Monthly State Let Construction Report For Austin District As Of May 15, 2013 Page 2 Of 7

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway SH 71
From IH 35
To 1500' EAST OF MONTOPOLIS DR.
CSJ 0113-13-148
Proj ID STP 2011(108)
Work Type LANDSCAPING AND IRRIGATION
 
6.360 519513.90 2800.00 544626.46 99.9
Work Order 09-14-10
Work Began 01-03-11
Work Completed  
Time Computed 11-13-10
Contract Working Days 88
Addl Days Granted 10
Working Days Charged 77
Percent Time Used 78
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-148
LONE STAR TRAFFIC SERVICE, INC.(0.69%)
DOWN UNDER CONSTRUCTION(3.00%)
CARTER PLUMBING, INC.(4.23%)
Contract # 08103019
Totals 519513.90 2800.00 544626.46 99.9

CountyTRAVIS
Highway SH 71
From EAST OF MONTOPOLIS DR
To US 183
CSJ 0113-13-149
Proj ID NH 1102(240)
Work Type CONST UNDERPASS, FRT RDS & MAIN LANES
 
1.419 33460488.85 998393.65 14099609.17 42.1
CountyTRAVIS
Highway SH 71
From EAST OF MONTOPOLIS DR
To US 183
CSJ 0113-13-151
Proj ID RW 113-13-151
Work Type ROW ACQ. AND UTL. ADJ.
 
1.300 1522117.70 0.00 1123929.41 73.8
Work Order 09-27-11
Work Began 01-26-12
Work Completed  
Time Computed 12-25-11
Contract Working Days 581
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 42
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-149
RICE ENVIRONMENTAL SERVICES(0.33%)
SCOTT DERR PAINTING CO, LLC(0.14%)
HIGHWAY TECHNOLOGIES, INC. (0.22%)
AUSTIN WOOD RECYCLING(0.09%)
INDUS CONSTRUCTION, L.P. (0.39%)
PRIMATE CONSTRUCTION, INC. (0.21%)
BMP SPECIALIST, LLC(0.08%)
TEX OP CONSTRUCTION, LP(0.01%)
PERFORMANCE EQUIPMENT(0.13%)
AUSTIN FILTER SYSTEMS, INC.(3.34%)
J.D. RAMMING PAVING CO., LTD.( 11.54%)
CRAIG OLDEN, INC.( 12.42%)
MCKINNEY DRILLING__(BUDA)(0.66%)
ROYAL VISTA INC. (9.79%)
AARON CONCRETE CONTRACTORS, L.P. (4.70%)
ROADWAY SPECIALTIES, INC.(0.54%)
BOOTHE BROTHERS PAVING COMPANY, INC. (1.34%)
FLASHER EQUIPMENT COMPANY(5.73%)
RANGER EXCAVATING, L.P.(0.00%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (2.11%)
BRYANT & FREY CONSTRUCTION (0.00%)
CHAMPION SITE PREP, L.P. (0.00%)
CENTRAL TEXAS REINFORCEMENT(0.01%)
CHANDLER CONCRETE, INC.(0.57%)
MG DRILLING(0.00%)
REINFORCING STEEL SUPPLY (0.00%)
LONE STAR SITEWORK, LLC(0.57%)
KRL CONSTRUCTION INC.(0.11%)
Contract # 08113002
Totals 34982606.55 998393.65 15223538.58 43.5

CountyTRAVIS
Highway LP 360
From BEE CAVES RD
To LP 1
CSJ 0113-13-152
Proj ID NH 1102(427)
Work Type MILL, SEAL & THIN OVERLAY
 
3.912 1640002.97 0.00 1838316.76 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-11
Work Began 09-05-12
Work Completed  
Time Computed 09-30-11
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 100
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-152
HIGHWAY TECHNOLOGIES, INC. (6.04%)
Contract # 08113273
Totals 1640002.97 0.00 1838316.76 99.9

CountyTRAVIS
Highway US 290
From 490 FT. EAST OF SHADOWGLEN BLVD CTL
To 1020 FT. EAST OF FM 973
CSJ 0114-02-098
Proj ID CC 114-2-98
Work Type ADD EB RIGHT TURN AND EB & WB LTLS
 
