Monthly State Let Construction Report For Austin District As Of Dec 10, 2014 Page 8 Of 8

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway RM 2222
From 500 W OF WESTSLOPE CIRCLE
To LP 1 SBFR
CSJ 2100-01-058
Proj ID STP 2014(535)
Work Type UNDERSEAL AND OVERLAY
 
3.154 747616.73 35726.35 572409.53 76.5
Work Order 04-15-14
Work Began 10-07-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 45
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-058
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
TEX OP CONSTRUCTION, LP(1.41%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.96%)
FLASHER EQUIPMENT COMPANY(5.71%)
Contract # 03143215
Totals 747616.73 35726.35 572409.53 76.5

CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-017
Proj ID STP 1402(060)
Work Type CONST 4 - LN DIV & LTL
 
2.022 11875032.06 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-019
Proj ID HP 2012(774)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232 490003.34 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1460
From 0.6 MI. N OF CR 111 (WESTINGHOUSE)
To 0.05 MI. N. OF UNIVERSITY BLVD
CSJ 2211-02-026
Proj ID STP 1402(059)MM
Work Type CONSTRUCT 4 - LANE DIVIDED SECTION
 
1.600 9154356.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 390
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OBRASCON HUARTE LAIN, S.A. INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143204
Totals 21519391.70 0.00 0.00 0.0

CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-023
Proj ID C 2293-1-23
Work Type ADD CTL & 2 - LANE DIVIDED WITH SHLDR
 
0.100 2375537.19 74498.81 2038280.53 87.3
CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-026
Proj ID RW 2293-1-23
Work Type ROW UTL. ADJ.
 
0.100 586353.33 0.00 618064.38 99.9
Work Order 01-06-14
Work Began 03-08-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 95
Addl Days Granted 30
Working Days Charged 173
Percent Time Used 138
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-023
AUSTIN WOOD RECYCLING(1.17%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.14%)
THE LEVY COMPANY, L.P. (1.03%)
M & M INDUSTRIAL PAINTING(0.18%)
FLASHER EQUIPMENT COMPANY(2.14%)
M. C. ETHRIDGE COMPANY ( 17.68%)
ROADWAY SPECIALTIES, INC.(2.35%)
ROSCH COMPANY(1.97%)
Contract # 08133055
Totals 2961890.52 74498.81 2656344.91 90.9

CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-024
Proj ID C 2293-1-24
Work Type ADD CENTER TURN LANE
 
0.840 5945396.48 352276.88 3351000.11 56.3
CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-025
Proj ID RW 2293-1-25
Work Type ADJUSTMENT OF UTILITIES
 
0.840 1005448.75 5582.50 84866.50 8.4
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 156
Percent Time Used 59
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-024
ANGEL BROTHERS ENTERPRISES, LTD. ( 16.23%)
ENCINO LANDSCAPE, INC. (1.01%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.89%)
GK CONSTRUCTION, LLC (0.45%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.52%)
THE LEVY COMPANY, L.P. (4.50%)
JUST GROOVING, LTD.(0.05%)
SCOTT DERR PAINTING CO (0.01%)
VOGES DRILLING (0.44%)
THOMAS TURF GRASS(0.32%)
Contract # 10133012
Totals 6950845.23 357859.38 3435866.61 49.4

CountyBURNET
Highway RM 2147
From 0.432 MI WEST OF WIRTZ DAM RD
To 1.022 MI EAST OF WIRTZ DAM RD
CSJ 2687-02-018
Proj ID STP 2015(019)
Work Type ADD LEFT TURN LANE
 
1.454 2455661.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 12-09-14
Work Completed  
Time Computed 11-30-14
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2687-02-018
AUSTIN WOOD RECYCLING(1.34%)
D. I. J. CONSTRUCTION, INC.(2.09%)
FLASHER EQUIPMENT COMPANY(0.26%)
MPB, INC.( 27.46%)
ROADWAY SPECIALTIES, INC.(2.63%)
Contract # 09143221
Totals 2455661.59 0.00 0.00 0.0

