Monthly State Let Construction Report For Austin District As Of Jan 11, 2017 Page 7 Of 8

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHAYS
HighwayRM 1826
FromAT DARDEN HILL RD
To.
CSJ1754-02-019
Proj IDCC 1754-2-19
Work TypeADD TURN LANES & SHOULDERS
 
0.365746842.80778356.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-05-15
Work Began02-02-15
Work Completed
Time Computed01-21-15
Contract Working Days129
Addl Days Granted0
Working Days Charged116
Percent Time Used89
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-019
ENVIRONMENTAL SAFETY SERVICES, INC. (4.64)
LONE STAR PAVING COMPANY (39.74)
TRP CONSTRUCTION GROUP, LLC (4.37)
ROADWAY SPECIALTIES, INC. (24.40)
Contract #10143210
Totals746842.800.00778356.5799.9

CountyHAYS
HighwayRM 1826
FromTRAVIS COUNTY LINE
ToNUTTY BROWN ROAD
CSJ1754-02-025
Proj IDSTP 1502(597)
Work TypeGRADING, BASE, ACP & PVMNT MARKINGS
 
2.1864013235.581485656.0237.0
Work Order01-22-16
Work Began03-01-16
Work Completed
Time Computed03-01-16
Contract Working Days252
Addl Days Granted0
Working Days Charged193
Percent Time Used76
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1754-02-025
A BROTHERS MILLING, LLC (0.85)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.57)
FLASHER EQUIPMENT COMPANY (0.35)
RAMMING PAVING COMPANY (52.04)
ROADWAY SPECIALTIES, INC. (6.33)
Contract #08153029
Totals4013235.5852882.341485656.0237.0

CountyHAYS
HighwayRM 967
FromCOLE SPRING ROAD
ToFM 1626
CSJ1776-01-032
Proj IDSTP 2013(655)
Work TypeADD TWLTL AND SHOULDERS
 
2.6184408237.864311103.4298.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-14
Work Began09-08-14
Work Completed
Time Computed09-08-14
Contract Working Days227
Addl Days Granted66
Working Days Charged328
Percent Time Used111
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1776-01-032
ALTUS TRAFFIC MANAGEMENT LLC (0.41)
AUSTIN WOOD RECYCLING (1.86)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.21)
FLASHER EQUIPMENT COMPANY (0.45)
FUQUAY, INC. (1.42)
RAMMING PAVING COMPANY (32.68)
ROADWAY SPECIALTIES, INC. (1.40)
Contract #05143014
Totals4408237.860.004311103.4298.5

CountyTRAVIS
HighwayFM 1825
From10TH STREET IN PFLUGERVILLE
ToFM 685
CSJ1902-01-027
Proj IDSTP 2015(738)
Work TypeFULL DEPTH REPAIR, SEAL & OVERLAY
 
0.904406530.37349221.6585.9
Work Order04-10-15
Work Began06-21-16
Work Completed
Time Computed05-11-15
Contract Working Days32
Addl Days Granted0
Working Days Charged9
Percent Time Used28
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1902-01-027
ENVIRONMENTAL SAFETY SERVICES, INC. (4.70)
TEX OP CONSTRUCTION, LP (2.82)
TRP CONSTRUCTION GROUP, LLC (6.25)
STRIPES & STOPS COMPANY, INC. (0.00)
Contract #03153028
Totals406530.3746029.31349221.6585.9

CountyLEE
HighwayFM 2239
FromBASTROP COUNTY LINE
ToFM 448
CSJ2098-02-008
Proj IDSTP 2017(323)
Work TypeWIDEN, REPAIR & SEAL COAT
 
4.9412468925.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2098-02-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163033
Totals2468925.070.000.000.0

CountyTRAVIS
HighwayRM 2244
From1000 FT. WEST OF BUCKEYE TRAIL
ToWALSH TARLTON
CSJ2102-01-064
Proj IDROW 2102-1-64
Work TypeUTILITY ADJUSTMENTS
 
