Monthly State Let Construction Report For Austin District As Of Nov 9, 2016 Page 3 Of 9

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway SL 360
From NORTH OF WALSH TARLTON
To SOUTH OF SL 1
CSJ 0113-13-157
Proj ID NH 2016(063)
Work Type WDN RDWY, OVRLY, SGLS, MBGF & PVMKS
 
1.771 6447812.17 548819.50 4008445.13 62.1
Work Order 11-16-15
Work Began 02-01-16
Work Completed  
Time Computed 02-01-16
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 93
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-157
INTERSTATE BARRICADES & MARKINGS, INC. (1.60%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 12.84%)
GK CONSTRUCTION, LLC (0.72%)
VOGES DRILLING CO. (0.90%)
ENVIRONMENTAL SAFETY SERVICES, INC.(6.09%)
ACU CONSTRUCTION LLC (0.32%)
APAC-TEXAS, INC. ( 26.78%)
KRL CONSTRUCTION INC.(2.47%)
G. CARTER CONSTRUCTION COMPANY, INC. (1.72%)
MYERS CONCRETE CONSTRUCTION, LP(2.59%)
AARON CONCRETE CONTRACTORS, L.P. (1.41%)
SPEEDY PAVING(2.26%)
Contract # 09153228
Totals 6447812.17 548819.50 4008445.13 62.1

CountyTRAVIS
Highway US 290
From US 290 AT SL 360
To .
CSJ 0113-13-158
Proj ID NH 1402(052)
Work Type LANDSCAPING
 
0.001 990414.00 2000.00 738144.00 74.5
CountyTRAVIS
Highway RM 620
From LOHMANS SPUR
To LOHMANS CROSSING
CSJ 0683-02-060
Proj ID STP 1402(053)
Work Type LANDSCAPING
 
0.472 373720.00 2000.00 261028.00 69.8
Work Order 11-05-14
Work Began 12-01-14
Work Completed  
Time Computed 11-21-14
Contract Working Days 60
Addl Days Granted 29
Working Days Charged 89
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-158
CLASSIC TEJAS CONSTRUCTION, INC. (5.15%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.89%)
TX DOWN UNDER CONSTRUCTION LLC (0.51%)
Contract # 08143047
Totals 1364134.00 4000.00 999172.00 73.2

CountyTRAVIS
Highway SL 360
From COURTYARD DR.
To WESTBANK DRIVE
CSJ 0113-13-161
Proj ID NH 1502(588)
Work Type GRADING, BASE, ACP & PVMNT MARKINGS
 
6.032 1169830.75 0.00 1911090.50 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-15
Work Began 01-18-16
Work Completed  
Time Computed 01-18-16
Contract Working Days 48
Addl Days Granted 26
Working Days Charged 74
Percent Time Used 100
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-161
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(2.66%)
LONE STAR PAVING ( 42.31%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.81%)
TRP CONSTRUCTION GROUP, LLC(3.48%)
Contract # 08153052
Totals 1169830.75 0.00 1911090.50 99.9

CountyTRAVIS
Highway US 290
From IH 35
To 0.04 MI W OF CAMERON RD
CSJ 0114-01-058
Proj ID STP 1502(589)HES
Work Type INSTALL MEDIAN BARRIER
 
0.685 63640.00 0.00 96213.12 99.9
CountyTRAVIS
Highway SS 69
From 0.571 MI W OF IH 35
To IH 35
CSJ 0114-01-059
Proj ID STP 1502(590)HES
Work Type INSTALL MEDIAN BARRIERS
 
0.571 525865.00 0.00 561338.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-15
Work Began 03-01-16
Work Completed  
Time Computed 11-18-15
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 132
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-01-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153248
Totals 589505.00 0.00 657551.72 99.9

CountyTRAVIS
Highway US 290
From 0.86 MI. EAST OF FM 734
To 0.06 MI. EAST OF 973
CSJ 0114-02-095
Proj ID NH 2014(515)
Work Type OVERLAY & RESTRIPE FOR AUX LANE
 
