Monthly State Let Construction Report For Austin District As Of Jul 11, 2014 Page 6 Of 8

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway VA
From VARIOUS LOCATIONS IN TRAVIS COUNTY
To ON IH 35 AND ON US 183
CSJ 0914-04-269
Proj ID STP 2012(551)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 775000.00 0.00 669177.84 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 08-13-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 98
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05123049
Totals 775000.00 0.00 669177.84 86.3

CountyWILLIAMSON
Highway CR
From ON CR 111 AT NORTH FORK MCNUTT CRK
To (STR AA0535001)
CSJ 0914-05-142
Proj ID BR 1102(561)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.087 609359.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-14
Work Began 00-00-00
Work Completed  
Time Computed 06-06-14
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-142
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143229
Totals 609359.30 0.00 0.00 0.0

CountyGILLESPIE
Highway CR
From ON OLD SAN ANTONIO AT PEDERNALES
To STR AA0119002
CSJ 0914-19-022
Proj ID BR 2012(703)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.500 2659843.09 192169.41 539651.75 20.2
Work Order 04-09-14
Work Began 05-05-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 623
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 4
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68%)
ALLEN KELLER COMPANY ( 24.37%)
J R RAMON, INC.(2.72%)
JUST GROOVING, LTD.(0.22%)
ROADWAY SPECIALTIES, INC.(4.79%)
FLASHER EQUIPMENT COMPANY(0.72%)
MESA ROD BUSTERS, INC. (0.25%)
Contract # 02143012
Totals 2659843.09 192169.41 539651.75 20.2

CountyLEE
Highway CR
From ON CR 306 AT MIDDLE YEGUA CREEK
To STR AA01-24-001
CSJ 0914-21-029
Proj ID BR 2012(236)
Work Type REPLACE BRIDGE & APPROACHES
 
0.059 255411.33 0.00 181804.10 99.9
CountyLEE
Highway CR
From ON CR 113 AT ELM CREEK
To STR AA00-34-001
CSJ 0914-21-030
Proj ID BR 2012(235)
Work Type REPLACE BRIDGE & APPROACHES
 
0.072 314588.67 0.00 305693.15 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-02-13
Work Began 08-19-13
Work Completed  
Time Computed 08-18-13
Contract Working Days 98
Addl Days Granted 23
Working Days Charged 181
Percent Time Used 149
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029
ROADWAY SPECIALTIES, INC.(3.59%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.08%)
BATTEN DRILLING, INC.(7.56%)
JIM"S SAND & GRAVEL(2.05%)
LONE STAR PAVING CO. (5.98%)
Contract # 05133025
Totals 570000.00 0.00 487497.25 99.1

CountyCALDWELL
Highway CR
From ON OAK GROVE RD AT W FORK PLUM CRK
To (STR AA02-28-001)
CSJ 0914-22-056
Proj ID BR 2013(195)
Work Type REPLACE BRIDGE & APPROACHES
 
0.155 656797.82 0.00 0.00 0.0
CountyCALDWELL
Highway CR
From ON OAK GROVE ROAD (CR 127) @
To TRIBUTARY TO WEST FORK PLUM CREEK
CSJ 0914-22-062
Proj ID CC 914-22-62
Work Type REPLACE STRUCTURE & APPROACHES
 
0.051 160259.62 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-22-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143036
Totals 817057.44 0.00 0.00 0.0

CountyLLANO
Highway CR
From ON CR 216 AT BOARD BRANCH
To STR AA0552001
CSJ 0914-25-006
Proj ID BR 2011(981)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 226113.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143026
Totals 226113.43 0.00 0.00 0.0

CountyHAYS
Highway CR
From ON CR 266 AT SAN MARCOS RIVER
To STR AA02-24-001
CSJ 0914-33-035
Proj ID BR 2005(711)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 576253.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-14
Work Began 00-00-00
Work Completed  
Time Computed 07-27-14
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143214
Totals 576253.11 0.00 0.00 0.0

CountyHAYS
Highway VA
From VARIOUS LOCATIONS IN HAYS COUNTY
To ON IH 35 AND SH 80
CSJ 0914-33-063
Proj ID STP 2012(552)
Work Type LANDSCAPE AND IRRIGATION
 
