Monthly State Let Construction Report For Austin District As Of Jun 10, 2015 Page 8 Of 10

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLLANO
Highway CR
From ON CR 216 AT BOARD BRANCH
To STR AA0552001
CSJ 0914-25-006
Proj ID BR 2011(981)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 226113.43 0.00 233493.26 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 09-22-14
Work Completed 03-09-15
Time Computed 09-22-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 82
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-006
BXB GROUP INCORPORATION( 46.45%)
TRP CONSTRUCTION GROUP, LLC(2.17%)
Contract # 05143026
Totals 226113.43 0.00 233493.26 100.0

CountyLLANO
Highway CR
From ON CR 202 AT LITTLE LLANO
To STR AA0630001
CSJ 0914-25-007
Proj ID BR 2011(982)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 299364.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-26-15
Work Began 00-00-00
Work Completed  
Time Computed 04-11-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3I CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153214
Totals 299364.78 0.00 0.00 0.0

CountyHAYS
Highway CR
From ON CR 266 AT SAN MARCOS RIVER
To STR AA02-24-001
CSJ 0914-33-035
Proj ID BR 2005(711)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 576253.11 0.00 559682.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-14
Work Began 10-13-14
Work Completed  
Time Computed 07-27-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 147
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-035
ALTUS TRAFFIC MANAGEMENT LLC (0.64%)
ENVIRONMENTAL SAFETY SERVICES, INC.( 11.82%)
FLASHER EQUIPMENT COMPANY(0.74%)
J.D. RAMMING PAVING CO./AUSTIN MATERIALS LLC (6.82%)
BAIRD DRILLING SERVICES, INC.(3.49%)
Contract # 05143214
Totals 576253.11 0.00 559682.00 99.9

CountyHAYS
Highway VA
From VARIOUS LOCATIONS IN HAYS COUNTY
To ON IH 35 AND SH 80
CSJ 0914-33-063
Proj ID STP 2012(552)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 467144.80 1150.80 496384.01 99.9
Work Order 06-14-12
Work Began 07-09-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 72
Addl Days Granted 6
Working Days Charged 78
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063
LONE STAR TRAFFIC SERVICE, INC.(1.37%)
TERRY PRATHER( 16.78%)
Contract # 05123226
Totals 467144.80 1150.80 496384.01 99.9

CountyBLANCO
Highway RM 165
From SL 163
To HAYS C/L
CSJ 0954-02-016
Proj ID STP 2012(553)HRR
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
11.900 816534.84 0.00 878235.90 99.9
CountyBLANCO
Highway RM 165
From SL 163
To BLANCO/HAYS COUNTY LINE
CSJ 0954-02-017
Proj ID STP 2012(553)HRR
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
11.949 4792086.66 0.00 5852644.62 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 10-02-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 261
Addl Days Granted 57
Working Days Charged 471
Percent Time Used 148
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017
HIGHWAY TECHNOLOGIES, INC. (1.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%)
ABC EROSION CONTROL, INC.(0.72%)
AUSTIN WOOD RECYCLING(1.45%)
JMHP, INC. (0.85%)
Contract # 05123212
Totals 5608621.50 0.00 6730880.52 99.9

CountyWILLIAMSON
Highway FM 619
From 0.089 MI. NORTH OF BRUSHY CREEK
To 0.100 MI. SOUTH OF BRUSHY CREEK
CSJ 0986-01-042
Proj ID BR 1502(149)
Work Type REPLACE BRIDGE
 
0.189 1143838.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0986-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153051
Totals 1143838.60 0.00 0.00 0.0

CountyBASTROP
Highway FM 696
From 1.165 MI N OF US 290
To 1.296 MI N OF US 290
CSJ 1073-01-020
Proj ID BR 1502(072)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 2191679.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153008
Totals 2191679.00 0.00 0.00 0.0

CountyGILLESPIE
Highway RM 783
From US 290
To 8.977 MI S OF US 290
CSJ 1135-01-026
Proj ID STP 2013(028)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
8.977 5106864.29 0.00 4706039.16 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 04-15-13
Work Completed 01-09-15
Time Computed 04-15-13
Contract Working Days 229
Addl Days Granted 0
Working Days Charged 331
Percent Time Used 144
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026
ROADWAY SPECIALTIES, INC.(3.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%)
RELMCO, INC. ( 31.14%)
D. I. J. CONSTRUCTION, INC.(1.16%)
VOGES DRILLING CO. (1.08%)
LONE STAR PAVING COMPANY (2.40%)
Contract # 02133212
Totals 5106864.29 0.00 4706039.16 100.0

