AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - STATEWIDE

Last Update: Friday, October 31, 2014
ITEMS 400 2001 TO 420 2018
Items Items Bid Code Range
0100 - 0193
0204 - 0292
0305 - 0368
0400 - 0499
0500 - 0560
0610 - 0690
0700 - 0788
0800 - 0800
1003 - 1151
2021 - 2322
3042 - 3287
4001 - 4682
5050 - 5997
6005 - 6986
7384 - 7661
8008 - 8999
9009 - 9059
400 2001 - 420 2018
420 2019 - 425 2006
425 2007 - 430 2107
430 2113 - 432 2071
432 2072 - 450 2058
450 2062 - 458 2004
458 2008 - 464 2003
464 2004 - 465 2098
465 2099 - 465 2405
465 2414 - 465 4118
465 4119 - 466 2153
466 2155 - 467 2102
467 2103 - 467 2305
467 2307 - 476 2015
476 2018 - 499 2001
Item No Description Units October 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
400 2001 STRUCT EXCAV CY 191.000 75.00000 185,547.670 1.52676 14
400 2002 STRUCT EXCAV (BOX) CY     7,956.000 3.22330 10
400 2003 STRUCT EXCAV (PIPE) CY     2,027.700 11.82374 12
400 2004 STRUCT EXCAV (BRIDGE) CY 6,456.000 15.57000 7,316.600 17.01780 5
400 2005 CEM STABIL BKFL CY 12,068.600 68.37240 286,892.550 44.52697 177
400 2006 CUT & RESTORING PAV SY 124.000 140.00000 19,612.120 84.44844 75
400 2007 STRUCT EXCAV (SPECIAL) CY     8,017.200 48.09604 7
400 2008 CUT & RESTORING PAV (ASPH) SY 458.000 100.00000 13,625.600 80.94003 31
400 2009 CUT & RESTORING PAV (CONC) SY 175.000 100.00000 4,350.800 74.29790 11
400 2010 CUT & RESTORING PAV (FLEX BASE) SY 606.000 52.04620 2,607.000 46.95666 9
400 2011 SAND BACKFILL CY     2,347.000 28.23789 5
400 2016 CEMENT STAB BACKFILL (INLET OR MH) CY 1,184.750 62.64836 12,039.300 35.89784 19
400 2017 CEM STABIL BKFL F CY     5,824.600 33.65141 2
400 2018 CUT & RESTORING PAV F SY     251.000 80.22908 2
400 2020 CEM STAB BCKFL (UNDER APPR SLAB) CY     184.000 116.30435 2
400 2023 CEM STAB BKFL (BEHIND ABUTMENT) CY     1,907.000 146.80049 7
401 2001 FLOWABLE BACKFILL CY 142.000 167.38556 10,442.670 132.64766 68
401 2002 FLOWABLE BACKFILL (MEDIAN) CY     308.000 154.04221 2
402 2001 TRENCH EXCAVATION PROTECTION LF 26,678.000 4.44632 615,645.000 2.21286 160
403 2001 TEMPORARY SPL SHORING SF 173,255.000 15.15808 1,904,224.090 9.38530 138
403 2002 TEMPORARY SPL SHORING (SOIL NAIL) SF     14,161.100 28.25038 4
403 2003 TEMPORARY SPL SHORING (BASE BID) SF     28.000 100.00000 1
403 2007 TEMPORARY SPL SHORING (ROCK NAIL) SF     147.000 52.50000 1
403 2010 TEMPORARY SPL SHORING (COFFERDAM) SF     39,192.000 18.01245 5
403 2011 TEMPORARY SPL SHORING (RAILROAD CANT) SF     751.000 135.00000 1
407 2001 SHEET PILING (PZ - 27) SF     3,878.000 48.61681 2
407 2002 STL H - PILING (HP 14 X 73) LF     6,098.000 92.93842 2
