Monthly State Let Construction Report For Austin District As Of Nov 9, 2016 Page 4 Of 9

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBURNET
Highway US 281
From HOUSTON CLINTON DR
To 0.100 MI S OF RM 1855
CSJ 0252-01-074
Proj ID NH 2016(896)
Work Type FULL DEPTH REPAIR, MILL, SEAL AND
 
8.755 2392271.35 1166174.10 2401084.82 99.9
Work Order 07-15-16
Work Began 08-31-16
Work Completed  
Time Computed 08-14-16
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 59
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0252-01-074
FLASHER EQUIPMENT COMPANY(0.24%)
D. I. J. CONSTRUCTION, INC.(7.28%)
Contract # 04163209
Totals 2392271.35 1166174.10 2401084.82 99.9

CountyBLANCO
Highway US 281
From 1.5 MI. NORTH OF CR 307
To 0.6 MI. NORTH OF CR 307
CSJ 0252-03-051
Proj ID STP 1602(236)HES
Work Type CNSTRCT PVD SHLDRS, CORRECT SUPRELV
 
0.900 896922.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163241
Totals 896922.60 0.00 0.00 0.0

CountyBASTROP
Highway SH 71
From 0.268 MI. WEST OF SH 95
To 0.477 MI. EAST OF SH 95
CSJ 0265-05-067
Proj ID STP 2012(629)
Work Type CONST. OVERPASS AND 4 MAIN LNS
 
0.745 15379463.01 910752.14 5413378.70 35.1
CountyBASTROP
Highway SH 71
From 0.358 MI. WEST OF SH 95
To 0.268 MI. WEST OF SH 95
CSJ 0265-05-078
Proj ID NH 1502(667)
Work Type ADD ENTRANCE RAMP BRIDGE
 
0.091 1129745.52 89074.00 429242.40 37.9
Work Order 05-17-16
Work Began 06-06-16
Work Completed  
Time Computed 06-06-16
Contract Working Days 350
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 26
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-067
ABC EROSION CONTROL, INC.(0.73%)
FLASHER EQUIPMENT COMPANY(0.53%)
AARON CONCRETE CONTRACTORS, L.P. (5.19%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.22%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90%)
ANCORTEX, INC. (5.88%)
AUSTIN WOOD RECYCLING(0.10%)
BRICK PAVING PLUS, INC.(0.43%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.10%)
GK CONSTRUCTION, LLC (0.25%)
HOUSTON SAWING & DRILLING(0.03%)
MURRAY CONSTRUCTION(0.20%)
ROADWAY SPECIALTIES, INC.(2.15%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
KRL CONSTRUCTION INC.(0.16%)
AUSTIN FORMULA UTILITIES (0.19%)
Contract # 12153204
Totals 16509208.53 999826.14 5842621.10 35.3

CountyBASTROP
Highway SH 71
From 0.654 MI WEST OF LP 150 EAST
To 0.502 MI EAST OF LP 150 EAST
CSJ 0265-05-071
Proj ID HP 2012(437)
Work Type CONSTRUCT OVERPASS
 
1.156 13669975.37 34139.20 13346681.82 97.6
Work Order 12-01-14
Work Began 03-02-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 346
Addl Days Granted 0
Working Days Charged 307
Percent Time Used 88
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-071
AARON CONCRETE CONTRACTORS, L.P. (4.81%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.63%)
EGGEMEYER LAND CLEARING, LLC (0.28%)
FLASHER EQUIPMENT COMPANY(0.73%)
HOUSTON SAWING & DRILLING(0.03%)
MCKINNEY DRILLING__(BUDA)(1.27%)
MCL CONTRACTING, LLC (0.13%)
MURRAY CONSTRUCTION(0.25%)
OSCAR ORDUNO, INC. (1.31%)
R K STEPHENS CONSTRUCTION, LLC (2.06%)
ROADWAY SPECIALTIES, INC.(3.84%)
SPEEDY PAVING(0.55%)
CHANDLER CONCRETE, INC.(0.96%)
AUSTIN FORMULA UTILITIES (0.17%)
KRL CONSTRUCTION INC.(0.14%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
GREEN MILLING GROUP(0.18%)
CENTRAL TEXAS REINFORCEMENT(0.07%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.25%)
THOMAS TURF GRASS(0.33%)
Contract # 09143006
Totals 13669975.37 34139.20 13346681.82 97.6

