Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBURNET
Highway RM 243
From SH 29
To WILLIAMSON C/L
CSJ 0440-04-013
Proj ID STP 2014(719)HES
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
12.534 622587.90 0.00 1004987.03 99.9
CountyBURNET
Highway RM 243
From 0.609 MI N OF SH 29
To 7.923 MI N OF SH 29
CSJ 0440-04-014
Proj ID STP 2014(720)HES
Work Type PROVIDE ADDITIONAL PAVED SURFACE WI
 
7.314 3173322.49 0.00 3509716.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 09-02-14
Work Completed  
Time Computed 08-20-14
Contract Working Days 247
Addl Days Granted 4
Working Days Charged 235
Percent Time Used 93
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0440-04-013
N-LINE TRAFFIC MAINTENANCE, L.P. (0.94%)
ROADWAY SPECIALTIES, INC.(6.58%)
LONE STAR PAVING, INC. ( 13.34%)
D. I. J. CONSTRUCTION, INC.(3.36%)
MPB, INC.( 15.66%)
BRYDL CONTRACTING, INC.(0.05%)
Contract # 06143207
Totals 3795910.39 0.00 4514703.86 99.9

CountyTRAVIS
Highway SH 130
From SH 130 @ FM 812
To .
CSJ 0440-06-014
Proj ID NH 1502(385)
Work Type LANDSCAPING AND IRRIGATION
 
0.100 642322.00 3000.00 583679.50 90.8
Work Order 08-31-15
Work Began 10-26-15
Work Completed  
Time Computed 10-26-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0440-06-014
N-LINE TRAFFIC MAINTENANCE, L.P. (0.70%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 12.85%)
M & M UNDERGROUND CONSTRUCTION (1.08%)
Contract # 07153257
Totals 642322.00 3000.00 583679.50 90.8

CountyCALDWELL
Highway SH 21
From HAYS COUNTY LINE
To BASTROP COUNTY LINE
CSJ 0471-04-029
Proj ID STP 2016(852)
Work Type REPAIR, LEVEL - UP, WIDEN AND OVERLAY
 
5.190 2356387.98 265587.20 1132283.69 48.7
Work Order 04-19-16
Work Began 06-27-16
Work Completed  
Time Computed 05-19-16
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 158
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0471-04-029
EGGEMEYER LAND CLEARING, LLC (2.08%)
FLASHER EQUIPMENT COMPANY(3.30%)
ROADWAY SPECIALTIES, INC.(0.25%)
A BROTHERS MILLING, LLC(3.00%)
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO(3.86%)
Contract # 03163214
Totals 2356387.98 265587.20 1132283.69 48.7

CountyBASTROP
Highway SH 21
From CARDINAL DRIVE
To 0.1 MI. WEST OF US 290
CSJ 0472-01-041
Proj ID STP 1602(367)HES
Work Type CONVERT 4 - LN UNDIV TO MODFD 2_W / SHL
 
5.411 423190.77 185194.98 427130.73 99.9
Work Order 08-05-16
Work Began 08-23-16
Work Completed  
Time Computed 08-23-16
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 73
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0472-01-041
D.I.J. CONSTRUCTION, INC ( 21.55%)
FLASHER EQUIPMENT COMPANY(0.68%)
DIIBS SPECIALISTS(1.04%)
Contract # 06163232
Totals 423190.77 185194.98 427130.73 99.9

CountyMASON
Highway SH 71
From 0.119 MILES SOUTH OF SH 71
To 0.303 MILES EAST OF RM 386
CSJ 0577-01-026
Proj ID STP 2016(898)
Work Type ADD LT TURN LN & ADD RT ACCEL LN
 
0.536 944570.87 236583.50 707149.88 74.8
Work Order 06-17-16
Work Began 07-18-16
Work Completed  
Time Computed 07-17-16
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 49
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0577-01-026
JM YANEZ CONSTRUCTION( 15.61%)
FLASHER EQUIPMENT COMPANY(5.58%)
BMP CONSTRUCTION, INC. (4.02%)
AUSTIN MATERIALS, LLC( 31.23%)
Contract # 04163024
Totals 944570.87 236583.50 707149.88 74.8

CountyMASON
Highway RM 386
From SH 71
To US 87/ SH 29
CSJ 0577-01-028
Proj ID STP 1502(146)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.887 1151527.25 9354.04 1311107.50 99.9
Work Order 07-07-15
Work Began 01-07-16
Work Completed  
Time Computed 09-06-15
Contract Working Days 247
Addl Days Granted 6
Working Days Charged 203
Percent Time Used 80
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0577-01-028
TRP CONSTRUCTION GROUP, LLC(2.97%)
ROADWAY SPECIALTIES, INC.(7.67%)
INCE ENTERPRISES, INC. (9.89%)
Contract # 05153231
Totals 1151527.25 9354.04 1311107.50 99.9

