|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HAYS |
| Highway |
US 290 |
| From |
0.43 MI E OF RM 12 |
| To |
0.34 MI W OF CANYONWOOD DR |
| CSJ |
0113-07-058 |
| Proj ID |
NH 2007(786) |
| Work Type |
CONSTRUCT CTL & SHOULDERS |
| |
|
2.723 |
6253076.28 |
1150502.17 |
5993544.63 |
95.8 |
| Work Order |
10-02-07 |
| Work Began |
11-05-07 |
| Work Completed |
|
| Time Computed |
10-18-07 |
| Contract Working Days |
253 |
| Addl Days Granted |
0 |
| Working Days Charged |
232 |
| Percent Time Used |
91 |
| Contractor(s) |
| JOE BLAND CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0113-07-058 AARON CONCRETE CONTRACTORS, L.P. (0.08%) ASPHALT PAVING COMPANY OF AUSTIN, INC. ( 26.37%) BRYANT & FREY CONSTRUCTION (3.60%) HIGHWAY TECHNOLOGIES (2.10%) ROADWAY SPECIALTIES, INC.(4.77%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.86%)
|
| Contract # |
08073207 |
|
Totals |
6253076.28 |
1150502.17 |
5993544.63 |
95.8 |
|
| County | CALDWELL |
| Highway |
FM 20 |
| From |
0.057 MI E OF US 183 |
| To |
0.974 MI E OF US 183 |
| CSJ |
0115-03-022 |
| Proj ID |
STP 2008(474) |
| Work Type |
DRAINAGE IMPROVEMENTS |
| |
|
1.295 |
639823.46 |
94670.94 |
408537.58 |
63.8 |
| Work Order |
05-15-08 |
| Work Began |
09-02-08 |
| Work Completed |
|
| Time Computed |
05-31-08 |
| Contract Working Days |
59 |
| Addl Days Granted |
0 |
| Working Days Charged |
50 |
| Percent Time Used |
84 |
| Contractor(s) |
| ACME BRIDGE COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0115-03-022 HIGHWAY TECHNOLOGIES, L.P. (0.77%) LONE STAR PAVING CO. (5.59%) ROADWAY SPECIALTIES, INC.(1.12%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.60%) F.D. CONCRETE, LLC ( 18.61%)
|
| Contract # |
04083226 |
|
Totals |
639823.46 |
94670.94 |
408537.58 |
63.8 |
|
| County | WILLIAMSON |
| Highway |
US 183 |
| From |
N OF LAKELINE BLVD |
| To |
TRAVIS COUNTY LINE |
| CSJ |
0151-05-064 |
| Proj ID |
C 151-5-64 |
| Work Type |
INSTALL FTM |
| |
|
3.248 |
2630131.28 |
155351.04 |
880658.82 |
34.8 |
| Work Order |
08-14-07 |
| Work Began |
02-11-08 |
| Work Completed |
|
| Time Computed |
08-30-07 |
| Contract Working Days |
345 |
| Addl Days Granted |
10 |
| Working Days Charged |
181 |
| Percent Time Used |
50 |
| Contractor(s) |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-064 UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.48%) COLLIER SERVICES, INC. (3.08%) COMPUTERIZED TRAFFIC CONTROL, INC. ( 10.82%) KRL CONSTRUCTION INC.(0.99%) M.G. DRILLING(0.14%) INTEGRATION SERVICES, LLC(0.22%) S & S BRIDGE PAINTING(0.11%)
|
| Contract # |
07073039 |
|
Totals |
2630131.28 |
155351.04 |
880658.82 |
34.8 |
|
| County | WILLIAMSON |
| Highway |
US 183 |
| From |
NORTH OF MCNEIL ROAD |
| To |
RM 620 (SH 45) |
| CSJ |
0151-05-084 |
| Proj ID |
NH 2002(966) |