CountyBURNET
Highway US 183
From AT NORTH ROCKY CREEK
To .
CSJ 0273-02-023
Proj ID BR 1502(384)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.195 2450973.55 96597.66 1494693.31 60.9
Work Order 11-13-15
Work Began 01-14-16
Work Completed  
Time Computed 12-13-15
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 132
Percent Time Used 81
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0273-02-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153032
Totals 2450973.55 96597.66 1494693.31 60.9

CountyWILLIAMSON
Highway US 183
From 0.28 MI S OF RM 1869
To 0.22 MI N OF RM 1869
CSJ 0273-04-033
Proj ID BR 2015(573)
Work Type ADD TURN LANES AND SIGNAL
 
0.499 1846967.10 0.00 1839841.02 99.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-15
Work Began 09-01-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 122
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 93
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0273-04-033
APAC-TEXAS, INC. (1.36%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.86%)
FLASHER EQUIPMENT COMPANY(0.00%)
G. CARTER CONSTRUCTION COMPANY, INC. (3.19%)
Contract # 02153035
Totals 1846967.10 0.00 1839841.02 99.6

CountyHAYS
Highway RM 12
From 1 MI EAST OF HUGO ROAD
To 0.1 MILE WEST OF SH 80
CSJ 0285-03-055
Proj ID STP 1402(055)MM
Work Type IMPROVE / ADD SHOULDERS
 
2.916 2183444.48 0.00 2189322.52 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 11-17-14
Work Completed  
Time Computed 11-17-14
Contract Working Days 101
Addl Days Granted 15
Working Days Charged 153
Percent Time Used 131
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0285-03-055
ENVIRONMENTAL SAFETY SERVICES, INC.(5.61%)
FLASHER EQUIPMENT COMPANY(4.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.44%)
A BROTHERS MILLING, LLC(1.62%)
RAMMING PAVING COMPANY ( 34.43%)
Contract # 08143031
Totals 2183444.48 0.00 2189322.52 99.9

CountyHAYS
Highway RM 12
From SADDLERIDGE DR
To HUGO RD
CSJ 0285-03-057
Proj ID STP 2015(880)
Work Type ADD CENTER TURN LANE AND SHOULDERS
 
2.503 3090648.55 48042.62 3011648.61 97.6
Work Order 06-18-15
Work Began 09-14-15
Work Completed  
Time Computed 08-18-15
Contract Working Days 161
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 103
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0285-03-057
AUSTIN WOOD RECYCLING(1.43%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.22%)
FLASHER EQUIPMENT COMPANY(2.66%)
FUQUAY, INC. ( 13.12%)
ROADWAY SPECIALTIES, INC.(1.29%)
RUCOBA & MAYA CONSTRUCTION ( 10.18%)
A BROTHERS MILLING, LLC(0.34%)
Contract # 04153018
Totals 3090648.55 48042.62 3011648.61 97.6

CountyHAYS
Highway SH 80
From AT IH 35
To .
CSJ 0286-01-055
Proj ID NH 2015(492)
Work Type LANDSCAPING AND IRRIGATION
 
0.078 295843.00 1500.00 278488.10 98.1
Work Order 02-10-15
Work Began 04-27-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 133
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0286-01-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153014
Totals 295843.00 1500.00 278488.10 98.1

CountyCALDWELL
Highway SH 80
From US 90
To 0.999 MI. SOUTH OF US 90
CSJ 0287-01-015
Proj ID STP 2016(173)
Work Type MILL, SEAL & INLAY
 
7.508 2205029.54 41641.94 2496508.95 99.9
Work Order 11-24-15
Work Began 06-16-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 100
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0287-01-015
TRP CONSTRUCTION GROUP, LLC(5.79%)
GREEN MILLING GROUP(4.57%)
SRIPE-IT-UP(1.08%)
Contract # 10153023
Totals 2205029.54 41641.94 2496508.95 99.9

CountyGILLESPIE
Highway SH 16
From BOOS LANE
To 0.5 MI SOUTH MORRIS RANCH ROAD
CSJ 0291-01-048
Proj ID STP 2015(276)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
6.670 6732998.40 1162337.62 4549125.52 67.5
CountyGILLESPIE
Highway SH 16
From 0.5 MI SOUTH OF MORRIS RANCH ROAD
To KERR/GILLESPIE COUNTY LINE
CSJ 0291-01-049
Proj ID STP 2015(493)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
6.714 5676561.76 2610003.14 5813185.67 99.9
CountyKERR
Highway SH 16
From GILLESPIE/KERR COUNTY LINE
To WOLF CREEK
CSJ 0291-02-035
Proj ID STP 2015(493)
Work Type UPGRADE TO SUPER 2 AND ADD LTLS
 
