Monthly State Let Construction Report For Austin District As Of Feb 10, 2017 Page 3 Of 7

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS ETC
HighwaySS 69 ETC
FromAT AIRPORT BLVD
To.
CSJ0114-01-060
Proj IDSTP 2017(550)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.966985635.440.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0114-01-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173042
Totals985635.440.000.000.0

CountyTRAVIS
HighwayUS 290
FromUS 183
ToFM 734
CSJ0114-02-100
Proj IDNH 1502(382)
Work TypeLANDSCAPING AND IRRIGATION
 
5.751834000.00733565.3087.9
Work Order10-20-15
Work Began02-09-16
Work Completed
Time Computed12-19-15
Contract Working Days120
Addl Days Granted0
Working Days Charged109
Percent Time Used90
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-100
ENVIRONMENTAL SAFETY SERVICES, INC. (6.37)
FLASHER EQUIPMENT COMPANY (0.78)
AMAYA UTILITY (2.15)
Contract #07153061
Totals834000.003400.00733565.3087.9

CountyBASTROP ETC
HighwayUS 290 ETC
FromSH 95 NORTH
ToSL 109
CSJ0114-04-068
Proj IDSTP 2016(754)HES
Work TypeSAFETY LIGHTING
 
3.5322027917.00839910.0041.4
Work Order04-01-16
Work Began10-03-16
Work Completed
Time Computed05-01-16
Contract Working Days120
Addl Days Granted0
Working Days Charged59
Percent Time Used49
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-04-068
KRL CONSTRUCTION INC. (17.82)
ROADWAY SPECIALTIES, INC. (8.32)
AARON CONCRETE CONTRACTORS, L.P. (6.38)
PHILLIPS TRAFFIC CONTROL (0.28)
Contract #02163005
Totals2027917.0086674.00839910.0041.4

CountyBASTROP
HighwayUS 290
From8.864 MI E OF FM 696
ToFM 2104
CSJ0114-06-030
Proj IDC 114-6-30
Work TypeWIDEN GR STRS BS & SURF
 
5.56619049776.5820325716.5799.9
Work Order01-23-14
Work Began02-03-14
Work Completed
Time Computed02-03-14
Contract Working Days301
Addl Days Granted90
Working Days Charged390
Percent Time Used99
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-06-030
FLASHER EQUIPMENT COMPANY (0.19)
BMP SPECIALIST, LLC (1.67)
J & M CONTRACTING, COMPANY (3.65)
PANTHER CREEK TRANSPORTATION, INC. (0.78)
VOGES DRILLING CO. (0.31)
SCR CONSTRUCTION CO., INC. (2.40)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.13)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.26)
MURRAY CONSTRUCTION (0.34)
D. I. J. CONSTRUCTION, INC. (0.99)
GK CONSTRUCTION, LLC (0.00)
LOCKHART CONTRACTING SERVICES, INC. (0.75)
CENTEX HYDROSEED (0.37)
HEMPHILL PILE DRIVING CO., A CORP. (0.01)
PEDRO CARLOS CONSTRUCTION CO. (0.34)
WEST TEXAS RUMBLE STRIP (0.04)
Contract #11133204
Totals19049776.5858450.0120325716.5799.9

CountyMASON
HighwayUS 377
FromSH 29 (NEAR GRIT COMMUNITY)
ToMENARD COUNTY LINE
CSJ0149-04-016
Proj IDSTP 1602(489)HES
Work TypeIMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
15.328765167.50736078.0096.1
Work Order09-15-16
Work Began10-04-16
Work Completed
Time Computed10-04-16
Contract Working Days87
Addl Days Granted0
Working Days Charged57
Percent Time Used65
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0149-04-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163226
Totals765167.50105510.15736078.0096.1

CountyWILLIAMSON
HighwayUS 183
From0.152 MI S. OF ANDERSON MILL RD
To0.03 MI S. OF MCNEIL RD
CSJ0151-05-108
Proj IDNH 2014(888)
Work TypeMILL, SEAL & OVERLAY FRONTAGE RD
 