| Work Type |
CONCRETE PAVEMENT AND DIRECT CONNECTOR'S |
| |
|
2.266 |
27969129.48 |
687124.08 |
26308191.78 |
95.9 |
| County | WILLIAMSON |
| Highway |
SH 45 |
| From |
WEST OF US 183 |
| To |
WEST OF FM 734 |
| CSJ |
0683-01-069 |
| Proj ID |
TTA 2002(243) |
| Work Type |
GRADING, BASE, STRUCTURES & SURFACING |
| |
|
2.492 |
73608228.69 |
171631.09 |
86108570.03 |
99.9 |
| County | ZERO COUNTIES |
| Highway |
|
| From |
|
| To |
|
| CSJ |
0683-01-077 |
| Proj ID |
|
| Work Type |
|
| |
|
|
0.00 |
-412132.30 |
24078089.60 |
0.0 |
| Work Order |
11-17-03 |
| Work Began |
12-01-03 |
| Work Completed |
|
| Time Computed |
12-03-03 |
| Contract Working Days |
1,014 |
| Addl Days Granted |
187 |
| Working Days Charged |
1,198 |
| Percent Time Used |
99 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0683-01-069 RANGER EXCAVATING, INC.(5.30%) UNITED RENTALS HIGHWAY TECHNOLOGIES(0.40%) CK & S, INC. (0.00%) ROYAL VISTA INC. (1.78%) H & T UTILITIES, L.C.(1.20%) H. L. CHAPMAN PIPELINE CONSTRUCTION, INC.(0.12%) PRIMATE CONSTRUCTION, INC. (0.19%) FISCHER UTILITY CONSTRUCTION CO., INC. (0.84%) STRIPING TECHNOLOGY, INC.(0.44%) S & J ELECTRIC (3.64%) W. W. FOUNDATION DRILLING, LTD.(1.96%) H. L. CHAPMAN PIPELINE CONSTRUCTION, INC.(0.07%) 5A TRANSPORTATION, INC.(0.80%) KELLYSTONE, INC(0.20%) S & S PAINTING (0.20%) RODBUSTERS, INC. (1.38%) MASTEC NORTH AMERICA, INC. (0.22%) ROADWAY SPECIALTIES, INC.(2.09%) W.W. WEBBER INC. (6.71%) LEDGENDS LANDSCAPES, LLC (0.46%) BRYANT & FREY CONSTRUCTION (0.09%) TEXAS TRUCKING COMPANY, INC. (0.40%) TEXAS SHAFTS, INC. (0.06%) BREDA COMPANY, INC.(0.01%) JOURNEYMAN CONSTRUCTION, LP(3.71%) TWS DRILLING & CONSTRUCTION, LLC (0.23%) MATOKA, INC. (0.56%) HYDRO STOP PRODUCTS(0.01%) AUSTIN FILTER SYSTEMS, INC.(0.69%) LASCO ACOUSTICS & DRYWALL, INC.(0.04%) THYSSEN KRUPP ELEVATOR (0.04%) U.S. STRUCTURAL CONCRETE INC.(0.70%) TRANSIT MIX CONCRETE & MATERIALS COMPANY (AUSTIN)(3.69%) TEXAS AMERICAN SHEETMETAL INC. (0.08%) D. I. J. CONSTRUCTION, INC.(0.00%) G. CARTER CONSTRUCTION COMPANY, INC. (0.00%) GRANITE CONSTRUCTION COMPANY (0.20%) METRO SERVICES, INC. (0.13%) CONNOR CONSTRUCTION COMPANY, LLC (0.15%) STA-DRI COMPANY(0.13%) MCKINNEY DRILLING__(BUDA)(0.00%) AARON CONCRETE CONTRACTORS, L.P. (0.03%) CENTRAL TEXAS REINFORCEMENT(0.05%) CIMA CONSTRUCTION, INC.(0.17%) SIMPLEX GRINNEL(0.02%) SOUTHWEST CONSTRUCTION SERVICES(0.06%) DUSTROL, INC.(0.02%) INDUS CONSTRUCTION, L.P. (0.51%) ABLE BODY LABOR(0.00%) D & W PAINTING INC.(0.05%) FOX & HEARN(0.19%) HULL SUPPLY COMPANY(0.02%) J. D. RAMMING PAVING CO., INC. (0.00%) JIM CONNELLY MASONRY INC.(0.15%) NATIONAL TERRAZZO TILE & MARBLE(0.04%) V. KING FIRE PROTECTION(0.01%) WHEELER COATINGS ASPHALT, INC. (0.00%) INTEGRATED FLOORING SYSTEMS(0.00%) K & J WOODWORKS(0.00%) DEA SPECIALTIES CO., INC.