407 2005 SHEET PILING (PZ - 22) SF     5,441.000 29.86896 3
407 2009 STL H - PILING (HP 12 X 84) LF     1,227.000 106.37000 1
407 2015 STEEL H - PILING (HP 12 X 53) LF     19,424.000 51.99020 2
409 2001 PRESTR CONC PIL (16 IN SQ) LF     42,334.000 48.26009 14
409 2002 PRESTR CONC PIL (18 IN SQ) LF     49,162.000 67.38264 12
409 2003 PRESTR CONC PIL (20 IN SQ) LF 3,168.000 105.00000 11,060.000 116.92643 4
409 2004 PRESTR CONC PIL (24 IN SQ) LF     1,818.000 128.00000 1
409 2015 PRESTR CONC PIL (16 IN SQ) (HPC) LF     564.000 130.00000 1
409 2016 PRESTR CONC PIL (18 IN SQ) (HPC) LF     550.000 130.00000 1
409 2017 PRESTR CONC PIL (20 IN SQ) (HPC) LF     1,300.000 160.00000 1
409 2018 PRESTR CONC PIL (24 IN SQ) (HPC) LF 3,878.000 275.00000 3,878.000 275.00000 1
409 2019 PRESTR CONC PIL (16 IN SQ) (SULF) LF     3,472.000 57.82258 2
409 2025 PRESTR CONC SHEET PIL (12") (HPC) SF     5,868.000 34.00000 1
416 2001 DRILL SHAFT (18 IN) LF 1,711.000 146.45835 18,210.000 73.24601 45
416 2002 DRILL SHAFT (24 IN) LF 1,934.000 121.13692 52,789.000 104.98955 61
416 2003 DRILL SHAFT (30 IN) LF 110.000 131.27000 83,174.000 130.95169 52
416 2004 DRILL SHAFT (36 IN) LF 27,908.000 165.51472 169,441.000 153.91418 104
416 2005 DRILL SHAFT (42 IN) LF 2,926.000 187.57000 43,656.400 202.49165 22
416 2006 DRILL SHAFT (48 IN) LF 8,399.000 228.36407 55,088.000 243.92441 23
416 2007 DRILL SHAFT (54 IN) LF     11,146.000 379.85643 12
416 2008 DRILL SHAFT (60 IN) LF 4,570.000 313.96493 7,470.000 326.20193 7
416 2009 DRILL SHAFT (66 IN) LF     1,215.000 421.79012 2
416 2010 DRILL SHAFT (72 IN) LF     2,666.800 608.47755 5
416 2011 DRILL SHAFT (78 IN) LF     186.000 494.87000 1
416 2012 DRILL SHAFT (84 IN) LF     34,536.000 596.19273 3
416 2015 DRILL SHAFT (NON - REINFORCED) (12 IN) LF     401.500 65.11370 13
416 2016 DRILL SHAFT (SIGN MTS) (12 IN) LF     229.000 109.76961 7
416 2018 DRILL SHAFT (SIGN MTS) (24 IN) LF 16.000 128.00000 2,142.000 125.96599 37
416 2019 DRILL SHAFT (SIGN MTS) (30 IN) LF     204.000 133.67912 5
416 2020 DRILL SHAFT (SIGN MTS) (36 IN) LF     1,556.200 191.78388 13
416 2021 DRILL SHAFT (SIGN MTS) (42 IN) LF     3,514.400 204.04504 15
416 2022 DRILL SHAFT (SIGN MTS) (48 IN) LF 1,252.600 512.09468 3,956.930 372.58536 22
416 2023 DRILL SHAFT (SIGN MTS) (54 IN) LF 130.000 668.70000 2,550.500 450.62094 20
416 2025 DRILL SHAFT (HIGH MAST POLE) (54 IN) LF     347.000 369.39481 2
416 2026 DRILL SHAFT (HIGH MAST POLE) (60 IN) LF 979.000 617.79000 4,493.000 528.90496 13
416 2027 DRILL SHAFT (HIGH MAST POLE) (66 IN) LF 195.000 665.96000 3,018.000 572.49648 5
