AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - STATEWIDE

Last Update: Friday, April 29, 2016
ITEMS 422 6001 TO 429 6011
Items Items Bid Code Range
0100 - 0193
0204 - 0292
0305 - 0361
0400 - 0499
0500 - 0560
0610 - 0690
0700 - 0788
1002 - 1160
2000 - 2349
3000 - 3271
4000 - 4116
5000 - 5969
6000 - 6920
7001 - 7089
8020 - 8999
9012 - 9054
400 2002 - 420 2003
420 2004 - 422 2003
422 6001 - 429 6011
429 6015 - 434 6029
434 6032 - 450 6037
450 6039 - 460 6029
460 6032 - 462 6098
462 6099 - 465 2003
465 2004 - 465 6126
465 6127 - 465 6242
465 6243 - 466 6095
466 6097 - 467 2215
467 2216 - 467 6199
467 6200 - 467 6426
467 6431 - 476 6026
476 6029 - 499 6001
Item No Description Units April 30, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
422 6001 REINF CONC SLAB SF 41,416.000 19.64829 2,431,625.635 16.10566 69
422 6002 REINF CONC SLAB (HPC) SF 112,800.000 14.55319 2,853,681.000 12.97147 46
422 6003 REINF CONC SLAB (EXTEND SLAB) SF     347,007.000 19.11815 12
422 6004 REINF CONC SLAB (EXTEND SLAB) (HPC) SF     134,914.400 20.85539 3
422 6005 REINF CONC SLAB (BOX BEAM) SF 3,490.300 14.78234 37,211.900 19.98657 10
422 6007 REINF CONC SLAB (SLAB BEAM) SF 6,843.000 14.82902 152,116.510 16.62624 25
422 6008 REINF CONC SLAB (SLAB BEAM) (HPC) SF     36,465.000 10.64406 2
422 6009 BRIDGE CURB SF 472.000 8.00000 666.000 11.20420 2
422 6010 BRIDGE CURB (HPC) SF     162.000 60.00000 1
422 6011 BRIDGE MEDIAN SF     13,978.000 4.65460 2
422 6012 BRIDGE MEDIAN (HPC) SF     18,370.000 8.51121 3
422 6013 BRIDGE SIDEWALK SF 4,843.000 13.14000 49,042.310 10.19118 16
422 6014 BRIDGE SIDEWALK (HPC) SF     91,500.000 8.33279 12
422 6015 APPROACH SLAB CY 457.400 425.45256 9,718.800 467.75500 65
422 6016 APPROACH SLAB (HPC) CY 299.800 432.62842 13,679.200 381.53340 40
422 6017 CONCRETE GIRDER CY     447.500 725.00000 1
422 6019 SLAB SPAN CY 103.000 1,120.00000 333.500 994.96252 3
422 6023 SHEAR KEY CY 24.100 378.50622 1,283.100 260.55685 14
422 6026 SLAB SPAN (EXTEND) CY 28.400 1,700.00000 665.700 1,265.66021 3
422 6030 CONCRETE PAN GIRDER (EXTEND) CY     443.900 1,373.41744 3
422 6031 CONCRETE PAN GIRDER (EXTEND) (HPC) CY     748.000 1,116.62032 2
422 6034 APPROACH SLAB (EXTEND) (HPC) CY     940.800 466.69855 2
422 6035 APPROACH SLAB (EXTEND) CY     29.800 860.00000 1
422 6036 APPROACH SLAB (MOD) CY     43.200 1,363.32986 1
423 2001 RETAINING WALL (MSE) SF     89,400.000 48.75000 1
423 2008 RETAINING WALL (STONE) SF     2,940.000 136.23000 1
423 2009 RETAINING WALL (SOIL NAILED) (FACIA) SF     6,170.000 40.00000 1
423 2011 RETAINING WALL (DRILL SHAFT) (FACIA) SF     13,739.000 40.38787 2