1.730 1076946.60 0.00 1356689.64 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 12-22-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 165
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-095
TRP CONSTRUCTION GROUP, LLC(4.87%)
MPB, INC.(4.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.53%)
A BROTHERS MILLING, LLC(4.34%)
ROADWAY SPECIALTIES, INC.(0.00%)
ROADWAY SPECIALTIES, INC.(6.01%)
Contract # 03143225
Totals 1076946.60 0.00 1356689.64 99.9

CountyTRAVIS
Highway US 290
From US 183
To FM 734
CSJ 0114-02-100
Proj ID NH 1502(382)
Work Type LANDSCAPING AND IRRIGATION
 
5.751 834000.00 3400.00 726765.30 87.1
Work Order 10-20-15
Work Began 02-09-16
Work Completed  
Time Computed 12-19-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 90
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-100
ENVIRONMENTAL SAFETY SERVICES, INC.(6.37%)
FLASHER EQUIPMENT COMPANY(0.78%)
AMAYA UTILITY(2.15%)
Contract # 07153061
Totals 834000.00 3400.00 726765.30 87.1

CountyTRAVIS
Highway US 290
From 0.091 MI. WEST OF WILLOW CREEK
To 0.083 MI. EAST OF WILLOW CREEK
CSJ 0114-03-025
Proj ID BR 2015(878)
Work Type REPLACE BRIDGE
 
0.174 1623285.68 145661.17 1716427.31 99.9
Work Order 06-08-15
Work Began 08-10-15
Work Completed  
Time Computed 07-09-15
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 95
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-03-025
VOGES DRILLING CO. (2.97%)
PENHALL COMPANY (AUSTIN) (0.25%)
FLASHER EQUIPMENT COMPANY(1.93%)
ENVIRONMENTAL SAFETY SERVICES, INC.(5.10%)
ACU CONSTRUCTION LLC (1.99%)
WHEELER COATINGS ASPHALT, L.P. ( 25.55%)
Contract # 04153038
Totals 1623285.68 145661.17 1716427.31 99.9

CountyBASTROP
Highway US 290 ETC
From SH 95 NORTH
To SL 109
CSJ 0114-04-068
Proj ID STP 2016(754)HES
Work Type SAFETY LIGHTING
 
3.532 2027917.00 360238.00 387994.00 19.1
Work Order 04-01-16
Work Began 10-03-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 14
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-04-068
KRL CONSTRUCTION INC.( 17.82%)
ROADWAY SPECIALTIES, INC.(8.32%)
AARON CONCRETE CONTRACTORS, L.P. (6.38%)
Contract # 02163005
Totals 2027917.00 360238.00 387994.00 19.1

CountyBASTROP
Highway US 290
From 8.864 MI E OF FM 696
To FM 2104
CSJ 0114-06-030
Proj ID C 114-6-30
Work Type WIDEN GR STRS BS & SURF
 
5.566 19049776.58 87760.21 20148537.22 99.9
Work Order 01-23-14
Work Began 02-03-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 301
Addl Days Granted 62
Working Days Charged 390
Percent Time Used 107
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0114-06-030
FLASHER EQUIPMENT COMPANY(0.19%)
BMP SPECIALIST, LLC(1.67%)
J & M CONTRACTING, COMPANY (3.65%)
PANTHER CREEK TRANSPORTATION, INC. (0.78%)
VOGES DRILLING CO. (0.31%)
SCR CONSTRUCTION CO., INC. (2.40%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.13%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.26%)
MURRAY CONSTRUCTION(0.34%)
D. I. J. CONSTRUCTION, INC.(0.99%)
GK CONSTRUCTION, LLC (0.00%)
LOCKHART CONTRACTING SERVICES, INC.(0.75%)
CENTEX HYDROSEED (0.37%)
HEMPHILL PILE DRIVING CO., A CORP. (0.01%)
PEDRO CARLOS CONSTRUCTION CO.(0.34%)
WEST TEXAS RUMBLE STRIP(0.04%)
Contract # 11133204
Totals 19049776.58 87760.21 20148537.22 99.9

CountyMASON
Highway US 377
From SH 29 (NEAR GRIT COMMUNITY)
To MENARD COUNTY LINE
CSJ 0149-04-016
Proj ID STP 1602(489)HES
Work Type IMPROVE GUARDRAIL & SFT TRT FXD OBJ
 
