|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | TRAVIS |
| Highway |
VA |
| From |
SAFE ROUTES TO SCHOOL-COUNTYLINE RD |
| To |
NEIDIG ELEM & ELGIN H.S. |
| CSJ |
0914-00-326 |
| Proj ID |
STP 1102(490)SRS |
| Work Type |
CONSTRUCT SIDEWALKS |
| |
|
0.445 |
397507.33 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-13-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-29-13 |
| Contract Working Days |
48 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BEAR CREEK CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-326 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133023 |
|
Totals |
397507.33 |
0.00 |
0.00 |
0.0 |
|
| County | TRAVIS |
| Highway |
VA |
| From |
VARIOUS ON-SYS LOCATIONS |
| To |
DISTRICTWIDE |
| CSJ |
0914-00-345 |
| Proj ID |
NH 2012(379) |
| Work Type |
SCHOOL ZONE UPGRADES |
| |
|
0.100 |
287731.00 |
26906.24 |
247143.32 |
85.8 |
| Work Order |
04-16-12 |
| Work Began |
12-03-12 |
| Work Completed |
|
| Time Computed |
07-15-12 |
| Contract Working Days |
102 |
| Addl Days Granted |
0 |
| Working Days Charged |
65 |
| Percent Time Used |
63 |
| Contractor(s) |
| SIEMENS INDUSTRY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-345 CODY DRILLING(5.44%) ESA ENGINEERING, LLC (5.05%)
|
| Contract # |
03123023 |
|
Totals |
287731.00 |
26906.24 |
247143.32 |
85.8 |
|
| County | TRAVIS |
| Highway |
CS |
| From |
ON OLD MANOR RD AT TANNEHILL BRANCH |
| To |
STR B021-07-001 |
| CSJ |
0914-04-187 |
| Proj ID |
BR 2002(468) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.001 |
948392.97 |
0.00 |
921369.93 |
97.1 |
| County | TRAVIS |
| Highway |
CS |
| From |
ON OLD MANOR RD AT TANNEHILL BRANCH |
| To |
STR B021-07-001 |
| CSJ |
0914-04-262 |
| Proj ID |
RW 914-4-262 |
| Work Type |
ROW UTL. ADJ. |
| |
|
0.001 |
328656.38 |
0.00 |
287575.00 |
87.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-14-11 |
| Work Began |
11-07-11 |
| Work Completed |
|
| Time Computed |
09-30-11 |
| Contract Working Days |
237 |
| Addl Days Granted |
0 |
| Working Days Charged |
237 |
| Percent Time Used |
100 |
| Contractor(s) |
| CAPITAL EXCAVATION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-187 AUSTIN WOOD RECYCLING(1.47%) BRYANT & FREY CONSTRUCTION (9.50%) EW WELLS GROUP LLC ( 15.66%) F & W ELECTRICAL CONTRACTORS, INC. (3.07%) HIGHWAY TECHNOLOGIES, INC. ( 11.47%) J.D. RAMMING PAVING CO., LTD.(3.92%) ROADWAY SPECIALTIES, INC.(3.59%) S & S PAINTING (0.21%) VOGES DRILLING (4.44%) SITESAFE PRODUCTS TEXAS(1.01%)
|
| Contract # |
08113023 |
|
Totals |
1277049.35 |
0.00 |
1208944.93 |
94.6 |
|
| County | TRAVIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN TRAVIS COUNTY |
| To |
. |
| CSJ |
0914-04-268 |
| Proj ID |
STP 2012(055) |
| Work Type |
CONSTRUCT CURB RAMPS |
| |
|
0.100 |
1195085.00 |
0.00 |
1571173.89 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-07-11 |
| Work Began |
03-19-12 |
| Work Completed |
|
| Time Computed |
12-06-11 |
| Contract Working Days |
213 |
| Addl Days Granted |
0 |
| Working Days Charged |
171 |
| Percent Time Used |
80 |
| Contractor(s) |
| TI-ZACK CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-268 HIGHWAY TECHNOLOGIES, INC. (0.58%) FUQUAY, INC. (4.69%) FAASS TRUCKING, INC. (0.00%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.75%)
|
| Contract # |
08113047 |
|
Totals |
1195085.00 |
0.00 |
1571173.89 |
99.9 |
|
| County | TRAVIS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN TRAVIS COUNTY |
| To |
ON IH 35 AND ON US 183 |
| CSJ |
0914-04-269 |
| Proj ID |
STP 2012(551) |
| Work Type |
LANDSCAPE AND IRRIGATION |
| |
|
0.100 |
775000.00 |
4294.25 |
653817.18 |
84.3 |
| Work Order |
07-12-12 |
| Work Began |
08-13-12 |
| Work Completed |
|
| Time Computed |
08-13-12 |
| Contract Working Days |
105 |
| Addl Days Granted |
0 |
| Working Days Charged |
103 |
