AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - STATEWIDE

Last Update: Friday, May 3, 2013
ITEMS 3035 2004 TO 3248 2002
Items Items Bid Code Range
0100 - 0193
0204 - 0292
0305 - 0368
0400 - 0497
0500 - 0560
0610 - 0690
0700 - 0788
0800 - 0800
1003 - 1137
2022 - 2116
3035 - 3275
4007 - 4640
5049 - 5997
6004 - 6986
7380 - 7624
8020 - 8941
9012 - 9012
3035 2004 - 3248 2002
3249 2001 - 3275 2001
Item No Description Units April 30, 2013 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
3035 2004 BLD LVL - UP TYD D - GR HMA SAC - B PG64 - 22 TON     4,100.000 73.00000 1
3042 2001 FIXED BOLLARDS EA     6.000 190.00000 1
3061 2001 FAST TRK CONC (CNT RNF HY STL) (12") SY 92,788.000 62.97040 248,535.000 69.07362 12
3061 2002 FAST TRK CONC (CNT RNF HY STL) (14") SY     6,526.420 100.78407 3
3061 2003 FAST TRK CONC (CONT RNF HY STL) (11") SY     1,388.556 74.18718 2
3061 2004 FAST TRK CONC (CONT REINF HY STL) (13") SY     38,827.000 70.92054 7
3061 2005 FAST TRK CONC (CONT REINF HY STL) (15") SY     76.000 166.00000 1
3061 2006 FAST TRK CONC (CONT REINF HY STL) (9") SY     1,282.000 85.00000 1
3061 2011 FST TRK CONC (CONT RNF HY STL) (DWY) (12" SY 3,130.000 70.73482 3,862.000 70.40601 3
3120 2001 ASPHALT - STABILIZED FLEXIBLE BASE TON     480.000 99.00000 1
3127 2001 TBPFC (MEMBRANE) GAL 61,415.000 3.46777 294,200.000 3.27554 5
3127 2002 TBPFC (ASPHALT) (PG 76 - 22) TON 1,177.000 107.34494 3,998.400 113.46533 5
3127 2003 TBPFC (AGGREGATE) (SAC - A) TON 16,252.000 107.64152 59,451.000 113.80480 5
3142 2001 UTBHMWC (MEMBRANE) GAL     36,995.000 3.41000 1
3142 2003 UTBHMWC (ASPHALT) (PG 76 - 22) TON 588.500 97.20000 2,281.500 108.88039 4
3142 2004 UTBHMWC (MEMBRANE) TON     644.000 715.00000 1
3142 2007 UTBHMWC (MEMBRANE) GAL 62,246.220 3.30000 228,276.220 3.52359 5
3142 2008 UTBHMWC (ASPHALT) TON     2,046.210 143.07096 3
3142 2009 UTBHMWC (AGGREGATE) (TY C) TON     40,962.000 142.44058 5
3142 2010 UTBHMWC (AGGREGATE) (TY B) TON 10,525.270 97.20000 36,644.270 96.34467 2
3143 2001 RUBBLIZING CONC PAVEMENT (TY - I OR II) SY     9,754.000 3.15000 1
3150 2001 WARRANTED MICROSURFACING TON     13,116.000 184.64764 4
3165 2001 CAM (ASPHALT) PG (76 - 22) TON     5,275.787 762.78193 8
3165 2002 CAM (ASPHALT) PG (70 - 22) TON 730.000 117.00000 1,102.000 117.00000 2
3165 2003 CAM (AGGREGATE) TON 9,278.000 117.00000 75,647.814 73.08680 10
3178 2001 HOT IN PLC RECYL OF ASPH CNC (SURF) 2" SY     384,166.000 4.17000 1
3178 2002 HOT IN PLC RECYL OF ACP (RECYL AGNT) GAL     198,085.000 3.41000 1
3186 2001 FASTRACK CONC PVMT (CRCP) (12") SY     11,258.270 100.00000 1
3187 2003 FAST TRK CONC PVMT (CNT RNF HY STL) (17" SY     643.000 125.00000 1
