONTALVO BRIDGE SYSTEMS, LLC (0.95)
THIRD COAST SERVICES LLC (4.03)
CURB PLANET INC. (0.06)
HIGHWAY 1 LLC (0.21)
C & C TRAFFIC CONTROL (0.03)
TEXOP CONSTRUCTION (0.03)
MORAN CONSTRUCTION, LLC (0.87)
BELLA PAVING, INC. (0.29)
WILLOW CITY SIGN & RAIL, INC. (0.35)
RAILPROS FIELD SERVICES, INC. (0.03)
MASTERPIECE GRINDING & GROOVING, LLC (0.26)
TRAFFIC SIGNS & LINES, LLC (0.03)
SEMARCK LANDSCAPE SERVICES, INC. (0.32)
MAIN LANE INDUSTRIES LTD. (0.03)
Contract #07193004
Totals25495057.260.0029970964.5099.9

CountyFORT BEND
HighwayFM 1092
FromHARRIS COUNTY LINE
ToSH 6
CSJ1257-01-052
Proj IDC 1257-1-52
Work TypeOVERLAY
 
5.9144238148.204825433.7899.9
Work Order04-12-22
Work Began11-07-22
Work Completed
Time Computed06-11-22
Contract Working Days103
Addl Days Granted0
Working Days Charged103
Percent Time Used100
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1257-01-052
TRAFFIC SIGNS & LINES, LLC (3.60)
STRIPE LINES, INC. (6.32)
INTERSTATE BARRICADES & MARKINGS, INC. (0.35)
MAIN LANE INDUSTRIES LTD. (4.58)
THIRD COAST SERVICES LLC (4.70)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.47)
HOLES INCORPORATED (0.35)
HOLES INCORPORATED (1.09)
Contract #03223010
Totals4238148.200.004825433.7899.9

CountyHARRIS
HighwayFM 1093
FromSOUTH KIRKWOOD ROAD
ToWESTERLAND DRIVE
CSJ1258-04-065
Proj IDSTP 2017(976)TP
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
3.56412691072.7911080609.1087.3
Work Order11-04-19
Work Began02-24-20
Work Completed
Time Computed03-03-20
Contract Working Days850
Addl Days Granted0
Working Days Charged838
Percent Time Used98
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1258-04-065
GEORGE MEEKS LANDPRO, INC. (6.25)
RAY"S THREADING AND FAB SHOP (0.70)
PROFESSIONAL TRAFFIC CONTROL LLC (2.29)
TEXAS WALL & LANDSCAPE (14.79)
THIRD COAST SERVICES LLC (30.90)
DOUBLE OAK EROSION, INC. (0.76)
CHERRY CRUSHED CONCRETE (0.59)
MVA CONSTRUCTION LLC (0.74)
BOOT CONSTRUCTION, LLC (0.16)
717 CONSTRUCTION SERVICES, LLC (5.32)
ZAMCO DIRECTIONAL DRILLING LLC (0.33)
MICKIE SERVICE, INC. (0.24)
GMJ PAVING COMPANY LLC (0.52)
Contract #09193206
Totals12691072.79150523.8111080609.1087.3

CountyMONTGOMERY
HighwayFM 1097
FromLAKE CONROE HILLS
ToANDERSON ROAD
CSJ1259-01-043
Proj IDSTP 2020(790)
Work TypeWIDEN NON-FREEWAY
 
2.00014690168.2816644644.2799.9
Work Order12-04-20
Work Began02-02-21
Work Completed
Time Computed02-02-21
Contract Working Days334
Addl Days Granted124
Working Days Charged394
Percent Time Used86
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-043
TRAFFIC SYSTEMS CONSTRUCTION, INC. (2.41)
LONESTAR TRAFFIC SAFETY, LLC (0.17)
WILLOW CITY SIGN & RAIL, INC. (0.61)
CEN TEX HYDROSEED, INC. (0.49)
HIGHWAY 1 LLC (1.11)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.82)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.33)
DUSTROL, INC. (1.22)
MESA ROD BUSTERS, INC. (5.80)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.11)
ROSALES TRUCKING (5.12)
ANCORTEX, INC. (0.45)
B & D MAINTENANCE (4.24)
AVILES CONSTRUCTION SERVICE, INC (2.56)
SOUTHEAST GRINDING AND GROOVING LLC (0.10)
CURB PLANET INC. (0.02)
CEDAR HILL SERVICES, LLC (0.01)
BUYERS BARRICADES HOUSTON, LLC (0.12)
Contract #10203003
Totals14690168.283775.6816644644.2799.9

CountyMONTGOMERY
HighwayFM 1097
FromWEST OF BLUEBERRY HILLS RD
ToLAKE CONROE HILLS DR
CSJ1259-01-044
Proj IDF 2021(653)
Work TypeWIDEN NON-FREEWAY
 