423 2012 RETAINING WALL (CAST - IN - PLACE) SF     15,852.000 52.50000 1
423 2017 RET WALL (MSE) (ASHLAR STONE) (SPECIAL) SF     6,170.000 .01000 1
423 6001 RETAINING WALL (MSE) SF     1,622,718.000 43.54767 37
423 6002 RETAINING WALL (MSE) (ASHLAR STONE FIN SF     54,732.000 32.03756 2
423 6003 RETAINING WALL (TEMP WALL) SF     134,890.000 15.78621 8
423 6004 RETAINING WALL (CONC BLOCK) SF     42,775.000 29.36155 8
423 6005 RETAINING WALL (SPREAD FOOTING) SF     73,678.000 46.33080 4
423 6006 RETAINING WALL (STONE) SF     288.000 50.00000 1
423 6007 RETAINING WALL (DRILL SHAFT) (FACIA) SF     96,320.000 45.63968 5
423 6008 RETAINING WALL (CAST - IN - PLACE) SF 2,260.300 120.68907 89,211.500 63.90657 24
423 6010 RET WALL (SPREAD FOOTING) (SPL) SF     22,634.000 63.16731 2
423 6014 RETAINING WALL (MSE) (HORIZONTAL SCHEME SF     42,754.000 25.59429 2
423 6015 RETAINING WALL (SPECIAL) SF     11,085.500 108.37391 7
423 6017 RET WALL (SOIL NAILED) (FASCIA) (HOR SCH SF 12,703.000 59.75284 139,003.000 36.70335 10
423 6019 RET WALL (MSE) (VERTICAL SCHEME) (SPL) SF     88,460.000 30.53697 3
423 6020 RET. WALL (SOIL NAILED) (GUNNITE FACIA SF     25,510.800 42.20820 3
423 6021 RETAINING WALL (EXISTING CIP) (FACIA) SF     4,324.000 40.00000 1
423 6022 RETAINING WALL (SOIL NAIL) (FACIA) SF     108,341.000 35.98795 7
423 6023 RETAINING WALL (ROCK NAILED) (FACIA) SF     3,662.400 90.00000 1
423 6024 RET WALL (SOIL NAIL) (ASHLAR FIN) SF     20,664.000 40.00000 1
423 6025 RETAINING WALL (EXISTING MSE) FASCIA SF     25,466.000 20.00000 1
425 2004 PRESTR CONC BEAM (TY IV) LF     11,097.490 150.00000 1
425 2008 PRESTR CONC BOX BEAM (4B28) LF     278.000 260.00000 1
425 2009 PRESTR CONC BOX BEAM (5B28) LF     139.000 365.00000 1
425 2019 PRESTR CONC U - BEAM (U54) LF     13,188.570 199.50000 1
425 2064 PRESTR CONC GIRDER (TX28) LF     831.000 155.00000 1
425 2065 PRESTR CONC GIRDER (TX34) LF     1,642.500 129.83166 2
425 2068 PRESTR CONC GIRDER (TX54) LF     44,542.628 119.50000 1
425 2069 PRESTR CONC GIRDER (TX62) LF     1,295.200 138.00000 1
425 2070 PRESTR CONC GIRDER (TX70) LF     14,077.064 155.50000 1
425 6001 PRESTR CONC BOX BEAM (4B20) LF 523.680 189.48671 3,830.200 181.77667 10
425 6002 PRESTR CONC BOX BEAM (5B20) LF 261.840 189.48671 2,115.970 196.20600 10
425 6003 PRESTR CONC BOX BEAM (4B28) LF     1,746.000 242.59794 4
425 6004 PRESTR CONC BOX BEAM (5B28) LF     1,170.000 240.52051 4
425 6005 PRESTR CONC BOX BEAM (4B34) LF     4,097.890 180.37281 4
425 6006 PRESTR CONC BOX BEAM (5B34) LF     9,052.500 186.95769 4
425 6007 PRESTR CONC BOX BEAM (4B40) LF     4,518.490 155.00000 1