(0.00%) ALL MASONRY AND CONCRETE (0.12%) DORAN STEEL, INC.(0.00%) TITUS ELECTRICAL CONTRACTING, INC. (0.03%) STAR INSULATION COMPANY, INC.(0.02%) TEMPSET CONTROLS (0.03%) HORIZON HARDWARE SPEC(0.00%) HULL SERVICES(0.00%) L.C. PERSONNEL, INC. DBA LABOR FINDERS (0.00%) H.R. MARC(0.02%) LIBERTY SIGNS(0.00%) JR'S CONCRETE CONSTRUCTION, INC. (0.06%) RGC ADVANCED GLASS (0.01%) SANTA ANA'S CONSTRUCTION COMPANY (0.15%) BECK STEEL (0.77%) RENAISSANCE CONTRACTORS PARTNERSHIP(4.47%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%) CRAIG OLDEN, INC.(0.64%) A & R DEMOLITION, INC. (0.26%) CRAFTCORPS, INC. (0.00%) NORTHEAST SERVICE, INC.(0.07%)
|
| Contract # |
09033001 |
|
Totals |
101577358.17 |
446622.87 |
136494851.41 |
99.9 |
|
| County | WILLIAMSON |
| Highway |
US 183 |
| From |
SPICEWOOD SPRINGS RD |
| To |
TRAVIS C/L |
| CSJ |
0151-05-088 |
| Proj ID |
NH 2008(810) |
| Work Type |
OVERLAY |
| |
|
0.189 |
157073.48 |
0.00 |
0.00 |
0.0 |
| County | TRAVIS |
| Highway |
US 183 |
| From |
WILLIAMSON C/L |
| To |
LP 360 |
| CSJ |
0151-06-132 |
| Proj ID |
NH 2008(810) |
| Work Type |
OVERLAY |
| |
|
3.674 |
2736863.27 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-18-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
48 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ASPHALT PAVING COMPANY OF AUSTIN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0151-06-132 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08083224 |
|
Totals |
2893936.75 |
0.00 |
0.00 |
0.0 |
|
| County | TRAVIS |
| Highway |
US 183 |
| From |
AT DRAW,0.8 MI N OF FM 1327 |
| To |
STR 152-1-20 |
| CSJ |
0152-01-070 |
| Proj ID |
BR 2008(656) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
0.100 |
167781.75 |
94513.10 |
94513.10 |
56.3 |
| County | TRAVIS |
| Highway |
US 183 |
| From |
AT SOUTH FORK OF DRY CREEK |
| To |
. |
| CSJ |
0152-01-072 |
| Proj ID |
BR 2008(656) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
0.100 |
340761.35 |
43184.13 |
43184.13 |
12.6 |
| Work Order |
07-10-08 |
| Work Began |
11-03-08 |
| Work Completed |
|
| Time Computed |
10-08-08 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
17 |
| Percent Time Used |
28 |
| Contractor(s) |
| AARON CONCRETE CONTRACTORS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-070 HIGHWAY TECHNOLOGIES (3.50%) ROADWAY SPECIALTIES, INC.( 18.81%)
|
| Contract # |
06083025 |
|
Totals |
508543.10 |
137697.23 |
137697.23 |
27.0 |
|
| County | CALDWELL |
| Highway |
US 183 |
| From |
0.12 MI N OF FM 672 |
| To |
0.44 MI S OF FM 672 |
| CSJ |
0152-02-058 |
| Proj ID |
STP 2008(201)RGS |
| Work Type |
CONSTRUCT GRADE SEPARATION |
| |
|
0.551 |
6118561.39 |
7531.44 |
6558939.82 |
99.9 |
| Work Order |
02-20-08 |
| Work Began |
03-11-08 |
| Work Completed |
|