0.466 584945.99 37653.07 411044.56 70.2
Work Order 03-13-15
Work Began 04-06-15
Work Completed  
Time Computed 03-29-15
Contract Working Days 333
Addl Days Granted 58
Working Days Charged 321
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0291-01-049
EGGEMEYER LAND CLEARING, LLC (0.35%)
BMP SPECIALIST, LLC(2.18%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.19%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57%)
MPB, INC.( 11.12%)
DUSTROL, INC.(0.47%)
CLARK CONSTRUCTION OF TEXAS, INC.(4.83%)
ROADWAY SPECIALTIES, INC.(0.62%)
RPV CONSTRUCTION (2.74%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 01153201
Totals 12994506.15 3809993.83 10773355.75 82.9

CountyWILLIAMSON
Highway SH 95
From AT WILLIS CREEK
To (STR 0320-03-032)
CSJ 0320-03-083
Proj ID BR 1502(592)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.105 2497365.80 156448.82 1518569.88 60.8
Work Order 12-10-15
Work Began 04-11-16
Work Completed  
Time Computed 02-05-16
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 71
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0320-03-083
FLASHER EQUIPMENT COMPANY(0.70%)
MCKINNEY DRILLING__(BUDA)(3.43%)
APAC-TEXAS, INC. (3.99%)
DUSTROL, INC.(0.30%)
FLASHER EQUIPMENT COMPANY(0.77%)
ROADWAY SPECIALTIES, INC.(6.66%)
WOOLERY CUSTOM FENCE CO. (0.20%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.58%)
Contract # 08153253
Totals 2497365.80 156448.82 1518569.88 60.8

CountyWILLIAMSON
Highway SH 95
From FM 971
To 0.1 MI S OF CHANDLER RD
CSJ 0320-03-095
Proj ID STP 2016(303)
Work Type LEVEL UP & SEAL COAT
 
7.393 861567.42 91932.75 363036.24 42.1
Work Order 01-29-16
Work Began 08-08-16
Work Completed  
Time Computed 08-01-15
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 79
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0320-03-095
ROADWAY SPECIALTIES, INC.( 37.63%)
TRP CONSTRUCTION GROUP, LLC(8.41%)
RUCOBA & MAYA CONSTRUCTION ( 15.75%)
Contract # 12153231
Totals 861567.42 91932.75 363036.24 42.1

CountyWILLIAMSON
Highway SH 95
From OLD COUPLAND ROAD
To TRAVIS C/L
CSJ 0321-01-054
Proj ID STP 1502(593)
Work Type CONVERT SUPER 2
 
14.826 13427785.21 1720146.58 13550917.48 99.9
Work Order 11-10-15
Work Began 01-04-16
Work Completed  
Time Computed 12-10-15
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 74
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-054
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.02%)
CHEROKEE SERVICES(0.19%)
ROADWAY SPECIALTIES, INC.(3.28%)
JORDAN FOSTER CONSTRUCTION, LLC( 22.59%)
S & S BRIDGE PAINTING, INC.(2.41%)
TEXAS TRUCKING COMPANY, INC. (0.00%)
TEX OP CONSTRUCTION, LP(3.30%)
TRP CONSTRUCTION GROUP, LLC(2.80%)
AUSTIN WOOD RECYCLING(0.49%)
PHILLIPS TRAFFIC CONTROL (0.05%)
AREA WIDE PROTECTIVE, INC. (0.06%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05%)
KRL CONSTRUCTION INC.(0.13%)
TEXOP CONSTRUCTION (0.82%)
G. CARTER CONSTRUCTION COMPANY, INC. (0.02%)
Contract # 08153009
Totals 13427785.21 1720146.58 13550917.48 99.9

CountyLEE
Highway FM 448
From US 77
To FM 2239
CSJ 0334-06-026
Proj ID STP 1502(595)
Work Type LEVEL - UP, OVERLAY, WIDEN & SEAL
 
