Monthly State Let Construction Report For Austin District As Of May 11, 2017 Page 4 Of 7

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILLIAMSON
HighwaySH 95
FromOLD COUPLAND ROAD
ToTRAVIS C/L
CSJ0321-01-054
Proj IDSTP 1502(593)
Work TypeCONVERT SUPER 2
 
14.82613427785.2114589649.0199.9
Work Order11-10-15
Work Began01-04-16
Work Completed
Time Computed12-10-15
Contract Working Days263
Addl Days Granted0
Working Days Charged254
Percent Time Used96
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-054
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.02)
CHEROKEE SERVICES (0.19)
ROADWAY SPECIALTIES, INC. (3.28)
JORDAN FOSTER CONSTRUCTION, LLC (22.59)
S & S BRIDGE PAINTING, INC. (2.41)
TEXAS TRUCKING COMPANY, INC. (0.00)
TEX OP CONSTRUCTION, LP (3.30)
TRP CONSTRUCTION GROUP, LLC (2.80)
AUSTIN WOOD RECYCLING (0.49)
PHILLIPS TRAFFIC CONTROL (0.05)
AREA WIDE PROTECTIVE, INC. (0.06)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05)
KRL CONSTRUCTION INC. (0.13)
TEXOP CONSTRUCTION (0.82)
G. CARTER CONSTRUCTION COMPANY, INC. (0.02)
CHANDLER CONCRETE, INC. (0.06)
Contract #08153009
Totals13427785.2143881.0514589649.0199.9

CountyLEE
HighwayFM 448
FromUS 77
ToFM 2239
CSJ0334-06-026
Proj IDSTP 1502(595)
Work TypeLEVEL-UP, OVERLAY, WIDEN & SEAL
 
4.8503138496.552806916.8189.4
Work Order04-06-16
Work Began06-20-16
Work Completed
Time Computed06-05-16
Contract Working Days95
Addl Days Granted0
Working Days Charged89
Percent Time Used93
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0334-06-026
EGGEMEYER LAND CLEARING, LLC (1.94)
FARR FOUNDATION, INC. (0.93)
MURRAY CONSTRUCTION (0.53)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.21)
ROADWAY SPECIALTIES, INC. (2.76)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.28)
BATTEN DRILLING, INC. (0.07)
Contract #08153040
Totals3138496.55181109.702806916.8189.4

CountyWILLIAMSON
HighwaySH 29
FromSOUTH AUSTIN AVE.
ToGEORGETOWN INNER LOOP
CSJ0337-02-040
Proj IDSTP 2016(635)
Work TypeOVERLAY
 
2.9051319538.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0337-02-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173008
Totals1319538.690.000.000.0

CountyHAYS
HighwaySH 123
From3500 FT NORTH OF RM 12
To3500 FT SOUTH OF RM 12
CSJ0366-01-066
Proj IDC 366-1-66
Work TypeCONST GRADE SEPARATION
 
1.32611596550.4811559666.2599.6
Work Order08-27-14
Work Began03-31-15
Work Completed
Time Computed02-22-15
Contract Working Days465
Addl Days Granted116
Working Days Charged505
Percent Time Used86
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0366-01-066
BMP SPECIALIST, LLC (1.56)
FLASHER EQUIPMENT COMPANY (1.80)
HOUSTON SAWING & DRILLING (0.04)
THE LEVY COMPANY, L.P. (3.95)
MCL CONTRACTING, LLC (0.24)
MURRAY CONSTRUCTION (0.22)
R K STEPHENS CONSTRUCTION, LLC (1.77)
VEGETATION MANAGEMENT SPECIALIST, INC. (0.06)
VOGES DRILLING CO. (0.73)
Contract #06143202
Totals11596550.48150014.7511559666.2599.6

CountyCALDWELL
HighwaySH 142
FromSH 80
ToBORCHERT LOOP
CSJ0384-01-021
Proj IDSTP 2017(021)
Work TypeSEAL & THIN OVERLAY
 