| Time Computed |
03-07-08 |
| Contract Working Days |
200 |
| Addl Days Granted |
0 |
| Working Days Charged |
180 |
| Percent Time Used |
90 |
| Contractor(s) |
| DAN WILLIAMS COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-058 AGGREGATE TECHNOLOGIES, INC. (0.73%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (3.36%) BATTERSON, L.L.P.(0.78%) BREDA COMPANY, INC.(0.76%) CAPROCK SPECIALITY CONTRACTORS (0.13%) HARDY HOLE DRILLING(3.10%) J.D. RAMMING PAVING CO., LTD.( 17.13%) MURRAY CONSTRUCTION(0.29%) ROADWAY SPECIALTIES, INC.(0.66%) SCOTT DERR PAINTING CO (0.06%) TEXAS TRUCKING COMPANY, INC. (2.66%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.71%) TEX OP CONSTRUCTION, LP(0.17%)
|
| Contract # |
12073209 |
|
Totals |
6118561.39 |
7531.44 |
6558939.82 |
99.9 |
|
| County | WILLIAMSON |
| Highway |
US 79 |
| From |
WEST OF FM 1460 |
| To |
CR 195 |
| CSJ |
0204-01-049 |
| Proj ID |
STP 2002(662) |
| Work Type |
UPGRADE TO 4 - LANE DIVIDED SECTION |
| |
|
1.550 |
9351882.68 |
0.00 |
9952669.42 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-03-06 |
| Work Began |
05-15-06 |
| Work Completed |
|
| Time Computed |
01-19-06 |
| Contract Working Days |
515 |
| Addl Days Granted |
25 |
| Working Days Charged |
540 |
| Percent Time Used |
100 |
| Contractor(s) |
| JOE BLAND CONSTRUCTION, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-049 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (5.91%) ROADWAY SPECIALTIES, INC.(1.32%) ATS DRILLING, L.P. (1.44%) AARON CONCRETE CONTRACTORS, L.P. (0.05%) BRYANT & FREY CONSTRUCTION (1.02%) PRIMATE CONSTRUCTION, INC. (0.05%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (1.48%) BMP SPECIALTIES, LLC.(0.12%) ASPHALT PAVING COMPANY OF AUSTIN, INC. ( 23.49%)
|
| Contract # |
10053203 |
|
Totals |
9351882.68 |
0.00 |
9952669.42 |
99.9 |
|
| County | WILLIAMSON |
| Highway |
US 79 |
| From |
AT FM 397 |
| To |
. |
| CSJ |
0204-03-041 |
| Proj ID |
CL 204-3-41 |
| Work Type |
LANDSCAPE & IRRIGATION |
| |
|
0.001 |
151832.76 |
480.00 |
141248.18 |
96.9 |
| County | WILLIAMSON |
| Highway |
SH 95 |
| From |
AT MUSTANG CREEK |
| To |
. |
| CSJ |
0321-01-046 |
| Proj ID |
CL 321-1-46 |
| Work Type |
LANDSCAPING AND IRRIGATION |
| |
|
0.266 |
105185.55 |
480.00 |
94162.29 |
93.2 |
| Work Order |
09-13-06 |
| Work Began |
10-16-06 |
| Work Completed |
|
| Time Computed |
09-29-06 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
42 |
| Percent Time Used |
93 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-046 LONE STAR TRAFFIC SERVICE, INC.(0.77%)
|
| Contract # |
08063015 |
|
Totals |
257018.31 |
960.00 |
235410.47 |
95.4 |
|
| County | LEE |
| Highway |
US 77 |
| From |
AT ALLEN CREEK |
| To |
. |
| CSJ |
0211-02-022 |
| Proj ID |
BR 2007(671) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.924 |
