| Item No |
Description |
Units |
January 31, 2012 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 420 2016 |
CL C CONC (COLLAR) |
EA |
2.000 |
550.00000 |
296.000 |
520.82432 |
24 |
| 420 2017 |
CL C CONC (BENT) (MASS PLACEMENT) |
CY |
|
|
9,197.700 |
524.76793 |
3 |
| 420 2018 |
CL C CONC (FOOTING) (MASS PLACEMENT) |
CY |
|
|
13,246.700 |
371.86682 |
8 |
| 420 2019 |
CL C CONC (CAP) |
CY |
20.400 |
700.00000 |
16,984.500 |
529.67423 |
18 |
| 420 2020 |
CL C CONC (CRASHWALL) |
CY |
|
|
655.000 |
430.07328 |
2 |
| 420 2022 |
CL E CONC (SEAL) |
CY |
|
|
945.960 |
228.21261 |
11 |
| 420 2023 |
CL F CONC (COLUMN) |
CY |
|
|
840.700 |
936.49637 |
3 |
| 420 2025 |
CL F CONC (FOOTING) (MASS PLACEMENT) |
CY |
|
|
237.800 |
556.06392 |
2 |
| 420 2026 |
CL F CONC (FOOTING) |
CY |
|
|
424.100 |
596.06225 |
2 |
| 420 2027 |
CL F CONC (BENT) |
CY |
|
|
208.900 |
1,020.15318 |
2 |
| 420 2029 |
CL S CONC (SLAB) |
CY |
452.800 |
433.95186 |
8,425.200 |
439.33274 |
43 |
| 420 2030 |
CL S CONC (PAN GIRD) |
CY |
|
|
127.200 |
275.00000 |
1 |
| 420 2031 |
CL S CONC (SHEAR KEY) |
CY |
163.400 |
165.78947 |
1,641.100 |
169.35203 |
18 |
| 420 2032 |
CL S CONC (CULV DIR TRAF) |
CY |
.680 |
1,500.00000 |
28.680 |
818.06137 |
3 |
| 420 2033 |
CL S CONC (APPR SLAB) |
CY |
529.500 |
349.19075 |
20,852.600 |
303.16526 |
70 |
| 420 2034 |
CL S CONC (BRIDGE SDWLK) |
CY |
|
|
1,540.440 |
298.38198 |
11 |
| 420 2035 |
CL S CONC (CIP SLAB SPAN) |
CY |
|
|
369.440 |
803.08575 |
2 |
| 420 2036 |
CL A CONC (SEAL) |
CY |
|
|
40.000 |
221.25000 |
3 |
| 420 2037 |
CL C CONC (VALLEY GUTTER) |
SY |
|
|
133.000 |
47.50000 |
1 |
| 420 2039 |
CL D CONC (MISC) |
CY |
|
|
211.200 |
255.93277 |
5 |
| 420 2041 |
CL C CONC (ABUT) (HPC) |
CY |
420.090 |
544.98488 |
6,982.190 |
542.22338 |
43 |
| 420 2042 |
CL C CONC (BENT) (HPC) |
CY |
430.400 |
513.52230 |
16,633.950 |
771.04507 |
30 |
| 420 2045 |
CL A CONC (MISC) (6") |
SY |
|
|
197.000 |
57.51000 |
1 |
| 420 2049 |
CL S CONC (BRIDGE MEDIAN) |
CY |
|
|
238.900 |
379.64755 |
6 |
| 420 2050 |
CL F CONC (CAP) |
CY |
|
|
22,566.700 |
461.21807 |
5 |
| 420 2051 |
CL C CONC (COLUMN) |
CY |
|
|
4,487.800 |
572.09495 |
12 |
| 420 2052 |
CL C CONC (PILASTER) |
CY |
|
|
104.600 |
1,032.00000 |
1 |
| 420 2055 |
CL C CONC (COLUMN) (MASS PLACEMENT) |
CY |
|
|
31,809.900 |
502.65473 |
8 |
| 420 2058 |
CL C CONC (COLLAR) |
CY |
|
|
5.290 |
905.48204 |
2 |
| 420 2059 |
CL C CONC (CAP) (MASS PLACEMENT) |
CY |
|
|
7,738.080 |
481.23416 |
5 |
| 420 2060 |
CL B CONC (DITCH INTERCEPTOR STRUCTURE |
EA |
|
|
4.000 |
1,320.00000 |
1 |
| 420 2061 |
CL S CONC (HPC) BAS |
CY |
|
|
3,760.400 |
319.00166 |
10 |
| 420 2062 |
CL S CONC (HPC) REINF CONC SLAB |