15.328 765167.50 283692.75 286057.25 37.3
Work Order 09-15-16
Work Began 10-04-16
Work Completed  
Time Computed 10-04-16
Contract Working Days 87
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 18
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0149-04-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163226
Totals 765167.50 283692.75 286057.25 37.3

CountyMASON
Highway SH 29
From MASON E CITY LIMITS
To MASON/LLANO COUNTY LINE
CSJ 0150-01-025
Proj ID STP 2016(391)
Work Type LEVEL UP & SEAL COAT
 
27.556 3757541.67 17500.90 3622738.74 96.4
Work Order 01-29-16
Work Began 06-09-16
Work Completed  
Time Computed 02-28-16
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 54
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0150-01-025
D. I. J. CONSTRUCTION, INC.(6.03%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 23.40%)
TRP CONSTRUCTION GROUP, LLC(0.24%)
Contract # 12153219
Totals 3757541.67 17500.90 3622738.74 96.4

CountyWILLIAMSON
Highway US 183
From APPROX. 920' S OF 183A
To RM 2243
CSJ 0151-04-067
Proj ID NH 2013(474)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
1.824 867875.03 0.00 706704.83 81.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-13
Work Began 06-30-14
Work Completed  
Time Computed 08-02-13
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 118
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-04-067
TEX OP CONSTRUCTION, LP(0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38%)
ROADWAY SPECIALTIES, INC.(0.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90%)
TEXAS TRUCKING COMPANY, INC. (2.49%)
D. I. J. CONSTRUCTION, INC.(4.91%)
Contract # 03133034
Totals 867875.03 0.00 706704.83 81.8

CountyWILLIAMSON
Highway US 183
From 0.030 MI SOUTH OF LAKE CREEK PKWY
To 0.152 MI SOUTH OF ANDERSON MILL RD
CSJ 0151-05-098
Proj ID STP 2014(518)
Work Type MILL, SEAL & OVERLAY NB & SB FRT RD
 
1.000 588778.08 0.00 584803.74 99.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 11-23-15
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 62
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-098
FLASHER EQUIPMENT COMPANY(5.50%)
THE LEVY COMPANY, L.P. (5.35%)
A BROTHERS MILLING, LLC(3.99%)
GREEN MILLING GROUP(3.99%)
Contract # 03143209
Totals 588778.08 0.00 584803.74 99.3

CountyWILLIAMSON
Highway US 183
From 0.152 MI S. OF ANDERSON MILL RD
To 0.03 MI S. OF MCNEIL RD
CSJ 0151-05-108
Proj ID NH 2014(888)
Work Type MILL, SEAL & OVERLAY FRONTAGE RD
 
1.636 1517070.86 115931.42 1094827.74 72.1
Work Order 08-15-14
Work Began 05-03-16
Work Completed  
Time Computed 08-31-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 84
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-108
GREEN MILLING GROUP(5.11%)
FLASHER EQUIPMENT COMPANY(2.02%)
TRP CONSTRUCTION GROUP, LLC(1.42%)
STRIPES & STOPS COMPANY, INC.(0.00%)
Contract # 07143040
Totals 1517070.86 115931.42 1094827.74 72.1

CountyTRAVIS
Highway US 183
From 0.714 MILES NORTH OF FM 812
To 0.601 MILES NORTH OF FM 812
CSJ 0152-01-078
Proj ID CC 152-1-78
Work Type WIDEN BRIDGE AND INSTALL LT LANE
 
0.110 432340.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163207
Totals 432340.50 0.00 0.00 0.0

CountyCALDWELL
Highway US 183
From PECAN STREET
To FM 20
CSJ 0152-02-070
Proj ID C 152-2-70
Work Type RECONSTRUCT TO 5 - LN URBAN SECTION
 
1.125 7221836.67 386861.90 6776964.72 99.9
CountyCALDWELL
Highway US 183
From FM 20
To 0.274 MI S. OF MLK/INDUSTRIAL BLVD
CSJ 0152-03-057
Proj ID C 152-3-57
Work Type RECONST TO 5 - LANE URBAN SECTION
 