3198 2003 FAST TRACK (CPCD) (8") SY     309.000 80.00000 1
3213 2001 CONTINUOUS DIAMOND GRINDING CONC PVMT SY 56,379.000 9.99702 56,379.000 9.99702 2
3213 2004 SPOT DIAMOND GRINDING ASPH PVMT SY     844.000 13.90000 1
3215 2001 ASPHALT PAVEMENT (STAMPED AND COLORED) SY     2,235.000 50.00000 1
3224 2003 D - GR HMA (QCQA) TY - A PG64 - 22 TON     5,534.000 69.01742 3
3224 2005 D - GR HMA (QCQA) TY - A PG70 - 22 TON     163.000 130.00000 1
3224 2008 D - GR HMA (QCQA) TY - B PG64 - 22 TON     1,298,015.890 62.31642 65
3224 2010 D - GR HMA (QCQA) TY - B PG70 - 22 TON     229,761.300 64.23224 10
3224 2020 D - GR HMA (QCQA) TY - C SAC - A PG64 - 22 TON     184,204.000 68.11818 8
3224 2021 D - GR HMA (QCQA) TY - C SAC - B PG64 - 22 TON     56,420.200 71.81857 9
3224 2022 D - GR HMA (QCQA) TY - C PG64 - 22 TON     22,340.000 88.05199 8
3224 2024 D - GR HMA (QCQA) TY - C SAC - B PG64 - 28 TON     47,603.000 68.52964 2
3224 2026 D - GR HMA (QCQA) TY - C SAC - A PG70 - 22 TON     308,519.000 76.74624 24
3224 2027 D - GR HMA (QCQA) TY - C SAC - B PG70 - 22 TON     595,183.290 71.32994 38
3224 2028 D - GR HMA (QCQA) TY - C PG70 - 22 TON     231,424.010 71.72725 15
3224 2029 D - GR HMA (QCQA) TY - C SAC - A PG76 - 22 TON     39,892.000 73.74353 4
3224 2030 D - GR HMA (QCQA) TY - C SAC - B PG76 - 22 TON     113,701.000 71.09012 11
3224 2031 D - GR HMA (QCQA) TY - C PG76 - 22 TON     43,793.900 64.03623 2
3224 2038 D - GR HMA (QCQA) TY - D SAC - A PG64 - 22 TON     39,498.000 87.73568 7
3224 2039 D - GR HMA (QCQA) TY - D SAC - B PG64 - 22 TON     128,813.000 71.61879 16
3224 2040 D - GR HMA (QCQA) TY - D PG64 - 22 TON     214,449.000 73.13177 21
3224 2041 D - GR HMA (QCQA) TY - D SAC - A PG70 - 22 TON     199,544.710 75.47751 16
3224 2042 D - GR HMA (QCQA) TY - D SAC - B PG70 - 22 TON     705,680.013 68.21822 43
3224 2043 D - GR HMA (QCQA) TY - D PG70 - 22 TON     84,767.600 69.77711 13
3224 2045 D - GR HMA (QCQA) TY - D SAC - B PG70 - 28 TON     223,590.000 73.36033 7
3224 2046 D - GR HMA (QCQA) TY - D PG70 - 28 TON     71,272.000 71.15293 4
3224 2047 D - GR HMA (QCQA) TY - D SAC - A PG76 - 22 TON     383,182.953 82.87957 26
3224 2048 D - GR HMA (QCQA) TY - D SAC - B PG76 - 22 TON     127,698.000 75.64148 7
3224 2049 D - GR HMA (QCQA) TY - D PG76 - 22 TON     5,011.000 95.71442 4
3224 2050 D - GR HMA (QCQA) TY - F SAC - A PG64 - 22 TON     4,364.960 125.00000 1
3224 2054 D - GR HMA (QCQA) TY - F SAC - B PG70 - 22 TON     34.000 127.50000 1
3224 2056 D - GR HMA (QCQA) TY - F SAC - A PG76 - 22 TON     8,986.000 96.57000 1
3224 2061 D - GR HMA (QCQA) TY - C PG76 - 22 (LEVEL - UP) TON     941.000 93.00000 1
