Monthly State Let Construction Report For Austin District As Of Feb 11, 2016 Page 4 Of 13

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBASTROP
Highway US 290 ETC
From SH 95 NORTH
To SL 109
CSJ 0114-04-068
Proj ID STP 2016(754)HES
Work Type SAFETY LIGHTING
 
3.532 2027917.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-04-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163005
Totals 2027917.00 0.00 0.00 0.0

CountyBASTROP
Highway US 290
From 8.864 MI E OF FM 696
To FM 2104
CSJ 0114-06-030
Proj ID C 114-6-30
Work Type WIDEN GR STRS BS & SURF
 
5.566 19049776.58 910670.41 16559526.48 86.9
Work Order 01-23-14
Work Began 02-03-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 301
Addl Days Granted 52
Working Days Charged 353
Percent Time Used 100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-06-030
FLASHER EQUIPMENT COMPANY(0.19%)
BMP SPECIALIST, LLC(1.67%)
J & M CONTRACTING, COMPANY (3.65%)
PANTHER CREEK TRANSPORTATION, INC. (0.78%)
VOGES DRILLING CO. (0.31%)
SCR CONSTRUCTION CO., INC. (2.40%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.13%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.26%)
MURRAY CONSTRUCTION(0.34%)
D. I. J. CONSTRUCTION, INC.(0.99%)
GK CONSTRUCTION, LLC (0.00%)
LOCKHART CONTRACTING SERVICES, INC.(0.75%)
CENTEX HYDROSEED (0.37%)
HEMPHILL PILE DRIVING CO., A CORP. (0.01%)
PEDRO CARLOS CONSTRUCTION CO.(0.34%)
Contract # 11133204
Totals 19049776.58 910670.41 16559526.48 86.9

CountyLEE
Highway US 290
From 3.745 MI. W OF US 77
To 2.532 MI. E OF US 77
CSJ 0114-07-073
Proj ID NH 2014(516)
Work Type PAVEMENT REPAIR, SEAL & OVERLAY
 
6.277 3515264.16 0.00 3595991.59 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 06-16-14
Work Completed 02-05-15
Time Computed 05-01-14
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 134
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-07-073
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23%)
D. I. J. CONSTRUCTION, INC.(2.13%)
PERFORMANCE EQUIPMENT(1.48%)
PEDRO CARLOS CONSTRUCTION CO.(0.39%)
Contract # 03143018
Totals 3515264.16 0.00 3595991.59 100.0

CountyLEE
Highway US 290
From BASTROP C/L
To 3.880 MI E OF BATROP C/L
CSJ 0114-07-075
Proj ID STP 1502(383)HES
Work Type INSTALL CONTINUOUS TURN LANE
 
3.880 4110149.66 52847.95 641153.48 15.5
Work Order 10-19-15
Work Began 11-19-15
Work Completed  
Time Computed 11-19-15
Contract Working Days 94
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 5
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-07-075
EGGEMEYER LAND CLEARING, LLC (1.86%)
MURRAY CONSTRUCTION(0.15%)
ROADWAY SPECIALTIES, INC.(1.01%)
TRP CONSTRUCTION GROUP, LLC(1.67%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 07153243
Totals 4110149.66 52847.95 641153.48 15.5

CountyTRAVIS
Highway LP 212
From LANE AVENUE
To US 290 E
CSJ 0114-20-009
Proj ID STP 2013(850)
Work Type PAVEMENT REPAIR, MILL, SEAL & OVERLAY
 
1.836 587548.40 0.00 516940.29 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 10-28-13
Work Completed 01-05-15
Time Computed 10-28-13
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 73
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-20-009
N-LINE TRAFFIC MAINTENANCE, L.P. (1.19%)
D. I. J. CONSTRUCTION, INC.(3.52%)
CHEROKEE SERVICES(2.22%)
Contract # 07133235
Totals 587548.40 0.00 516940.29 100.0

CountyMASON
Highway SH 29
From MASON E CITY LIMITS
To MASON/LLANO COUNTY LINE
CSJ 0150-01-025
Proj ID STP 2016(391)
Work Type LEVEL UP & SEAL COAT
 
27.556 3757541.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0150-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153219
Totals 3757541.67 0.00 0.00 0.0

CountyLLANO
Highway SH 29
From PECAN CREEK
To STR 0150-02-046
CSJ 0150-02-037
Proj ID BR 1502(591)
Work Type REPLACE BRIDGE DECK
 
0.188 1621092.65 400827.35 400827.35 24.7
Work Order 11-16-15
Work Began 01-04-16
Work Completed  
Time Computed 12-16-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 10
Contractor(s)
JAY-REESE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0150-02-037
D. I. J. CONSTRUCTION, INC.(3.60%)
HOUSTON SAWING & DRILLING(0.18%)
ALTUS TRAFFIC MANAGEMENT LLC (0.62%)
ROADWAY SPECIALTIES, INC.(8.28%)
S & S BRIDGE PAINTING, INC.(8.86%)
Contract # 08153233
Totals 1621092.65 400827.35 400827.35 24.7

