Monthly State Let Construction Report For Austin District As Of Feb 10, 2017 Page 5 Of 7

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwaySH 71
FromWEST OF THOMAS SPRINGS ROAD
ToWEST OF COVERED BRIDGE ROAD
CSJ0700-03-125
Proj IDC 700-3-125
Work TypeADD LEFT TURN LANE & SHOULDERS
 
5.70215965613.3216200066.0999.9
Work Order03-18-14
Work Began06-16-14
Work Completed
Time Computed05-17-14
Contract Working Days289
Addl Days Granted72
Working Days Charged440
Percent Time Used121
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-125
PANTHER CREEK TRANSPORTATION, INC. (4.57)
BRYANT & FREY CONSTRUCTION (2.07)
ROADWAY SPECIALTIES, INC. (1.42)
FLASHER EQUIPMENT COMPANY (1.12)
SCOTT DERR PAINTING CO, LLC (0.00)
TEXAS HIGHWAY WALLS (0.63)
THE LEVY COMPANY, L.P. (2.36)
HAEGELIN CONSTRUCTION CO., LTD. (8.02)
SCOTT DERR PAINTING CO, LLC (0.08)
AUSTIN WOOD RECYCLING (0.45)
RAMI MATERIALS TRANSPORT, LLC (1.25)
BREDA COMPANY, INC. (0.00)
CANTU CONSTRUCTION, INC. (0.15)
MCKINNEY DRILLING COMPANY (0.09)
ROSCH COMPANY (0.85)
CHLOR-SERV, INC. (0.03)
DRILL TECH DRILLING & SHORING, INC. (0.49)
RAMMING PAVING COMPANY (22.04)
APAC-TEXAS, INC. (0.44)
Contract #11133027
Totals15965613.3211300.0716200066.0999.9

CountyTRAVIS
HighwaySH 71
FromRM 3238 (HAMILTON POOL RD)
ToRM 620
CSJ0700-03-130
Proj IDSTP 2016(899)
Work TypeSEAL & OVERLAY
 
1.207425202.19348873.0982.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-16
Work Began09-12-16
Work Completed
Time Computed06-22-16
Contract Working Days20
Addl Days Granted0
Working Days Charged8
Percent Time Used40
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0700-03-130
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04163224
Totals425202.190.00348873.0982.0

CountyWILLIAMSON
HighwayFM 685
FromUS 79
ToSH 130
CSJ0757-01-020
Proj IDC 757-1-20
Work TypeRECONSTRUCT TO 4-LANE DIVIDED RDWY
 
1.82010553004.7810017938.1695.3
CountyWILLIAMSON
HighwayFM 685
FromUS 79
ToSH 130
CSJ0757-01-021
Proj IDRW 757-1-21
Work TypeROW ACQ, RELOC ASSIST. & UTL. ADJ.
 
1.820464544.39484879.8499.9
Work Order08-27-14
Work Began10-20-14
Work Completed
Time Computed10-20-14
Contract Working Days441
Addl Days Granted0
Working Days Charged475
Percent Time Used107
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0757-01-020
ABC EROSION CONTROL, INC. (0.61)
AUSTIN WOOD RECYCLING (0.49)
TRP CONSTRUCTION GROUP, LLC (50.52)
GUERRA UNDERGROUND, LLC (2.61)
BEAIRD DRILLING (1.78)
MENDEZ EXCAVATION (0.32)
TEXAS ROAD BORING (0.32)
ROADWAY SPECIALTIES, INC. (0.64)
EVT CONSTRUCTION (1.00)
THE LEVY COMPANY, L.P. (1.64)
BREDA COMPANY, INC. (72.86)
AARON CONCRETE CONTRACTORS, L.P. (2.96)
INDUS CONSTRUCTION, L.P. (0.10)
JUST GROOVING, LTD. (0.16)
RAMMING PAVING COMPANY (17.28)
A & R DEMOLITION (0.27)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.01)
PENHALL COMPANY (0.08)
Contract #02143003
Totals11017549.17518567.6710502818.0095.7

CountyHAYS
HighwayRM 150
FromCENTER STREET
ToSILVERADO DR.
CSJ0805-04-025
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALK & BIKE LANES
 
0.612364407.34266831.1073.2
CountyHAYS
HighwayFM 2770
FromFAIRWAY DRIVE
ToBOB SHELTON STADIUM
CSJ3210-01-012
Proj IDSTP 2013(285)MM
Work TypeCONSTRUCT SIDEWALKS & BIKE LANES
 
0.998484671.17115539.8323.8
Work Order07-14-16
Work Began09-06-16
Work Completed
Time Computed08-13-16
Contract Working Days84
Addl Days Granted0
Working Days Charged82
Percent Time Used97
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0805-04-025
F & W ELECTRICAL CONTRACTORS, INC. (6.20)
FLASHER EQUIPMENT COMPANY (2.51)
RICE ENVIRONMENTAL SERVICES (4.91)
Contract #05163235
Totals849078.5162517.25382370.9345.0