0.599 372486.10 0.00 0.00 0.0
CountyTRAVIS
Highway LP 212
From 1775 FT. SOUTH OF US 290
To US 290
CSJ 0114-20-010
Proj ID CC 114-20-10
Work Type ADD SB RIGHT & NB LEFT TURN LANES
 
0.336 397395.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133227
Totals 769881.60 0.00 0.00 0.0

CountyBASTROP
Highway US 290
From 0.28 MI EAST OF COUNTY LINE ROAD
To 0.44 MI EAST OF COUNTY LINE ROAD
CSJ 0114-04-064
Proj ID CC 114-4-64
Work Type EXTEND LEFT TURN LANE AT MEDIAN
 
0.159 107797.28 39100.52 39100.52 36.2
Work Order 02-19-13
Work Began 03-27-13
Work Completed  
Time Computed 03-07-13
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 36
Contractor(s)
DIAMOND X CONTRACTING, INC
SUBCONTRACTOR(S) FOR CCSJ: 0114-04-064
N-LINE TRAFFIC MAINTENANCE, L.P. (6.18%)
D. I. J. CONSTRUCTION, INC.(6.48%)
ENVIRONMENTAL SAFETY SERVICES, INC.(2.28%)
LONE STAR PAVING CO. ( 22.82%)
AARON CONCRETE CONTRACTORS, L.P. (4.67%)
Contract # 12123205
Totals 107797.28 39100.52 39100.52 36.2

CountyCALDWELL
Highway FM 20
From SH 80
To 1.881 MI W OF US 183
CSJ 0115-02-017
Proj ID STP 2013(473)
Work Type FULL DEPTH REPAIR, LEVEL - UP & SEAL
 
11.115 1097372.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0115-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133004
Totals 1097372.07 0.00 0.00 0.0

CountyBASTROP
Highway FM 20
From 0.261 MI S OF FM 535
To 0.175 MI N OF FM 535
CSJ 0115-04-042
Proj ID STP 2012(548)
Work Type WDN, RE - ALIGN VERT, TWLTL, CULV, OV
 
0.850 1527586.43 1448.12 1453004.54 95.1
Work Order 07-09-12
Work Began 10-22-12
Work Completed  
Time Computed 09-07-12
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 95
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0115-04-042
HIGHWAY TECHNOLOGIES, INC. (0.41%)
AUSTIN WOOD RECYCLING(0.66%)
MPB, INC.(3.36%)
ROADWAY SPECIALTIES, INC.(0.92%)
MURRAY CONSTRUCTION(1.13%)
FLASHER EQUIPMENT COMPANY(0.85%)
Contract # 05123210
Totals 1527586.43 1448.12 1453004.54 95.1

CountyLEE
Highway SH 21
From 0.383 MI. W OF FM 3403
To 0.009 MI. W OF FM 141
CSJ 0116-01-028
Proj ID NH 2013(191)
Work Type ADD SHLDRS., PAV REPAIR, SEAL COAT
 
10.251 7525070.79 847484.40 1282412.22 17.0
Work Order 01-23-13
Work Began 03-11-13
Work Completed  
Time Computed 03-11-13
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 15
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0116-01-028
AUSTIN WOOD RECYCLING(1.25%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
D. I. J. CONSTRUCTION, INC.(3.55%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.91%)
HIGHWAY TECHNOLOGIES, INC. (0.37%)
ROADWAY SPECIALTIES, INC.(1.92%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.24%)
Contract # 11123217
Totals 7525070.79 847484.40 1282412.22 17.0

CountyLLANO
Highway SH 29
From RM 2241
To RM 1431
CSJ 0150-04-043
Proj ID STP 2013(246)
Work Type LEVEL - UP & SEAL COAT
 
12.867 1485594.91 860687.67 860687.67 57.9
Work Order 03-08-13
Work Began 04-08-13
Work Completed  
Time Computed 03-24-13
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 40
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0150-04-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123024
Totals 1485594.91 860687.67 860687.67 57.9

CountyBURNET
Highway SH 29
From FANIN STREET IN BURNET
To HILL STREET
CSJ 0151-01-040
Proj ID STP 2011(355)
Work Type REHAB RDWY
 
1.000 1416556.10 0.00 1685895.62 99.9
CountyBURNET
Highway US 281
From HOUSTON CLINTON DR
To GREEN MILE RD
CSJ 0252-01-069
Proj ID STP 2011(355)
Work Type REHAB RDWY
 