1.2307057669.4043990.000.6
CountyTRAVIS
HighwayRM 2244
From0.1 MILE EAST OF REDBUD TRAIL
To1000 FT. WEST OF BUCKEYE TRAIL
CSJ2102-01-066
Proj IDSTP 1502(598)
Work TypeCONST 4-LN URBAN RDWY W/ CONT LTL
 
1.79921695145.831896651.028.7
Work Order03-11-16
Work Began11-01-16
Work Completed
Time Computed06-09-16
Contract Working Days524
Addl Days Granted0
Working Days Charged19
Percent Time Used3
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2102-01-064
AUSTIN WOOD RECYCLING (1.55)
BRICK PAVING PLUS, INC. (0.02)
BRYANT & FREY CONSTRUCTION (6.08)
CHLOR-SERV, INC. (0.03)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.64)
FLASHER EQUIPMENT COMPANY (0.63)
OSCAR ORDUNO, INC. (1.35)
GK CONSTRUCTION, LLC (0.10)
SCOTT DERR PAINTING CO, LLC (0.10)
MICKIE SERVICE, INC. (0.28)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (4.09)
LONE STAR PAVING (14.80)
G. CARTER CONSTRUCTION COMPANY, INC. (5.11)
Contract #11153004
Totals28752815.231204049.971940641.026.7

CountyBASTROP
HighwayFM 1209
FromFM 969
ToSH 21
CSJ2176-01-008
Proj IDSSW 2176-1-8
Work TypePROVIDE ADDITIONAL PAVED SURFACE WI
 
4.6411990497.911295280.8765.0
Work Order08-11-16
Work Began09-06-16
Work Completed
Time Computed09-06-16
Contract Working Days124
Addl Days Granted0
Working Days Charged66
Percent Time Used53
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2176-01-008
DELGADOS CONSTRUCTION, DBA ERNESTO A. DELGADO (19.28)
EGGEMEYER LAND CLEARING, LLC (3.39)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.67)
THE LEVY COMPANY, L.P. (2.77)
MURRAY CONSTRUCTION (1.06)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.75)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.88)
TRP CONSTRUCTION GROUP, LLC (1.68)
Contract #07163227
Totals1990497.91178160.291295280.8765.0

CountyBURNET
HighwayRM 2341
From0.85 MI N OF CR 114
ToSH 29
CSJ2206-01-015
Proj IDSTP 1502(390)HES
Work TypeSAFETY TREATMENTS, ADD PAVE WIDTH
 
5.4003547716.583193144.9090.2
Work Order09-11-15
Work Began10-12-15
Work Completed
Time Computed10-12-15
Contract Working Days187
Addl Days Granted0
Working Days Charged196
Percent Time Used104
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2206-01-015
N-LINE TRAFFIC MAINTENANCE, L.P. (0.54)
ROADWAY SPECIALTIES, INC. (8.86)
DELGADO"S CONSTRUCTION (1.37)
AUSTIN WOOD RECYCLING (1.73)
LONE STAR PAVING COMPANY (6.71)
INCE ENTERPRISES, INC. (3.53)
Contract #07153212
Totals3547716.5880639.993193144.9090.2

CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-017
Proj IDSTP 1402(060)
Work TypeCONST 4-LN DIV<L
 
2.02211875032.065190409.9243.7
CountyWILLIAMSON
HighwayFM 1460
From0.1 MI. N. OF QUAIL VALLEY DRIVE
To0.6 MI. N. OF CR 111 (WESTINGHOUSE)
CSJ2211-02-019
Proj IDHP 2012(774)
Work TypeROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
2.232490003.34447169.3691.2
CountyWILLIAMSON
HighwayFM 1460
From0.6 MI. N OF CR 111 (WESTINGHOUSE)
To0.05 MI. N. OF UNIVERSITY BLVD
CSJ2211-02-026
Proj IDSTP 1402(059)MM
Work TypeCONSTRUCT 4-LANE DIVIDED SECTION
 