CountyBURNET
Highway SH 29
From 0.344 MILES WEST OF CR 258/303
To 0.342 MILES EAST OF CR 258/303
CSJ 0151-01-042
Proj ID STP 1402(054)
Work Type ADD LEFT TURN LANE
 
0.686 577171.90 0.00 628763.23 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-20-14
Work Began 11-10-14
Work Completed 10-19-15
Time Computed 11-05-14
Contract Working Days 74
Addl Days Granted 25
Working Days Charged 95
Percent Time Used 95
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0151-01-042
LONE STAR PAVING COMPANY ( 28.41%)
RICE ENVIRONMENTAL SERVICES(2.77%)
ROADWAY SPECIALTIES, INC.(4.52%)
FLASHER EQUIPMENT COMPANY(0.66%)
CHANDLER CONCRETE, INC.( 12.05%)
D. I. J. CONSTRUCTION, INC.(6.20%)
Contract # 08143208
Totals 577171.90 0.00 628763.23 100.0

CountyWILLIAMSON
Highway US 183
From APPROX. 920' S OF 183A
To RM 2243
CSJ 0151-04-067
Proj ID NH 2013(474)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
1.824 867875.03 12184.00 701692.33 81.2
Work Order 06-03-13
Work Began 06-30-14
Work Completed  
Time Computed 08-02-13
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 118
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-04-067
TEX OP CONSTRUCTION, LP(0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38%)
ROADWAY SPECIALTIES, INC.(0.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90%)
TEXAS TRUCKING COMPANY, INC. (2.49%)
D. I. J. CONSTRUCTION, INC.(4.91%)
Contract # 03133034
Totals 867875.03 12184.00 701692.33 81.2

CountyWILLIAMSON
Highway US 183
From RM 2243
To DISCOVERY BLVD.
CSJ 0151-05-096
Proj ID NH 2014(517)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
4.445 1540182.25 32586.26 1651224.74 99.9
Work Order 04-17-14
Work Began 04-13-15
Work Completed  
Time Computed 05-03-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 90
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-096
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
D. I. J. CONSTRUCTION, INC.(5.36%)
TEX OP CONSTRUCTION, LP(4.43%)
Contract # 03143023
Totals 1540182.25 32586.26 1651224.74 99.9

CountyWILLIAMSON
Highway US 183
From AT NEW HOPE DRIVE
To .
CSJ 0151-05-097
Proj ID C 151-5-97
Work Type CONSTRUCT DECELERATION LANE
 
0.100 529532.04 0.00 622204.80 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-20-13
Work Began 01-28-14
Work Completed 12-05-14
Time Computed 01-19-14
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 100
Contractor(s)
BPI ENVIRONMENTAL SERVICES INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-097
FLASHER EQUIPMENT COMPANY(2.51%)
RAMMING PAVING COMPANY ( 23.92%)
SPEEDY PAVING(0.55%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.34%)
Contract # 08133059
Totals 529532.04 0.00 622204.80 100.0

CountyWILLIAMSON
Highway US 183
From 0.030 MI SOUTH OF LAKE CREEK PKWY
To 0.152 MI SOUTH OF ANDERSON MILL RD
CSJ 0151-05-098
Proj ID STP 2014(518)
Work Type MILL, SEAL & OVERLAY NB & SB FRT RD
 
1.000 588778.08 23058.81 506534.67 86.0
Work Order 04-15-14
Work Began 11-23-15
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 48
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-098
FLASHER EQUIPMENT COMPANY(5.50%)
THE LEVY COMPANY, L.P. (5.35%)
A BROTHERS MILLING, LLC(3.99%)
GREEN MILLING GROUP(3.99%)
Contract # 03143209
Totals 588778.08 23058.81 506534.67 86.0

CountyWILLIAMSON
Highway US 183
From 350 FEET NORTH OF WALTON WAY
To 350 FEET SOUTH OF WALTON WAY
CSJ 0151-05-103
Proj ID C 151-5-103
Work Type ADD RIGHT TURN & DUAL LEFT TURN LANES
 
0.100 344399.00 0.00 271330.24 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-04-13
Work Began 03-10-14
Work Completed 06-24-15
Time Computed 10-20-13
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 238
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-103
BUYERS BARRICADES, INC.(1.91%)
ROADMASTER, INC. (1.32%)
WHEELER COATINGS ASPHALT, INC. ( 44.64%)
SMITCO CONCRETE CONSTRUCTION (4.96%)
Contract # 08133256
Totals 344399.00 0.00 271330.24 100.0

CountyWILLIAMSON
Highway US 183
From 0.152 MI S. OF ANDERSON MILL RD
To 0.03 MI S. OF MCNEIL RD
CSJ 0151-05-108
Proj ID NH 2014(888)
Work Type MILL, SEAL & OVERLAY FRONTAGE RD
 