5387504.68 |
381674.86 |
4786031.15 |
88.9 |
| Work Order |
08-31-07 |
| Work Began |
09-17-07 |
| Work Completed |
|
| Time Computed |
09-16-07 |
| Contract Working Days |
285 |
| Addl Days Granted |
17 |
| Working Days Charged |
306 |
| Percent Time Used |
101 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0211-02-022 GUAJARDO STEEL (0.94%) INTERSTATE BARRICADES & MARKINGS, INC. (0.89%) LONE STAR TRAFFIC SERVICE, INC.(0.28%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.20%) PNEU-ROCK TRANSPORTATION, INC. (1.76%) PRIMATE CONSTRUCTION, INC. (0.39%) SCOTT DERR PAINTING CO (0.08%) TONY A. ENTERPRISES, INC.(2.67%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.86%) STATE DEVELOPMENT CORPORATION(0.08%) J.D. RAMMING PAVING CO., LTD.( 16.63%) FORTSON CONTRACTING, INC.(0.94%) TEXAS CUTTING & CORING, INC. (0.24%)
|
| Contract # |
07073227 |
|
Totals |
5387504.68 |
381674.86 |
4786031.15 |
88.9 |
|
| County | BURNET |
| Highway |
US 281 |
| From |
N END OF COLORADO RIVER BRIDGE |
| To |
N OF MISSION HILLS INTERSECTION |
| CSJ |
0252-01-064 |
| Proj ID |
STP 2008(256) |
| Work Type |
MILL & OVERLAY |
| |
|
5.132 |
1668430.20 |
0.00 |
1674972.34 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-20-08 |
| Work Began |
03-12-08 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ASPHALT PAVING COMPANY OF AUSTIN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0252-01-064 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01083223 |
|
Totals |
1668430.20 |
0.00 |
1674972.34 |
99.9 |
|
| County | BASTROP |
| Highway |
SH 71 |
| From |
0.15 MI E OF LP 150E |
| To |
0.50 MI W OF FM 153 |
| CSJ |
0265-05-070 |
| Proj ID |
STP 2008(258) |
| Work Type |
SEAL & OVERLAY |
| |
|
10.168 |
4932682.31 |
444490.81 |
4986174.92 |
99.9 |
| Work Order |
02-20-08 |
| Work Began |
04-22-08 |
| Work Completed |
|
| Time Computed |
03-07-08 |
| Contract Working Days |
48 |
| Addl Days Granted |
4 |
| Working Days Charged |
92 |
| Percent Time Used |
176 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-070 TEXAS SAFE SITE PRODUCTS, LP (0.13%) CRAWFORD YANT(0.10%) INTERSTATE BARRICADES & MARKINGS, INC. (0.11%) D. I. J. CONSTRUCTION, INC.(4.59%)
|
| Contract # |
01083210 |
|
Totals |
4932682.31 |
444490.81 |
4986174.92 |
99.9 |
|
| County | BASTROP |
| Highway |
LP 230 |
| From |
AT COLORADO RIVER IN SMITHVILLE |
| To |
. |
| CSJ |
0265-13-004 |
| Proj ID |
BR 2007(627) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.644 |
7676203.70 |
215682.02 |
6778658.59 |
88.3 |
| Work Order |
08-06-07 |
| Work Began |
10-01-07 |
| Work Completed |
|
| Time Computed |
08-22-07 |
| Contract Working Days |
317 |
| Addl Days Granted |
0 |
| Working Days Charged |
275 |
| Percent Time Used |