CountyWILLIAMSON
Highway SH 45
From AT PEARSON RANCH ROAD
To .
CSJ 0683-01-085
Proj ID CC 683-1-85
Work Type CONST. SPLIT DIAMOND INTERSECTION
 
0.097 2492120.70 5808.04 2321035.08 93.1
Work Order 08-26-15
Work Began 10-19-15
Work Completed  
Time Computed 09-25-15
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 97
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 0683-01-085
THE LEVY COMPANY, L.P. ( 11.85%)
OLDEN, INC.(2.84%)
FLASHER EQUIPMENT COMPANY(1.03%)
FUQUAY, INC. (1.52%)
BREDA COMPANY, INC.(0.03%)
APAC-TEXAS, INC. ( 11.80%)
Contract # 04153058
Totals 2492120.70 5808.04 2321035.08 93.1

CountyTRAVIS
Highway RM 620
From 500 FT N OF LOHMANS CROSSING RD
To LADERA BLVD.
CSJ 0683-02-063
Proj ID STP 1502(596)
Work Type OPERATIONAL IMPROVEMENTS
 
0.938 1419535.80 376754.11 633524.11 44.6
Work Order 02-08-16
Work Began 09-15-16
Work Completed  
Time Computed 03-09-16
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 56
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0683-02-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153229
Totals 1419535.80 376754.11 633524.11 44.6

CountyTRAVIS
Highway RM 3238
From 0.31 MI W OF SH 71
To RM 12
CSJ 0683-04-018
Proj ID STP 2015(574)
Work Type ADD SHOULDERS AND LEFT TURN LANE
 
6.337 1504303.45 13742.10 1699542.70 99.9
Work Order 03-26-15
Work Began 06-08-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 106
Addl Days Granted 60
Working Days Charged 166
Percent Time Used 100
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-04-018
ALTUS TRAFFIC MANAGEMENT LLC (0.58%)
APAC-TEXAS, INC. ( 30.25%)
AUSTIN WOOD RECYCLING(1.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(6.55%)
FLASHER EQUIPMENT COMPANY(3.59%)
ROADWAY SPECIALTIES, INC.(1.87%)
Contract # 02153022
Totals 1504303.45 13742.10 1699542.70 99.9

CountyHAYS
Highway RM 12
From AT OLD FITZHUGH RD.
To .
CSJ 0683-05-011
Proj ID STP 1502(388)
Work Type INSTALL FLASH BEACON / REALIGN INTER.
 
0.001 232728.36 8930.40 270439.93 99.9
CountyHAYS
Highway RM 12
From 0.25 MI N OF OLD FITZHUGH RD.
To 0.25 MI S OF OLD FITZHUGH RD.
CSJ 0683-05-012
Proj ID STP 1502(387)HES
Work Type ADD CENTER TURN LANE AND SHOULDERS
 
0.560 826750.43 -3742.10 975965.80 99.9
Work Order 10-05-15
Work Began 04-25-16
Work Completed  
Time Computed 11-04-15
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 77
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-05-012
AUSTIN WOOD RECYCLING(1.05%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.83%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.22%)
FLASHER EQUIPMENT COMPANY(4.33%)
LONE STAR PAVING, INC. ( 23.03%)
Contract # 07153036
Totals 1059478.79 5188.30 1246405.73 99.9

CountyWILLIAMSON
Highway SH 45
From WEST OF RATTAN CRK
To MCNEIL ROAD
CSJ 0683-06-027
Proj ID C 683-6-27
Work Type GR, BASE, STRUC, ACP, SGN & PVMT MK
 
1.256 24729960.53 0.00 27977700.86 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-27-11
Work Began 11-08-11
Work Completed  
Time Computed 11-08-11
Contract Working Days 495
Addl Days Granted 142
Working Days Charged 677
Percent Time Used 106
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0683-06-027
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (3.26%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.30%)
AUSTIN WOOD RECYCLING(0.04%)
BEAIRD DRILLING(2.06%)
CARTEL PLACERS, LLC(0.00%)
FLASHER EQUIPMENT COMPANY(0.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.27%)
PRIMATE CONSTRUCTION, INC. (0.16%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(0.80%)
H. L. CHAPMAN PIPELINE CONSTRUCTION, INC.(0.49%)
VALLEY PLACERS, LLC(0.10%)
ROADWAY SPECIALTIES, INC.(0.76%)
TEXAS HIGHWAY WALLS(3.26%)
ZACHRY CONSTRUCTION CORPORATION( 89.37%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
APAC-TEXAS, INC. (0.62%)
AARON CONCRETE CONTRACTORS, L.P. (1.04%)
KELLYSTONE, INC(0.12%)
NORTH TEXAS REBAR, LLC (2.79%)
Contract # 07113013
Totals 24729960.53 0.00 27977700.86 99.9