| Percent Time Used |
98 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-269 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05123049 |
|
Totals |
775000.00 |
4294.25 |
653817.18 |
84.3 |
|
| County | WILLIAMSON |
| Highway |
CR |
| From |
ON CR 351 AT DONAHOE CREEK |
| To |
(STR AA02-90-002) |
| CSJ |
0914-05-172 |
| Proj ID |
BR 1102(528) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.066 |
596333.03 |
0.00 |
659926.73 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-12-12 |
| Work Began |
08-06-12 |
| Work Completed |
|
| Time Computed |
07-28-12 |
| Contract Working Days |
115 |
| Addl Days Granted |
0 |
| Working Days Charged |
85 |
| Percent Time Used |
73 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-172 BEAIRD DRILLING(1.82%) ENVIRONMENTAL SAFETY SERVICES, INC.(4.00%) A & R DEMOLITION (0.58%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.10%) RAMMING PAVING COMPANY (1.71%) RICE ENVIRONMENTAL SERVICES( 27.08%) BREDA COMPANY, INC.(0.55%) GK CONSTRUCTION, LLC (0.05%)
|
| Contract # |
05123052 |
|
Totals |
596333.03 |
0.00 |
659926.73 |
99.9 |
|
| County | LEE |
| Highway |
PW |
| From |
AT LAKE SOMMERVILLE SP, NAILS CRK |
| To |
. |
| CSJ |
0914-21-027 |
| Proj ID |
C 914-21-27 |
| Work Type |
PAVE VARIOUS ROADS / PARKING AREAS |
| |
|
0.001 |
725104.15 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-10-13 |
| Work Began |
05-06-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
56 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-027 N-LINE TRAFFIC MAINTENANCE, L.P. (3.01%) CEN TEX HYDROSEED, INC.(0.20%) PEDRO CARLOS CONSTRUCTION CO.(1.01%)
|
| Contract # |
02133012 |
|
Totals |
725104.15 |
0.00 |
0.00 |
0.0 |
|
| County | LEE |
| Highway |
CR |
| From |
ON CR 306 AT MIDDLE YEGUA CREEK |
| To |
STR AA01-24-001 |
| CSJ |
0914-21-029 |
| Proj ID |
BR 2012(236) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.059 |
255411.33 |
0.00 |
0.00 |
0.0 |
| County | LEE |
| Highway |
CR |
| From |
ON CR 113 AT ELM CREEK |
| To |
STR AA00-34-001 |
| CSJ |
0914-21-030 |
| Proj ID |
BR 2012(235) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.072 |
314588.67 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
98 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LEGENDS LANDSCAPES LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0914-21-029 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133025 |
|
Totals |
570000.00 |
0.00 |
0.00 |
0.0 |
|
| County | HAYS |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN HAYS COUNTY |
| To |
ON IH 35 AND SH 80 |
| CSJ |
0914-33-063 |
| Proj ID |
STP 2012(552) |
| Work Type |
LANDSCAPE AND IRRIGATION |
| |
|
0.100 |
467144.80 |
0.00 |
392582.11 |
84.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-14-12 |
| Work Began |
07-09-12 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
72 |
| Addl Days Granted |
6 |
| Working Days Charged |
78 |
| Percent Time Used |
100 |
| Contractor(s) |
| LANDSCAPE CONTRACTING AND IRRIGATION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-063 LONE STAR TRAFFIC SERVICE, INC.(1.37%) TERRY PRATHER( 16.78%)
|
| Contract # |
05123226 |
|
Totals |
467144.80 |
0.00 |
392582.11 |
84.0 |
|
| County | BLANCO |
| Highway |
RM 165 |
| From |
SL 163 |
| To |
HAYS C/L |
| CSJ |
0954-02-016 |
| Proj ID |
STP 2012(553)HRR |
| Work Type |
GUARDRAIL & SAFETY TREAT FIXED OBJCTS |
| |
|
11.900 |
816534.84 |
49955.09 |
609989.01 |
74.7 |
| County | BLANCO |
| Highway |
RM 165 |
| From |
SL 163 |
| To |
BLANCO/HAYS COUNTY LINE |
| CSJ |
0954-02-017 |
| Proj ID |
STP 2012(553)HRR |
| Work Type |
PROVIDE ADDITIONAL PAVED SURFACE WI |
| |
|
11.949 |
4792086.66 |
174187.09 |
1570170.27 |
32.7 |
| Work Order |
07-12-12 |
| Work Began |
10-02-12 |
| Work Completed |
|
| Time Computed |
09-10-12 |
| Contract Working Days |
261 |
| Addl Days Granted |