17.5412587289.35988351.5038.2
Work Order10-26-16
Work Began02-02-17
Work Completed
Time Computed01-24-17
Contract Working Days45
Addl Days Granted0
Working Days Charged18
Percent Time Used40
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0384-01-021
MV HENKE COMPANY, LLC (0.91)
FLASHER EQUIPMENT COMPANY (0.15)
ROADWAY SPECIALTIES, INC. (4.16)
D.I.J. CONSTRUCTION, INC (4.51)
Contract #09163207
Totals2587289.3517127.20988351.5038.2

CountyCALDWELL
HighwayFM 1854
FromSH 21
To0.039 MI N OF FM 672
CSJ0384-04-030
Proj IDSTP 2017(947)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.740986625.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0384-04-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173207
Totals986625.980.000.000.0

CountyTRAVIS
HighwaySH 130
FromSH 130 @ FM 812
To.
CSJ0440-06-014
Proj IDNH 1502(385)
Work TypeLANDSCAPING AND IRRIGATION
 
0.100642322.00598783.5093.2
Work Order08-31-15
Work Began10-26-15
Work Completed
Time Computed10-26-15
Contract Working Days60
Addl Days Granted0
Working Days Charged60
Percent Time Used100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-06-014
N-LINE TRAFFIC MAINTENANCE, L.P. (0.70)
CLASSIC TEJAS CONSTRUCTION, INC. (12.85)
M & M UNDERGROUND CONSTRUCTION (1.08)
Contract #07153257
Totals642322.003000.00598783.5093.2

CountyCALDWELL
HighwaySH 21
FromHAYS COUNTY LINE
ToBASTROP COUNTY LINE
CSJ0471-04-029
Proj IDSTP 2016(852)
Work TypeREPAIR, LEVEL-UP, WIDEN AND OVERLAY
 
5.1902356387.982269913.2797.6
Work Order04-19-16
Work Began06-27-16
Work Completed
Time Computed05-19-16
Contract Working Days36
Addl Days Granted0
Working Days Charged77
Percent Time Used213
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0471-04-029
EGGEMEYER LAND CLEARING, LLC (2.08)
FLASHER EQUIPMENT COMPANY (3.30)
ROADWAY SPECIALTIES, INC. (0.25)
A BROTHERS MILLING, LLC (3.00)
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO (3.86)
Contract #03163214
Totals2356387.98822594.912269913.2797.6

CountyBASTROP
HighwaySH 21
From@ SL 150 (EAST)
To.
CSJ0472-01-042
Proj IDSTP 2017(572)HES
Work TypeREALIGN INTERSECTION
 
0.195286003.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-30-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JIMMY EVANS COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0472-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173009
Totals286003.250.000.000.0

CountyMASON
HighwaySH 71
From0.119 MILES SOUTH OF SH 71
To0.303 MILES EAST OF RM 386
CSJ0577-01-026
Proj IDSTP 2016(898)
Work TypeADD LT TURN LN & ADD RT ACCEL LN
 
0.536944570.87720243.0876.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-16
Work Began07-18-16
Work Completed
Time Computed07-17-16
Contract Working Days108
Addl Days Granted0
Working Days Charged53
Percent Time Used49
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0577-01-026
JM YANEZ CONSTRUCTION (15.61)
FLASHER EQUIPMENT COMPANY (5.58)
BMP CONSTRUCTION, INC. (4.02)
AUSTIN MATERIALS, LLC (31.23)
Contract #04163024
Totals944570.870.00720243.0876.2

CountyMASON
HighwayRM 386
FromSH 71
ToUS 87/ SH 29
CSJ0577-01-028
Proj IDSTP 1502(146)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.8871151527.251311107.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-15
Work Began01-07-16
Work Completed
Time Computed09-06-15
Contract Working Days247
Addl Days Granted6
Working Days Charged203
Percent Time Used80
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0577-01-028
TRP CONSTRUCTION GROUP, LLC (2.97)
ROADWAY SPECIALTIES, INC. (7.67)
INCE ENTERPRISES, INC. (9.89)
Contract #05153231
Totals1151527.250.001311107.5099.9

CountyTRAVIS
HighwayRM 620
From500 FT N OF LOHMANS CROSSING RD
ToLADERA BLVD.
CSJ0683-02-063
Proj IDSTP 1502(596)
Work TypeOPERATIONAL IMPROVEMENTS
 
