Monthly State Let Construction Report For Austin District As Of Feb 10, 2017 Page 6 Of 7

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayFM 969
FromDECKER CREEK DRIVE
ToBASTROP COUNTY LINE
CSJ1186-01-087
Proj IDSTP 2015(277)HES
Work TypePROVIDE ADD'L PAVED SURFACE WIDTH
 
7.1015894316.374759741.0780.7
Work Order01-05-15
Work Began03-17-15
Work Completed
Time Computed03-17-15
Contract Working Days398
Addl Days Granted0
Working Days Charged365
Percent Time Used91
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC. (7.14)
TRP CONSTRUCTION GROUP, LLC (2.30)
LONE STAR PAVING, INC. (47.54)
Contract #11143219
Totals5894316.378849.654759741.0780.7

CountyTRAVIS
HighwayFM 969
FromTANNEHILL LANE
ToFM 3177
CSJ1186-01-089
Proj IDSTP 2016(636)
Work TypeMILL, SEAL & TY D OVERLAY
 
2.0511000145.831163820.2799.9
CountyTRAVIS
HighwayFM 969
FromAIRPORT BLVD
ToTANNEHILL LN
CSJ1186-01-093
Proj IDSTP 2016(853)
Work TypeMILL,SEAL & OVERLAY
 
2.0831067405.851012004.1094.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days38
Addl Days Granted0
Working Days Charged40
Percent Time Used105
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-089
FLASHER EQUIPMENT COMPANY (0.16)
ROADWAY SPECIALTIES, INC. (2.65)
CHEROKEE SERVICES (1.86)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.20)
TRP CONSTRUCTION GROUP, LLC (4.29)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.41)
Contract #03163028
Totals2067551.680.002175824.3799.9

CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-090
Proj IDPTF 2017(143)
Work TypeREHAB ROADWAY; ADD TWLTL & SHLDRS
 
2.1944540893.020.000.0
CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-096
Proj IDROW 1186-1-96
Work TypeUTILITY ADJUSTMENTS
 
2.1942107410.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days321
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173041
Totals6648303.620.000.000.0

CountyTRAVIS
HighwayFM 973
From1.2 MILES N OF THE COLORADO RIVER
ToSH 71
CSJ1200-03-028
Proj IDBR 2013(930)
Work TypeREPLACE BRIDGE & APPROACHES
 
1.53011659867.5411875008.4899.9
CountyTRAVIS
HighwayFM 973
From1.2 MILES N OF THE COLORADO RIVER
ToSH 71
CSJ1200-03-048
Proj IDSTP 2012(591)
Work TypeROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.5302188836.252248824.7299.9
Work Order02-13-14
Work Began05-19-14
Work Completed
Time Computed05-19-14
Contract Working Days296
Addl Days Granted36
Working Days Charged349
Percent Time Used105
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15)
C4 CONSTRUCTION SERVICES, LLC (0.88)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.67)
LINDAMOOD DEMOLITION, INC. (0.95)
MURRAY CONSTRUCTION (0.13)
ROADWAY SPECIALTIES, INC. (1.54)
M & M STRIPING & POWER WASHING, LLC (0.43)
AARON CONCRETE CONTRACTORS, L.P. (0.81)
AUSTIN WOOD RECYCLING (0.28)
BRYANT & FREY CONSTRUCTION (1.50)
TEX OP CONSTRUCTION, LP (0.14)
APAC-TEXAS, INC. (11.02)
CP REBAR AND PT INSTALLATION (0.46)
PRIMATE CONSTRUCTION, INC. (0.12)
MCKINNEY DRILLING COMPANY (2.77)
TEXAS HIGHWAY WALLS (3.63)
PANTHER CREEK TRANSPORTATION, INC. (0.89)
Contract #12133203
Totals13848703.7954674.2914123833.2099.9

CountyWILLIAMSON
HighwayFM 487
FromIH35
ToBELL COUNTY LINE
CSJ1201-02-018
Proj IDSTP 2015(737)
Work TypeREHAB RDWY
 
