Monthly State Let Construction Report For Austin District As Of Aug 12, 2014 Page 3 Of 8

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLEE
Highway SH 21
From 0.383 MI. W OF FM 3403
To 0.009 MI. W OF FM 141
CSJ 0116-01-028
Proj ID NH 2013(191)
Work Type ADD SHLDRS., PAV REPAIR, SEAL COAT
 
10.251 7525070.79 61038.18 7393476.10 98.2
Work Order 01-23-13
Work Began 03-11-13
Work Completed  
Time Computed 03-11-13
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 168
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0116-01-028
AUSTIN WOOD RECYCLING(1.25%)
COWBELL TRAFFIC SERVICES, INC. (0.13%)
D. I. J. CONSTRUCTION, INC.(3.55%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.91%)
HIGHWAY TECHNOLOGIES, INC. (0.37%)
ROADWAY SPECIALTIES, INC.(1.92%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.24%)
FLASHER EQUIPMENT COMPANY(0.37%)
NEWMAN & KENG PAVING COMPANY, INC. (6.95%)
TEXAS CUTTING & CORING, INC. (0.13%)
Contract # 11123217
Totals 7525070.79 61038.18 7393476.10 98.2

CountyBURNET
Highway SH 29
From 0.344 MILES WEST OF CR 258/303
To 0.342 MILES EAST OF CR 258/303
CSJ 0151-01-042
Proj ID STP 1402(054)
Work Type ADD LEFT TURN LANE
 
0.686 577171.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0151-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143208
Totals 577171.90 0.00 0.00 0.0

CountyWILLIAMSON
Highway SH 29
From 1145 FT. WEST OF CR 200
To FM 1869
CSJ 0151-03-039
Proj ID STP 2013(338)
Work Type MILL, SEAL & OVERLAY
 
1.542 509202.94 0.00 525180.59 99.9
CountyWILLIAMSON
Highway SH 29
From FM 1869
To 1775 FT. EAST OF EAST END OF LP 332
CSJ 0151-04-068
Proj ID STP 2013(338)
Work Type MILL, SEAL & OVERLAY
 
0.704 217918.73 0.00 247546.94 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-13
Work Began 09-15-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 56
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-03-039
D. I. J. CONSTRUCTION, INC.(3.98%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.33%)
PENNTEX MILLING INC. (0.68%)
TEXAS TRUCKING COMPANY, INC. (3.00%)
Contract # 01133029
Totals 727121.67 0.00 772727.53 99.9

CountyWILLIAMSON
Highway US 183
From APPROX. 920' S OF 183A
To RM 2243
CSJ 0151-04-067
Proj ID NH 2013(474)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
1.824 867875.03 232102.29 232102.29 26.7
Work Order 06-03-13
Work Began 06-30-14
Work Completed  
Time Computed 08-02-13
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 54
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-04-067
TEX OP CONSTRUCTION, LP(0.46%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38%)
ROADWAY SPECIALTIES, INC.(0.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.90%)
TEXAS TRUCKING COMPANY, INC. (2.49%)
D. I. J. CONSTRUCTION, INC.(4.91%)
Contract # 03133034
Totals 867875.03 232102.29 232102.29 26.7

CountyWILLIAMSON
Highway US 183
From RM 2243
To DISCOVERY BLVD.
CSJ 0151-05-096
Proj ID NH 2014(517)
Work Type PAVEMENT REPAIR, UNDERSEAL & OVERLAY
 
4.445 1540182.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-17-14
Work Began 00-00-00
Work Completed  
Time Computed 05-03-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143023
Totals 1540182.25 0.00 0.00 0.0

CountyWILLIAMSON
Highway US 183
From AT NEW HOPE DRIVE
To .
CSJ 0151-05-097
Proj ID C 151-5-97
Work Type CONSTRUCT DECELERATION LANE
 
0.100 529532.04 174.75 616843.66 99.9
Work Order 11-20-13
Work Began 01-28-14
Work Completed  
Time Computed 01-19-14
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 100
Contractor(s)
BPI ENVIRONMENTAL SERVICES INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-097
FLASHER EQUIPMENT COMPANY(2.51%)
RAMMING PAVING COMPANY ( 23.92%)
SPEEDY PAVING(0.55%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.34%)
Contract # 08133059
Totals 529532.04 174.75 616843.66 99.9

CountyWILLIAMSON
Highway US 183
From 0.030 MI SOUTH OF LAKE CREEK PKWY
To 0.152 MI SOUTH OF ANDERSON MILL RD
CSJ 0151-05-098
Proj ID STP 2014(518)
Work Type MILL, SEAL & OVERLAY NB & SB FRT RD
 
1.000 588778.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-098
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143209
Totals 588778.08 0.00 0.00 0.0

CountyWILLIAMSON
Highway US 183
From 350 FEET NORTH OF WALTON WAY
To 350 FEET SOUTH OF WALTON WAY
CSJ 0151-05-103
Proj ID C 151-5-103
Work Type ADD RIGHT TURN & DUAL LEFT TURN LANES
 