SF |
|
|
6,143.300 |
15.90000 |
1 |
| 420 2064 |
CL A CONC (PLUG) |
EA |
1.000 |
285.00000 |
15.000 |
760.33333 |
4 |
| 420 2065 |
CL A CONC (STEPS) |
CY |
|
|
7.000 |
700.00000 |
1 |
| 420 2068 |
CL S CONC (HPC) (SLAB) |
CY |
|
|
66.900 |
777.24215 |
2 |
| 420 2069 |
CL S CONC (HPC) (SHEAR KEY) |
CY |
|
|
44.800 |
220.10000 |
1 |
| 420 2071 |
CL S CONC (BENT) |
CY |
|
|
96.400 |
373.00000 |
1 |
| 420 2077 |
CL C CONC (HPC) (CRASHWALL) |
CY |
|
|
283.200 |
540.00000 |
1 |
| 420 2082 |
CL C CONC (MEDIAN) |
CY |
|
|
36.000 |
494.95556 |
2 |
| 420 2084 |
CL A CONC (CURB OUTLET) (TY I) |
EA |
|
|
3.000 |
800.00000 |
2 |
| 420 2085 |
CL A CONC (CURB OUTLET) (TY II) |
EA |
|
|
2.000 |
950.00000 |
2 |
| 420 2087 |
CL F CONC (ABUT) |
CY |
|
|
352.000 |
510.00000 |
2 |
| 420 2088 |
CL S CONC (DIAPHRAGM) |
CY |
|
|
2.600 |
1,000.00000 |
1 |
| 420 2089 |
CL F CONC (CAP) (MASS PLACEMENT) |
CY |
|
|
810.800 |
645.14356 |
2 |
| 420 2090 |
CL A CONC (COLLAR) |
EA |
1.000 |
465.00000 |
17.000 |
848.41176 |
5 |
| 420 2091 |
CL B CONC (MISC) |
CY |
|
|
58.820 |
451.88116 |
3 |
| 420 2092 |
CL C CONC (CAP) (MASS PLACEMENT) (HPC) |
CY |
|
|
2,290.900 |
436.33441 |
3 |
| 420 2093 |
CL C CONC (COLUMN) (MASS PLACE) (HPC) |
CY |
|
|
6,239.300 |
495.61603 |
3 |
| 420 2094 |
CL C CONC (FOOTING) (MASS PLACE) (HPC) |
CY |
|
|
305.500 |
435.07201 |
2 |
| 420 2099 |
CL C CONC (CURB FLUME) (SPL) |
EA |
|
|
2.000 |
1,400.00000 |
1 |
| 420 2101 |
CL A CONC (RAMPS, STAIRS AND WALLS) |
CY |
|
|
8.000 |
900.00000 |
1 |
| 420 2102 |
CL A CONC (MEDIAN) |
CY |
|
|
377.800 |
346.99751 |
3 |
| 420 2104 |
CL A CONC (FLUME) |
CY |
|
|
3.000 |
690.00000 |
2 |
| 420 2112 |
CL C CONC (BENT) (BASE BID) |
CY |
|
|
25.300 |
780.00000 |
1 |
| 420 2115 |
CL F CONC (COLUMN) (MASS PLACEMENT) |
CY |
|
|
272.600 |
500.00000 |
1 |
| 420 2117 |
CL C CONC (SIGN FOOTING) |
CY |
|
|
722.200 |
452.57491 |
6 |
| 420 2123 |
CL C CONC (FOOTING) (HPC) |
CY |
|
|
2,467.200 |
1,500.00000 |
1 |
| 420 2124 |
CL S CONC (SLAB) |
SF |
|
|
13,581.000 |
16.54761 |
3 |
| 420 2213 |
CL H CONC (FASCIA PANEL) |
CY |
|
|
42.000 |
2,000.00000 |
1 |
| 420 2216 |
CL S CONC (SUPPORT SLAB) |
CY |
|
|
85.600 |
363.28692 |
4 |
| 420 2217 |
CL C CONC (PEDESTAL) |
CY |
|
|
29.760 |
447.79872 |
2 |
| 420 2220 |
CL C CONC (SHEAR KEY) |
CY |
|
|
10.500 |
900.00000 |
1 |
| 420 2221 |
CL S CONC (JUNCTION BOX) |
CY |
|
|
47.000 |
1,062.23404 |
2 |
| 420 2223 |
CL C CONC (COLUMN) (HPC) |
CY |
|
|
2,952.800 |
537.56015 |
9 |
| 420 2224 |
CL C CONC (MISC) (HPC) |
CY |
|
|
219.500 |
331.24770 |
2 |
| 420 2228 |
CL C CONC (MOUNTABLE MEDIAN NOSE) |
EA |
|
|
20.000 |
1,411.28000 |
1 |
| 420 2240 |
CL A CONC (SPANDREL) |
CY |
|
|