1.6361517070.861126037.8874.2
Work Order08-15-14
Work Began05-03-16
Work Completed
Time Computed08-31-14
Contract Working Days38
Addl Days Granted0
Working Days Charged32
Percent Time Used84
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-108
GREEN MILLING GROUP (5.11)
FLASHER EQUIPMENT COMPANY (2.02)
TRP CONSTRUCTION GROUP, LLC (1.42)
STRIPES & STOPS COMPANY, INC. (0.00)
Contract #07143040
Totals1517070.8631210.141126037.8874.2

CountyTRAVIS
HighwayUS 183
From0.714 MILES NORTH OF FM 812
To0.601 MILES NORTH OF FM 812
CSJ0152-01-078
Proj IDCC 152-1-78
Work TypeWIDEN BRIDGE AND INSTALL LT LANE
 
0.110432340.50103672.0023.9
Work Order11-15-16
Work Began12-19-16
Work Completed
Time Computed12-15-16
Contract Working Days60
Addl Days Granted0
Working Days Charged19
Percent Time Used31
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-078
ENVIRONMENTAL SAFETY SERVICES, INC. (5.97)
APAC-TEXAS, INC. (7.40)
FLASHER EQUIPMENT COMPANY (5.03)
VOGES DRILLING CO. (3.93)
GK CONSTRUCTION, LLC (0.23)
Contract #03163207
Totals432340.5035587.00103672.0023.9

CountyCALDWELL
HighwayUS 183
FromPECAN STREET
ToFM 20
CSJ0152-02-070
Proj IDC 152-2-70
Work TypeRECONSTRUCT TO 5-LN URBAN SECTION
 
1.1257221836.678040813.0799.9
CountyCALDWELL
HighwayUS 183
FromFM 20
To0.274 MI S. OF MLK/INDUSTRIAL BLVD
CSJ0152-03-057
Proj IDC 152-3-57
Work TypeRECONST TO 5-LANE URBAN SECTION
 
0.9094477082.25344371.717.6
Work Order04-25-14
Work Began03-23-15
Work Completed
Time Computed10-22-14
Contract Working Days267
Addl Days Granted1
Working Days Charged390
Percent Time Used145
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-070
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.89)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (6.48)
ROADWAY SPECIALTIES, INC. (0.62)
PIPELAYERS, INC. (25.18)
FLASHER EQUIPMENT COMPANY (1.70)
R K STEPHENS CONSTRUCTION, LLC (12.70)
HILL COUNTRY BRIDGE, INC (0.00)
A BROTHERS MILLING, LLC (0.14)
Contract #11133003
Totals11698918.92538955.408385184.7875.7

CountyCALDWELL
HighwayUS 183
FromAT CLEAR FORK PLUM CREEK
To(STR 152-3-9)
CSJ0152-03-056
Proj IDBR 1502(520)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2582746129.861673498.9465.4
Work Order10-30-15
Work Began02-11-16
Work Completed
Time Computed12-29-15
Contract Working Days213
Addl Days Granted53
Working Days Charged238
Percent Time Used89
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0152-03-056
FLASHER EQUIPMENT COMPANY (1.52)
APAC-TEXAS, INC. (7.60)
RICE ENVIRONMENTAL SERVICES (1.35)
W. W. FOUNDATION DRILLING, LTD. (3.13)
TEXOP CONSTRUCTION (0.25)
Contract #09153207
Totals2746129.8640634.061673498.9465.4

CountyWILLIAMSON
HighwayUS 79
FromAT FM 1460
To.
CSJ0204-01-061
Proj IDSTP 2015(570)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.100280240.68331053.7999.9
CountyCALDWELL
HighwaySH 142
FromAT FM 1966
To.
CSJ0384-01-022
Proj IDSTP 2015(571)HES
Work TypeADD FLASHING BEACON & SFTY LGHTNG
 
