Monthly State Let Construction Report For Austin District As Of Aug 11, 2017 Page 5 Of 7

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-319
Proj IDNH 1402(057)
Work TypeFY 2014 SITE-SPECIFIC SIGNALS
 
0.1001113486.77993320.7589.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-04-14
Work Began02-02-15
Work Completed
Time Computed11-20-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-319
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.63)
HIGHWAY 19 CONSTRUCTION, LLC (9.08)
TX DOWN UNDER CONSTRUCTION LLC (4.00)
UNION ELECTRICAL CONTRACTOR, INC. (1.24)
FLASHER EQUIPMENT COMPANY (1.57)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (1.24)
MORGAN UTILITY CONSTRUCTION (1.04)
WG ENGINEERING & CONSTRUCTION, LLC (3.06)
Contract #08143029
Totals1113486.770.00993320.7589.2

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-320
Proj IDNH 2014(015)
Work TypeFY 2013 SIGNING
 
0.100452778.70475444.5199.9
Work Order10-07-13
Work Began06-17-14
Work Completed
Time Computed10-23-13
Contract Working Days77
Addl Days Granted0
Working Days Charged29
Percent Time Used37
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-320
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09133233
Totals452778.701060.50475444.5199.9

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-343
Proj IDSTP 1502(147)
Work TypeFY 2015 SITE-SPECIFIC SIGNALS
 
0.003614705.10584803.3495.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-15
Work Began01-15-16
Work Completed
Time Computed08-01-15
Contract Working Days132
Addl Days Granted0
Working Days Charged139
Percent Time Used105
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-343
M & M STRIPING & POWER WASHING, LLC (4.38)
UNION ELECTRICAL CONTRACTOR, INC. (8.97)
Contract #05153246
Totals614705.100.00584803.3495.8

CountyTRAVIS
HighwayVA
FromVARIOUS_ON SYSTEM LOCATIONS
To.
CSJ0914-00-366
Proj IDSTP 1702(553)
Work TypeNON-SITE SPECIFIC ITS MAINT
 
0.003988888.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-366
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173039
Totals988888.500.000.000.0

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-368
Proj IDNH 1602(280)
Work TypeFY 2016 SITE-SPECIFIC SIGNALS
 
0.0031041312.89659809.9163.3
Work Order09-20-16
Work Began01-19-17
Work Completed
Time Computed10-20-16
Contract Working Days150
Addl Days Granted0
Working Days Charged120
Percent Time Used80
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-368
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.20)
M & M STRIPING & POWER WASHING, LLC (14.13)
WG ENGINEERING & CONSTRUCTION, LLC (12.08)
UNION ELECTRICAL CONTRACTOR, INC. (5.89)
H6 BORING, LLC (1.24)
4D UTILITY CONSTRUCTION, LLC (0.61)
Contract #07163030
Totals1041312.8953659.83659809.9163.3

CountyTRAVIS
HighwayVA
FromAT VARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-369
Proj IDNH 1602(020)
Work TypeFY 2016 NON-SITE SPECIFIC SIGNALS
 
0.0031104881.001058694.9595.8
Work Order05-12-16
Work Began08-23-16
Work Completed
Time Computed06-11-16
Contract Working Days300
Addl Days Granted0
Working Days Charged230
Percent Time Used76
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-369
D. I. J. CONSTRUCTION, INC. (1.16)
G. CARTER CONSTRUCTION COMPANY, INC. (5.37)
Contract #03163231
Totals1104881.0010700.001058694.9595.8

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATION IN AUSTIN
ToDISTRICT
CSJ0914-00-391
Proj IDNH 1602(493)
Work TypeTRAFFIC MANAGEMENT SYSTEM
 
0.00311464497.252206462.0019.2
Work Order12-28-16
Work Began05-02-17
Work Completed
Time Computed01-27-17
Contract Working Days360
Addl Days Granted0
Working Days Charged43
Percent Time Used11
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-391
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163208
Totals11464497.25973743.502206462.0019.2

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-395
Proj IDSTP 2017(791)
Work TypeFY 17 NON-SITE SPECIFIC SIGNALS
 
0.0031439774.00141402.009.8
Work Order04-12-17
Work Began06-21-17
Work Completed
Time Computed06-11-17
Contract Working Days300
Addl Days Granted0
Working Days Charged23
Percent Time Used7
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-395
KRL CONSTRUCTION INC. (8.59)
D. I. J. CONSTRUCTION, INC. (1.82)
Contract #03173204
Totals1439774.0074550.00141402.009.8

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-396
Proj IDSTP 1702(554)
Work TypeFY 2017 SITE SPECIFIC SIGNALS
 
0.0031663381.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-396
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173219
Totals1663381.120.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US290
CSJ0914-00-406
Proj IDNH 1702(582)
Work TypeCONCRETE PAVEMENT REPAIRS
 
0.1001116909.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-406
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173246
Totals1116909.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH35, LP1,SH71
ToUS183 & US 290
CSJ0914-00-407
Proj IDNH 1702(583)
Work TypeASPHALTIC PAVEMENT REPAIRS
 
0.1002168168.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-407
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173247
Totals2168168.000.000.000.0

CountyTRAVIS
HighwayCR
FromON LUND CARLSON RD AT WILLOW CREEK
ToSTR AA1531002
CSJ0914-04-227
Proj IDBR 2008(234)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.066377671.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-227
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173228
Totals377671.080.000.000.0

