Monthly State Let Construction Report For Austin District As Of Aug 16, 2016 Page 8 Of 9

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway FM 487
From IH35
To BELL COUNTY LINE
CSJ 1201-02-018
Proj ID STP 2015(737)
Work Type REHAB RDWY
 
4.212 6851307.42 501235.51 2762949.22 40.3
CountyWILLIAMSON
Highway FM 487
From IH35
To BELL COUNTY LINE
CSJ 1201-02-020
Proj ID ROW 1201-2-20
Work Type ROW ACQ & UTIL ADJ
 
4.212 286200.00 0.00 236610.66 82.6
Work Order 10-20-15
Work Began 01-11-16
Work Completed  
Time Computed 11-19-15
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 47
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-018
TRP CONSTRUCTION GROUP, LLC(0.95%)
RAMMING PAVING COMPANY ( 11.19%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.34%)
ACTION SERVICES(0.12%)
R K STEPHENS CONSTRUCTION, LLC (6.55%)
Contract # 03153230
Totals 7137507.42 501235.51 2999559.88 42.0

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 5836.95 5999427.82 97.8
Work Order 04-16-14
Work Began 06-25-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 284
Percent Time Used 98
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40%)
AUSTIN WOOD RECYCLING(1.19%)
TEXAS HIGHWAY WALLS(5.57%)
R K STEPHENS CONSTRUCTION, LLC (3.21%)
D. I. J. CONSTRUCTION, INC.(0.77%)
J & M CONTRACTING, COMPANY (7.41%)
ROADWAY SPECIALTIES, INC.(2.24%)
SAN-ANN-CO., INC.(0.55%)
LONE STAR PAVING CO. ( 10.66%)
INDUS CONSTRUCTION, L.P. (0.07%)
Contract # 02143227
Totals 6128687.87 5836.95 5999427.82 97.8

CountyWILLIAMSON
Highway FM 487
From 1500 FEET WEST OF CR 233
To IH 35
CSJ 1201-02-021
Proj ID STP 2015(190)
Work Type REHAB RDWY
 
7.186 9058441.29 279043.13 6741640.20 74.4
Work Order 01-05-15
Work Began 02-09-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 306
Addl Days Granted 21
Working Days Charged 292
Percent Time Used 89
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-021
AARON CONCRETE CONTRACTORS, L.P. (5.81%)
D&S TEXAS ICON CONSTRUCTION, LLC (3.67%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.67%)
FLASHER EQUIPMENT COMPANY(0.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.45%)
R K STEPHENS CONSTRUCTION, LLC (4.64%)
TRP CONSTRUCTION GROUP, LLC(1.39%)
CHANDLER CONCRETE, INC.(2.57%)
AUSTIN FORMULA UTILITIES (0.31%)
EGGEMEYER LAND CLEARING, LLC (0.68%)
Contract # 10143016
Totals 9058441.29 279043.13 6741640.20 74.4

CountyWILLIAMSON
Highway FM 972
From IH 35
To 0.128 MILES WEST OF CR 150
CSJ 1202-01-017
Proj ID STP 1502(073)
Work Type REHAB PVMT, ADD SHLDR & SAFTY TREAT
 
3.198 4156413.83 476332.75 2059744.39 49.5
Work Order 11-24-15
Work Began 01-04-16
Work Completed  
Time Computed 01-04-16
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 39
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-017
APAC-TEXAS, INC. (8.51%)
ROADWAY SPECIALTIES, INC.(3.02%)
TRP CONSTRUCTION GROUP, LLC(0.98%)
Contract # 09153204
Totals 4156413.83 476332.75 2059744.39 49.5

CountyCALDWELL
Highway FM 1322 ETC
From 4.914 MI. NORTH OF FM 86
To FM 86
CSJ 1375-01-010
Proj ID STP 2016(174)
Work Type ACP, LVL - UP, FULL DEPTH REPAIR & SC
 
31.597 2572762.09 0.00 2501494.52 97.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-24-15
Work Began 02-15-16
Work Completed  
Time Computed 11-24-15
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 80
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1375-01-010
GREEN MILLING GROUP(1.78%)
TRP CONSTRUCTION GROUP, LLC(7.88%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 27.45%)
Contract # 10153006
Totals 2572762.09 0.00 2501494.52 97.2

CountyTRAVIS
Highway RM 1431
From BURNET COUNTY LINE
To BAR K RANCH RD IN LAGO VISTA
CSJ 1378-01-036
Proj ID STP 1602(494)HES
Work Type IMPROVE GUARDRAIL & SFTY TRT FIXED OB
 
9.973 1136825.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 99
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1378-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163045
Totals 1136825.40 0.00 0.00 0.0

CountyWILLIAMSON
Highway RM 1431
From FM 734
To CR 175
CSJ 1378-02-036
Proj ID PTF 2014(560)
Work Type WIDEN TO 6 - LANE URBAN ROADWAY
 