CountyBURNET
Highway SH 71
From AT CR 401
To .
CSJ 0700-01-040
Proj ID STP 1602(151)HESG
Work Type INSTALL INTERSECTION FLASHING BEAC
 
0.409 113531.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIGNAL SERVICES GROUP INC.
SUBCONTRACTOR(S) FOR CCSJ: 0700-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163007
Totals 113531.00 0.00 0.00 0.0

CountyTRAVIS
Highway SH 71
From 1.49 MI. EAST OF BEE CREEK ROAD
To 0.2 MI. WEST OF VAIL DIVIDE
CSJ 0700-03-122
Proj ID C 700-3-122
Work Type ADD LEFT TURN LANE & SHOULDERS
 
0.449 1633474.93 0.00 1532564.16 93.8
CountyTRAVIS
Highway SH 71
From 0.15 MI. EAST OF VAIL DIVIDE
To 0.2 MI. WEST OF RM 3238
CSJ 0700-03-123
Proj ID C 700-3-123
Work Type ADD LEFT TURN LANE & SHOULDERS
 
1.533 6535849.48 0.00 6732616.95 99.9
CountyTRAVIS
Highway SH 71
From 0.15 MI. EAST OF VAIL DIVIDE
To 0.2 MI. WEST OF RM 3238
CSJ 0700-03-132
Proj ID RW 700-3-132
Work Type ROW UTL. ADJ.
 
1.536 76681.00 0.00 76681.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-13
Work Began 02-17-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 161
Addl Days Granted 127
Working Days Charged 328
Percent Time Used 113
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-123
ROADWAY SPECIALTIES, INC.(3.25%)
AUSTIN WOOD RECYCLING(0.27%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.12%)
TEX OP CONSTRUCTION, LP(0.21%)
PANTHER CREEK TRANSPORTATION, INC. (2.15%)
BRYANT & FREY CONSTRUCTION (0.26%)
TEXAS HIGHWAY WALLS(5.50%)
RAMMING PAVING COMPANY ( 35.78%)
FLASHER EQUIPMENT COMPANY(1.98%)
JAG TRUCKING INC (0.77%)
Contract # 08133049
Totals 8246005.41 0.00 8341862.11 99.9

CountyTRAVIS
Highway SH 71
From WEST OF THOMAS SPRINGS ROAD
To WEST OF COVERED BRIDGE ROAD
CSJ 0700-03-125
Proj ID C 700-3-125
Work Type ADD LEFT TURN LANE & SHOULDERS
 
5.702 15965613.32 46289.10 16137374.52 99.9
Work Order 03-18-14
Work Began 06-16-14
Work Completed  
Time Computed 05-17-14
Contract Working Days 289
Addl Days Granted 72
Working Days Charged 440
Percent Time Used 121
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-125
PANTHER CREEK TRANSPORTATION, INC. (4.57%)
BRYANT & FREY CONSTRUCTION (2.07%)
ROADWAY SPECIALTIES, INC.(1.42%)
FLASHER EQUIPMENT COMPANY(1.12%)
SCOTT DERR PAINTING CO, LLC(0.00%)
TEXAS HIGHWAY WALLS(0.63%)
THE LEVY COMPANY, L.P. (2.36%)
HAEGELIN CONSTRUCTION CO., LTD.(8.02%)
SCOTT DERR PAINTING CO, LLC(0.08%)
AUSTIN WOOD RECYCLING(0.45%)
RAMI MATERIALS TRANSPORT, LLC(1.25%)
BREDA COMPANY, INC.(0.00%)
CANTU CONSTRUCTION, INC. (0.15%)
MCKINNEY DRILLING COMPANY(0.09%)
ROSCH COMPANY(0.85%)
CHLOR-SERV, INC. (0.03%)
DRILL TECH DRILLING & SHORING, INC.(0.49%)
RAMMING PAVING COMPANY ( 22.04%)
APAC-TEXAS, INC. (0.44%)
Contract # 11133027
Totals 15965613.32 46289.10 16137374.52 99.9

CountyTRAVIS
Highway SH 71
From RM 3238 (HAMILTON POOL RD)
To RM 620
CSJ 0700-03-130
Proj ID STP 2016(899)
Work Type SEAL & OVERLAY
 
1.207 425202.19 3878.75 348873.09 82.0
Work Order 05-23-16
Work Began 09-12-16
Work Completed  
Time Computed 06-22-16
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 40
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-130
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163224
Totals 425202.19 3878.75 348873.09 82.0

CountyWILLIAMSON
Highway FM 685
From US 79
To SH 130
CSJ 0757-01-020
Proj ID C 757-1-20
Work Type RECONSTRUCT TO 4 - LANE DIVIDED RDWY
 
1.820 10553004.78 539775.99 9069952.82 85.9
CountyWILLIAMSON
Highway FM 685
From US 79
To SH 130
CSJ 0757-01-021
Proj ID RW 757-1-21
Work Type ROW ACQ, RELOC ASSIST. & UTL. ADJ.
 