4.2126851307.425846575.0885.3
CountyWILLIAMSON
HighwayFM 487
FromIH35
ToBELL COUNTY LINE
CSJ1201-02-020
Proj IDROW 1201-2-20
Work TypeROW ACQ & UTIL ADJ
 
4.212286200.00287010.6699.9
Work Order10-20-15
Work Began01-11-16
Work Completed
Time Computed11-19-15
Contract Working Days263
Addl Days Granted0
Working Days Charged245
Percent Time Used93
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-018
TRP CONSTRUCTION GROUP, LLC (0.95)
RAMMING PAVING COMPANY (11.19)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.34)
ACTION SERVICES (0.12)
R K STEPHENS CONSTRUCTION, LLC (6.55)
Contract #03153230
Totals7137507.42231625.986133585.7485.9

CountyWILLIAMSON
HighwayFM 487
FromSH 195
To1500 FEET WEST OF CR 233
CSJ1201-02-019
Proj IDSTP 2014(420)
Work TypeREHAB RDWY
 
5.3036128687.876506119.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-14
Work Began06-25-14
Work Completed
Time Computed05-02-14
Contract Working Days287
Addl Days Granted8
Working Days Charged290
Percent Time Used98
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40)
AUSTIN WOOD RECYCLING (1.19)
TEXAS HIGHWAY WALLS (5.57)
R K STEPHENS CONSTRUCTION, LLC (3.21)
D. I. J. CONSTRUCTION, INC. (0.77)
J & M CONTRACTING, COMPANY (7.41)
ROADWAY SPECIALTIES, INC. (2.24)
SAN-ANN-CO., INC. (0.55)
LONE STAR PAVING CO. (10.66)
INDUS CONSTRUCTION, L.P. (0.07)
Contract #02143227
Totals6128687.870.006506119.6299.9

CountyWILLIAMSON
HighwayFM 487
From1500 FEET WEST OF CR 233
ToIH 35
CSJ1201-02-021
Proj IDSTP 2015(190)
Work TypeREHAB RDWY
 
7.1869058441.298383124.3492.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began02-09-15
Work Completed
Time Computed01-21-15
Contract Working Days306
Addl Days Granted21
Working Days Charged327
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-021
AARON CONCRETE CONTRACTORS, L.P. (5.81)
D&S TEXAS ICON CONSTRUCTION, LLC (3.67)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.67)
FLASHER EQUIPMENT COMPANY (0.26)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.45)
R K STEPHENS CONSTRUCTION, LLC (4.64)
TRP CONSTRUCTION GROUP, LLC (1.39)
CHANDLER CONCRETE, INC. (2.57)
AUSTIN FORMULA UTILITIES (0.31)
EGGEMEYER LAND CLEARING, LLC (0.68)
Contract #10143016
Totals9058441.290.008383124.3492.5

CountyWILLIAMSON
HighwayFM 972
FromIH 35
To0.128 MILES WEST OF CR 150
CSJ1202-01-017
Proj IDSTP 1502(073)
Work TypeREHAB PVMT, ADD SHLDR & SAFTY TREAT
 
3.1984156413.833906524.8993.9
Work Order11-24-15
Work Began01-04-16
Work Completed
Time Computed01-04-16
Contract Working Days234
Addl Days Granted0
Working Days Charged195
Percent Time Used83
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-017
APAC-TEXAS, INC. (8.51)
ROADWAY SPECIALTIES, INC. (3.02)
TRP CONSTRUCTION GROUP, LLC (0.98)
Contract #09153204
Totals4156413.83166680.363906524.8993.9

CountyTRAVIS
HighwayRM 1431
FromBURNET COUNTY LINE
ToBAR K RANCH RD IN LAGO VISTA
CSJ1378-01-036
Proj IDSTP 1602(494)HES
Work TypeIMPROVE GUARDRAIL&SFTY TRT FIXED OB
 
9.9731136825.40441540.7838.8
Work Order09-22-16
Work Began11-28-16
Work Completed
Time Computed11-21-16
Contract Working Days99
Addl Days Granted0
Working Days Charged31
Percent Time Used31
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1378-01-036
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
RPV CONSTRUCTION (39.22)
BMP SPECIALIST, LLC (1.35)
Contract #08163045
Totals1136825.40249465.15441540.7838.8