1.491 17353255.75 776206.07 15372504.50 88.5
Work Order 06-05-14
Work Began 08-17-14
Work Completed  
Time Computed 06-21-14
Contract Working Days 269
Addl Days Granted 150
Working Days Charged 362
Percent Time Used 86
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48%)
ABC EROSION CONTROL, INC.(0.65%)
AUSTIN WOOD RECYCLING(0.11%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.30%)
FLASHER EQUIPMENT COMPANY(1.47%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06%)
GK CONSTRUCTION, LLC (0.07%)
KELLYSTONE, INC(0.94%)
ROADWAY SPECIALTIES, INC.(2.95%)
ROYAL VISTA INC. ( 16.40%)
VOGES DRILLING CO. (0.14%)
TEXAS CUTTING & CORING, INC. (0.03%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.25%)
SCOTT DERR PAINTING CO, LLC(0.02%)
SPEEDY PAVING(0.99%)
Contract # 04143201
Totals 17353255.75 776206.07 15372504.50 88.5

CountyWILLIAMSON
Highway RM 1431
From ANDERSON MILL RD
To 600 FT WEST OF 183A
CSJ 1378-02-039
Proj ID C 1378-2-39
Work Type INNOVATIVE INTERSECTION IMPROVEMNTS
 
1.417 3965954.63 9987.80 3951108.97 99.6
Work Order 11-13-13
Work Began 03-05-14
Work Completed  
Time Computed 01-12-14
Contract Working Days 108
Addl Days Granted 72
Working Days Charged 175
Percent Time Used 97
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-039
PERFORMANCE EQUIPMENT(0.15%)
RAMMING PAVING COMPANY ( 40.83%)
ROADWAY SPECIALTIES, INC.(0.58%)
FLASHER EQUIPMENT COMPANY(4.37%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.73%)
Contract # 08133073
Totals 3965954.63 9987.80 3951108.97 99.6

CountyWILLIAMSON
Highway RM 1431
From 1000 WEST OF CHANDLER CREEK
To 200 EAST OF UNIVERSITY OAKS BLVD.
CSJ 1378-02-040
Proj ID STP 2013(297)
Work Type CONST DIVERGING DIAMOND INTRSCTN
 
0.392 6684011.97 19331.93 7371431.96 99.9
Work Order 08-13-14
Work Began 10-20-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 177
Addl Days Granted 25
Working Days Charged 202
Percent Time Used 100
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-040
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37%)
ROADWAY SPECIALTIES, INC.(5.23%)
CHEROKEE SERVICES(0.32%)
SPEEDY PAVING(1.10%)
TEXAS TRUCKING COMPANY, INC. (0.95%)
EARTH REINFORCEMENT SPECIALISTS(4.83%)
VOGES DRILLING (0.40%)
FLASHER EQUIPMENT COMPANY(1.16%)
APAC-TEXAS, INC. (FORT WORTH)( 21.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 12.44%)
Contract # 06143242
Totals 6684011.97 19331.93 7371431.96 99.9

CountyWILLIAMSON
Highway RM 1431
From 183A (TOLL) NBFR
To 0.20 MI. EAST OF CR 185
CSJ 1378-02-045
Proj ID STP 2014(938)
Work Type MILL, SEAL, OVRLAY & RESTRP TO 6 - LN
 
0.821 430708.20 17108.45 536090.98 99.9
Work Order 08-15-14
Work Began 09-23-14
Work Completed  
Time Computed 09-22-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 97
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-045
D. I. J. CONSTRUCTION, INC.(8.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.81%)
Contract # 07143241
Totals 430708.20 17108.45 536090.98 99.9

CountyWILLIAMSON
Highway FM 3406
From 0.13 MI. EAST OF WYOMING SPRINGS DR
To 0.05 MI. WEST OF GTRR
CSJ 1378-06-011
Proj ID STP 2015(882)
Work Type WIDEN TO 5 - LANE WITH CENTER LTL
 
1.290 4776174.80 170576.17 3577467.32 74.9
Work Order 06-04-15
Work Began 07-30-15
Work Completed  
Time Computed 07-05-15
Contract Working Days 260
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 94
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 1378-06-011
ENVIRONMENTAL SAFETY SERVICES, INC.(7.01%)
BEAIRD DRILLING(0.56%)
FARR FOUNDATION, INC.(3.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.64%)
FLASHER EQUIPMENT COMPANY(1.66%)
APAC-TEXAS, INC. ( 14.93%)
KRL CONSTRUCTION INC.(0.80%)
M.G. DRILLING(0.12%)
VIKING FENCE CO, LTD.(0.22%)
Contract # 04153233
Totals 4776174.80 170576.17 3577467.32 74.9

CountyLEE
Highway FM 1624
From SL 123
To US 77
CSJ 1537-01-016
Proj ID STP 1602(496)HES
Work Type IMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
17.864 1148468.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1537-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163047
Totals 1148468.60 0.00 0.00 0.0

CountyHAYS
Highway RM 1826
From AT DARDEN HILL RD
To .
CSJ 1754-02-019
Proj ID CC 1754-2-19
Work Type ADD TURN LANES & SHOULDERS
 