1.636 1517070.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-15-14
Work Began 00-00-00
Work Completed  
Time Computed 08-31-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-108
GREEN MILLING GROUP(5.11%)
FLASHER EQUIPMENT COMPANY(2.02%)
Contract # 07143040
Totals 1517070.86 0.00 0.00 0.0

CountyTRAVIS
Highway US 183
From LP 1
To LP 360
CSJ 0151-06-136
Proj ID NH 1402(045)
Work Type REPAIR, MILL, SEAL & OVERLAY FRT RDS
 
0.884 459965.16 0.00 620311.67 99.9
CountyTRAVIS
Highway SL 1
From BRAKER LANE
To 1200 FT. NORTH OF STECK AVENUE
CSJ 3136-01-181
Proj ID NH 1402(045)
Work Type REPAIR, MILL, SEAL & OVERLAY FRT RD
 
1.794 895396.48 54869.96 1269954.35 99.9
Work Order 09-15-14
Work Began 04-15-15
Work Completed  
Time Computed 10-01-14
Contract Working Days 41
Addl Days Granted 7
Working Days Charged 49
Percent Time Used 102
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-06-136
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.78%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.47%)
INTERSTATE BARRICADES & MARKINGS, INC. (6.48%)
DUSTROL, INC.( 14.35%)
Contract # 08143243
Totals 1355361.64 54869.96 1890266.02 99.9

CountyTRAVIS
Highway US 183
From 0.4 MI NORTH OF FM 973
To VON QUINTUS RD
CSJ 0152-01-076
Proj ID NH 2016(302)
Work Type OVERLAY
 
2.167 937584.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153225
Totals 937584.89 0.00 0.00 0.0

CountyTRAVIS
Highway US 183
From BURLESON RD
To FM 812
CSJ 0152-01-077
Proj ID NH 2014(303)
Work Type OVERLAY
 
1.290 698386.33 4442.76 917200.52 100.0
Work Order 01-17-14
Work Began 06-17-14
Work Completed 01-25-16
Time Computed 02-02-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 85
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-077
SCR CONSTRUCTION CO., INC. (5.06%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.96%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.16%)
BMP SPECIALIST, LLC(8.07%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
Contract # 12133011
Totals 698386.33 4442.76 917200.52 100.0

CountyCALDWELL
Highway US 183
From PECAN STREET
To FM 20
CSJ 0152-02-070
Proj ID C 152-2-70
Work Type RECONSTRUCT TO 5 - LN URBAN SECTION
 
1.125 7221836.67 415104.03 4242583.54 60.0
CountyCALDWELL
Highway US 183
From FM 20
To 0.274 MI S. OF MLK/INDUSTRIAL BLVD
CSJ 0152-03-057
Proj ID C 152-3-57
Work Type RECONST TO 5 - LANE URBAN SECTION
 
0.909 4477082.25 29665.58 50761.09 1.1
Work Order 04-25-14
Work Began 03-23-15
Work Completed  
Time Computed 10-22-14
Contract Working Days 267
Addl Days Granted 1
Working Days Charged 197
Percent Time Used 73
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-070
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.89%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(6.48%)
ROADWAY SPECIALTIES, INC.(0.62%)
PIPELAYERS, INC. ( 25.18%)
FLASHER EQUIPMENT COMPANY(1.70%)
R K STEPHENS CONSTRUCTION, LLC ( 12.70%)
Contract # 11133003
Totals 11698918.92 444769.61 4293344.63 37.5

CountyCALDWELL
Highway US 183
From AT CLEAR FORK PLUM CREEK
To (STR 152-3-9)
CSJ 0152-03-056
Proj ID BR 1502(520)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.258 2746129.86 61026.88 61026.88 2.2
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 12-29-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0152-03-056
FLASHER EQUIPMENT COMPANY(1.52%)
APAC-TEXAS, INC. (7.60%)
RICE ENVIRONMENTAL SERVICES(1.35%)
W. W. FOUNDATION DRILLING, LTD.(3.13%)
Contract # 09153207
Totals 2746129.86 61026.88 61026.88 2.2

CountyWILLIAMSON
Highway US 79
From AT FM 1460
To .
CSJ 0204-01-061
Proj ID STP 2015(570)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 280240.68 0.00 156606.08 55.8
CountyCALDWELL
Highway SH 142
From AT FM 1966
To .
CSJ 0384-01-022
Proj ID STP 2015(571)HES
Work Type ADD FLASHING BEACON & SFTY LGHTNG
 
0.100 28690.34 0.00 0.00 0.0
CountyTRAVIS
Highway FM 685
From AT FM 1825
To .
CSJ 0757-02-016
Proj ID STP 2015(572)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 125512.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-15
Work Began 00-00-00
Work Completed  
Time Computed 05-24-15
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 1
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-061
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.70%)
HIGHWAY 19 CONSTRUCTION, LLC (7.59%)
FLASHER EQUIPMENT COMPANY(0.69%)
TX DOWN UNDER CONSTRUCTION LLC (4.69%)
Contract # 02153229
Totals 434443.63 0.00 156606.08 36.0