CountyWILLIAMSON
HighwayRM 1431
FromFM 734
ToCR 175
CSJ1378-02-036
Proj IDPTF 2014(560)
Work TypeWIDEN TO 6-LANE URBAN ROADWAY
 
1.49117353255.7519506728.6399.9
Work Order06-05-14
Work Began08-17-14
Work Completed
Time Computed06-21-14
Contract Working Days269
Addl Days Granted150
Working Days Charged419
Percent Time Used100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48)
ABC EROSION CONTROL, INC. (0.65)
AUSTIN WOOD RECYCLING (0.11)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.30)
FLASHER EQUIPMENT COMPANY (1.47)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06)
GK CONSTRUCTION, LLC (0.07)
KELLYSTONE, INC (0.94)
ROADWAY SPECIALTIES, INC. (2.95)
ROYAL VISTA INC. (16.40)
VOGES DRILLING CO. (0.14)
TEXAS CUTTING & CORING, INC. (0.03)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.25)
SCOTT DERR PAINTING CO, LLC (0.02)
SPEEDY PAVING (0.99)
PRIMATE CONSTRUCTION, INC. (0.02)
Contract #04143201
Totals17353255.75180988.2019506728.6399.9

CountyWILLIAMSON
HighwayRM 1431
FromCOTTONWOOD CREEK TR
ToMARKET STREET
CSJ1378-02-038
Proj IDC 1378-2-38
Work TypeWIDEN TO 6-LN DIVIDED ROADWAY
 
1.14212847144.690.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days333
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163003
Totals12847144.690.000.000.0

CountyWILLIAMSON
HighwayRM 1431
FromANDERSON MILL RD
To600 FT WEST OF 183A
CSJ1378-02-039
Proj IDC 1378-2-39
Work TypeINNOVATIVE INTERSECTION IMPROVEMNTS
 
1.4173965954.634245810.9299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-13
Work Began03-05-14
Work Completed
Time Computed01-12-14
Contract Working Days108
Addl Days Granted72
Working Days Charged175
Percent Time Used97
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-039
PERFORMANCE EQUIPMENT (0.15)
RAMMING PAVING COMPANY (40.83)
ROADWAY SPECIALTIES, INC. (0.58)
FLASHER EQUIPMENT COMPANY (4.37)
G. CARTER CONSTRUCTION COMPANY, INC. (7.73)
Contract #08133073
Totals3965954.630.004245810.9299.9

CountyWILLIAMSON
HighwayRM 1431
From1000 WEST OF CHANDLER CREEK
To200 EAST OF UNIVERSITY OAKS BLVD.
CSJ1378-02-040
Proj IDSTP 2013(297)
Work TypeCONST DIVERGING DIAMOND INTRSCTN
 
0.3926684011.977371431.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-14
Work Began10-20-14
Work Completed
Time Computed08-29-14
Contract Working Days177
Addl Days Granted25
Working Days Charged202
Percent Time Used100
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-040
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
ROADWAY SPECIALTIES, INC. (5.23)
CHEROKEE SERVICES (0.32)
SPEEDY PAVING (1.10)
TEXAS TRUCKING COMPANY, INC. (0.95)
EARTH REINFORCEMENT SPECIALISTS (4.83)
VOGES DRILLING (0.40)
FLASHER EQUIPMENT COMPANY (1.16)
APAC-TEXAS, INC. (FORT WORTH) (21.11)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (12.44)
Contract #06143242
Totals6684011.970.007371431.9699.9

CountyBURNET
HighwayRM 1431
From0.155 MI WEST OF RM 1980
To0.084 MI WEST OF PHILLIPS RANCH RD
CSJ1378-04-048
Proj IDSTP 1602(491)
Work TypeMILL, SEAL AND OVERLAY
 
6.4541437078.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-04-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163209
Totals1437078.590.000.000.0