CountyTRAVIS
Highway RM 2769
From STATE MAINTENANCE ENDS
To 0.971 MILES WEST OF RM 620
CSJ 2718-01-012
Proj ID STP 2014(536)
Work Type FULL DEPTH REPAIR, UNDERSEAL & OVERLAY
 
6.046 1549763.40 0.00 6015.26 0.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 00-00-00
Work Completed  
Time Computed 05-25-14
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2718-01-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143009
Totals 1549763.40 0.00 6015.26 0.3

CountyGILLESPIE
Highway RM 2721
From RM 1631
To RM 1623
CSJ 2719-01-008
Proj ID STP 2013(029)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
6.022 2899581.31 183822.27 2165124.78 82.4
Work Order 10-18-12
Work Began 11-26-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 159
Addl Days Granted 3
Working Days Charged 451
Percent Time Used 278
Contractor(s)
THE HANOVER INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2719-01-008
D. I. J. CONSTRUCTION, INC.(1.49%)
ROADWAY SPECIALTIES, INC.(0.36%)
RICE ENVIRONMENTAL SERVICES(2.31%)
DIAMOND X CONTRACTING, INC (1.72%)
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.(2.51%)
RIATA ENTERPRISES(0.64%)
DOUBLE S PAVING, INC.(4.48%)
ALLEN KELLER COMPANY (101.69%)
INCE ENTERPRISES, INC. (2.55%)
R & S EXCAVATION, LLC(0.43%)
Contract # 09123212
Totals 2899581.31 183822.27 2165124.78 82.4

CountyTRAVIS
Highway LP 1
From US 290
To BRUSH COUNTRY ROAD
CSJ 3136-01-169
Proj ID STP 1102(330)
Work Type LANDSCAPING AND IRRIGATION
 
1.935 246629.48 0.00 231653.66 93.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-11
Work Began 03-05-12
Work Completed  
Time Computed 12-12-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 56
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-169
N-LINE TRAFFIC MAINTENANCE, L.P. (1.52%)
Contract # 08113269
Totals 246629.48 0.00 231653.66 93.9

CountyTRAVIS
Highway LP 1
From NORTH OF LP 360
To NORTH OF US 290
CSJ 3136-01-172
Proj ID C 3136-1-172
Work Type ADD BICYCLE BRIDGE
 
0.448 7396549.39 122267.07 2199927.49 29.7
CountyTRAVIS
Highway LP 1
From LP 360
To 0.5 MI NORTH OF SOUTHWEST PARKWAY
CSJ 3136-01-173
Proj ID C 3136-1-173
Work Type MILL & OVERLAY FOR RESTRIPE SBML
 
1.050 376467.39 0.00 0.00 0.0
Work Order 01-23-14
Work Began 02-10-14
Work Completed  
Time Computed 02-08-14
Contract Working Days 549
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 37
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-172
FLASHER EQUIPMENT COMPANY(1.33%)
RUSSO CORPORATION(7.36%)
ROADWAY SPECIALTIES, INC.(4.32%)
AUSTIN WOOD RECYCLING(0.88%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.29%)
A BROTHERS (OLD PRIME) (0.21%)
APAC-TEXAS, INC. (5.66%)
CARMA CONSTRUCTION, LLC(2.31%)
CHEROKEE SERVICES(0.32%)
THE LEVY COMPANY, L.P. ( 12.72%)
MCL CONTRACTING, LLC (0.45%)
R K STEPHENS CONSTRUCTION, LLC (2.38%)
SCOTT DERR PAINTING CO, LLC(0.25%)
SOUTHEAST GRINDING & GROOVING, LLC (0.04%)
TEXAS HIGHWAY WALLS(3.07%)
Contract # 10133028
Totals 7773016.78 122267.07 2199927.49 28.3