6 |
| Working Days Charged |
137 |
| Percent Time Used |
51 |
| Contractor(s) |
| DEAN WORD COMPANY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0954-02-017 HIGHWAY TECHNOLOGIES, INC. (1.93%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.76%) ABC EROSION CONTROL, INC.(0.72%) AUSTIN WOOD RECYCLING(1.45%) JMHP, INC. (0.85%)
|
| Contract # |
05123212 |
|
Totals |
5608621.50 |
224142.18 |
2180159.28 |
38.8 |
|
| County | GILLESPIE |
| Highway |
RM 783 |
| From |
US 290 |
| To |
8.977 MI S OF US 290 |
| CSJ |
1135-01-026 |
| Proj ID |
STP 2013(028)HES |
| Work Type |
PROVIDE ADDITIONAL PAVED SURFACE WI |
| |
|
8.977 |
5106864.29 |
169331.09 |
169331.09 |
3.3 |
| Work Order |
04-03-13 |
| Work Began |
04-15-13 |
| Work Completed |
|
| Time Computed |
04-15-13 |
| Contract Working Days |
229 |
| Addl Days Granted |
0 |
| Working Days Charged |
11 |
| Percent Time Used |
4 |
| Contractor(s) |
| ALLEN KELLER COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1135-01-026 ROADWAY SPECIALTIES, INC.(3.51%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.40%) RELMCO, INC. ( 31.14%)
|
| Contract # |
02133212 |
|
Totals |
5106864.29 |
169331.09 |
169331.09 |
3.3 |
|
| County | TRAVIS |
| Highway |
FM 812 |
| From |
SAN JOSE AVE. |
| To |
BASTROP C/L |
| CSJ |
1149-01-025 |
| Proj ID |
STP 2011(687) |
| Work Type |
PAVEMENT REPAIR, SEAL & THIN OVERLAY |
| |
|
5.008 |
1174207.13 |
0.00 |
1688655.48 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-06-10 |
| Work Began |
09-15-11 |
| Work Completed |
|
| Time Computed |
03-06-11 |
| Contract Working Days |
57 |
| Addl Days Granted |
0 |
| Working Days Charged |
57 |
| Percent Time Used |
100 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1149-01-025 HIGHWAY TECHNOLOGIES, INC. (3.92%) ROADWAY SPECIALTIES, INC.(8.61%) PRIMATE CONSTRUCTION, INC. (2.94%)
|
| Contract # |
11103229 |
|
Totals |
1174207.13 |
0.00 |
1688655.48 |
99.9 |
|
| County | TRAVIS |
| Highway |
FM 969 |
| From |
0.30 MI. W. OF HUNTERS BEND RD. |
| To |
HUNTERS BEND RD. |
| CSJ |
1186-01-088 |
| Proj ID |
CC 1186-1-88 |
| Work Type |
ADD DUAL LEFT FROM HUNTERS BEND RD. |
| |
|
0.303 |
398287.40 |
0.00 |
396471.18 |
100.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
07-14-11 |
| Work Began |
09-06-11 |
| Work Completed |
05-10-13 |
| Time Computed |
09-06-11 |
| Contract Working Days |
57 |
| Addl Days Granted |
0 |
| Working Days Charged |
39 |
| Percent Time Used |
68 |
| Contractor(s) |
| AARON CONCRETE CONTRACTORS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-088 APAC-TEXAS, INC. ( 28.09%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. ( 22.90%) HIGHWAY TECHNOLOGIES, INC. (4.74%) ROADWAY SPECIALTIES, INC.(3.69%)
|
| Contract # |
06113234 |
|
Totals |
398287.40 |
0.00 |
396471.18 |
100.0 |
|
| County | TRAVIS |
| Highway |
FM 973 |
| From |
175' S. OF FM 969 |
| To |
1922' S. GREEN GROVE DR |
| CSJ |
1200-03-030 |
| Proj ID |
STP 1102(371) |
| Work Type |
REHABILITATE ROADWAY |
| |
|
2.910 |
1342739.02 |
0.00 |
1435764.47 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-10-11 |
| Work Began |
10-04-11 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
55 |
| Addl Days Granted |
5 |
| Working Days Charged |
58 |
| Percent Time Used |
96 |
| Contractor(s) |
| RAMMING PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1200-03-030 A GREATER AUSTIN DEVELOPMENT COMPANY, LTD. (6.37%) AARON CONCRETE CONTRACTORS, L.P. ( 15.67%) M.V. HENKE ENTERPRISES, INC. (1.40%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.52%) PENNTEX MILLING, LLC (0.61%) RICE ENVIRONMENTAL SERVICES(2.91%) TRP CONSTRUCTION GROUP, LLC(3.62%)
|
| Contract # |
07113037 |
|
Totals |
1342739.02 |
0.00 |
1435764.47 |
99.9 |
|
| County | TRAVIS |
| Highway |
FM 973 |
| From |
FM 812 |
| To |
US 183 |
| CSJ |
1200-05-017 |
| Proj ID |
