Monthly State Let Construction Report For Austin District As Of May 15, 2013 Page 1 Of 7

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWILLIAMSON
Highway IH 35
From 0.710 MI SOUTH OF LAKEWAY DRIVE
To 0.246 MI NORTH OF LAKEWAY DRIVE
CSJ 0015-08-116
Proj ID IM 0353(283)
Work Type REPLACE EXISTING UNDERPASS STRUCTUR
 
1.810 5649298.80 157672.71 2297065.30 40.6
CountyWILLIAMSON
Highway IH 35
From AT BI 35M NORTH AND LAKEWAY DR
To .
CSJ 0015-08-126
Proj ID RW 15-8-126
Work Type ROW ACQUISITION, UTIL & RELOC
 
0.001 98041.62 0.00 37620.21 38.3
Work Order 10-05-11
Work Began 11-08-11
Work Completed  
Time Computed 10-21-11
Contract Working Days 481
Addl Days Granted 0
Working Days Charged 356
Percent Time Used 74
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-116
BEAIRD DRILLING(0.84%)
BMP SPECIALIST, LLC(0.87%)
CERTIFIED PLACERS LLC(1.06%)
EW WELLS GROUP LLC (0.91%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.04%)
FLASHER EQUIPMENT COMPANY(1.29%)
HIGHWAY TECHNOLOGIES, INC. (1.64%)
J.D. RAMMING PAVING CO., LTD.( 17.37%)
PRIMATE CONSTRUCTION, INC. (0.09%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(0.18%)
SOUTH TEXAS PAINTING COMPANY (0.13%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (5.68%)
MONTELONGO"S CONCRETE(1.57%)
CHASCO CONSTRUCTORS( 94.71%)
APAC-TEXAS, INC. ( 22.38%)
HAYWARD BAKER, INC.(0.90%)
Contract # 07113238
Totals 5747340.42 157672.71 2334685.51 40.6

CountyWILLIAMSON
Highway IH 35
From 1310 FT SOUTH OF LAKEWAY DRIVE
To 2250 FT NORTH OF LAKEWAY DRIVE
CSJ 0015-08-137
Proj ID IM 0353(285)
Work Type LANDSCAPING AND IRRIGATION
 
0.815 418380.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-24-12
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08123043
Totals 418380.00 0.00 0.00 0.0

CountyWILLIAMSON
Highway IH 35
From FM 3406
To S. SAN GABRIEL RIVER
CSJ 0015-09-165
Proj ID IM 0353(284)
Work Type PAVEMENT REPAIR AND OVERLAY
 
6.380 3689560.42 835.43 1004776.56 27.2
Work Order 11-16-11
Work Began 07-17-12
Work Completed  
Time Computed 12-02-11
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 78
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0015-09-165
HIGHWAY TECHNOLOGIES, INC. (8.21%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.11%)
SCR CONSTRUCTION CO., INC. (1.32%)
Contract # 10113219
Totals 3689560.42 835.43 1004776.56 27.2

CountyTRAVIS
Highway LP 275
From 400' S OF WALNUT CREEK BRIDGE
To RUTLAND DR
CSJ 0015-11-062
Proj ID STP 2013(470)
Work Type MILL, SEAL & THIN OVERLAY
 
1.944 1249601.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-11-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133031
Totals 1249601.80 0.00 0.00 0.0

CountyTRAVIS
Highway IH 35
From BRAKER LN
To BEN WHITE BLVD
CSJ 0015-13-338
Proj ID STP 2012(545)MM
Work Type CONST SIDEWALKS ON BOTH SIDES IH 35
 
11.000 1651934.64 67773.35 252139.41 15.2
CountyTRAVIS
Highway US 183
From IH 35
To NORWOOD PARK
CSJ 0151-09-144
Proj ID NH 2012(546)
Work Type CONSTRUCT SIDEWALKS
 
0.474 234806.96 13385.00 234159.75 99.7
Work Order 08-10-12
Work Began 10-15-12
Work Completed  
Time Computed 08-26-12
Contract Working Days 288
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 37
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-338
N-LINE TRAFFIC MAINTENANCE, L.P. (0.91%)
PEK, INC.( 35.86%)
Contract # 05123246
Totals 1886741.60 81158.35 486299.16 25.7