15.700 |
420.00000 |
1 |
| 420 2246 |
CL H CONC (DIAPHRAGM) (HPC) (MASS PLA) |
CY |
|
|
238.400 |
520.00000 |
1 |
| 420 2247 |
CL H CONC (CIP BOX) (HPC) |
CY |
67.400 |
710.00000 |
338.500 |
1,262.61152 |
2 |
| 420 2251 |
CL A CONC (COLLAR) |
CY |
|
|
1.000 |
2,000.00000 |
1 |
| 420 2252 |
CL HES CONC (MISC) |
CY |
|
|
8.670 |
400.00000 |
1 |
| 420 2256 |
CL S CONC (APPR SLAB) (HPC) |
CY |
778.600 |
389.82790 |
7,186.130 |
359.71835 |
24 |
| 420 2258 |
CL F CONC (BENT) (HPC) |
CY |
1,890.900 |
575.00000 |
6,632.500 |
878.83415 |
2 |
| 420 2261 |
CL S CONC (APPR SLAB) (HPC) |
CY |
|
|
76.500 |
330.00000 |
1 |
| 420 2263 |
CL C CONC (BENT) (HPC) (MASS PLACEMENT) |
CY |
|
|
887.400 |
620.00000 |
1 |
| 420 2264 |
CL H CONC (COLUMN) (MASS PLACEMENT) (HPC |
CY |
|
|
366.700 |
1,100.00000 |
1 |
| 420 2265 |
CL H CONC (PEDESTALS) (HPC) |
CY |
|
|
7.200 |
1,700.00000 |
1 |
| 420 2268 |
CL C CONC (RAIL FOUNDATION) (HPC) |
CY |
|
|
93.000 |
375.00000 |
1 |
| 420 2269 |
CL C CONC (CAP) (HPC) |
CY |
|
|
4,242.500 |
576.52488 |
8 |
| 420 2271 |
CL C CONC (RAIL FOUNDATION) (OPT1) |
CY |
|
|
61.000 |
267.64000 |
1 |
| 420 2276 |
CL C CONC (WALL) |
CY |
|
|
64.800 |
1,300.00000 |
1 |
| 420 2277 |
CL S CONC (DIAPHRAGM) (HPC) |
CY |
|
|
532.400 |
555.00000 |
1 |
| 420 2278 |
CL F CONC (CAP) (MASS PLACEMENT) (HPC) |
CY |
|
|
5,161.200 |
445.00000 |
1 |
| 420 2279 |
CL C CONC (PEDESTAL) (HPC) |
CY |
|
|
135.300 |
320.00000 |
1 |
| 420 2280 |
CL H CONC (DIAPHRAGM) (HPC) |
CY |
|
|
1,033.600 |
583.00000 |
1 |
| 420 2283 |
CL F CONC (END WALL) |
CY |
|
|
235.600 |
1,800.00000 |
1 |
| 420 2285 |
CL F CONC (GRADE BEAM) |
CY |
|
|
1,497.200 |
620.00000 |
1 |
| 420 2286 |
CL H CONC (PRECAST PANEL) |
SF |
|
|
66,793.000 |
19.00000 |
1 |
| 420 2287 |
CL S CONC (APPR SLAB) (MOD) |
CY |
|
|
145.400 |
362.30000 |
1 |
| 420 2288 |
CL C CONC (MONUMENT) (TY 1) |
CY |
|
|
92.000 |
754.00000 |
1 |
| 420 2289 |
CL C CONC (MONUMENT) (TY 2) |
CY |
|
|
156.000 |
648.00000 |
1 |
| 420 2290 |
CL C CONC (MONUMENT) (TY 3) |
CY |
|
|
112.000 |
769.00000 |
1 |
| 420 2292 |
CL S CONC (BRIDGE SDWLK) (HPC) |
CY |
|
|
363.900 |
368.84999 |
1 |
| 422 2001 |
REINF CONC SLAB |
SF |
7,280.000 |
14.00000 |
6,812,621.600 |
8.39532 |
69 |
| 422 2002 |
REINF CONC SLAB (EXT SLAB) |
SF |
|
|
37,629.000 |
20.05366 |
4 |
| 422 2003 |
REINF CONC SLAB (HPC) (CL S) |
SF |
178,249.750 |
14.04548 |
3,587,388.750 |
12.05454 |
43 |
| 422 2008 |
REINF CONC SLAB (EXT SLAB) (HPC) (CL S) |
SF |
|
|
9,637.000 |
22.36224 |
2 |
| 423 2001 |
RETAINING WALL (MSE) |
SF |
111,926.000 |
23.00000 |
2,256,286.180 |
29.26395 |
40 |
| 423 2003 |
RETAINING WALL (MSE) (ASHLAR STONE FIN) |
SF |
|
|
188,805.000 |
22.99027 |
2 |