Monthly State Let Construction Report For Austin District As Of Aug 12, 2014 Page 7 Of 8

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTRAVIS
Highway FM 973
From FM 812
To US 183
CSJ 1200-05-017
Proj ID STP 2013(477)
Work Type PVMT REPAIR, SEAL & THIN OVERLAY
 
2.481 742733.15 0.00 680825.94 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 03-03-14
Work Completed 07-30-14
Time Computed 07-22-13
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 21
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1200-05-017
FLASHER EQUIPMENT COMPANY(4.96%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
ROADWAY SPECIALTIES, INC.(0.13%)
Contract # 03133014
Totals 742733.15 0.00 680825.94 100.0

CountyTRAVIS
Highway SH 45
From AT KENDRICK BLVD
To .
CSJ 1200-06-007
Proj ID STP 2013(931)
Work Type INSTALL LTL & PAVED SHOULDERS
 
0.208 540496.95 4000.00 525349.59 100.0
Work Order 01-06-14
Work Began 03-03-14
Work Completed 07-24-14
Time Computed 01-22-14
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 96
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-007
FLASHER EQUIPMENT COMPANY(5.78%)
N-LINE TRAFFIC MAINTENANCE, L.P. (3.13%)
LONE STAR PAVING CO. ( 53.50%)
ABC EROSION CONTROL, INC.(1.08%)
Contract # 08133265
Totals 540496.95 4000.00 525349.59 100.0

CountyTRAVIS
Highway SH 45
From LOOP 1
To RM 1826
CSJ 1200-06-010
Proj ID STP 2014(724)
Work Type MILL, SEAL & THIN OVERLAY
 
2.599 1283793.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-04-14
Work Began 00-00-00
Work Completed  
Time Computed 08-20-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1200-06-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143028
Totals 1283793.90 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 487
From SH 195
To 1500 FEET WEST OF CR 233
CSJ 1201-02-019
Proj ID STP 2014(420)
Work Type REHAB RDWY
 
5.303 6128687.87 420581.19 593487.58 9.6
Work Order 04-16-14
Work Began 06-25-14
Work Completed  
Time Computed 05-02-14
Contract Working Days 287
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 3
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1201-02-019
AARON CONCRETE CONTRACTORS, L.P. (1.40%)
AUSTIN WOOD RECYCLING(1.19%)
TEXAS HIGHWAY WALLS(5.57%)
R K STEPHENS CONSTRUCTION, LLC (3.21%)
D. I. J. CONSTRUCTION, INC.(0.77%)
J & M CONTRACTING, COMPANY (7.41%)
ROADWAY SPECIALTIES, INC.(2.24%)
Contract # 02143227
Totals 6128687.87 420581.19 593487.58 9.6

CountyWILLIAMSON
Highway FM 487
From BELL C/L
To BELL C/L IN BARTLETT
CSJ 1201-03-021
Proj ID STP 2012(417)
Work Type PAVMNT RESTORATION AND ADD SHLDRS
 
7.520 6421595.35 302011.32 3508545.12 54.6
CountyBELL
Highway FM 487
From WILLIAMSON CO LINE W OF FM 2115
To WILLIAMSON CO LINE E OF FM 2115
CSJ 1201-05-010
Proj ID STP 2012(423)
Work Type PAV RESTORATION AND ADD SHOULDERS
 
0.395 285832.17 2657.25 286490.20 99.9
Work Order 05-04-12
Work Began 05-20-13
Work Completed  
Time Computed 05-20-12
Contract Working Days 391
Addl Days Granted 0
Working Days Charged 226
Percent Time Used 57
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1201-03-021
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
SILVA CONTRACTING COMPANY, INC.( 11.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%)
MURRAY CONSTRUCTION(0.48%)
D. I. J. CONSTRUCTION, INC.(1.28%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.04%)
JAG TRUCKING INC (0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
THE LEVY COMPANY, L.P. (0.25%)
R K STEPHENS CONSTRUCTION, LLC (6.66%)
Contract # 03123002
Totals 6707427.52 304668.57 3795035.32 56.5

CountyWILLIAMSON
Highway FM 972
From 0.652 MI E OF FM 1105
To 0.841 MI E OF FM 1105
CSJ 1202-01-016
Proj ID BR 2013(932)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.189 535693.01 0.00 565531.14 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-13
Work Began 01-16-14
Work Completed  
Time Computed 12-09-13
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 91
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1202-01-016
GK CONSTRUCTION, LLC (1.06%)
BEAIRD DRILLING(4.90%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.46%)
ROADWAY SPECIALTIES, INC.(2.84%)
RAMMING PAVING COMPANY (8.93%)
D. I. J. CONSTRUCTION, INC.(1.12%)
Contract # 08133270
Totals 535693.01 0.00 565531.14 99.9

CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK
To (STR 1202-3-12)
CSJ 1202-03-010
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.115 643228.90 7297.65 151690.62 23.5
CountyWILLIAMSON
Highway FM 1063
From AT TURKEY CREEK RELIEF
To (STR 1202-3-11)
CSJ 1202-03-011
Proj ID BR 2014(534)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 286828.45 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1063
From AT DRAW
To (STR 1202-3-10)
CSJ 1202-03-012
Proj ID BR 2014(673)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.131 609386.85 170799.80 315660.40 51.7
Work Order 04-25-14
Work Began 05-19-14
Work Completed  
Time Computed 05-11-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 28
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1202-03-010
FLASHER EQUIPMENT COMPANY(1.52%)
GK CONSTRUCTION, LLC (0.78%)
HOUSTON SAWING & DRILLING(0.23%)
ROADWAY SPECIALTIES, INC.(0.62%)
APAC-TEXAS, INC. (9.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.81%)
Contract # 03143222
Totals 1539444.20 178097.45 467351.02 30.3

CountyTRAVIS
Highway FM 1325
From LP 1
To US 183
CSJ 1376-02-039
Proj ID STP 2013(478)
Work Type MILL, SEAL & THIN OVERLAY
 
2.500 2027036.96 56519.49 1725045.12 85.8
Work Order 06-03-13
Work Began 09-30-13
Work Completed  
Time Computed 08-02-13
Contract Working Days 50
Addl Days Granted 26
Working Days Charged 96
Percent Time Used 126
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1376-02-039
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.98%)
D. I. J. CONSTRUCTION, INC.(3.65%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20%)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. (2.98%)
ROADWAY SPECIALTIES, INC.(0.42%)
NEWMAN & KENG PAVING COMPANY, INC. ( 19.25%)
TEX OP CONSTRUCTION, LP(0.43%)
TEXAS TRUCKING COMPANY, INC. (3.37%)
Contract # 03133230
Totals 2027036.96 56519.49 1725045.12 85.8

CountyWILLIAMSON
Highway RM 1431
From 0.2 MI E OF CR 185
To IH 35
CSJ 1378-02-033
Proj ID STP 2012(251)
Work Type FULL DEPTH REPAIR, SEAL & THIN OV
 
6.888 2895175.70 0.00 2356744.75 82.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-22-12
Work Began 06-03-13
Work Completed  
Time Computed 03-09-12
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 163
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-033
D. I. J. CONSTRUCTION, INC.(4.01%)
CPAVE, INC.(2.17%)
RPV CONSTRUCTION ( 15.51%)
Contract # 01123226
Totals 2895175.70 0.00 2356744.75 82.5

CountyWILLIAMSON
Highway RM 1431
From FM 734
To CR 175
CSJ 1378-02-036
Proj ID PTF 2014(560)
Work Type WIDEN TO 6 - LANE URBAN ROADWAY
 
1.491 17353255.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-05-14
Work Began 00-00-00
Work Completed  
Time Computed 06-21-14
Contract Working Days 269
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-036
AARON CONCRETE CONTRACTORS, L.P. (4.48%)
ABC EROSION CONTROL, INC.(0.65%)
AUSTIN WOOD RECYCLING(0.11%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.30%)
FLASHER EQUIPMENT COMPANY(1.47%)
G. CARTER CONSTRUCTION COMPANY, INC. (7.06%)
GK CONSTRUCTION, LLC (0.07%)
KELLYSTONE, INC(0.94%)
ROADWAY SPECIALTIES, INC.(2.95%)
ROYAL VISTA INC. ( 16.40%)
VOGES DRILLING CO. (0.14%)
Contract # 04143201
Totals 17353255.75 0.00 0.00 0.0

CountyWILLIAMSON
Highway RM 1431
From US 183
To 183-A
CSJ 1378-02-037
Proj ID STP 1102(351)
Work Type LANDSCAPING, IRRIGATION & PAVERS
 
0.904 357255.50 7500.00 344858.62 96.5
Work Order 09-13-11
Work Began 03-05-12
Work Completed  
Time Computed 12-12-11
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 95
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-037
N-LINE TRAFFIC MAINTENANCE, L.P. (1.04%)
Contract # 08113010
Totals 357255.50 7500.00 344858.62 96.5

CountyWILLIAMSON
Highway RM 1431
From ANDERSON MILL RD
To 600 FT WEST OF 183A
CSJ 1378-02-039
Proj ID C 1378-2-39
Work Type INNOVATIVE INTERSECTION IMPROVEMNTS
 
1.417 3965954.63 636163.23 2185825.86 55.1
Work Order 11-13-13
Work Began 03-05-14
Work Completed  
Time Computed 01-12-14
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 81
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-039
PERFORMANCE EQUIPMENT(0.15%)
Contract # 08133073
Totals 3965954.63 636163.23 2185825.86 55.1

CountyWILLIAMSON
Highway RM 1431
From 1000 WEST OF CHANDLER CREEK
To 200 EAST OF UNIVERSITY OAKS BLVD.
CSJ 1378-02-040
Proj ID STP 2013(297)
Work Type CONST DIVERGING DIAMOND INTRSCTN
 