1.52416095270.669387376.6858.3
Work Order09-21-21
Work Began01-19-22
Work Completed
Time Computed01-19-22
Contract Working Days328
Addl Days Granted68
Working Days Charged296
Percent Time Used74
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-044
CEN TEX HYDROSEED, INC. (0.54)
LONESTAR TRAFFIC SAFETY, LLC (0.16)
WILLOW CITY SIGN & RAIL, INC. (0.74)
MESA ROD BUSTERS, INC. (6.99)
J KRU LAND SERVICES, LLC (0.03)
SARVICUS LLC (2.18)
DUSTROL, INC. (0.86)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.08)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.26)
HIGHWAY 1 LLC (0.98)
BUYERS BARRICADES, INC. (0.00)
BUYERS BARRICADES HOUSTON, LLC (0.09)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.97)
PRIMATE CONSTRUCTION, LP (0.40)
TOM-MAC, INC. (2.77)
AVILES CONSTRUCTION SERVICE, INC (1.35)
Contract #08213010
Totals16095270.66793684.089387376.6858.3

CountyMONTGOMERY
HighwayFM 1774
FromFM 1488
ToFM 149
CSJ1400-04-040
Proj IDSTP 2022(697)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0531870035.502036346.9999.9
Work Order09-15-22
Work Began04-27-23
Work Completed
Time Computed10-15-22
Contract Working Days260
Addl Days Granted0
Working Days Charged154
Percent Time Used59
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08223021
Totals1870035.500.002036346.9999.9

CountyMONTGOMERY
HighwayFM 1375
FromFM 149
ToWALKER C/L
CSJ1402-03-012
Proj IDF 2023(339)
Work TypeOVERLAY
 
5.9592012093.412314560.0999.9
Work Order09-07-23
Work Began10-20-23
Work Completed
Time Computed10-20-23
Contract Working Days58
Addl Days Granted0
Working Days Charged58
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1402-03-012
HIGHWAY 1 LLC (8.41)
WILLOW CITY SIGN & RAIL, INC. (3.79)
Contract #08233208
Totals2012093.4177854.272314560.0999.9

CountyGALVESTON
HighwayFM 528
FromBRAZORIA COUNTY LINE
ToFALCON RIDGE BLVD
CSJ1414-01-021
Proj IDF 2024(141)
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
656556.335914.100.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days61
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1414-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233020
Totals656556.330.005914.100.9

CountyGALVESTON
HighwayFM 528
FromAT IRRIGATION CANAL
To.
CSJ1414-01-022
Proj IDC 1414-1-22
Work TypeBRIDGE MAINTENANCE
 
0.833614813.73737486.0199.9
Work Order10-26-22
Work Began11-28-22
Work Completed
Time Computed11-25-22
Contract Working Days101
Addl Days Granted0
Working Days Charged98
Percent Time Used97
Contractor(s)
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1414-01-022
TRAFFIC SIGNS & LINES, LLC (12.11)
MOBILE ENTERPRISES, INC. (6.59)
HERMANOS STEEL, LLC (1.18)
HOUSTON SAWING & DRILLING (0.37)
SCOTT DERR PAINTING CO, LLC (0.40)
AMERICAN PARKING CONTROL (8.24)
Contract #09223022
Totals614813.730.00737486.0199.9

CountyFORT BEND
HighwayFM 1464
FromWEST AIRPORT BLVD.
ToSH 99
CSJ1415-02-051
Proj IDC 1415-2-51
Work TypeTRAFFIC CONTROL DEVICES
 
3.2201186118.88974217.0582.1
Work Order10-13-22
Work Began05-05-23
Work Completed
Time Computed01-11-23
Contract Working Days260
Addl Days Granted0
Working Days Charged159
Percent Time Used61
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1415-02-051
RICK & VIVIAN COMPANY LLC (17.89)
KHONSU ENTERPRISE LLC (1.26)
Contract #09223014
Totals1186118.8833140.42974217.0582.1

CountyMONTGOMERY
HighwayFM 1486
FromFM 1774
ToSH 105
CSJ1416-03-018
Proj IDC 1416-3-18
Work TypeOVERLAY
 
10.5914541531.813192641.0070.5
Work Order06-28-23
Work Began08-28-23
Work Completed
Time Computed08-27-23
Contract Working Days107
Addl Days Granted0
Working Days Charged118
Percent Time Used110
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1416-03-018
BATTERSON, LLP (7.66)
LONESTAR TRAFFIC SAFETY, LLC (0.23)
THIRD COAST SERVICES LLC (1.56)
WILLIAMS ROAD, LLC (2.15)
WILLOW CITY SIGN & RAIL, INC. (1.69)
Contract #02233016
Totals4541531.811834160.803192641.0070.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13