4.850 3138496.55 344576.29 1693281.05 53.9
Work Order 04-06-16
Work Began 06-20-16
Work Completed  
Time Computed 06-05-16
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 60
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0334-06-026
EGGEMEYER LAND CLEARING, LLC (1.94%)
FARR FOUNDATION, INC.(0.93%)
MURRAY CONSTRUCTION(0.53%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.21%)
ROADWAY SPECIALTIES, INC.(2.76%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.28%)
BATTEN DRILLING, INC.(0.07%)
Contract # 08153040
Totals 3138496.55 344576.29 1693281.05 53.9

CountyWILLIAMSON
Highway SH 29
From RIVER CHASE BLVD.
To IH 35 NBFR
CSJ 0337-01-036
Proj ID STP 2016(897)
Work Type OVERLAY
 
0.964 662749.49 14599.41 631622.60 95.3
Work Order 05-18-16
Work Began 06-27-16
Work Completed  
Time Computed 06-17-16
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 57
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0337-01-036
N-LINE TRAFFIC MAINTENANCE, L.P. (1.19%)
TEXOP CONSTRUCTION (8.04%)
CHEROKEE SERVICES(6.27%)
D.I.J. CONSTRUCTION, INC (7.06%)
ROADWAY SPECIALTIES, INC.(2.62%)
Contract # 04163035
Totals 662749.49 14599.41 631622.60 95.3

CountyWILLIAMSON
Highway SH 29
From CEDAR HOLLOW ROAD
To RIVER CHASE BOULEVARD
CSJ 0337-01-038
Proj ID STP 2016(575)
Work Type UNDERSEAL & THIN OVERLAY
 
3.506 2014970.43 775665.19 1940371.29 96.2
Work Order 05-02-16
Work Began 08-04-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 81
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0337-01-038
ENVIRONMENTAL SAFETY SERVICES, INC.(6.31%)
D.I.J. CONSTRUCTION, INC (2.34%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.53%)
PERFORMANCE EQUIPMENT SERVICE(5.69%)
TEXOP CONSTRUCTION (5.08%)
Contract # 01163021
Totals 2014970.43 775665.19 1940371.29 96.2

CountyWILLIAMSON
Highway SH 29
From INNER LOOP
To MILEHAM CREEK BRIDGE
CSJ 0337-02-041
Proj ID STP 2016(576)
Work Type UNDERSEAL & THIN OVERLAY
 
6.286 1499000.00 44467.68 1482752.24 98.9
Work Order 03-28-16
Work Began 07-11-16
Work Completed  
Time Computed 04-27-16
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 77
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-041
N-LINE TRAFFIC MAINTENANCE, L.P. (0.65%)
CHEROKEE SERVICES(3.01%)
PERFORMANCE EQUIPMENT SERVICE(3.16%)
ENVIRONMENTAL SAFETY SERVICES, INC.( 12.29%)
D.I.J. CONSTRUCTION, INC (4.37%)
TEXOP CONSTRUCTION (3.16%)
MOORE CLEAN, LLC (0.56%)
TRP CONSTRUCTION GROUP, LLC(0.87%)
Contract # 01163208
Totals 1499000.00 44467.68 1482752.24 98.9

CountyHAYS
Highway SH 123
From 3500 FT NORTH OF RM 12
To 3500 FT SOUTH OF RM 12
CSJ 0366-01-066
Proj ID C 366-1-66
Work Type CONST GRADE SEPARATION
 
1.326 11596550.48 278984.59 9805861.47 84.5
Work Order 08-27-14
Work Began 03-31-15
Work Completed  
Time Computed 02-23-15
Contract Working Days 465
Addl Days Granted 116
Working Days Charged 396
Percent Time Used 68
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-066
BMP SPECIALIST, LLC(1.56%)
FLASHER EQUIPMENT COMPANY(1.80%)
HOUSTON SAWING & DRILLING(0.04%)
THE LEVY COMPANY, L.P. (3.95%)
MCL CONTRACTING, LLC (0.24%)
MURRAY CONSTRUCTION(0.22%)
R K STEPHENS CONSTRUCTION, LLC (1.77%)
VEGETATION MANAGEMENT SPECIALIST, INC. (0.06%)
VOGES DRILLING CO. (0.73%)
Contract # 06143202
Totals 11596550.48 278984.59 9805861.47 84.5

CountyCALDWELL
Highway SH 142
From SH 80
To BORCHERT LOOP
CSJ 0384-01-021
Proj ID STP 2017(021)
Work Type SEAL & THIN OVERLAY
 
17.541 2587289.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-26-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0384-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163207
Totals 2587289.35 0.00 0.00 0.0