CountyTRAVIS
Highway FM 969
From DECKER CREEK DRIVE
To BASTROP COUNTY LINE
CSJ 1186-01-087
Proj ID STP 2015(277)HES
Work Type PROVIDE ADD'L PAVED SURFACE WIDTH
 
7.101 5894316.37 66702.55 296110.85 5.0
Work Order 01-05-15
Work Began 03-17-15
Work Completed  
Time Computed 03-17-15
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 8
Contractor(s)
M.A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC.(7.14%)
TRP CONSTRUCTION GROUP, LLC(2.30%)
LONE STAR PAVING, INC. ( 47.54%)
Contract # 11143219
Totals 5894316.37 66702.55 296110.85 5.0

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 395328.73 6623426.42 56.8
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 6799.48 1467060.02 67.0
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 3
Working Days Charged 180
Percent Time Used 60
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
PANTHER CREEK TRANSPORTATION, INC. (0.89%)
Contract # 12133203
Totals 13848703.79 402128.21 8090486.44 58.4

CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To 600 FT. SOUTH OF MURCHISON ST.
CSJ 1200-03-045
Proj ID CC 1200-3-45
Work Type ADD CONTINUOUS LEFT TURN LANE
 
0.312 85872.74 0.00 3400.00 3.9
CountyTRAVIS
Highway FM 973
From 0.159 MI. SOUTH OF BLAKE MANOR RD.
To DECKER CREEK
CSJ 1200-03-052
Proj ID STP 1402(058)
Work Type REHAB RDWY, ADD 6' SHOULDERS
 
4.911 3246677.62 4000.00 637537.02 19.6
Work Order 11-12-14
Work Began 01-26-15
Work Completed  
Time Computed 11-28-14
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 25
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-052
M.V. HENKE ENTERPRISES, INC. (1.13%)
ROADWAY SPECIALTIES, INC.(7.55%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.83%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.69%)
Contract # 09143236
Totals 3332550.36 4000.00 640937.02 19.2

CountyTRAVIS
Highway FM 973
From 3880 FT SOUTH OF SH 71
To FM 812
CSJ 1200-03-046
Proj ID STP 2014(621)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
3.418 4060301.69 135715.07 2870239.69 70.6
Work Order 05-29-14
Work Began 08-07-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 48
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046
AUSTIN WOOD RECYCLING(1.13%)
CHEROKEE SERVICES(0.13%)
FLASHER EQUIPMENT COMPANY(2.42%)
ROADWAY SPECIALTIES, INC.(7.52%)
TRP CONSTRUCTION GROUP, LLC(0.43%)
RELMCO, INC. ( 13.01%)
HAYWOOD BAKER(4.07%)
THE LEVY COMPANY, L.P. (0.10%)
MURRAY CONSTRUCTION(0.53%)
VOGES DRILLING CO. (1.38%)
Contract # 04143030
Totals 4060301.69 135715.07 2870239.69 70.6

CountyWILLIAMSON
Highway FM 1466
From AT DRAW
To (STR 1200-4-6)
CSJ 1200-04-011
Proj ID BR 1502(353)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 597945.34 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1200-04-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153052
Totals 597945.34 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-016
Proj ID STP 2014(559)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
2.466 3060816.52 6483.25 2551429.85 83.3
Work Order 06-16-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 81
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-016
AUSTIN WOOD RECYCLING(1.13%)
D. I. J. CONSTRUCTION, INC.(1.12%)
THE LEVY COMPANY, L.P. (0.14%)
MURRAY CONSTRUCTION(0.88%)
RELMCO, INC. ( 30.62%)
ROADWAY SPECIALTIES, INC.(4.85%)
TRP CONSTRUCTION GROUP, LLC(0.28%)
Contract # 04143018
Totals 3060816.52 6483.25 2551429.85 83.3

CountyTRAVIS
Highway SH 45
From LOOP 1
To RM 1826
CSJ 1200-06-010
Proj ID STP 2014(724)
Work Type MILL, SEAL & THIN OVERLAY
 
2.599 1283793.90 0.00 1158500.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 09-03-14
Work Completed 03-03-15
Time Computed 08-20-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 134
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
D. I. J. CONSTRUCTION, INC.(3.74%)
ROADWAY SPECIALTIES, INC.(4.80%)
Contract # 06143028
Totals 1283793.90 0.00 1158500.75 100.0