2.300 3255002.03 15188.91 3486903.59 99.9
Work Order 09-15-10
Work Began 10-12-10
Work Completed  
Time Computed 10-12-10
Contract Working Days 387
Addl Days Granted 66
Working Days Charged 404
Percent Time Used 89
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0252-01-069
J.D. RAMMING PAVING CO., LTD.( 27.80%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.61%)
F & W ELECTRICAL CONTRACTORS, INC. (2.47%)
D. I. J. CONSTRUCTION, INC.(0.71%)
Contract # 08103110
Totals 4671558.13 15188.91 5172799.21 99.9

CountyWILLIAMSON
Highway SH 29
From 1145 FT. WEST OF CR 200
To FM 1869
CSJ 0151-03-039
Proj ID STP 2013(338)
Work Type MILL, SEAL & OVERLAY
 
1.542 509202.94 0.00 0.00 0.0
CountyWILLIAMSON
Highway SH 29
From FM 1869
To 1775 FT. EAST OF EAST END OF LP 332
CSJ 0151-04-068
Proj ID STP 2013(338)
Work Type MILL, SEAL & OVERLAY
 
0.704 217918.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-13
Work Began 00-00-00
Work Completed  
Time Computed 05-01-13
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-03-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133029
Totals 727121.67 0.00 0.00 0.0

CountyWILLIAMSON
Highway US 183
From APPROX. 920' S OF 183A
To RM 2243
CSJ 0151-04-067
Proj ID NH 2013(474)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
1.824 867875.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-04-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133034
Totals 867875.03 0.00 0.00 0.0

CountyWILLIAMSON
Highway US 183
From DISCOVERY BLVD
To AVERY RANCH BLVD
CSJ 0151-05-095
Proj ID NH 2012(306)
Work Type MILL, SEAL & OVERLAY
 
2.626 1366638.30 417473.14 418256.04 30.6
Work Order 03-12-12
Work Began 12-10-12
Work Completed  
Time Computed 05-11-12
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 24
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-095
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.33%)
MPB, INC.(0.37%)
HIGHWAY TECHNOLOGIES, INC. (5.73%)
TEX OP CONSTRUCTION, LP(4.76%)
Contract # 02123031
Totals 1366638.30 417473.14 418256.04 30.6

CountyTRAVIS
Highway LP 111
From BOLM RD
To US 183
CSJ 0151-06-130
Proj ID STP 2012(049)MM
Work Type CONSTRUCT SIDEWALK ON AIRPORT BLVD
 
0.486 117198.00 0.00 115928.43 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-08-11
Work Began 02-13-12
Work Completed 05-01-13
Time Computed 01-07-12
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 49
Contractor(s)
GARCIA J CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-06-130
TEXAS CONCRETE COMPANY ( 18.21%)
Contract # 09113027
Totals 117198.00 0.00 115928.43 100.0

CountyTRAVIS
Highway US 183
From BURNET RD
To IH 35
CSJ 0151-06-135
Proj ID STP 1102(322)
Work Type MILL, SEAL & OVERLAY FRONTAGE RDS
 
3.476 1912437.45 0.00 1957389.26 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-19-11
Work Began 09-12-11
Work Completed 04-17-13
Time Computed 09-12-11
Contract Working Days 58
Addl Days Granted 6
Working Days Charged 74
Percent Time Used 115
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0151-06-135
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (4.24%)
HIGHWAY TECHNOLOGIES, INC. (7.03%)
Contract # 06113246
Totals 1912437.45 0.00 1957389.26 100.0

CountyTRAVIS
Highway US 183
From 0.46 MI W. OF SPRINGDALE
To 0.68 MI S. OF BOLM RD
CSJ 0151-09-139
Proj ID NH 2011(722)
Work Type PVMT SURF REHAB - 2IN ML IP RCYC
 
6.939 1359831.37 0.00 1672906.21 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-11
Work Began 04-18-11
Work Completed 04-17-13
Time Computed 04-06-11
Contract Working Days 53
Addl Days Granted 12
Working Days Charged 65
Percent Time Used 100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0151-09-139
HIGHWAY TECHNOLOGIES, INC. (7.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (2.32%)
AGGREGATE TECHNOLOGIES, INC. (2.10%)
BMP SPECIALIST, LLC(0.32%)
ROADWAY SPECIALTIES, INC.(4.13%)
Contract # 12103224
Totals 1359831.37 0.00 1672906.21 100.0

