I-35 Capital Express Central: US 290 East to US 290 West

Timeline:
2024-2033

Cost:
$4,500,000,000

Public benefits:
Driver benefits*
Add two non-tolled managed lanes in each direction

Project name:
I-35 Capital Express North: SH 45 North to US 290 East

Timeline:
2023-2029

Cost:
$606,000,000

Public benefits:
Driver benefits*
Add one non-tolled managed lane in each direction

Project name:
I-35 Capital Express South: US 290 West to SH 45 Southeast

Timeline:
2022-2025

Cost:
$548,000,000

Public benefits:
Driver benefits*
Add two non-tolled managed lanes in each direction

Project name:
Loop 360 at Courtyard Drive/RM 2222

Timeline:
2026-2028

Cost:
$46,000,000

Public benefits:
Driver benefits*
Remove traffic signal at Courtyard Drive and replace with an underpass
Reconstruct the RM 2222 intersection to include a diverging diamond interchange

Project name:
Oak Hill Parkway: US 290 from West of FM 1826 to SL 1. SH 71 from US 290 West to Silvermine Dr.

Timeline:
2021-2026

Cost:
$731,000,000

Public benefits:
Driver benefits*
Reconstruct 4-lane divided roadway to 6-lane controlled access highway.
Reconstruct the US 290/SH 71 interchange and add flyovers

Completed projects

Project name:
I-35 from US 79 to SH 45 North (southbound)

Timeline:
2022-2023

Cost:
$9,300,000

Public benefits:
Driver benefits*
Construct auxiliary lane to remove merging conflicts on the southbound I-35 mainlanes between RM 620 and Hesters Crossing

Project name:
I-35: At 51st Street

Timeline:
2016-2018

Cost:
$19,200,000

Public benefits:
Driver benefits*
Added a new roundabout at the southbound I-35 frontage road at I-35, realigned the frontage road

Project name:
I-35: At Oltorf Street

Timeline:
2017-2020

Cost:
$51,400,000

Public benefits:
Driver benefits*
Reconstructed the I-35 at Oltorf Street intersection

Project name:
I-35: At Parmer Lane

Timeline:
2019-2022

Cost:
$33,600,000

Public benefits:
Driver benefits*
Construct diverging diamond interchange to alleviate an existing bottleneck at the intersection of FM 734 (Parmer Lane) and I-35

Project name:
I-35: Rundberg Lane to US 290 East

Timeline:
2018-2022

Cost:
$199,700,000

Public benefits:
Driver benefits*
Add three flyovers at the I-35/US 183 interchange
Improve the existing northbound I-35 to northbound US 183 flyover

Project name:
Traffic Management System Upgrade: I-35 Capital Area - Bell County Line to Comal County Line

Timeline:
2016-2019

Cost:
$11,500,000

Public benefits:
Driver benefits*

Project name:
US 183: Metric Blvd. to I-35

Timeline:
2020-2020

Cost:
$2,300,000

Public benefits:
Driver benefits*
Add northbound and southbound auxiliary lanes on US 183 between Metric Boulevard and I-35 flyovers to alleviate bottleneck in this area

*Driver benefits include:
  • Reducing Congestion
  • Improve Safety and Mobility
  • Increasing Operational Efficiency
  • Providing Reliable Travel Time