0.392 6684011.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143242
Totals 6684011.97 0.00 0.00 0.0

CountyWILLIAMSON
Highway RM 1431
From 183A (TOLL) NBFR
To 0.20 MI. EAST OF CR 185
CSJ 1378-02-045
Proj ID STP 2014(938)
Work Type MILL, SEAL, OVRLAY & RESTRP TO 6 - LN
 
0.821 430708.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1378-02-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143241
Totals 430708.20 0.00 0.00 0.0

CountyCALDWELL
Highway FM 1977
From SAN MARCOS RIVER
To (STR 1434-03-002)
CSJ 1434-03-010
Proj ID BR 2013(250)
Work Type REPLACE BRIDGE & APPROACHES
 
0.104 1254724.88 49548.64 786135.11 73.4
Work Order 01-15-13
Work Began 06-10-13
Work Completed  
Time Computed 01-31-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 278
Percent Time Used 347
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1434-03-010
O & S TRAFFIC SUPPLIES (0.51%)
RICE ENVIRONMENTAL SERVICES(3.26%)
FLASHER EQUIPMENT COMPANY(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 16.88%)
Contract # 12123209
Totals 1254724.88 49548.64 786135.11 73.4

CountyHAYS
Highway RM 967
From COLE SPRING ROAD
To FM 1626
CSJ 1776-01-032
Proj ID STP 2013(655)
Work Type ADD TWLTL AND SHOULDERS
 
2.618 4408237.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 227
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05143014
Totals 4408237.86 0.00 0.00 0.0

CountyTRAVIS
Highway RM 2222
From 500 W OF WESTSLOPE CIRCLE
To LP 1 SBFR
CSJ 2100-01-058
Proj ID STP 2014(535)
Work Type UNDERSEAL AND OVERLAY
 
3.154 747616.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2100-01-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143215
Totals 747616.73 0.00 0.00 0.0

CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-017
Proj ID STP 1402(060)
Work Type CONST 4 - LN DIV & LTL
 
2.022 11875032.06 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1460
From 0.1 MI. N. OF QUAIL VALLEY DRIVE
To 0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ 2211-02-019
Proj ID HP 2012(774)
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232 490003.34 0.00 0.00 0.0
CountyWILLIAMSON
Highway FM 1460
From 0.6 MI. N OF CR 111 (WESTINGHOUSE)
To 0.05 MI. N. OF UNIVERSITY BLVD
CSJ 2211-02-026
Proj ID STP 1402(059)MM
Work Type CONSTRUCT 4 - LANE DIVIDED SECTION
 
1.600 9154356.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 390
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
OBRASCON HUARTE LAIN, S.A. INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143204
Totals 21519391.70 0.00 0.00 0.0

CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-023
Proj ID C 2293-1-23
Work Type ADD CTL & 2 - LANE DIVIDED WITH SHLDR
 
0.100 2375537.19 170173.87 1409009.71 59.3
CountyHAYS
Highway FM 2439
From CENTERPOINT ROAD
To POSEY ROAD
CSJ 2293-01-026
Proj ID RW 2293-1-23
Work Type ROW UTL. ADJ.
 
0.100 586353.33 44985.86 583493.92 99.5
Work Order 01-06-14
Work Began 03-08-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 95
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 96
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-023
AUSTIN WOOD RECYCLING(1.17%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.14%)
THE LEVY COMPANY, L.P. (1.03%)
M & M INDUSTRIAL PAINTING(0.18%)
FLASHER EQUIPMENT COMPANY(2.14%)
M. C. ETHRIDGE COMPANY ( 17.68%)
ROADWAY SPECIALTIES, INC.(2.35%)
ROSCH COMPANY(1.97%)
Contract # 08133055
Totals 2961890.52 215159.73 1992503.63 67.2

CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-024
Proj ID C 2293-1-24
Work Type ADD CENTER TURN LANE
 
0.840 5945396.48 470848.13 2102494.47 35.3
CountyHAYS
Highway FM 2439
From WONDER WORLD DR
To BISHOP STREET
CSJ 2293-01-025
Proj ID RW 2293-1-25
Work Type ADJUSTMENT OF UTILITIES
 
0.840 1005448.75 0.00 15492.00 1.5
Work Order 01-09-14
Work Began 03-17-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 34
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-024
ANGEL BROTHERS ENTERPRISES, LTD. ( 16.23%)
ENCINO LANDSCAPE, INC. (1.01%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.89%)
GK CONSTRUCTION, LLC (0.45%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.52%)
THE LEVY COMPANY, L.P. (4.50%)
JUST GROOVING, LTD.(0.05%)
SCOTT DERR PAINTING CO (0.01%)
VOGES DRILLING (0.44%)
Contract # 10133012
Totals 6950845.23 470848.13 2117986.47 30.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8