CountyWILLIAMSON
Highway FM 487
From IH35
To BELL COUNTY LINE
CSJ 1201-02-018
Proj ID STP 2015(737)
Work Type REHAB RDWY
 
4.212 6851307.42 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 487
From IH35
To BELL COUNTY LINE
CSJ 1201-02-020
Proj ID ROW 1201-2-20
Work Type ROW ACQ & UTIL ADJ
 
4.212 286200.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
M.A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153230
Totals 7137507.42 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 151239.50 3267925.46 53.3
Work Order 04-16-14
Work Began 06-25-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 60
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40%)
AUSTIN WOOD RECYCLING(1.19%)
TEXAS HIGHWAY WALLS(5.57%)
R K STEPHENS CONSTRUCTION, LLC (3.21%)
D. I. J. CONSTRUCTION, INC.(0.77%)
J & M CONTRACTING, COMPANY (7.41%)
ROADWAY SPECIALTIES, INC.(2.24%)
SAN-ANN-CO., INC.(0.55%)
LONE STAR PAVING CO. ( 10.66%)
INDUS CONSTRUCTION, L.P. (0.07%)
Contract # 02143227
Totals 6128687.87 151239.50 3267925.46 53.3

CountyWILLIAMSON
Highway FM 487
From 1500 FEET WEST OF CR 233
To IH 35
CSJ 1201-02-021
Proj ID STP 2015(190)
Work Type REHAB RDWY
 
7.186 9058441.29 17334.67 778559.02 8.5
Work Order 01-05-15
Work Began 02-09-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 18
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-021
AARON CONCRETE CONTRACTORS, L.P. (5.81%)
D&S TEXAS ICON CONSTRUCTION, LLC (3.67%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.67%)
FLASHER EQUIPMENT COMPANY(0.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.45%)
R K STEPHENS CONSTRUCTION, LLC (4.64%)
TRP CONSTRUCTION GROUP, LLC(1.39%)
CHANDLER CONCRETE, INC.(2.57%)
AUSTIN FORMULA UTILITIES (0.31%)
EGGEMEYER LAND CLEARING, LLC (0.68%)
Contract # 10143016
Totals 9058441.29 17334.67 778559.02 8.5

CountyWILLIAMSON
Highway FM 487
From BELL C/L
To BELL C/L IN BARTLETT
CSJ 1201-03-021
Proj ID STP 2012(417)
Work Type PAVMNT RESTORATION AND ADD SHLDRS
 
7.520 6421595.35 47400.00 7033684.57 99.9
CountyBELL
Highway FM 487
From WILLIAMSON CO LINE W OF FM 2115
To WILLIAMSON CO LINE E OF FM 2115
CSJ 1201-05-010
Proj ID STP 2012(423)
Work Type PAV RESTORATION AND ADD SHOULDERS
 
0.395 285832.17 0.00 304542.53 99.9
Work Order 05-04-12
Work Began 05-20-13
Work Completed  
Time Computed 05-20-12
Contract Working Days 391
Addl Days Granted 0
Working Days Charged 319
Percent Time Used 81
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
SILVA CONTRACTING COMPANY, INC.( 11.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%)
MURRAY CONSTRUCTION(0.48%)
D. I. J. CONSTRUCTION, INC.(1.28%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%)
JAG TRUCKING INC (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
THE LEVY COMPANY, L.P. (0.25%)
R K STEPHENS CONSTRUCTION, LLC (6.66%)
Contract # 03123002
Totals 6707427.52 47400.00 7338227.10 99.9

CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK
To (STR 1202-3-12)
CSJ 1202-03-010
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.115 643228.90 900.00 658774.41 99.9
CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK RELIEF
To (STR 1202-3-11)
CSJ 1202-03-011
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 286828.45 0.00 287636.28 99.9
CountyWILLIAMSON
Highway FM 1063
From AT DRAW
To (STR 1202-3-10)
CSJ 1202-03-012
Proj ID BR 2014(673)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 609386.85 0.00 603965.78 99.1
Work Order 04-25-14
Work Began 05-19-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 98
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-010
FLASHER EQUIPMENT COMPANY(1.52%)
GK CONSTRUCTION, LLC (0.78%)
HOUSTON SAWING & DRILLING(0.23%)
ROADWAY SPECIALTIES, INC.(0.62%)
APAC-TEXAS, INC. (9.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.81%)
SAN-ANN-CO., INC.(0.42%)
Contract # 03143222
Totals 1539444.20 900.00 1550376.47 99.9