STP 2013(477) |
| Work Type |
PVMT REPAIR, SEAL & THIN OVERLAY |
| |
|
2.481 |
742733.15 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
102 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HUNTER INDUSTRIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133014 |
|
Totals |
742733.15 |
0.00 |
0.00 |
0.0 |
|
| County | WILLIAMSON |
| Highway |
FM 487 |
| From |
BELL C/L |
| To |
BELL C/L IN BARTLETT |
| CSJ |
1201-03-021 |
| Proj ID |
STP 2012(417) |
| Work Type |
PAVMNT RESTORATION AND ADD SHLDRS |
| |
|
7.520 |
6421595.35 |
0.00 |
49200.00 |
0.7 |
| County | BELL |
| Highway |
FM 487 |
| From |
WILLIAMSON CO LINE W OF FM 2115 |
| To |
WILLIAMSON CO LINE E OF FM 2115 |
| CSJ |
1201-05-010 |
| Proj ID |
STP 2012(423) |
| Work Type |
PAV RESTORATION AND ADD SHOULDERS |
| |
|
0.395 |
285832.17 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-04-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-20-12 |
| Contract Working Days |
391 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021 SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%) SILVA CONTRACTING COMPANY, INC.( 11.18%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%) MURRAY CONSTRUCTION(0.48%) D. I. J. CONSTRUCTION, INC.(1.28%) ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%)
|
| Contract # |
03123002 |
|
Totals |
6707427.52 |
0.00 |
49200.00 |
0.7 |
|
| County | BASTROP |
| Highway |
FM 1100 |
| From |
COUNTY LINE RD. |
| To |
1014 FT WEST OF SH 95 |
| CSJ |
1234-02-011 |
| Proj ID |
STP 1102(492)SRS |
| Work Type |
CONST. SIDEWALKS & CROSSWALKS |
| |
|
1.232 |
657300.75 |
64867.82 |
637635.83 |
97.0 |
| Work Order |
08-20-12 |
| Work Began |
10-15-12 |
| Work Completed |
|
| Time Computed |
09-05-12 |
| Contract Working Days |
100 |
| Addl Days Granted |
26 |
| Working Days Charged |
126 |
| Percent Time Used |
100 |
| Contractor(s) |
| BEAR CREEK CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1234-02-011 D. I. J. CONSTRUCTION, INC.(1.06%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.97%) ROADWAY SPECIALTIES, INC.(2.60%)
|
| Contract # |
07123205 |
|
Totals |
657300.75 |
64867.82 |
637635.83 |
97.0 |
|
| County | TRAVIS |
| Highway |
FM 1325 |
| From |
LP 1 |
| To |
US 183 |
| CSJ |
1376-02-039 |
| Proj ID |
STP 2013(478) |
| Work Type |
MILL, SEAL & THIN OVERLAY |
| |
|
2.500 |
2027036.96 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
50 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RAMMING PAVING COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1376-02-039 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133230 |
|
Totals |
2027036.96 |
0.00 |
0.00 |
0.0 |
|
| County | TRAVIS |
| Highway |
RM 1431 |
| From |
1300' W OF LAGO VISTA W.C.L. |
| To |
800' EAST OF WEST CITY LIMIT |
| CSJ |
1378-01-032 |
| Proj ID |
CC 1378-1-32 |
| Work Type |
ADD LEFT TURN LANE |
| |
|
0.402 |
494228.44 |
800.00 |
800.00 |
0.1 |
| Work Order |
04-03-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-19-13 |
| Contract Working Days |
125 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 1378-01-032 RICE ENVIRONMENTAL SERVICES(2.72%) HIGHWAY TECHNOLOGIES, INC. (8.66%)
|
| Contract # |
02133230 |
|
Totals |
494228.44 |
800.00 |
800.00 |
0.1 |
|
| County | WILLIAMSON |
| Highway |
RM 1431 |
| From |
0.2 MI E OF CR 185 |
| To |
IH 35 |
| CSJ |
1378-02-033 |
| Proj ID |
STP 2012(251) |
| Work Type |
FULL DEPTH REPAIR, SEAL & THIN OV |
| |
|
6.888 |
2895175.70 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-22-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
03-09-12 |
| Contract Working Days |
66 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANGEL BROTHERS ENTERPRISES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-033 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01123226 |
|
Totals |
2895175.70 |
0.00 |
0.00 |
0.0 |
|