0.100 344399.00 13986.77 113303.43 37.6
Work Order 10-04-13
Work Began 03-10-14
Work Completed  
Time Computed 10-20-13
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 150
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-103
BUYERS BARRICADES, INC.(1.91%)
ROADMASTER, INC. (1.32%)
WHEELER COATINGS ASPHALT, INC. ( 44.64%)
Contract # 08133256
Totals 344399.00 13986.77 113303.43 37.6

CountyWILLIAMSON
Highway US 183
From 0.152 MI S. OF ANDERSON MILL RD
To 0.03 MI S. OF MCNEIL RD
CSJ 0151-05-108
Proj ID NH 2014(888)
Work Type MILL, SEAL & OVERLAY FRONTAGE RD
 
1.636 1517070.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0151-05-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143040
Totals 1517070.86 0.00 0.00 0.0

CountyTRAVIS
Highway US 183
From LP 1
To LP 360
CSJ 0151-06-136
Proj ID NH 1402(045)
Work Type REPAIR, MILL, SEAL & OVERLAY FRT RDS
 
0.884 459965.16 0.00 0.00 0.0
CountyTRAVIS
Highway SL 1
From BRAKER LANE
To 1200 FT. NORTH OF STECK AVENUE
CSJ 3136-01-181
Proj ID NH 1402(045)
Work Type REPAIR, MILL, SEAL & OVERLAY FRT RD
 
1.794 895396.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-06-136
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143243
Totals 1355361.64 0.00 0.00 0.0

CountyTRAVIS
Highway US 183
From BURLESON RD
To FM 812
CSJ 0152-01-077
Proj ID NH 2014(303)
Work Type OVERLAY
 
1.290 698386.33 606599.45 859042.43 99.9
Work Order 01-17-14
Work Began 06-17-14
Work Completed  
Time Computed 02-02-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 68
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-01-077
SCR CONSTRUCTION CO., INC. (5.06%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.96%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.16%)
BMP SPECIALIST, LLC(8.07%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
Contract # 12133011
Totals 698386.33 606599.45 859042.43 99.9

CountyCALDWELL
Highway US 183
From PECAN STREET
To FM 20
CSJ 0152-02-070
Proj ID C 152-2-70
Work Type RECONSTRUCT TO 5 - LN URBAN SECTION
 
1.125 7221836.67 0.00 94059.00 1.3
CountyCALDWELL
Highway US 183
From FM 20
To 0.274 MI S. OF MLK/INDUSTRIAL BLVD
CSJ 0152-03-057
Proj ID C 152-3-57
Work Type RECONST TO 5 - LANE URBAN SECTION
 
0.909 4477082.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 267
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133003
Totals 11698918.92 0.00 94059.00 0.8

CountyCALDWELL
Highway US 183
From 5.0 MI SOUTH OF FM 20
To 0.5 MI SOUTH OF FM 86
CSJ 0152-03-053
Proj ID NH 2013(553)
Work Type PAVEMENT REPAIR, MILL, SEAL & OVERLAY
 
8.000 7526709.80 804.80 6857066.69 91.1
Work Order 06-20-13
Work Began 06-26-13
Work Completed  
Time Computed 06-26-13
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 172
Percent Time Used 98
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0152-03-053
FLASHER EQUIPMENT COMPANY(0.27%)
RELMCO, INC. (2.20%)
D. I. J. CONSTRUCTION, INC.(2.29%)
ROADWAY SPECIALTIES, INC.(1.99%)
R.P.V. CONSTRUCTION(0.05%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 04133206
Totals 7526709.80 804.80 6857066.69 91.1

CountyWILLIAMSON
Highway US 79
From COTTONWOOD CREEK BRDG EAST ABUTMENT
To EXCHANGE BOULEVARD
CSJ 0204-02-030
Proj ID NH 2014(359)
Work Type MILL, UNDERSEAL & THIN OVERLAY
 
1.008 554433.42 39626.75 558740.86 99.9
Work Order 03-04-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0204-02-030
ALTUS TRAFFIC MANAGEMENT LLC (0.58%)
CHEROKEE SERVICES(0.73%)
D. I. J. CONSTRUCTION, INC.(4.35%)
R K STEPHENS CONSTRUCTION, LLC (3.59%)
ROADWAY SPECIALTIES, INC.(5.93%)
TEX OP CONSTRUCTION, LP(6.19%)
Contract # 01143225
Totals 554433.42 39626.75 558740.86 99.9

CountyLEE
Highway US 77
From AT SPRING BRANCH
To (STR 211-2-33)
CSJ 0211-02-024
Proj ID BR 2014(616)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.193 1883084.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-23-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-02-024
N-LINE TRAFFIC MAINTENANCE, L.P. (0.27%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.24%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
ROADWAY SPECIALTIES, INC.(2.49%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.58%)
Contract # 04143036
Totals 1883084.21 0.00 0.00 0.0