425 6008 PRESTR CONC BOX BEAM (5B40) LF     2,946.890 155.00000 1
425 6009 PRESTR CONC SLAB BEAM (4SB12) LF 278.000 185.00000 7,370.170 149.73560 14
425 6010 PRESTR CONC SLAB BEAM (5SB12) LF 599.490 185.00000 11,742.710 160.12111 15
425 6011 PRESTR CONC SLAB BEAM (4SB15) LF     10,770.280 143.93777 14
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 475.000 225.00000 24,081.330 158.52573 19
425 6016 PRESTR CONC DECK SLAB BEAM (6DS23) LF     478.630 499.99373 2
425 6017 PRESTR CONC DECK SLAB BEAM (7DS23) LF     299.170 447.74997 1
425 6020 PRESTR CONC BOX BEAM (5XB20) LF     1,186.000 186.97740 2
425 6035 PRESTR CONC GIRDER (TX28) LF 1,313.180 175.79616 70,771.910 124.66272 38
425 6036 PRESTR CONC GIRDER (TX34) LF 337.990 200.00000 63,958.320 138.07801 32
425 6037 PRESTR CONC GIRDER (TX40) LF 680.000 150.00000 35,407.520 121.45072 16
425 6038 PRESTR CONC GIRDER (TX46) LF 3,042.680 136.28150 87,617.580 135.35167 29
425 6039 PRESTR CONC GIRDER (TX54) LF 15,243.180 133.81812 335,403.120 134.98504 31
425 6040 PRESTR CONC GIRDER (TX62) LF     45,695.030 153.31425 6
425 6041 PRESTR CONC GIRDER (TX70) LF     18,954.000 148.65820 5
425 6044 PRESTR CONC GIRDER (STX8) LF     798.000 1,200.00000 1
425 6049 PRESTR CONC BEAM (TY IV) LF     4,123.570 197.74855 2
425 6050 PRESTR CONC BEAM (TY C) LF     874.390 200.00000 1
427 6002 CONCRETE PAINT FINISH SF     546,561.000 .35306 14
427 6003 OPAQUE SEALER FINISH SF 2,175.000 2.00000 2,790,721.000 .47728 11
427 6004 SILICONE RESIN PAINT FINISH SF     985,911.000 .90553 6
428 2001 CONC SURF TREAT (CLASS I) SY     10,019.000 1.00000 1
428 2002 CONC SURF TREAT (CLASS II) SY     1,013.000 8.00000 1
428 6001 PENETRATING CONCRETE SURFACE TREATMENT SY     44,072.000 8.19380 4
429 6001 CONC STR REPAIR (CLEAN & COAT WTH EPOXY SF     3,500.000 155.08571 7
429 6002 CONC STR REPAIR (EPOXY MORTAR) SF     4,590.000 124.07821 9
429 6003 CONC STR REPAIR (DECK REP (PART DEPTH) ) SF     934.000 137.45182 3
429 6004 CONC STR REPAIR (RAPID DECK REP (PRT DPT SF     3,533.400 62.97328 4
429 6005 CONC STR REPAIR (DECK REP (FULL DEPTH) ) SF 50.000 375.00000 5,473.000 167.78465 18
429 6006 CONC STR REPR (RAPID DECK REP (FULL DPT) SF     1,295.800 130.07131 2
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF     5,863.000 185.89303 24
429 6008 CONC STR REPR (RAPID VERT AND OVERHEAD) SF     670.000 375.00000 1
429 6009 CONC STR REPAIR (STANDARD) SF 20.000 131.27000 732.500 206.90840 12
429 6010 CONC STR REPR (REMOV AND REPL BACKWALL) CY     3.600 6,000.00000 1
429 6011 CONC STR REPR (REMOV AND REPL WINGWALL) CY     3.000 1,500.00000 1