CountyTRAVIS
Highway IH 35
From IN AUSTIN FROM 6TH ST TO 8TH ST
To GOVERNOR'S COMMUNITY ACHIEVEMENT
CSJ 0015-13-353
Proj ID IM 0353(279)
Work Type LANDSCAPING
 
0.140 254930.73 875.00 251408.15 98.6
Work Order 02-18-11
Work Began 04-04-11
Work Completed  
Time Computed 03-06-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 55
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-353
LEXTEX, INC. (4.11%)
Contract # 01113214
Totals 254930.73 875.00 251408.15 98.6

CountyTRAVIS
Highway IH 35 ETC
From AT E MARTIN LUTHER KING BLVD
To .
CSJ 0015-13-357
Proj ID STP 2011(771)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.900 1035409.77 0.00 1074788.81 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-18-11
Work Began 07-13-11
Work Completed  
Time Computed 05-04-11
Contract Working Days 170
Addl Days Granted 31
Working Days Charged 209
Percent Time Used 103
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SYSTEMS, CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-357
TX DOWN UNDER CONSTRUCTION LLC (8.41%)
HIGHWAY TECHNOLOGIES, INC. (0.46%)
Contract # 03113006
Totals 1035409.77 0.00 1074788.81 99.9

CountyHAYS
Highway IH 35
From 2250 FT N OF MAIN ST
To 2000 FT S OF MAIN ST
CSJ 0016-02-104
Proj ID HP 2009(650)ES
Work Type REPL BRIDGE & APPRS, WIDEN FRTG RDS
 
0.777 7858394.07 0.00 9399409.11 99.9
CountyHAYS
Highway IH 35
From 2000 FT N OF FM 2001
To FM 2001
CSJ 0016-02-130
Proj ID STP 2010(004)ES
Work Type SEAL COAT, MILL & INLAY, OVERLAY PFC
 
0.379 431995.37 0.00 305076.93 70.6
CountyHAYS
Highway CS
From ON MAIN STREET 440' W OF CR 117
To 825' EAST OF CR 117
CSJ 0914-33-060
Proj ID CC 914-33-60
Work Type WIDEN ROADWAY
 
0.001 1032278.34 0.00 1074699.91 99.9
CountyHAYS
Highway CS
From ON MAIN STEET 120' W OF CR 117
To 840' EAST OF CR 117
CSJ 0914-33-061
Proj ID RW 914-33-61
Work Type UTILITY ADJ IN CONST. CONTRACT
 
0.001 70858.83 0.00 63831.38 90.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-09
Work Began 11-02-09
Work Completed  
Time Computed 10-25-09
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 644
Percent Time Used 106
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-104
ASPHALT PAVING COMPANY OF AUSTIN, INC. ( 16.75%)
AUSTEX TREE SERVICE, INC.(0.01%)
BOOTHE BROTHERS PAVING COMPANY, INC. (1.11%)
CARTEL PLACERS, LLC(0.42%)
E W WELLS GROUP LLC(0.84%)
F & W ELECTRICAL CONTRACTORS, INC. (5.24%)
HIGHWAY TECHNOLOGIES, INC. (1.48%)
MCKINNEY DRILLING__(BUDA)(1.43%)
RICE ENVIRONMENTAL SERVICES(0.00%)
ROADWAY SPECIALTIES, INC.(1.64%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.18%)
TEXAS HIGHWAY SYSTEMS, INC.(0.25%)
EVANS ENVIRONMENTAL CONTRACTING, LLC.(0.79%)
RIVER CITIES SAWING LLC(0.05%)
LONE STAR TRAFFIC SERVICE, INC.(0.45%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.22%)
ENVIRONMENTAL SERVICES, INC. (0.08%)
WILLIAMS-JOHN CONSTRUCTION, LLC(2.73%)
MUNDO VERDE IRRIGATION & LANDSCAPING, INC. (1.78%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.47%)
Contract # 08093207
Totals 9393526.61 0.00 10843017.33 99.9