CountyLEE
Highway US 77 ETC
From MILAM COUNTY LINE
To LP 123 NORTH
CSJ 0211-02-025
Proj ID STP 2014(889)HESG
Work Type TEXTURIZE SHOULDERS - PROFILE MARKERS
 
62.679 284700.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 16
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0211-02-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143227
Totals 284700.16 0.00 0.00 0.0

CountyLEE
Highway US 77
From 1.829 MI. SOUTH OF US 290
To FAYETTE COUNTY LINE
CSJ 0211-05-018
Proj ID NH 2014(711)
Work Type PAVEMENT REPAIR, LEVEL - UP & SEAL
 
5.618 1225862.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-18-14
Work Began 00-00-00
Work Completed  
Time Computed 08-03-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0211-05-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143026
Totals 1225862.63 0.00 0.00 0.0

CountyBURNET
Highway US 281
From ON US 281 AT COLORADO RIVER
To (STR 0252-02-017)
CSJ 0252-02-046
Proj ID BR 2010(786)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.568 28272713.57 978370.54 27459321.76 97.1
CountyBURNET
Highway US 281
From ON US 281 AT COLORADO RIVER
To .
CSJ 0252-02-049
Proj ID BR 2009(641)
Work Type ROW ACQ. AND RELOC. ASSIST.
 
0.001 375131.40 0.00 366309.84 97.6
Work Order 07-15-10
Work Began 12-07-10
Work Completed  
Time Computed 12-07-10
Contract Working Days 1,177
Addl Days Granted 0
Working Days Charged 1,040
Percent Time Used 88
Contractor(s)
ARCHER-WESTERN CONTRACTORS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0252-02-046
AARON CONCRETE CONTRACTORS, L.P. (0.65%)
AFS ENVIRONMENTAL, INC.(0.22%)
APAC-TEXAS, INC. (2.51%)
BPI ENVIRONMENTAL SERVICES INC.(0.61%)
BREDA COMPANY, INC.(0.37%)
CONCRETE CUTTING BY BOND (0.11%)
DUSTROL, INC. (ROANOKE)(0.01%)
PENHALL COMPANY(0.07%)
ROADWAY SPECIALTIES, INC.(1.73%)
SCOTT DERR PAINTING CO, LLC(0.37%)
THE LEVY COMPANY, L.P. (2.27%)
TREVCON, INC.(1.90%)
W. W. FOUNDATION DRILLING, LTD.(3.29%)
PANTHER CREEK TRANSPORTATION, INC. (0.35%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.02%)
HIGHWAY TECHNOLOGIES, INC. (0.23%)
SWEEP ACROSS TEXAS (0.00%)
MUSTANG COLT SERVICES, INC.(0.00%)
OMEGA DEMOLITION CORPORATION (3.33%)
D. I. J. CONSTRUCTION, INC.(0.13%)
Contract # 05103201
Totals 28647844.97 978370.54 27825631.60 97.1

CountyBLANCO
Highway US 281 ETC
From BURNET C/L
To US 290 IN JOHNSON CITY
CSJ 0252-03-049
Proj ID STP 2011(045)HES
Work Type GUARDRAIL & SAFETY TREAT FIXED OBJCTS
 
66.151 1471795.60 0.00 1631966.84 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-10
Work Began 10-25-10
Work Completed  
Time Computed 10-25-10
Contract Working Days 360
Addl Days Granted 55
Working Days Charged 413
Percent Time Used 99
Contractor(s)
WAGNER MATERIALS & CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0252-03-049
HILL COUNTRY BRIDGE, INC.( 45.55%)
F.D. CONCRETE, LLC (9.89%)
RICE ENVIRONMENTAL SERVICES( 16.33%)
M.V. HENKE ENTERPRISES, INC. (0.95%)
Contract # 07103068
Totals 1471795.60 0.00 1631966.84 99.9

CountyBLANCO
Highway US 281
From SOUTH OF RM 32
To 0.422 MI. SOUTH OF KOCH ROAD
CSJ 0253-01-055
Proj ID C 253-1-55
Work Type UPGRADE TO SUPER 2
 
2.550 2620770.59 85305.69 2089303.42 79.7
CountyBLANCO
Highway US 281
From 0.422 MI. SOUTH OF KOCH ROAD
To STALLION ESTATE ROAD
CSJ 0253-02-030
Proj ID C 253-2-30
Work Type UPGRADE TO SUPER 2
 
4.800 3680726.21 102238.50 2013023.20 54.6
Work Order 11-14-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 146
Addl Days Granted 15
Working Days Charged 155
Percent Time Used 96
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0253-02-030
VEGETATION MANAGEMENT SERVICES (0.60%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.20%)
DU MOR ENTERPRISES (1.05%)
MPB, INC.( 10.78%)
ROADWAY SPECIALTIES, INC.(3.17%)
D&S TEXAS ICON CONSTRUCTION, LLC (2.31%)
D. I. J. CONSTRUCTION, INC.(1.37%)
EGGEMEYER LAND CLEARING, LLC (1.39%)
Contract # 08133021
Totals 6301496.80 187544.19 4102326.62 65.1