0.10028690.3427142.2194.6
CountyTRAVIS
HighwayFM 685
FromAT FM 1825
To.
CSJ0757-02-016
Proj IDSTP 2015(572)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.100125512.61137762.3699.9
Work Order05-08-15
Work Began02-02-16
Work Completed
Time Computed05-24-15
Contract Working Days67
Addl Days Granted0
Working Days Charged63
Percent Time Used94
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-061
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.70)
HIGHWAY 19 CONSTRUCTION, LLC (7.59)
FLASHER EQUIPMENT COMPANY (0.69)
TX DOWN UNDER CONSTRUCTION LLC (4.69)
UNION ELECTRICAL CONTRACTOR, INC. (2.01)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (2.01)
Contract #02153229
Totals434443.633120.16495958.3699.9

CountyWILLIAMSON
HighwayUS 79
FromFM 1460
To0.60 MILES EAST OF FM 1460
CSJ0204-01-067
Proj IDNH 1602(386)
Work TypeMEDIAN MODIFICATIONS
 
0.810265696.00144527.4755.5
Work Order09-14-16
Work Began11-14-16
Work Completed
Time Computed11-14-16
Contract Working Days28
Addl Days Granted0
Working Days Charged35
Percent Time Used125
Contractor(s)
NNA CONSTRUCTION & CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-067
N-LINE TRAFFIC MAINTENANCE, L.P. (4.71)
DIIBS SPECIALISTS (0.14)
TRP CONSTRUCTION GROUP, LLC (2.10)
WHEELER COATINGS ASPHALT, INC. (20.50)
Contract #07163013
Totals265696.0018061.37144527.4755.5

CountyBURNET
HighwayUS 281
FromLAMPASAS/BURNET COUNTY LINE
To1.688 MI S OF RM 2340
CSJ0251-07-025
Proj IDSTP 2017(569)HES
Work TypeCONVERT 4 LN UNDIV TO SUPER 2 W/SHL
 
18.3603585893.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days58
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0251-07-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173226
Totals3585893.330.000.000.0

CountyBLANCO
HighwayUS 281
From1.5 MI. NORTH OF CR 307
To0.6 MI. NORTH OF CR 307
CSJ0252-03-051
Proj IDSTP 1602(236)HES
Work TypeCNSTRCT PVD SHLDRS,CORRECT SUPRELV
 
0.900896922.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163241
Totals896922.600.000.000.0

CountyBASTROP
HighwaySH 71
FromAT TUCKER HILL LN
To.
CSJ0265-03-048
Proj IDSTP 2017(548)HES
Work TypeLENGTHEN LEFT TURN LANE
 
0.418286525.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0265-03-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173255
Totals286525.300.000.000.0

CountyBASTROP
HighwaySH 71
From0.268 MI. WEST OF SH 95
To0.477 MI. EAST OF SH 95
CSJ0265-05-067
Proj IDSTP 2012(629)
Work TypeCONST. OVERPASS AND 4 MAIN LNS
 
0.74515379463.017518778.3848.8
CountyBASTROP
HighwaySH 71
From0.358 MI. WEST OF SH 95
To0.268 MI. WEST OF SH 95
CSJ0265-05-078
Proj IDNH 1502(667)
Work TypeADD ENTRANCE RAMP BRIDGE
 
0.0911129745.52733787.4064.9
Work Order05-17-16
Work Began06-06-16
Work Completed
Time Computed06-06-16
Contract Working Days350
Addl Days Granted49
Working Days Charged150
Percent Time Used37
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-067
ABC EROSION CONTROL, INC. (0.73)
FLASHER EQUIPMENT COMPANY (0.53)
AARON CONCRETE CONTRACTORS, L.P. (5.19)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.22)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90)
ANCORTEX, INC. (5.88)
AUSTIN WOOD RECYCLING (0.10)
BRICK PAVING PLUS, INC. (0.43)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.10)
GK CONSTRUCTION, LLC (0.25)
HOUSTON SAWING & DRILLING (0.03)
MURRAY CONSTRUCTION (0.20)
ROADWAY SPECIALTIES, INC. (2.15)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
KRL CONSTRUCTION INC. (0.16)
AUSTIN FORMULA UTILITIES (0.19)
Contract #12153204
Totals16509208.53633425.888252565.7849.9