CountyTRAVIS
Highway LP 1
From TUSCAN TERRACE AT LOOP 1 (MOPAC)
To APPROX 500 FT N. OF BARTON CREEK
CSJ 3136-01-174
Proj ID STP 1402(061)MM
Work Type CONSTRUCT BICYCLE & PED BRDG (PH 1)
 
0.498 2985697.49 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-01-14
Work Began 00-00-00
Work Completed  
Time Computed 12-17-14
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-174
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143214
Totals 2985697.49 0.00 0.00 0.0

CountyTRAVIS
Highway LP 1
From BARTON CREEK
To SOUTHWEST PARKWAY
CSJ 3136-01-178
Proj ID STP 2014(561)
Work Type OVERLAY FRONTAGE ROADS
 
0.501 740923.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-10-14
Work Began 00-00-00
Work Completed  
Time Computed 06-26-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-178
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143220
Totals 740923.26 0.00 0.00 0.0

CountyTRAVIS
Highway LP 1
From WILLIAM CANNON BOULEVARD
To SLAUGHTER LANE
CSJ 3136-01-179
Proj ID STP 2013(341)
Work Type REPAIR, LEVEL & THIN OVERLAY
 
2.385 1466461.46 297078.91 1448853.93 99.1
Work Order 04-15-13
Work Began 08-04-14
Work Completed  
Time Computed 05-01-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 113
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-179
A BROTHERS MILLING, LLC(0.51%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
ROADWAY SPECIALTIES, INC.( 11.56%)
D. I. J. CONSTRUCTION, INC.(4.10%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.93%)
Contract # 01133022
Totals 1466461.46 297078.91 1448853.93 99.1

CountyTRAVIS
Highway FM 3177
From US 290
To 0.02 MI NORTH OF LINDELL LN
CSJ 3277-01-013
Proj ID STP 1302(009)
Work Type REALIGN RDWY
 
0.838 3616126.77 2800.00 2170713.39 60.0
Work Order 01-06-14
Work Began 02-03-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 159
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 61
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 3277-01-013
AUSTIN WOOD RECYCLING(0.53%)
FLASHER EQUIPMENT COMPANY(1.53%)
APAC-TEXAS, INC. ( 25.79%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84%)
DUSTROL, INC.(0.45%)
ROADWAY SPECIALTIES, INC.(3.30%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.10%)
Contract # 08133051
Totals 3616126.77 2800.00 2170713.39 60.0

CountyTRAVIS
Highway FM 734
From 1630 FEET WEST OF LP 1
To TOMANET TRAIL
CSJ 3417-01-027
Proj ID NH 2013(706)
Work Type OVERLAY & RESTRIPE FOR BICYCLE LANE
 
0.590 335191.45 0.00 429593.47 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 06-09-14
Work Completed  
Time Computed 08-16-13
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 109
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3417-01-027
ROADWAY SPECIALTIES, INC.(1.18%)
D. I. J. CONSTRUCTION, INC.( 15.52%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.96%)
SCR CONSTRUCTION CO., INC. ( 10.95%)
Contract # 05133039
Totals 335191.45 0.00 429593.47 99.9

CountyTRAVIS
Highway FM 734
From 0.166 MI. NW OF DESSAU ROAD
To 0.280 MI. SE OF DESSAU ROAD
CSJ 3417-03-017
Proj ID C 3417-3-17
Work Type ADD LEFT AND RIGHT TURN LANES
 
0.446 1481100.48 15974.80 1543696.36 99.9
Work Order 08-19-13
Work Began 09-27-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 96
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-017
ROADWAY SPECIALTIES, INC.(1.67%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 19.58%)
WHEELER COATINGS ASPHALT, INC. ( 34.98%)
FLASHER EQUIPMENT COMPANY( 15.34%)
KRL CONSTRUCTION INC.(1.15%)
Contract # 04133027
Totals 1481100.48 15974.80 1543696.36 99.9