86 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0265-13-004 MURRAY CONSTRUCTION(0.24%) MCKINNEY DRILLING__(BUDA)( 13.98%) SCOTT DERR PAINTING CO (0.06%) KELLYSTONE, INC(0.31%) SAM, INC.(SURVEYING & MAPPING, INC.) (0.10%) HIGHWAY TECHNOLOGIES (0.79%) INDUS CONSTRUCTION, L.P. (4.34%) INTERSTATE BARRICADES & MARKINGS, INC. (0.22%) LEVY COMPANY (0.98%) J.D. RAMMING PAVING CO., LTD.(8.29%) ROADWAY SPECIALTIES, INC.(2.38%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.16%) AGGREGATE TECHNOLOGIES, INC. (1.36%) STOMPER DEMOLITION (8.00%)
|
| Contract # |
06073205 |
|
Totals |
7676203.70 |
215682.02 |
6778658.59 |
88.3 |
|
| County | WILLIAMSON |
| Highway |
SH 95 |
| From |
AT BRUSHY CREEK |
| To |
. |
| CSJ |
0321-01-049 |
| Proj ID |
BR 2009(052) |
| Work Type |
REPL BRIDGE AND APPROACHES |
| |
|
0.320 |
2185579.62 |
49650.84 |
49650.84 |
2.2 |
| Work Order |
11-05-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-21-08 |
| Contract Working Days |
173 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0321-01-049 LONE STAR PAVING CO. (7.45%) PRIMATE CONSTRUCTION, INC. (0.32%) HIGHWAY TECHNOLOGIES (0.91%) J.L. STEEL REINFORCING, LLC(1.06%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.45%) HIGHWAY TECHNOLOGIES (0.33%) ROADWAY SPECIALTIES, INC.(6.81%)
|
| Contract # |
09083010 |
|
Totals |
2185579.62 |
49650.84 |
49650.84 |
2.2 |
|
| County | TRAVIS |
| Highway |
SH 130 |
| From |
WILLIAMSON C/L |
| To |
SOUTH OF US 290 |
| CSJ |
0440-06-004 |
| Proj ID |
HP 1196(1) |
| Work Type |
GRADING, BASE, STRUCTURES & SURFACI |
| |
|
12.240 |
986521577.00 |
1162797.00 |
826101734.00 |
83.8 |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
1,784 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LONE STAR INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 0440-06-004 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
06023501 |
|
Totals |
0.00 |
0.00 |
0.00 |
0.0 |
|
| County | CALDWELL |
| Highway |
FM 86 |
| From |
2.989 MI N OF US 183 |
| To |
2.534 MI N OF US 183 |
| CSJ |
0571-02-022 |
| Proj ID |
BR 2006(591) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
1.478 |
4294441.21 |
82796.24 |
367944.74 |
8.5 |
| Work Order |
08-15-08 |
| Work Began |
10-20-08 |
| Work Completed |
|
| Time Computed |
10-20-08 |
| Contract Working Days |
214 |
| Addl Days Granted |
0 |
| Working Days Charged |
27 |
| Percent Time Used |
12 |
| Contractor(s) |
| MANN CONTRACTORS, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0571-02-022 M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.60%) JUST GROOVING, LTD.(0.17%) ASPHALT PAVING COMPANY OF AUSTIN, INC. (8.13%) EGGEMEYER LAND CLEARING, LLC (2.11%) HIGHWAY TECHNOLOGIES (0.32%) STOMPER DEMOLITION COMPANY, INC. (6.47%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.23%)
|
| Contract # |