CountyHAYS
Highway IH 35
From FM 1626 (KYLE PARKWAY)
To S OF RM 150
CSJ 0016-02-127
Proj ID PTF 2012(094)
Work Type CONST SB FRONTAGE RD
 
2.746 6298068.75 1024995.01 4760546.96 75.5
Work Order 07-18-12
Work Began 08-13-12
Work Completed  
Time Computed 08-03-12
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 68
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-127
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.00%)
FLASHER EQUIPMENT COMPANY(1.68%)
THE LEVY COMPANY, L.P. (5.04%)
MURRAY CONSTRUCTION(0.55%)
ROADWAY SPECIALTIES, INC.(1.36%)
S & S BRIDGE PAINTING, INC.(0.01%)
Contract # 05123206
Totals 6298068.75 1024995.01 4760546.96 75.5

CountyHAYS
Highway IH 35
From SH 80
To LP 82
CSJ 0016-03-097
Proj ID IM 0353(282)
Work Type LANDSCAPING AND IRRIGATION
 
0.975 248787.75 2375.00 214755.18 86.3
Work Order 09-27-11
Work Began 12-26-11
Work Completed  
Time Computed 01-25-12
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 83
Contractor(s)
TEXAS ASPHALT
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08113213
Totals 248787.75 2375.00 214755.18 86.3

CountyCALDWELL
Highway US 90
From GUADALUPE COUNTY LINE
To IH 10
CSJ 0029-03-054
Proj ID STP 2013(471)
Work Type FULL DEPTH REPAIR, MILL, SEAL & TOM
 
7.423 2600277.03 0.00 0.00 0.0
CountyLEE
Highway US 290
From 2.0 MILES EAST OF BASTROP C/L
To 4.0 MILES EAST OF BASTROP C/L
CSJ 0114-07-074
Proj ID NH 2013(472)
Work Type SPOT REPAIR, LEVEL - UP & TOM
 
2.000 943592.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0029-03-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133210
Totals 3543869.28 0.00 0.00 0.0

CountyGILLESPIE
Highway US 290
From 0.101 MI W OF MARIPOSA DR.
To 0.021 MI W OF OLD SAN ANTONIO RD.
CSJ 0113-01-041
Proj ID STP 2012(442)SB
Work Type INSTALL CTL & WIDEN PAVED SHOULDERS
 
0.343 2418067.64 75797.02 1263833.49 52.2
CountyGILLESPIE
Highway US 290
From 0.021 MI W OF OLD SAN ANTONIO RD.
To 0.148 MI E OF OLD SAN ANTONIO RD.
CSJ 0113-02-058
Proj ID STP 2012(442)SB
Work Type INSTALL CTL & WIDEN PAVED SHOULDERS
 
0.169 400597.34 46.00 141403.60 35.2
Work Order 07-16-12
Work Began 10-30-12
Work Completed  
Time Computed 10-30-12
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 73
Contractor(s)
SHANNON-MONK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-01-041
INTERSTATE BARRICADES & MARKINGS, INC. (1.64%)
EGGEMEYER LAND CLEARING, LLC (0.35%)
ROADWAY SPECIALTIES, INC.(6.16%)
HILL COUNTRY BRIDGE, INC.( 28.77%)
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.(8.12%)
W. W. FOUNDATION DRILLING, LTD.(2.89%)
GK CONSTRUCTION, LLC (0.46%)
PRESIDIO ENGINEERS & CONTRACTORS, INC. (2.34%)
Contract # 05123229
Totals 2818664.98 75843.02 1405237.09 49.8

CountyGILLESPIE
Highway US 290
From JUNG LANE
To 1230' EAST OF JENSCHKE ROAD
CSJ 0113-02-059
Proj ID STP 2012(547)
Work Type ADD TWO WAY LEFT TURN LANE
 