CountyWILLIAMSON
HighwayFM 3406
From0.13 MI. EAST OF WYOMING SPRINGS DR
To0.05 MI. WEST OF GTRR
CSJ1378-06-011
Proj IDSTP 2015(882)
Work TypeWIDEN TO 5-LANE WITH CENTER LTL
 
1.2904776174.804916312.5399.9
Work Order06-04-15
Work Began07-30-15
Work Completed
Time Computed07-05-15
Contract Working Days260
Addl Days Granted26
Working Days Charged284
Percent Time Used99
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 1378-06-011
ENVIRONMENTAL SAFETY SERVICES, INC. (7.01)
BEAIRD DRILLING (0.56)
FARR FOUNDATION, INC. (3.11)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.64)
FLASHER EQUIPMENT COMPANY (1.66)
APAC-TEXAS, INC. (14.93)
KRL CONSTRUCTION INC. (0.80)
M.G. DRILLING (0.12)
VIKING FENCE CO, LTD. (0.22)
Contract #04153233
Totals4776174.8070035.604916312.5399.9

CountyLEE
HighwayFM 1624
FromSL 123
ToUS 77
CSJ1537-01-016
Proj IDSTP 1602(496)HES
Work TypeIMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
17.8641148468.60343164.0029.8
Work Order09-26-16
Work Began12-14-16
Work Completed
Time Computed11-25-16
Contract Working Days108
Addl Days Granted0
Working Days Charged23
Percent Time Used21
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1537-01-016
D & D ENTERPRISES (22.75)
Contract #08163047
Totals1148468.60255108.00343164.0029.8

CountyHAYS
HighwayFM 1626
FromFM 2770
ToIH 35
CSJ1539-03-001
Proj IDSTP 2017(322)
Work TypeREPAIR AND OVERLAY
 
2.9951037967.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1539-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173033
Totals1037967.600.000.000.0

CountyHAYS
HighwayRM 1826
FromAT DARDEN HILL RD
To.
CSJ1754-02-019
Proj IDCC 1754-2-19
Work TypeADD TURN LANES & SHOULDERS
 
0.365746842.80778356.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began02-02-15
Work Completed
Time Computed01-21-15
Contract Working Days129
Addl Days Granted0
Working Days Charged116
Percent Time Used89
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-019
ENVIRONMENTAL SAFETY SERVICES, INC. (4.64)
LONE STAR PAVING COMPANY (39.74)
TRP CONSTRUCTION GROUP, LLC (4.37)
ROADWAY SPECIALTIES, INC. (24.40)
Contract #10143210
Totals746842.800.00778356.5799.9

CountyHAYS
HighwayRM 1826
FromTRAVIS COUNTY LINE
ToNUTTY BROWN ROAD
CSJ1754-02-025
Proj IDSTP 1502(597)
Work TypeGRADING, BASE, ACP & PVMNT MARKINGS
 
2.1864013235.581590780.6439.6
Work Order01-22-16
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days252
Addl Days Granted0
Working Days Charged211
Percent Time Used83
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-025
A BROTHERS MILLING, LLC (0.85)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57)
FLASHER EQUIPMENT COMPANY (0.35)
RAMMING PAVING COMPANY (52.04)
ROADWAY SPECIALTIES, INC. (6.33)
Contract #08153029
Totals4013235.58105124.621590780.6439.6

CountyHAYS
HighwayRM 967
FromCOLE SPRING ROAD
ToFM 1626
CSJ1776-01-032
Proj IDSTP 2013(655)
Work TypeADD TWLTL AND SHOULDERS
 
2.6184408237.864311103.4298.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-14
Work Began09-08-14
Work Completed
Time Computed09-08-14
Contract Working Days227
Addl Days Granted66
Working Days Charged328
Percent Time Used111
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
ALTUS TRAFFIC MANAGEMENT LLC (0.41)
AUSTIN WOOD RECYCLING (1.86)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.21)
FLASHER EQUIPMENT COMPANY (0.45)
FUQUAY, INC. (1.42)
RAMMING PAVING COMPANY (32.68)
ROADWAY SPECIALTIES, INC. (1.40)
Contract #05143014
Totals4408237.860.004311103.4298.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7