CountyCALDWELL
Highway US 183
From 5.0 MI SOUTH OF FM 20
To 0.5 MI SOUTH OF FM 86
CSJ 0152-03-053
Proj ID NH 2013(553)
Work Type PAVEMENT REPAIR, MILL, SEAL & OVERLAY
 
8.000 7526709.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-03-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133206
Totals 7526709.80 0.00 0.00 0.0

CountyBURNET
Highway US 281
From ON US 281 AT COLORADO RIVER
To (STR 0252-02-017)
CSJ 0252-02-046
Proj ID BR 2010(786)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.568 28272713.57 521409.40 17390540.03 61.5
CountyBURNET
Highway US 281
From ON US 281 AT COLORADO RIVER
To .
CSJ 0252-02-049
Proj ID BR 2009(641)
Work Type ROW ACQ. AND RELOC. ASSIST.
 
0.001 375131.40 -294.82 366309.84 97.6
Work Order 07-15-10
Work Began 12-07-10
Work Completed  
Time Computed 12-07-10
Contract Working Days 1,177
Addl Days Granted 0
Working Days Charged 676
Percent Time Used 57
Contractor(s)
ARCHER-WESTERN CONTRACTORS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0252-02-046
AARON CONCRETE CONTRACTORS, L.P. (0.65%)
AFS ENVIRONMENTAL, INC.(0.22%)
APAC-TEXAS, INC. (2.51%)
BPI ENVIRONMENTAL SERVICES INC.(0.61%)
BREDA COMPANY, INC.(0.37%)
CONCRETE CUTTING BY BOND (0.11%)
DUSTROL, INC. (ROANOKE)(0.01%)
PENHALL COMPANY(0.07%)
ROADWAY SPECIALTIES, INC.(1.73%)
SCOTT DERR PAINTING CO, LLC(0.37%)
THE LEVY COMPANY, L.P. (2.27%)
TREVCON, INC.(1.90%)
W. W. FOUNDATION DRILLING, LTD.(3.29%)
PANTHER CREEK TRANSPORTATION, INC. (0.35%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.02%)
HIGHWAY TECHNOLOGIES, INC. (0.23%)
SWEEP ACROSS TEXAS (0.00%)
MUSTANG COLT SERVICES, INC.(0.00%)
OMEGA DEMOLITION CORPORATION (3.33%)
Contract # 05103201
Totals 28647844.97 521114.58 17756849.87 62.0

CountyBURNET
Highway US 281
From SH 71
To BLANCO COUNTY LINE
CSJ 0252-02-053
Proj ID STP 2013(247)
Work Type MILL, SEAL & OVERLAY
 
3.093 1090537.74 0.00 0.00 0.0
CountyBLANCO
Highway US 281
From BURNET COUNTY LINE
To US 290 WEST IN JOHNSON CITY
CSJ 0252-03-047
Proj ID STP 2013(247)
Work Type MILL, SEAL & OVERLAY
 
15.051 3601894.57 15819.50 26729.50 0.7
Work Order 01-23-13
Work Began 00-00-00
Work Completed  
Time Computed 02-08-13
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-047
INTERSTATE BARRICADES & MARKINGS, INC. (0.00%)
Contract # 12123010
Totals 4692432.31 15819.50 26729.50 0.5

CountyBLANCO
Highway US 281
From AT N CYPRESS CREEK
To (STR 0252-03-010)
CSJ 0252-03-045
Proj ID BR 2011(955)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 742748.14 0.00 811696.19 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 01-10-12
Work Completed  
Time Computed 06-30-11
Contract Working Days 99
Addl Days Granted 10
Working Days Charged 170
Percent Time Used 155
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-045
D. I. J. CONSTRUCTION, INC.(1.33%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.81%)
TURNKEY OPERATIONS (0.67%)
BMP SPECIALIST, LLC(1.38%)
ROADWAY SPECIALTIES, INC.(0.50%)
Contract # 05113004
Totals 742748.14 0.00 811696.19 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7