CountyTRAVIS
HighwayVA
FromVARIOUS
To.
CSJ0914-00-301
Proj IDNH 2012(007)
Work TypeFY 2012 NON-SITE SPECIFIC ITS MAINT
 
0.1004204759.504549610.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-11
Work Began02-21-12
Work Completed
Time Computed11-10-11
Contract Working Days508
Addl Days Granted0
Working Days Charged499
Percent Time Used98
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-301
ROADWAY SPECIALTIES, INC. (2.80)
AUSTIN UNDERGROUND INCORPORATED (2.05)
M.G. DRILLING (0.62)
Contract #09113230
Totals4204759.500.004549610.1099.9

CountyTRAVIS
HighwayVA
FromVARIOUS
To(ON-SYSTEM)
CSJ0914-00-314
Proj IDNH 2013(027)
Work TypeFY 2013 NON-SITE SPECIFIC ITS MAINT
 
0.1002958819.251671880.9156.5
Work Order10-12-12
Work Began02-03-16
Work Completed
Time Computed10-28-12
Contract Working Days508
Addl Days Granted0
Working Days Charged169
Percent Time Used33
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-314
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09123244
Totals2958819.25128850.841671880.9156.5

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-319
Proj IDNH 1402(057)
Work TypeFY 2014 SITE-SPECIFIC SIGNALS
 
0.1001113486.77949688.9385.2
Work Order11-04-14
Work Began02-02-15
Work Completed
Time Computed11-20-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.63)
HIGHWAY 19 CONSTRUCTION, LLC (9.08)
TX DOWN UNDER CONSTRUCTION LLC (4.00)
UNION ELECTRICAL CONTRACTOR, INC. (1.24)
FLASHER EQUIPMENT COMPANY (1.57)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (1.24)
MORGAN UTILITY CONSTRUCTION (1.04)
WG ENGINEERING & CONSTRUCTION, LLC (3.06)
Contract #08143029
Totals1113486.7787285.72949688.9385.2

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-320
Proj IDNH 2014(015)
Work TypeFY 2013 SIGNING
 
0.100452778.70469081.5199.9
Work Order10-07-13
Work Began06-17-14
Work Completed
Time Computed10-23-13
Contract Working Days77
Addl Days Granted0
Working Days Charged29
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09133233
Totals452778.701060.50469081.5199.9

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-343
Proj IDSTP 1502(147)
Work TypeFY 2015 SITE-SPECIFIC SIGNALS
 
0.003614705.10584803.3495.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-15
Work Began01-15-16
Work Completed
Time Computed08-01-15
Contract Working Days132
Addl Days Granted0
Working Days Charged139
Percent Time Used105
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
M & M STRIPING & POWER WASHING, LLC (4.38)
UNION ELECTRICAL CONTRACTOR, INC. (8.97)
Contract #05153246
Totals614705.100.00584803.3495.8

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-344
Proj IDNH 2015(575)
Work TypeFY 2015 NON-SITE SPECIFIC SIGNALS
 
0.0031083323.501351927.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-20-15
Work Began08-31-15
Work Completed
Time Computed08-31-15
Contract Working Days300
Addl Days Granted0
Working Days Charged239
Percent Time Used79
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-344
D. I. J. CONSTRUCTION, INC. (4.07)
MG DRILLING (3.18)
KRL CONSTRUCTION INC. (13.11)
G. CARTER CONSTRUCTION COMPANY, INC. (5.57)
Contract #02153027
Totals1083323.500.001351927.0099.9

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
ToINCLUDE IH 35, SH 71, SL 360, ETC
CSJ0914-00-367
Proj IDNH 2016(104)
Work TypeFY 2016 SIGNING
 
0.003278620.64305016.8599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-15
Work Began05-31-16
Work Completed
Time Computed02-19-16
Contract Working Days133
Addl Days Granted0
Working Days Charged81
Percent Time Used60
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-367
ROADWAY SPECIALTIES, INC. (9.10)
JCD CONSTRUCTION, LLC (3.58)
BREDA COMPANY, INC. (0.00)
Contract #09153020
Totals278620.640.00305016.8599.9

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-368
Proj IDNH 1602(280)
Work TypeFY 2016 SITE-SPECIFIC SIGNALS
 
0.0031041312.896385.200.6
Work Order09-20-16
Work Began01-19-17
Work Completed
Time Computed10-20-16
Contract Working Days150
Addl Days Granted0
Working Days Charged5
Percent Time Used3
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-368
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.20)
M & M STRIPING & POWER WASHING, LLC (14.13)
WG ENGINEERING & CONSTRUCTION, LLC (12.08)
Contract #07163030
Totals1041312.896385.206385.200.6

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-369
Proj IDNH 1602(020)
Work TypeFY 2016 NON-SITE SPECIFIC SIGNALS
 