07083006 |
|
Totals |
4294441.21 |
82796.24 |
367944.74 |
8.5 |
|
| County | CALDWELL |
| Highway |
FM 86 |
| From |
AT PLUM CREEK |
| To |
. |
| CSJ |
0571-02-023 |
| Proj ID |
BR 2009(010) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.326 |
1999591.30 |
227670.16 |
227670.16 |
11.3 |
| Work Order |
10-28-08 |
| Work Began |
11-13-08 |
| Work Completed |
|
| Time Computed |
11-13-08 |
| Contract Working Days |
145 |
| Addl Days Granted |
0 |
| Working Days Charged |
10 |
| Percent Time Used |
6 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0571-02-023 EGGEMEYER LAND CLEARING, LLC (1.43%) VOGES DRILLING CO. (3.01%) ASPHALT PAVING COMPANY OF AUSTIN, INC. ( 37.75%) 76 MILLING, INC. (0.26%) STOMPER DEMOLITION COMPANY, INC. (3.04%) SCOTT DERR PAINTING CO (0.06%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.43%) ROADWAY SPECIALTIES, INC.(2.49%) INTERSTATE BARRICADES & MARKINGS, INC. (0.99%)
|
| Contract # |
09083205 |
|
Totals |
1999591.30 |
227670.16 |
227670.16 |
11.3 |
|
| County | LLANO |
| Highway |
SH 71 |
| From |
MASON C/L |
| To |
SH 29 |
| CSJ |
0577-04-018 |
| Proj ID |
STP 2007(157)SB |
| Work Type |
SAFETY TREAT FIXED OBJECTS |
| |
|
64.500 |
2796553.25 |
3447.00 |
2922389.94 |
99.9 |
| Work Order |
02-28-07 |
| Work Began |
04-04-07 |
| Work Completed |
|
| Time Computed |
03-16-07 |
| Contract Working Days |
279 |
| Addl Days Granted |
17 |
| Working Days Charged |
235 |
| Percent Time Used |
79 |
| Contractor(s) |
| MANN CONTRACTORS, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0577-04-018 ABC EROSION CONTROL, INC.(6.01%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.74%)
|
| Contract # |
01073224 |
|
Totals |
2796553.25 |
3447.00 |
2922389.94 |
99.9 |
|
| County | TRAVIS |
| Highway |
SH 45 |
| From |
WILLIAMSON C/L |
| To |
SH 130 |
| CSJ |
0683-07-003 |
| Proj ID |
TTA 2002(252) |
| Work Type |
GRADING, BASE, STRUCTURES & SURFACI |
| |
|
1.515 |
34057983.41 |
0.00 |
33057188.73 |
99.7 |
| County | ZERO COUNTIES |
| Highway |
|
| From |
|
| To |
|
| CSJ |
0683-07-006 |
| Proj ID |
|
| Work Type |
|
| |
|
|
0.00 |
0.00 |
683241.89 |
0.0 |
| County | ZERO COUNTIES |
| Highway |
|
| From |
|
| To |
|
| CSJ |
0683-07-007 |
| Proj ID |
|
| Work Type |
|
| |
|
|
0.00 |
0.00 |
8940369.91 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-24-04 |
| Work Began |
06-09-04 |
| Work Completed |
|
| Time Computed |
06-09-04 |
| Contract Working Days |
565 |
| Addl Days Granted |
307 |
| Working Days Charged |
1,129 |
| Percent Time Used |