0.9381419535.801316166.0692.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-08-16
Work Began09-15-16
Work Completed
Time Computed03-09-16
Contract Working Days58
Addl Days Granted0
Working Days Charged52
Percent Time Used89
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0683-02-063
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.39)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.95)
LONE STAR PAVING CO. (48.99)
N-LINE TRAFFIC MAINTENANCE, L.P. (4.43)
TRP CONSTRUCTION GROUP, LLC (2.69)
Contract #09153229
Totals1419535.800.001316166.0692.7

CountyHAYS
HighwayRM 12
FromAT OLD FITZHUGH RD.
To.
CSJ0683-05-011
Proj IDSTP 1502(388)
Work TypeINSTALL FLASH BEACON/REALIGN INTER.
 
0.001232728.36271229.0599.9
CountyHAYS
HighwayRM 12
From0.25 MI N OF OLD FITZHUGH RD.
To0.25 MI S OF OLD FITZHUGH RD.
CSJ0683-05-012
Proj IDSTP 1502(387)HES
Work TypeADD CENTER TURN LANE AND SHOULDERS
 
0.560826750.43977034.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-15
Work Began04-25-16
Work Completed
Time Computed11-04-15
Contract Working Days98
Addl Days Granted0
Working Days Charged76
Percent Time Used77
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-05-011
AUSTIN WOOD RECYCLING (1.05)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.83)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.22)
FLASHER EQUIPMENT COMPANY (4.33)
LONE STAR PAVING, INC. (23.03)
Contract #07153036
Totals1059478.790.001248263.4499.9

CountyBURNET
HighwaySH 71
FromAT CR 401
To.
CSJ0700-01-040
Proj IDSTP 1602(151)HESG
Work TypeINSTALL INTERSECTION FLASHING BEAC
 
0.409113531.00114574.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-16
Work Began11-28-16
Work Completed
Time Computed09-07-16
Contract Working Days64
Addl Days Granted0
Working Days Charged64
Percent Time Used100
Contractor(s)
SIGNAL SERVICES GROUP INC.
SUBCONTRACTOR(S) FOR CCSJ: 0700-01-040
TIMOTHY D. COVERT (1.27)
Contract #06163007
Totals113531.000.00114574.0099.9

CountyTRAVIS
HighwaySH 71
FromWEST OF THOMAS SPRINGS ROAD
ToWEST OF COVERED BRIDGE ROAD
CSJ0700-03-125
Proj IDC 700-3-125
Work TypeADD LEFT TURN LANE & SHOULDERS
 
5.70215965613.3216296119.4699.9
Work Order03-18-14
Work Began06-16-14
Work Completed
Time Computed05-17-14
Contract Working Days289
Addl Days Granted72
Working Days Charged440
Percent Time Used121
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-125
PANTHER CREEK TRANSPORTATION, INC. (4.57)
BRYANT & FREY CONSTRUCTION (2.07)
ROADWAY SPECIALTIES, INC. (1.42)
FLASHER EQUIPMENT COMPANY (1.12)
SCOTT DERR PAINTING CO, LLC (0.00)
TEXAS HIGHWAY WALLS (0.63)
THE LEVY COMPANY, L.P. (2.36)
HAEGELIN CONSTRUCTION CO., LTD. (8.02)
SCOTT DERR PAINTING CO, LLC (0.08)
AUSTIN WOOD RECYCLING (0.45)
RAMI MATERIALS TRANSPORT, LLC (1.25)
BREDA COMPANY, INC. (0.00)
CANTU CONSTRUCTION, INC. (0.15)
MCKINNEY DRILLING COMPANY (0.09)
ROSCH COMPANY (0.85)
CHLOR-SERV, INC. (0.03)
DRILL TECH DRILLING & SHORING, INC. (0.49)
RAMMING PAVING COMPANY (22.04)
APAC-TEXAS, INC. (0.44)
Contract #11133027
Totals15965613.3296053.3716296119.4699.9

CountyWILLIAMSON
HighwayFM 685
FromUS 79
ToSH 130
CSJ0757-01-020
Proj IDC 757-1-20
Work TypeRECONSTRUCT TO 4-LANE DIVIDED RDWY
 
1.82010553004.7810354683.5098.4
CountyWILLIAMSON
HighwayFM 685
FromUS 79
ToSH 130
CSJ0757-01-021
Proj IDRW 757-1-21
Work TypeROW ACQ, RELOC ASSIST. & UTL. ADJ.
 