416 2029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 3,502.000 141.32955 14,557.000 140.46912 62
416 2030 DRILL SHAFT (TRF SIG POLE) (24 IN) LF 130.000 201.16231 1,001.800 140.38628 25
416 2031 DRILL SHAFT (TRF SIG POLE) (30 IN) LF 56.000 242.05714 1,356.200 186.46197 34
416 2032 DRILL SHAFT (TRF SIG POLE) (36 IN) LF 349.000 222.03507 7,844.200 217.40834 104
416 2033 DRILL SHAFT (TRF SIG POLE) (42 IN) LF     370.400 268.00499 11
416 2034 DRILL SHAFT (TRF SIG POLE) (48 IN) LF 338.000 423.80355 4,768.800 319.31303 58
416 2038 DRILL SHAFT (108 IN) LF     123.000 800.00000 1
416 2039 DRILL SHAFT (144 IN) LF     153.000 2,000.00000 1
416 2043 DRILL SHAFT (54 IN) (BASE BID) LF     18.000 380.00000 1
416 2047 DRILL SHAFT (96 IN) LF     1,650.000 600.00000 1
416 2049 DRILL SHAFT (96 IN) LF     90.000 691.88000 1
416 2050 DRILL SHAFT (90 IN) LF     212.000 663.87000 1
416 2051 DRILL SHAFT (120 IN) LF     1,765.000 1,401.98300 2
416 2052 DRILLED SHAFT (12 IN) LF 7.000 40.00000 27.000 25.18519 2
416 2055 DRILL SHAFT (TRF SIG POLE) (30 IN) (ROCK LF     69.300 268.97648 3
416 2056 DRILL SHAFT (TRF SIG POLE) (36 IN) (ROCK LF     172.200 301.05726 3
416 2068 DRILL SHAFT (SIGN MTS) (60 IN) LF     916.000 385.80786 2
416 2078 CASING (36 IN.) LF 256.000 120.00000 256.000 120.00000 1
416 2086 DRILL SHAFT (RDWY ILL POLE) (24 IN) LF     699.500 100.48034 2
416 2094 DRILL SHAFT (60 IN) (CORED) LF     216.000 1,025.00000 1
420 2001 CL A CONC (MISC) CY 54.000 581.70370 1,550.800 362.85827 15
420 2002 CL B CONC (FLUME) CY     1,699.450 318.62298 12
420 2003 CL C CONC (ABUT) CY 194.400 790.24691 12,136.390 743.78871 114
420 2004 CL C CONC (BENT) CY 121.800 1,000.00000 15,397.600 862.18307 64
420 2005 CL C CONC (FOOTING) CY     4,918.200 624.78833 13
420 2006 CL C CONC (RAIL FOUNDATION) CY 923.400 357.04874 4,228.000 334.97042 29
420 2007 CL C CONC (CULV) CY     1,155.300 753.56704 8
420 2008 CL C CONC (WINGWALLS) CY     5.000 1,340.00000 1
420 2009 CL C CONC (HDWL) CY     10.200 2,341.17647 2
420 2010 CL C CONC (SIGN COLUMN) CY     2,670.480 582.02458 8
420 2011 CL C CONC (RETAINING WALL) CY     231.000 1,576.36364 2
420 2013 CL C CONC (MISC) CY 25.300 629.16996 1,630.620 522.17967 30
420 2014 CL C CONC (CURB OUTLET) (TY I) EA     3.000 1,666.66667 2
420 2015 CL C CONC (CURB OUTLET) (TY II) EA     3.000 1,766.66667 2
420 2016 CL C CONC (COLLAR) EA 25.000 1,706.47440 197.000 943.39056 21
420 2017 CL C CONC (BENT) (MASS PLACEMENT) CY     1,900.400 690.00000 1
420 2018 CL C CONC (FOOTING) (MASS PLACEMENT) CY 2,046.400 451.54000 10,926.800 463.54712 6