0.0031104881.00844750.0576.4
Work Order05-12-16
Work Began08-23-16
Work Completed
Time Computed06-11-16
Contract Working Days300
Addl Days Granted0
Working Days Charged118
Percent Time Used39
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-369
D. I. J. CONSTRUCTION, INC. (1.16)
Contract #03163231
Totals1104881.00349024.95844750.0576.4

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATION IN AUSTIN
ToDISTRICT
CSJ0914-00-391
Proj IDNH 1602(493)
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
0.00311464497.2597200.000.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-391
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163208
Totals11464497.250.0097200.000.8

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
To.
CSJ0914-04-298
Proj IDSTP 1602(290)
Work TypeLANDSCAPING AND IRRIGATION
 
0.0011177598.30396061.0033.6
Work Order08-24-16
Work Began12-19-16
Work Completed
Time Computed09-23-16
Contract Working Days160
Addl Days Granted0
Working Days Charged21
Percent Time Used13
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-298
FLASHER EQUIPMENT COMPANY (0.85)
J & V UTILTIY (1.06)
Contract #07163209
Totals1177598.30211097.00396061.0033.6

CountyWILLIAMSON
HighwayVA
FromWITHIN GRANGER WMA
To.
CSJ0914-05-182
Proj IDC 914-5-182
Work TypeOVERLAY
 
0.22577034.5065223.5084.6
Work Order10-25-16
Work Began12-16-16
Work Completed
Time Computed12-16-16
Contract Working Days18
Addl Days Granted0
Working Days Charged11
Percent Time Used61
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-182
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163229
Totals77034.506366.4065223.5084.6

CountyBASTROP
HighwayCS
FromAT BARTONS CREEK ON BARTON OAKS RD
ToSTR# 011-AA07-10-001
CSJ0914-18-091
Proj IDBR 2014(689)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.159529317.55207024.0039.1
Work Order11-22-16
Work Began12-12-16
Work Completed
Time Computed12-12-16
Contract Working Days95
Addl Days Granted0
Working Days Charged23
Percent Time Used24
Contractor(s)
MAC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-091
AAR INCORPORATED (3.02)
FLASHER EQUIPMENT COMPANY (1.52)
DIIBS SPECIALISTS (3.24)
VOGES DRILLING CO. (14.81)
Contract #08163011
Totals529317.55150520.00207024.0039.1

CountyBASTROP
HighwayCR
FromAT ALUM CREEK TRIBUTARY ON ALUM CR
ToRD (CR190) STR#011-AA01-90-001
CSJ0914-18-108
Proj IDBR 2017(112)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.077431059.21233659.4054.2
Work Order11-22-16
Work Began12-12-16
Work Completed
Time Computed12-12-16
Contract Working Days75
Addl Days Granted0
Working Days Charged27
Percent Time Used36
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-18-108
D.I.J. CONSTRUCTION, INC (1.16)
VOGES DRILLING CO. (8.42)
LONE STAR PAVING (6.18)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.77)
W. W. FOUNDATION DRILLING, LTD. (4.87)
LONESTAR TRAFFIC SAFETY, LLC (0.80)
Contract #09163034
Totals431059.21113921.90233659.4054.2

CountyGILLESPIE
HighwayCR
FromON OLD SAN ANTONIO AT PEDERNALES
ToSTR AA0119002
CSJ0914-19-022
Proj IDBR 2012(703)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.5002659843.092538746.8395.4
Work Order04-09-14
Work Began05-05-14
Work Completed
Time Computed05-05-14
Contract Working Days623
Addl Days Granted0
Working Days Charged521
Percent Time Used83
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-19-022
O & S TRAFFIC SUPPLIES (0.95)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.68)
ALLEN KELLER COMPANY (24.37)
J R RAMON, INC. (2.72)
JUST GROOVING, LTD. (0.22)
ROADWAY SPECIALTIES, INC. (4.79)
FLASHER EQUIPMENT COMPANY (0.72)
MESA ROD BUSTERS, INC. (0.25)
METALINK CORPORATION (0.29)
PENHALL COMPANY (0.30)
MCL CONTRACTING, LLC (0.07)
AARON CONCRETE CONTRACTORS, L.P. (0.90)
Contract #02143012
Totals2659843.0942929.822538746.8395.4

CountyBASTROP
HighwayFM 696
From1.165 MI N OF US 290
To1.296 MI N OF US 290
CSJ1073-01-020
Proj IDBR 1502(072)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1312191679.002186938.9799.9
Work Order08-26-15
Work Began01-05-16
Work Completed
Time Computed10-25-15
Contract Working Days202
Addl Days Granted45
Working Days Charged266
Percent Time Used107
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020
ROADWAY SPECIALTIES, INC. (1.90)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.35)
MESA ROD BUSTERS, INC. (0.82)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95)
AUSTIN WOOD RECYCLING (0.71)
MURRAY CONSTRUCTION (0.14)
TEXAS CUTTING & CORING, INC. (0.20)
Contract #06153008
Totals2191679.00177555.882186938.9799.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7