2.758 3481347.21 307414.37 1002338.44 28.7
Work Order 06-21-12
Work Began 09-17-12
Work Completed  
Time Computed 08-20-12
Contract Working Days 156
Addl Days Granted 15
Working Days Charged 169
Percent Time Used 98
Contractor(s)
MATL CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0113-02-059
ROADWAY SPECIALTIES, INC.(0.40%)
RICE ENVIRONMENTAL SERVICES(1.13%)
D. I. J. CONSTRUCTION, INC.(1.67%)
ABC EROSION CONTROL, INC.(0.52%)
SURVEYING AND MAPPING, INC.(0.00%)
Contract # 05123032
Totals 3481347.21 307414.37 1002338.44 28.7

CountyHAYS
Highway US 290
From MCGREGOR LANE
To MIGHTY TIGER TRAIL
CSJ 0113-07-050
Proj ID CC 113-7-50
Work Type ADD CENTER TURN LANE AND SHOULDERS
 
2.784 6460153.61 957906.35 5897211.02 91.2
Work Order 09-06-11
Work Began 01-17-12
Work Completed  
Time Computed 09-22-11
Contract Working Days 285
Addl Days Granted 0
Working Days Charged 280
Percent Time Used 98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0113-07-050
BMP SPECIALIST, LLC(0.98%)
CRAIG OLDEN, INC.(1.76%)
D. I. J. CONSTRUCTION, INC.(1.08%)
F & W ELECTRICAL CONTRACTORS, INC. (1.65%)
FLASHER EQUIPMENT COMPANY(0.29%)
RELMCO, INC. ( 13.16%)
RICE ENVIRONMENTAL SERVICES(2.07%)
SCOTT DERR PAINTING CO, LLC(0.07%)
SITE-SAFE PRODUCTS OF TEXAS, L.P.(2.41%)
VOGES DRILLING CO. (1.40%)
ROADWAY SPECIALTIES, INC.(0.63%)
AUSTIN WOOD RECYCLING(0.15%)
Contract # 07113019
Totals 6460153.61 957906.35 5897211.02 91.2

CountyTRAVIS
Highway US 290
From CIRCLE DR
To OLIVER DR
CSJ 0113-08-069
Proj ID NH 1102(368)
Work Type INSTALL CTL & PAVED SHOULDERS
 
0.730 2493084.79 0.00 2493017.13 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-11
Work Began 10-19-11
Work Completed  
Time Computed 09-18-11
Contract Working Days 275
Addl Days Granted 15
Working Days Charged 266
Percent Time Used 91
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-069
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.00%)
FARR FOUNDATION, INC.(0.66%)
FLASHER EQUIPMENT COMPANY(0.75%)
HIGHWAY TECHNOLOGIES, INC. (0.76%)
J.D. RAMMING PAVING CO., LTD.(0.81%)
ROADWAY SPECIALTIES, INC.(2.50%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.09%)
Contract # 07113049
Totals 2493084.79 0.00 2493017.13 99.9

CountyTRAVIS
Highway US 290
From WEST OF RM 1826
To EAST OF CONVICT HILL
CSJ 0113-08-075
Proj ID NH 2012(641)
Work Type PROVIDE SIGNALIZED INTERSECTIONS
 
0.860 4079142.96 0.00 0.00 0.0
CountyTRAVIS
Highway US 290
From WEST OF RM 1826
To EAST OF CONVICT HILL
CSJ 0113-08-078
Proj ID RW 113-8-78
Work Type ROW UTL. ADJ.
 
0.860 559727.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 217
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-075
AUSTIN WOOD RECYCLING(0.92%)
BRYANT & FREY CONSTRUCTION (4.55%)
HIGHWAY TECHNOLOGIES, INC. (2.34%)
RAMMING PAVING COMPANY ( 22.40%)
THE LEVY COMPANY, L.P. ( 13.88%)
Contract # 10123228
Totals 4638870.66 0.00 0.00 0.0

CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-076
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
1.176 5090960.00 0.00 0.00 0.0
CountyTRAVIS
Highway US 290
From 585 FT EAST OF CONVICT HILL
To 372 FT WEST OF JOE TANNER LANE
CSJ 0113-08-079
Proj ID RW 113-8-79
Work Type UTILITY ADJUSTMENTS
 