CountyBASTROP
HighwaySH 71
From0.654 MI WEST OF LP 150 EAST
To0.502 MI EAST OF LP 150 EAST
CSJ0265-05-071
Proj IDHP 2012(437)
Work TypeCONSTRUCT OVERPASS
 
1.15613669975.3713346681.8297.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began03-02-15
Work Completed
Time Computed03-01-15
Contract Working Days346
Addl Days Granted0
Working Days Charged307
Percent Time Used88
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-071
AARON CONCRETE CONTRACTORS, L.P. (4.81)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.63)
EGGEMEYER LAND CLEARING, LLC (0.28)
FLASHER EQUIPMENT COMPANY (0.73)
HOUSTON SAWING & DRILLING (0.03)
MCKINNEY DRILLING__(BUDA) (1.27)
MCL CONTRACTING, LLC (0.13)
MURRAY CONSTRUCTION (0.25)
OSCAR ORDUNO, INC. (1.31)
R K STEPHENS CONSTRUCTION, LLC (2.06)
ROADWAY SPECIALTIES, INC. (3.84)
SPEEDY PAVING (0.55)
CHANDLER CONCRETE, INC. (0.96)
AUSTIN FORMULA UTILITIES (0.17)
KRL CONSTRUCTION INC. (0.14)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
GREEN MILLING GROUP (0.18)
CENTRAL TEXAS REINFORCEMENT (0.07)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.25)
THOMAS TURF GRASS (0.33)
Contract #09143006
Totals13669975.370.0013346681.8297.6

CountyBURNET
HighwayUS 183
FromAT NORTH ROCKY CREEK
To.
CSJ0273-02-023
Proj IDBR 1502(384)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1952450973.551734020.8670.7
Work Order11-13-15
Work Began01-14-16
Work Completed
Time Computed12-13-15
Contract Working Days161
Addl Days Granted0
Working Days Charged149
Percent Time Used92
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0273-02-023
ENVIRONMENTAL SAFETY SERVICES, INC. (0.44)
ROADWAY SPECIALTIES, INC. (1.17)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.38)
Contract #09153032
Totals2450973.55122397.001734020.8670.7

CountyHAYS
HighwayRM 12
FromSADDLERIDGE DR
ToHUGO RD
CSJ0285-03-057
Proj IDSTP 2015(880)
Work TypeADD CENTER TURN LANE AND SHOULDERS
 
2.5033090648.553011648.6197.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-18-15
Work Began09-14-15
Work Completed
Time Computed08-18-15
Contract Working Days161
Addl Days Granted0
Working Days Charged167
Percent Time Used103
Contractor(s)
CURRAN CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0285-03-057
AUSTIN WOOD RECYCLING (1.43)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.22)
FLASHER EQUIPMENT COMPANY (2.66)
FUQUAY, INC. (13.12)
ROADWAY SPECIALTIES, INC. (1.29)
RUCOBA & MAYA CONSTRUCTION (10.18)
A BROTHERS MILLING, LLC (0.34)
Contract #04153018
Totals3090648.550.003011648.6197.6

CountyHAYS
HighwaySH 80
FromAT IH 35
To.
CSJ0286-01-055
Proj IDNH 2015(492)
Work TypeLANDSCAPING AND IRRIGATION
 
0.078295843.00282988.1099.6
Work Order02-10-15
Work Began04-27-15
Work Completed
Time Computed02-26-15
Contract Working Days60
Addl Days Granted0
Working Days Charged80
Percent Time Used133
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0286-01-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01153014
Totals295843.001500.00282988.1099.6

CountyCALDWELL
HighwaySH 80
FromUS 90
To0.999 MI. SOUTH OF US 90
CSJ0287-01-015
Proj IDSTP 2016(173)
Work TypeMILL, SEAL & INLAY
 
7.5082205029.542496508.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-24-15
Work Began06-16-16
Work Completed
Time Computed12-24-15
Contract Working Days40
Addl Days Granted0
Working Days Charged40
Percent Time Used100
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0287-01-015
TRP CONSTRUCTION GROUP, LLC (5.79)
GREEN MILLING GROUP (4.57)
SRIPE-IT-UP (1.08)
Contract #10153023
Totals2205029.540.002496508.9599.9