CountyTRAVIS
HighwayCR
FromHAYS C/L (ON FITZHUGH RD)
ToUS 290
CSJ0914-04-289
Proj IDSTP 1602(245)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.00116803.000.000.0
CountyHAYS
HighwayCR
FromBLANCO C/L ON W FITZHUGH RD
ToTRAVIS C/L
CSJ0914-33-070
Proj IDSTP 2017(895)HES
Work TypeINSTALL WARN/GUIDE SIGN/DELINEATOR
 
0.001132962.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-289
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173019
Totals149765.000.000.000.0

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
To.
CSJ0914-04-298
Proj IDSTP 1602(290)
Work TypeLANDSCAPING AND IRRIGATION
 
0.0011177598.30989564.0584.0
Work Order08-24-16
Work Began12-19-16
Work Completed
Time Computed09-23-16
Contract Working Days160
Addl Days Granted0
Working Days Charged100
Percent Time Used62
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-04-298
FLASHER EQUIPMENT COMPANY (0.85)
J & V UTILTIY (1.06)
Contract #07163209
Totals1177598.3043500.75989564.0584.0

CountyMASON
HighwayCR
FromKATEMCY RD @ DRY PRONG KATEMCY CRK
ToSTR AA0180001
CSJ0914-26-007
Proj IDBR 1402(184)
Work TypeREPLACE BRIDGE & APPROACHES
 
0.064264228.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-26-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173011
Totals264228.000.000.000.0

CountyHAYS
HighwayCR
FromON POST RD (CR 140)
ToAT THE BLANCO RIVER
CSJ0914-33-072
Proj IDBR 2016(787)
Work TypeBRIDGE REPLACEMENT
 
0.126905345.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-06-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days139
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-072
AUSTIN MATERIALS, LLC (3.21)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.04)
VOGES DRILLING CO. (2.96)
ROADWAY SPECIALTY ENTERPRISES (4.77)
FLASHER EQUIPMENT COMPANY (1.59)
Contract #05173018
Totals905345.350.000.000.0

CountyBASTROP
HighwayFM 696
From1.165 MI N OF US 290
To1.296 MI N OF US 290
CSJ1073-01-020
Proj IDBR 1502(072)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1312191679.002243323.5999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-15
Work Began01-05-16
Work Completed
Time Computed10-25-15
Contract Working Days202
Addl Days Granted64
Working Days Charged266
Percent Time Used100
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1073-01-020
ROADWAY SPECIALTIES, INC. (1.90)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.35)
MESA ROD BUSTERS, INC. (0.82)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.95)
AUSTIN WOOD RECYCLING (0.71)
MURRAY CONSTRUCTION (0.14)
TEXAS CUTTING & CORING, INC. (0.20)
Contract #06153008
Totals2191679.000.002243323.5999.9

CountyTRAVIS
HighwayFM 969
FromDECKER CREEK DRIVE
ToBASTROP COUNTY LINE
CSJ1186-01-087
Proj IDSTP 2015(277)HES
Work TypePROVIDE ADD'L PAVED SURFACE WIDTH
 
7.1015894316.376163873.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began03-17-15
Work Completed
Time Computed03-17-15
Contract Working Days398
Addl Days Granted0
Working Days Charged385
Percent Time Used96
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-087
ENVIRONMENTAL SAFETY SERVICES, INC. (7.14)
TRP CONSTRUCTION GROUP, LLC (2.30)
LONE STAR PAVING, INC. (47.54)
Contract #11143219
Totals5894316.370.006163873.4499.9

CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-090
Proj IDPTF 2017(143)
Work TypeREHAB ROADWAY; ADD TWLTL & SHLDRS
 
2.1944540893.02277891.406.1
CountyTRAVIS
HighwayFM 969
FromFM 3177
To0.108 MI. EAST OF FM 973
CSJ1186-01-096
Proj IDROW 1186-1-96
Work TypeUTILITY ADJUSTMENTS
 
2.1942107410.600.000.0
Work Order02-27-17
Work Began06-05-17
Work Completed
Time Computed03-29-17
Contract Working Days321
Addl Days Granted0
Working Days Charged30
Percent Time Used9
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-090
LONE STAR PAVING (15.32)
ESSL,LLC (6.81)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33)
BRYANT & FREY CONSTRUCTION (0.96)
TRP CONSTRUCTION GROUP, LLC (0.48)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.92)
AUSTIN WOOD RECYCLING (0.71)
Contract #01173041
Totals6648303.62262738.80277891.404.1

CountyWILLIAMSON
HighwayFM 1660
FromFM 973
ToSH 95
CSJ1200-01-023
Proj IDSTP 2017(949)
Work TypeREHAB RDWY
 
3.3434076992.4523623.820.5
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days145
Addl Days Granted0
Working Days Charged7
Percent Time Used4
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-01-023
AWP, INC. (0.14)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.86)
FLASHER EQUIPMENT COMPANY (1.68)
MURRAY CONSTRUCTION (0.63)
ROADWAY SPECIALTIES, INC. (6.22)
RUCOBA & MAYA CONSTRUCTION (23.18)
AUSTIN WOOD RECYCLING (0.65)
THE DAVEY TREE EXPERT COMPANY (0.07)
Contract #04173229
Totals4076992.4523623.8223623.820.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7