1.820464544.39484879.8499.9
Work Order08-27-14
Work Began10-20-14
Work Completed
Time Computed10-20-14
Contract Working Days441
Addl Days Granted10
Working Days Charged475
Percent Time Used105
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0757-01-020
ABC EROSION CONTROL, INC. (0.61)
AUSTIN WOOD RECYCLING (0.49)
TRP CONSTRUCTION GROUP, LLC (50.52)
GUERRA UNDERGROUND, LLC (2.61)
BEAIRD DRILLING (1.78)
MENDEZ EXCAVATION (0.32)
TEXAS ROAD BORING (0.32)
ROADWAY SPECIALTIES, INC. (0.64)
EVT CONSTRUCTION (1.00)
THE LEVY COMPANY, L.P. (1.64)
BREDA COMPANY, INC. (72.86)
AARON CONCRETE CONTRACTORS, L.P. (2.96)
INDUS CONSTRUCTION, L.P. (0.10)
JUST GROOVING, LTD. (0.16)
RAMMING PAVING COMPANY (17.28)
A & R DEMOLITION (0.27)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.01)
PENHALL COMPANY (0.08)
Contract #02143003
Totals11017549.1720100.1810839563.3498.6

CountyHAYS
HighwayRM 150
FromCENTER STREET
ToSILVERADO DR.
CSJ0805-04-025
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALK & BIKE LANES
 
0.612364407.34240790.1474.4
CountyHAYS
HighwayFM 2770
FromFAIRWAY DRIVE
ToBOB SHELTON STADIUM
CSJ3210-01-012
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALKS & BIKE LANES
 
0.998484671.17260927.3353.8
Work Order07-14-16
Work Began09-06-16
Work Completed
Time Computed08-13-16
Contract Working Days84
Addl Days Granted0
Working Days Charged134
Percent Time Used159
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0805-04-025
F & W ELECTRICAL CONTRACTORS, INC. (6.20)
FLASHER EQUIPMENT COMPANY (2.51)
RICE ENVIRONMENTAL SERVICES (4.91)
Contract #05163235
Totals849078.5133555.25501717.4762.6

CountyTRAVIS
HighwayVA
FromVARIOUS
To(ON-SYSTEM)
CSJ0914-00-314
Proj IDNH 2013(027)
Work TypeFY 2013 NON-SITE SPECIFIC ITS MAINT
 
0.1002958819.252052148.5369.3
Work Order10-12-12
Work Began02-03-16
Work Completed
Time Computed10-28-12
Contract Working Days508
Addl Days Granted0
Working Days Charged219
Percent Time Used43
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09123244
Totals2958819.25212617.622052148.5369.3

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-319
Proj IDNH 1402(057)
Work TypeFY 2014 SITE-SPECIFIC SIGNALS
 
0.1001113486.77989873.8788.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-04-14
Work Began02-02-15
Work Completed
Time Computed11-20-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.63)
HIGHWAY 19 CONSTRUCTION, LLC (9.08)
TX DOWN UNDER CONSTRUCTION LLC (4.00)
UNION ELECTRICAL CONTRACTOR, INC. (1.24)
FLASHER EQUIPMENT COMPANY (1.57)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (1.24)
MORGAN UTILITY CONSTRUCTION (1.04)
WG ENGINEERING & CONSTRUCTION, LLC (3.06)
Contract #08143029
Totals1113486.770.00989873.8788.8

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-320
Proj IDNH 2014(015)
Work TypeFY 2013 SIGNING
 
0.100452778.70472263.0199.9
Work Order10-07-13
Work Began06-17-14
Work Completed
Time Computed10-23-13
Contract Working Days77
Addl Days Granted0
Working Days Charged29
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09133233
Totals452778.701060.50472263.0199.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7