0.365 746842.80 0.00 778356.57 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-05-15
Work Began 02-02-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 89
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-019
ENVIRONMENTAL SAFETY SERVICES, INC.(4.64%)
LONE STAR PAVING COMPANY ( 39.74%)
TRP CONSTRUCTION GROUP, LLC(4.37%)
ROADWAY SPECIALTIES, INC.( 24.40%)
Contract # 10143210
Totals 746842.80 0.00 778356.57 99.9

CountyHAYS
Highway RM 1826
From TRAVIS C/L
To RM 150
CSJ 1754-02-024
Proj ID STP 2015(193)HESG
Work Type C.L & SHOULDERS RAISED PROF MARKS
 
26.276 605145.34 0.00 679000.74 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-14
Work Began 07-21-15
Work Completed  
Time Computed 11-30-14
Contract Working Days 40
Addl Days Granted 12
Working Days Charged 75
Percent Time Used 144
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-024
ROADWAY SPECIALTIES, INC.( 30.11%)
NIXON ENGINEERING(3.74%)
Contract # 10143009
Totals 605145.34 0.00 679000.74 99.9

CountyHAYS
Highway RM 1826
From TRAVIS COUNTY LINE
To NUTTY BROWN ROAD
CSJ 1754-02-025
Proj ID STP 1502(597)
Work Type GRADING, BASE, ACP & PVMNT MARKINGS
 
2.186 4013235.58 132150.32 1025479.43 25.5
Work Order 01-22-16
Work Began 03-01-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 35
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-025
A BROTHERS MILLING, LLC(0.85%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57%)
FLASHER EQUIPMENT COMPANY(0.35%)
RAMMING PAVING COMPANY ( 52.04%)
ROADWAY SPECIALTIES, INC.(6.33%)
Contract # 08153029
Totals 4013235.58 132150.32 1025479.43 25.5

CountyHAYS
Highway RM 967
From COLE SPRING ROAD
To FM 1626
CSJ 1776-01-032
Proj ID STP 2013(655)
Work Type ADD TWLTL AND SHOULDERS
 
2.618 4408237.86 97127.97 4282333.66 97.9
Work Order 07-11-14
Work Began 09-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 227
Addl Days Granted 66
Working Days Charged 328
Percent Time Used 111
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
AUSTIN WOOD RECYCLING(1.86%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.21%)
FLASHER EQUIPMENT COMPANY(0.45%)
FUQUAY, INC. (1.42%)
RAMMING PAVING COMPANY ( 32.68%)
ROADWAY SPECIALTIES, INC.(1.40%)
Contract # 05143014
Totals 4408237.86 97127.97 4282333.66 97.9

CountyCALDWELL
Highway FM 1966
From SH 21
To SH 142
CSJ 1850-01-015
Proj ID STP 1602(240)HES
Work Type CENTERLINE TEXTURING
 
11.182 88314.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-29-16
Work Began 08-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1850-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163234
Totals 88314.42 0.00 0.00 0.0

CountyTRAVIS
Highway FM 1825
From 10TH STREET IN PFLUGERVILLE
To FM 685
CSJ 1902-01-027
Proj ID STP 2015(738)
Work Type FULL DEPTH REPAIR, SEAL & OVERLAY
 
0.904 406530.37 98482.09 297635.32 73.2
Work Order 04-10-15
Work Began 06-21-16
Work Completed  
Time Computed 05-11-15
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 28
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1902-01-027
ENVIRONMENTAL SAFETY SERVICES, INC.(4.70%)
TEX OP CONSTRUCTION, LP(2.82%)
TRP CONSTRUCTION GROUP, LLC(6.25%)
Contract # 03153028
Totals 406530.37 98482.09 297635.32 73.2

CountyTRAVIS
Highway RM 2222
From LP 1
To LAMAR BLVD
CSJ 2100-01-056
Proj ID NH 2015(739)
Work Type MILL, SEAL & OVERLAY
 
2.089 1390365.50 0.00 1596126.50 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-15
Work Began 09-21-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 112
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-056
THE LEVY COMPANY, L.P. (5.86%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.69%)
LONE STAR PAVING ( 30.11%)
TRP CONSTRUCTION GROUP, LLC(3.14%)
Contract # 03153227
Totals 1390365.50 0.00 1596126.50 99.9

CountyTRAVIS
Highway RM 2222
From 500 W OF WESTSLOPE CIRCLE
To LP 1 SBFR
CSJ 2100-01-058
Proj ID STP 2014(535)
Work Type UNDERSEAL AND OVERLAY
 
3.154 747616.73 0.00 819480.04 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 10-07-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 105
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-058
N-LINE TRAFFIC MAINTENANCE, L.P. (0.46%)
TEX OP CONSTRUCTION, LP(1.41%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.96%)
FLASHER EQUIPMENT COMPANY(5.71%)
Contract # 03143215
Totals 747616.73 0.00 819480.04 99.9