1.176 900042.50 0.00 0.00 0.0
CountyTRAVIS
Highway US 290
From 372 FT WEST OF JOE TANNER LANE
To 800 FT EAST OF JOE TANNER LANE
CSJ 0113-09-069
Proj ID NH 2013(403)
Work Type INNOVATIVE INTERSECTION IMPROVEMENT
 
0.222 532369.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 335
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CF JORDAN CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133227
Totals 6523371.50 0.00 0.00 0.0

CountyTRAVIS
Highway US 290
From AT LOOP 1
To .
CSJ 0113-09-052
Proj ID PTF 2010(873)
Work Type PHASE IV: CONST 2 REMAINING DIRECT C
 
1.018 8418678.59 17949.00 8770614.75 99.9
Work Order 08-20-10
Work Began 10-06-10
Work Completed  
Time Computed 10-06-10
Contract Working Days 370
Addl Days Granted 45
Working Days Charged 536
Percent Time Used 129
Contractor(s)
SAFECO INSURANCE COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 0113-09-052
HIGHWAY TECHNOLOGIES, INC. (0.33%)
MCKINNEY DRILLING__(BUDA)(2.77%)
ROADWAY SPECIALTIES, INC.(0.89%)
ASPHALT PAVING COMPANY OF AUSTIN, INC. (1.50%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (2.27%)
PRIME CONTRACTING, LLC ( 17.20%)
CHOCTAW ERECTORS, INC. (6.09%)
BREDA COMPANY, INC.(1.50%)
ARICON 3, INC. (6.27%)
A & R DEMOLITION (0.19%)
INDUS CONSTRUCTION, L.P. (1.25%)
KEYSTONE CONSTRUCTION INC. (0.99%)
ANDERSON COLUMBIA CO., INC.(0.00%)
PRIMATE CONSTRUCTION, INC. (0.14%)
SCOTT DERR PAINTING CO (0.23%)
Contract # 06103202
Totals 8418678.59 17949.00 8770614.75 99.9

CountyTRAVIS
Highway US 290
From E OF S CONGRESS
To W OF BURLESON RD
CSJ 0113-13-106
Proj ID NH 2010(122)
Work Type CONST 4 REMAINING DIRECT CONNECTORS
 
0.357 25630378.39 0.00 29111554.37 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-06-10
Work Began 05-03-10
Work Completed  
Time Computed 04-22-10
Contract Working Days 468
Addl Days Granted 44
Working Days Charged 512
Percent Time Used 100
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-106
AARON CONCRETE CONTRACTORS, L.P. (2.48%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (2.05%)
BMP SPECIALTIES, LLC.(0.06%)
BOOTHE BROTHERS PAVING COMPANY, INC. (0.53%)
CRAIG OLDEN, INC.(0.44%)
J.D. RAMMING PAVING CO., LTD.(5.29%)
HIGHWAY TECHNOLOGIES, INC. (1.68%)
MCKINNEY DRILLING COMPANY(1.80%)
RIVER CITIES SAWING LLC(0.10%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.54%)
ROADWAY SPECIALTIES, INC.(0.66%)
ROYAL VISTA INC. (1.69%)
INDUS CONSTRUCTION, L.P. (1.42%)
CENTRAL TEXAS REINFORCEMENT(0.17%)
PENNTEX MILLING, LLC (0.15%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.15%)
TEXAS CUTTING & CORING, INC. (0.24%)
Contract # 02103039
Totals 25630378.39 0.00 29111554.37 99.9

CountyTRAVIS
Highway US 290
From MANCHACA RD
To EAST OF CONGRESS AVE
CSJ 0113-13-144
Proj ID NH 1102(426)
Work Type REHABILITATE ROADWAY
 
2.331 1192681.83 0.00 1206410.59 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-13-11
Work Began 07-02-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 108
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-144
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (4.79%)
HIGHWAY TECHNOLOGIES, INC. ( 11.77%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.24%)
TEX OP CONSTRUCTION, LP(8.67%)
Contract # 08113221
Totals 1192681.83 0.00 1206410.59 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7