0.909 4477082.25 16777.75 194339.82 4.3
Work Order 04-25-14
Work Began 03-23-15
Work Completed  
Time Computed 10-22-14
Contract Working Days 267
Addl Days Granted 1
Working Days Charged 390
Percent Time Used 145
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-070
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.89%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(6.48%)
ROADWAY SPECIALTIES, INC.(0.62%)
PIPELAYERS, INC. ( 25.18%)
FLASHER EQUIPMENT COMPANY(1.70%)
R K STEPHENS CONSTRUCTION, LLC ( 12.70%)
HILL COUNTRY BRIDGE, INC (0.00%)
Contract # 11133003
Totals 11698918.92 403639.65 6971304.54 63.6

CountyCALDWELL
Highway US 183
From AT CLEAR FORK PLUM CREEK
To (STR 152-3-9)
CSJ 0152-03-056
Proj ID BR 1502(520)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.258 2746129.86 93788.28 1418630.78 54.0
Work Order 10-30-15
Work Began 02-11-16
Work Completed  
Time Computed 12-29-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 83
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0152-03-056
FLASHER EQUIPMENT COMPANY(1.52%)
APAC-TEXAS, INC. (7.60%)
RICE ENVIRONMENTAL SERVICES(1.35%)
W. W. FOUNDATION DRILLING, LTD.(3.13%)
TEXOP CONSTRUCTION (0.38%)
Contract # 09153207
Totals 2746129.86 93788.28 1418630.78 54.0

CountyWILLIAMSON
Highway US 79
From AT FM 1460
To .
CSJ 0204-01-061
Proj ID STP 2015(570)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 280240.68 0.00 324397.78 99.9
CountyCALDWELL
Highway SH 142
From AT FM 1966
To .
CSJ 0384-01-022
Proj ID STP 2015(571)HES
Work Type ADD FLASHING BEACON & SFTY LGHTNG
 
0.100 28690.34 0.00 24579.49 85.6
CountyTRAVIS
Highway FM 685
From AT FM 1825
To .
CSJ 0757-02-016
Proj ID STP 2015(572)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 125512.61 0.00 108930.21 86.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-15
Work Began 02-02-16
Work Completed  
Time Computed 05-24-15
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 94
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-061
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.70%)
HIGHWAY 19 CONSTRUCTION, LLC (7.59%)
FLASHER EQUIPMENT COMPANY(0.69%)
TX DOWN UNDER CONSTRUCTION LLC (4.69%)
UNION ELECTRICAL CONTRACTOR, INC.(2.01%)
SHERON STONE DBA DOUBLE-S CONSTRUCTION (2.01%)
Contract # 02153229
Totals 434443.63 0.00 457907.48 99.9

CountyWILLIAMSON
Highway US 79
From 0.42 MILES W. OF FM 1460
To CR 110
CSJ 0204-01-062
Proj ID NH 2015(632)
Work Type MILL, SEAL & THIN OVERLAY
 
3.903 2077266.70 0.00 2263766.80 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-15
Work Began 06-22-15
Work Completed  
Time Computed 05-08-15
Contract Working Days 61
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 98
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-062
ROADWAY SPECIALTIES, INC.( 13.53%)
SCR CONSTRUCTION CO., INC. (0.49%)
FLASHER EQUIPMENT COMPANY(6.72%)
Contract # 02153030
Totals 2077266.70 0.00 2263766.80 99.9

CountyWILLIAMSON
Highway US 79
From FM 1460
To 0.60 MILES EAST OF FM 1460
CSJ 0204-01-067
Proj ID NH 1602(386)
Work Type MEDIAN MODIFICATIONS
 
0.810 265696.00 0.00 4750.00 1.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NNA CONSTRUCTION & CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-067
N-LINE TRAFFIC MAINTENANCE, L.P. (4.71%)
DIIBS SPECIALISTS(0.14%)
TRP CONSTRUCTION GROUP, LLC(2.10%)
WHEELER COATINGS ASPHALT, INC. ( 20.50%)
Contract # 07163013
Totals 265696.00 0.00 4750.00 1.7