129 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0683-07-003 WIMS ENVIRONMENTAL, INC. (0.78%) T. J. LAMBRECHT CONSTRUCTION, INC. (8.08%) RENAISSANCE CONTRACTORS, INC.(8.78%) Z & L CONCRETE CONTRACTORS, INC. (0.68%) W.W. WEBBER INC. ( 15.99%) JOURNEYMAN CONSTRUCTION, LP( 12.43%) AUSTIN NURSERY AND LANDSCAPE (0.49%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.58%) ROYAL VISTA INC. (3.41%) RAYMOND PAINTING, INC. (0.01%) DUSTROL, INC. (ROANOKE)(0.02%) KIWI COMPANY (0.08%) J.L. STEEL, L.P. (0.11%) SANTA ANA'S CONSTRUCTION COMPANY (0.05%) MCKINNEY DRILLING__(BUDA)(0.35%) PRIMATE CONSTRUCTION, INC. (0.04%) THE LEVY COMPANY, L.P. (3.62%) NATIONAL TERRAZZO TILE & MARBLE(0.12%) SOUTHWEST CONSTRUCTION SERVICES(0.17%) BECK STEEL (2.14%) BRYANT & FREY CONSTRUCTION (0.07%) TEXAS TRENCH LTD (0.05%) THYSSEN KRUPP ELEVATOR (0.12%) ADVANCED GLASS INC.(0.03%) INTEGRATED FLOORING SYSTEMS(0.00%) LASCO ACOUSTICS & DRYWALL, INC.(0.14%) V. KING FIRE PROTECTION(0.05%) K & J WOODWORKS(0.01%) D & W PAINTING INC.(0.11%) U.S. STRUCTURAL CONCRETE INC.(1.99%) BADECO, INC(0.81%) TEXAS TRUCKING COMPANY, INC. (1.24%) GEORGETOWN TRANSPORTATION, INC.(1.07%) METRO SERVICES, INC. (0.29%) CENTRAL TEXAS REINFORCEMENT(0.01%) AUSTIN FILTER SYSTEMS, INC.(0.10%) SEABERS SERVICES, L.L.C. (0.30%) ABLE BODY LABOR(0.02%) CIMA CONSTRUCTION, INC.(0.02%) JAMES INTERIORS(0.01%) STAR INSULATION COMPANY, INC.(0.02%) TRICON PRECAST, LTD. (0.49%) TEMPSET CONTROLS (0.11%) RODBUSTERS, INC. (0.47%) K. SAVAGE TRUCKING, INC. (0.43%) H & T UTILITIES, L.C.(0.15%) SIMPLEX GRINNEL(0.07%) INDUS CONSTRUCTION, L.P. (0.42%) AARON CONCRETE CONTRACTORS, L.P. (1.15%) CRAFTCORPS, INC. (0.00%) MANAGED_NETWORK CABLING(0.07%) LIBERTY SIGNS(0.00%) TITUS ELECTRICAL CONTRACTING, INC. (0.11%) BAKER PLUMBING/SEPTIC SERVICE(0.00%) A & R DEMOLITION, INC. (0.01%) HEARN CO.(0.06%) H.R. MARC(0.03%) UNITED CABLE NETWORK, INC. (0.19%) MIKE BUTLER CONSTRUCTION (0.08%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.09%) CG CONSTRUCTORS(0.00%) LOGIC MECHANICAL, INC. (0.00%) LEGENDS LANDSCAPES LLC (0.22%)
|
| Contract # |
03043001 |
|
Totals |
34057983.41 |
0.00 |
42680800.53 |
99.9 |
|
| County | BURNET |
| Highway |
SH 71 |
| From |
AT LITTLE CYPRESS CREEK |
| To |
. |
| CSJ |
0700-01-028 |
| Proj ID |
BR 2006(760) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
1.102 |
2553950.05 |
0.00 |
2828168.40 |
99.9 |
| Work Order |
09-19-06 |
| Work Began |
10-04-06 |
| Work Completed |
|
| Time Computed |
10-05-06 |
| Contract Working Days |
211 |
| Addl Days Granted |
102 |
| Working Days Charged |
311 |
| Percent Time Used |
99 |
| Contractor(s) |
| CACTUS CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0700-01-028 ATS DRILLING, L.P. (7.35%) DIAMOND X CONTRACTING, INC.( 13.14%) ASPHALT PAVING COMPANY OF AUSTIN, INC. ( 10.95%) ROADWAY SPECIALTIES, INC.(2.42%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (1.94%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.09%)
|
| Contract # |
08063023 |
|
Totals |
2553950.05 |
0.00 |
2828168.40 |
99.9 |
|