3224 2062 D - GR HMA (QCQA) TY - D PG64 - 22 (LEVEL - UP) TON     47,799.000 71.80656 14
3224 2064 D - GR HMA (QCQA) TY - D PG 70 - 22 (LEVEL - UP TON     36,293.050 63.54264 3
3224 2066 D - GR HMA (QCQA) TY - C PG70 - 22 (LEVEL - UP) TON     1,909.000 84.68077 2
3224 2073 D - GR HMA (QCQA) TY B SAC - A PG 76 - 22 TON     50,244.000 75.48806 3
3224 2075 D - GR HMA (QC / QA) TY B SAC - B PG (76 - 22) TON     66,198.000 77.78966 6
3224 2076 D - GR HMA (QC / QA) TY B SAC - B PG (64 - 22) TON     54,234.000 74.30647 6
3224 2081 D - GR HMA (QCQA) TY - C OR D PG64 - 22 (LVL - UP TON     174.000 104.00000 1
3224 2085 D - GR HMA (QCQA) TY - D SAC - A PG 76 - 28 TON     193,946.000 87.40228 8
3224 2086 D - GR HMA (QCQA) TY - B PG70 - 28 TON     109,095.000 98.50120 5
3224 2087 D - GR HMA (QCQA) TY - B PG 76 - 28 TON     79,737.000 87.80066 4
3224 2088 D - GR HMA (QCQA) TY - C SAC - B PG70 - 28 TON     10,111.000 65.70000 1
3224 2090 D - GR HMA (QCQA) TY D PG 76 - 28 (LEVEL - UP TON     8,922.000 96.79346 2
3233 2001 MEMBRANE UNDERSEAL GAL 27,983.000 3.30000 205,228.700 3.63018 8
3235 2001 ASPH (TIER I) GAL     4,208,912.200 3.08629 6
3235 2002 ASPH (TIER II) GAL 15,145.000 3.50000 5,033,599.000 3.12854 7
3235 2003 ASPH (TIER III) GAL     160,930.000 2.64000 1
3235 2004 ASPH (TIER I) ALT 1X GAL     47,597.000 3.00000 1
3235 2005 ASPH (TIER II) ALT 1X GAL     52,300.000 3.33000 1
3235 2007 ASPH (TIER I) ALT 2X GAL     30,024.000 3.00000 1
3235 2031 AGGR (TIER I) CY     60,776.000 71.83485 5
3235 2032 AGGR (TIER II) CY     123,547.600 63.85505 5
3235 2033 AGGR (TIER III) CY     3,850.000 38.00000 1
3235 2034 AGGR (TIER I) ALT 1X CY     1,133.000 61.00000 1
3235 2035 AGGR (TIER II) ALT 1X CY     1,189.000 69.00000 1
3235 2037 AGGR (TIER I) ALT 2X CY     715.000 61.00000 1
3235 2091 AGGR (GR 3) CY     40,576.000 54.00000 1
3235 2092 AGGR (GR 4) CY     6,249.000 64.00000 1
3235 2096 ASPH (TIER II) (EMUL) GAL     1,242,529.800 2.78000 1
3239 2001 TOM (ASPHALT) PG 76 - 22 TON 128.000 130.00000 4,168.000 129.27515 13
3239 2002 TOM (ASPHALT) PG 70 - 22 TON     2,423.000 661.64824 5
3239 2003 TOM (AGGREGATE) SAC A TON 1,650.000 130.00000 45,376.000 112.50946 11
3239 2004 TOM (AGGREGATE) SAC B TON     39,007.000 80.36993 7
3243 2001 FGSM (ASPHALT) PG 76 - 22 TON     70.000 950.00000 1
3243 2005 FGSM (AGGREGATE) (TY I FGPFC) SAC - A TON     1,004.000 187.78000 1
3246 2001 FGSM (ASPHALT) (TYII SMA PG76 - 22) TON     22.000 153.00000 1
3246 2002 FGSM (AGGR) (TYII SMA) (SAC A) TON     313.000 153.00000 1
3248 2001 REMOVING PAVEMENT TEXTURING (INLAY) LF     41,051.000 1.00000 1
3248 2002 REM PAVEMENT TEXTURING (PLANE & INLAY) LF     37,192.000 2.00000 1