0.100 467144.80 7311.80 460742.81 98.6
Work Order 06-14-12
Work Began 07-09-12
Work Completed  
Time Computed 07-09-12
Contract Working Days 72
Addl Days Granted 6
Working Days Charged 78
Percent Time Used 100
Contractor(s)
LANDSCAPE CONTRACTING AND IRRIGATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063
LONE STAR TRAFFIC SERVICE, INC.(1.37%)
TERRY PRATHER( 16.78%)
Contract # 05123226
Totals 467144.80 7311.80 460742.81 98.6

CountyBLANCO
Highway RM 165
From SL 163
To HAYS C/L
CSJ 0954-02-016
Proj ID STP 2012(553)HRR
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
11.900 816534.84 5748.48 860945.26 99.9
CountyBLANCO
Highway RM 165
From SL 163
To BLANCO/HAYS COUNTY LINE
CSJ 0954-02-017
Proj ID STP 2012(553)HRR
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
11.949 4792086.66 191099.46 4030168.64 86.4
Work Order 07-12-12
Work Began 10-02-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 261
Addl Days Granted 57
Working Days Charged 418
Percent Time Used 131
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017
HIGHWAY TECHNOLOGIES, INC. (1.93%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%)
ABC EROSION CONTROL, INC.(0.72%)
AUSTIN WOOD RECYCLING(1.45%)
JMHP, INC. (0.85%)
Contract # 05123212
Totals 5608621.50 196847.94 4891113.90 89.2

CountyGILLESPIE
Highway RM 783
From US 290
To 8.977 MI S OF US 290
CSJ 1135-01-026
Proj ID STP 2013(028)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
8.977 5106864.29 26578.50 3765831.46 76.5
Work Order 04-03-13
Work Began 04-15-13
Work Completed  
Time Computed 04-15-13
Contract Working Days 229
Addl Days Granted 0
Working Days Charged 297
Percent Time Used 129
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026
ROADWAY SPECIALTIES, INC.(3.51%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%)
RELMCO, INC. ( 31.14%)
D. I. J. CONSTRUCTION, INC.(1.16%)
VOGES DRILLING CO. (1.08%)
LONE STAR PAVING COMPANY (2.40%)
Contract # 02133212
Totals 5106864.29 26578.50 3765831.46 76.5

CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-028
Proj ID BR 2013(930)
Work Type REPLACE BRIDGE & APPROACHES
 
1.530 11659867.54 1294523.81 1296949.31 11.1
CountyTRAVIS
Highway FM 973
From 1.2 MILES N OF THE COLORADO RIVER
To SH 71
CSJ 1200-03-048
Proj ID STP 2012(591)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.530 2188836.25 4367.60 4367.60 0.1
Work Order 02-13-14
Work Began 05-19-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 296
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 6
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-028
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
C4 CONSTRUCTION SERVICES, LLC(0.88%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.67%)
LINDAMOOD DEMOLITION, INC. (0.95%)
MURRAY CONSTRUCTION(0.13%)
ROADWAY SPECIALTIES, INC.(1.54%)
M & M STRIPING & POWER WASHING, LLC(0.43%)
AARON CONCRETE CONTRACTORS, L.P. (0.81%)
AUSTIN WOOD RECYCLING(0.28%)
BRYANT & FREY CONSTRUCTION (1.50%)
TEX OP CONSTRUCTION, LP(0.14%)
APAC-TEXAS, INC. ( 11.02%)
CP REBAR AND PT INSTALLATION (0.46%)
PRIMATE CONSTRUCTION, INC. (0.12%)
MCKINNEY DRILLING COMPANY(2.77%)
TEXAS HIGHWAY WALLS(3.63%)
Contract # 12133203
Totals 13848703.79 1298891.41 1301316.91 9.3

CountyTRAVIS
Highway FM 973
From 3880 FT SOUTH OF SH 71
To FM 812
CSJ 1200-03-046
Proj ID STP 2014(621)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
3.418 4060301.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-29-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143030
Totals 4060301.69 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-016
Proj ID STP 2014(559)
Work Type ADD SHOULDERS, REPAIR & OVERLAY
 
2.466 3060816.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143018
Totals 3060816.52 0.00 0.00 0.0

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-017
Proj ID STP 2013(477)
Work Type PVMT REPAIR, SEAL & THIN OVERLAY
 