1.820 464544.39 0.00 450498.35 96.9
Work Order 08-27-14
Work Began 10-20-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 441
Addl Days Granted 0
Working Days Charged 439
Percent Time Used 99
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0757-01-020
ABC EROSION CONTROL, INC.(0.61%)
AUSTIN WOOD RECYCLING(0.49%)
TRP CONSTRUCTION GROUP, LLC( 50.52%)
GUERRA UNDERGROUND, LLC(2.61%)
BEAIRD DRILLING(1.78%)
MENDEZ EXCAVATION(0.32%)
TEXAS ROAD BORING(0.32%)
ROADWAY SPECIALTIES, INC.(0.64%)
EVT CONSTRUCTION (1.00%)
THE LEVY COMPANY, L.P. (1.64%)
BREDA COMPANY, INC.( 72.86%)
AARON CONCRETE CONTRACTORS, L.P. (2.96%)
INDUS CONSTRUCTION, L.P. (0.10%)
JUST GROOVING, LTD.(0.16%)
RAMMING PAVING COMPANY ( 17.28%)
A & R DEMOLITION (0.27%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.01%)
PENHALL COMPANY(0.08%)
Contract # 02143003
Totals 11017549.17 539775.99 9520451.17 86.4

CountyHAYS
Highway RM 150
From CENTER STREET
To SILVERADO DR.
CSJ 0805-04-025
Proj ID STP 2013(285)MM
Work Type CONSTRUCT SIDEWALK & BIKE LANES
 
0.612 364407.34 141156.05 141156.05 38.7
CountyHAYS
Highway FM 2770
From FAIRWAY DRIVE
To BOB SHELTON STADIUM
CSJ 3210-01-012
Proj ID STP 2013(285)MM
Work Type CONSTRUCT SIDEWALKS & BIKE LANES
 
0.998 484671.17 10998.60 10998.60 2.2
Work Order 07-14-16
Work Began 09-06-16
Work Completed  
Time Computed 08-13-16
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 40
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0805-04-025
F & W ELECTRICAL CONTRACTORS, INC. (6.20%)
FLASHER EQUIPMENT COMPANY(2.51%)
RICE ENVIRONMENTAL SERVICES(4.91%)
Contract # 05163235
Totals 849078.51 152154.65 152154.65 17.9

CountyTRAVIS
Highway VA
From VARIOUS
To .
CSJ 0914-00-301
Proj ID NH 2012(007)
Work Type FY 2012 NON - SITE SPECIFIC ITS MAINT
 
0.100 4204759.50 0.00 4549610.10 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-25-11
Work Began 02-21-12
Work Completed  
Time Computed 11-10-11
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 499
Percent Time Used 98
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-301
ROADWAY SPECIALTIES, INC.(2.80%)
AUSTIN UNDERGROUND INCORPORATED(2.05%)
M.G. DRILLING(0.62%)
Contract # 09113230
Totals 4204759.50 0.00 4549610.10 99.9

CountyTRAVIS
Highway VA
From VARIOUS
To (ON-SYSTEM)
CSJ 0914-00-314
Proj ID NH 2013(027)
Work Type FY 2013 NON - SITE SPECIFIC ITS MAINT
 
0.100 2958819.25 33525.00 1281524.07 43.3
Work Order 10-12-12
Work Began 02-03-16
Work Completed  
Time Computed 10-28-12
Contract Working Days 508
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 25
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123244
Totals 2958819.25 33525.00 1281524.07 43.3

CountyTRAVIS
Highway VA
From AT VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0914-00-319
Proj ID NH 1402(057)
Work Type FY 2014 SITE - SPECIFIC SIGNALS
 
0.100 1113486.77 153990.78 744502.23 66.8
Work Order 11-04-14
Work Began 02-02-15
Work Completed  
Time Computed 11-20-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 357
Percent Time Used 97
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(2.63%)
HIGHWAY 19 CONSTRUCTION, LLC (9.08%)
TX DOWN UNDER CONSTRUCTION LLC (4.00%)
UNION ELECTRICAL CONTRACTOR, INC.(1.24%)
FLASHER EQUIPMENT COMPANY(1.57%)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (1.24%)
MORGAN UTILITY CONSTRUCTION(1.04%)
Contract # 08143029
Totals 1113486.77 153990.78 744502.23 66.8