2.481 742733.15 0.00 680825.94 91.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 03-03-14
Work Completed  
Time Computed 07-22-13
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 21
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-017
FLASHER EQUIPMENT COMPANY(4.96%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
ROADWAY SPECIALTIES, INC.(0.13%)
Contract # 03133014
Totals 742733.15 0.00 680825.94 91.6

CountyTRAVIS
Highway SH 45
From AT KENDRICK BLVD
To .
CSJ 1200-06-007
Proj ID STP 2013(931)
Work Type INSTALL LTL & PAVED SHOULDERS
 
0.208 540496.95 15450.80 521349.59 96.4
Work Order 01-06-14
Work Began 03-03-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 96
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-007
FLASHER EQUIPMENT COMPANY(5.78%)
N-LINE TRAFFIC MAINTENANCE, L.P. (3.13%)
LONE STAR PAVING CO. ( 53.50%)
ABC EROSION CONTROL, INC.(1.08%)
Contract # 08133265
Totals 540496.95 15450.80 521349.59 96.4

CountyTRAVIS
Highway SH 45
From LOOP 1
To RM 1826
CSJ 1200-06-010
Proj ID STP 2014(724)
Work Type MILL, SEAL & THIN OVERLAY
 
2.599 1283793.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143028
Totals 1283793.90 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 172906.39 172906.39 2.8
Work Order 04-16-14
Work Began 00-00-00
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143227
Totals 6128687.87 172906.39 172906.39 2.8

CountyWILLIAMSON
Highway FM 487
From BELL C/L
To BELL C/L IN BARTLETT
CSJ 1201-03-021
Proj ID STP 2012(417)
Work Type PAVMNT RESTORATION AND ADD SHLDRS
 
7.520 6421595.35 281061.06 3206533.80 49.9
CountyBELL
Highway FM 487
From WILLIAMSON CO LINE W OF FM 2115
To WILLIAMSON CO LINE E OF FM 2115
CSJ 1201-05-010
Proj ID STP 2012(423)
Work Type PAV RESTORATION AND ADD SHOULDERS
 
0.395 285832.17 6420.00 283832.95 99.3
Work Order 05-04-12
Work Began 05-20-13
Work Completed  
Time Computed 05-20-12
Contract Working Days 391
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 53
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
SILVA CONTRACTING COMPANY, INC.( 11.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%)
MURRAY CONSTRUCTION(0.48%)
D. I. J. CONSTRUCTION, INC.(1.28%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%)
JAG TRUCKING INC (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
THE LEVY COMPANY, L.P. (0.25%)
R K STEPHENS CONSTRUCTION, LLC (6.66%)
Contract # 03123002
Totals 6707427.52 287481.06 3490366.75 52.0

CountyWILLIAMSON
Highway FM 972
From 0.652 MI E OF FM 1105
To 0.841 MI E OF FM 1105
CSJ 1202-01-016
Proj ID BR 2013(932)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.189 535693.01 0.00 565531.14 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-13
Work Began 01-16-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 91
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-016
GK CONSTRUCTION, LLC (1.06%)
BEAIRD DRILLING(4.90%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.46%)
ROADWAY SPECIALTIES, INC.(2.84%)
RAMMING PAVING COMPANY (8.93%)
D. I. J. CONSTRUCTION, INC.(1.12%)
Contract # 08133270
Totals 535693.01 0.00 565531.14 99.9

CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK
To (STR 1202-3-12)
CSJ 1202-03-010
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.115 643228.90 94142.97 144392.97 22.4
CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK RELIEF
To (STR 1202-3-11)
CSJ 1202-03-011
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 286828.45 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1063
From AT DRAW
To (STR 1202-3-10)
CSJ 1202-03-012
Proj ID BR 2014(673)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 609386.85 144860.60 144860.60 23.7
Work Order 04-25-14
Work Began 05-19-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 14
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-010
FLASHER EQUIPMENT COMPANY(1.52%)
GK CONSTRUCTION, LLC (0.78%)
HOUSTON SAWING & DRILLING(0.23%)
ROADWAY SPECIALTIES, INC.(0.62%)
APAC-TEXAS, INC. (9.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.81%)
Contract # 03143222
Totals 1539444.20 239003.57 289253.57 18.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8