1.6009154356.302224268.7624.2
Work Order05-14-15
Work Began02-08-16
Work Completed
Time Computed11-10-15
Contract Working Days390
Addl Days Granted20
Working Days Charged201
Percent Time Used49
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-017
R K STEPHENS CONSTRUCTION, LLC (3.23)
TRP CONSTRUCTION GROUP, LLC (0.25)
FLASHER EQUIPMENT COMPANY (0.08)
AUSTIN WOOD RECYCLING (0.18)
AARON CONCRETE CONTRACTORS, L.P. (4.21)
JUST GROOVING, LTD. (0.01)
G. CARTER CONSTRUCTION COMPANY, INC. (3.87)
BREDA COMPANY, INC. (0.10)
BEAIRD DRILLING (0.44)
TEXAS TRUCKING COMPANY, INC. (0.00)
ROADWAY SPECIALTIES, INC. (0.60)
SMITH CONTRACTING, INC., S.A. (0.12)
AUSTIN MATERIALS, LLC (3.37)
Contract #08143204
Totals21519391.70750007.017861848.0436.5

CountyHAYS
HighwayFM 2439
FromMOORE ST
ToNORTH OF BISHOP ST.
CSJ2293-01-027
Proj IDSTP 2016(304)
Work TypeMILL, SEAL & OVERLAY
 
0.758274000.00305997.5499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-10-15
Work Began06-13-16
Work Completed
Time Computed01-09-16
Contract Working Days23
Addl Days Granted0
Working Days Charged6
Percent Time Used26
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2293-01-027
ENVIRONMENTAL SAFETY SERVICES, INC. (0.29)
TXI OPERATIONS, L.P. (4.01)
TRP CONSTRUCTION GROUP, LLC (8.69)
Contract #11153021
Totals274000.000.00305997.5499.9

CountyBLANCO
HighwayRM 2766
FromUS 281
To0.03 MI E OF RM 3232(END ST MAINT)
CSJ2677-01-008
Proj IDSTP 2015(717)HES
Work TypeGUARDRAIL&SAFETY TREAT FIXED OBJCTS
 
9.194263702.00321247.4099.9
CountyBLANCO
HighwayRM 2766
FromUS 281
To0.03 MILES EAST OF RM 3232
CSJ2677-01-009
Proj IDSTP 2015(718)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE WI
 
9.1944031197.974300828.6599.9
Work Order04-22-15
Work Began06-08-15
Work Completed
Time Computed05-08-15
Contract Working Days184
Addl Days Granted70
Working Days Charged300
Percent Time Used118
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2677-01-008
D.I.J. CONSTRUCTION, INC (3.46)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.46)
Contract #03153210
Totals4294899.9715398.084622076.0599.9

CountyLEE
HighwayFM 180
FromUS 290
ToFM 1697
CSJ3114-01-012
Proj IDSTP 1502(058)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE WI
 
9.7064218820.704254175.2599.9
Work Order06-18-15
Work Began09-21-15
Work Completed
Time Computed08-18-15
Contract Working Days129
Addl Days Granted28
Working Days Charged154
Percent Time Used98
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3114-01-012
BMP SPECIALIST, LLC (0.25)
FLASHER EQUIPMENT COMPANY (2.09)
MURRAY CONSTRUCTION (0.50)
PEDRO CARLOS CONSTRUCTION CO. (2.85)
ROADWAY SPECIALTIES, INC. (2.03)
Contract #04153255
Totals4218820.70148930.784254175.2599.9

CountyTRAVIS
HighwayLP 1
FromNORTH OF LP 360
ToNORTH OF US 290
CSJ3136-01-172
Proj IDC 3136-1-172
Work TypeADD BICYCLE BRIDGE
 
0.4487396549.397507141.9899.9
CountyTRAVIS
HighwayLP 1
FromLP 360
To0.5 MI NORTH OF SOUTHWEST PARKWAY
CSJ3136-01-173
Proj IDC 3136-1-173
Work TypeMILL & OVERLAY FOR RESTRIPE SBML
 
1.050376467.390.000.0
Work Order01-23-14
Work Began02-10-14
Work Completed
Time Computed02-08-14
Contract Working Days549
Addl Days Granted155
Working Days Charged704
Percent Time Used100
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-172
FLASHER EQUIPMENT COMPANY (1.33)
RUSSO CORPORATION (7.36)
ROADWAY SPECIALTIES, INC. (4.32)
AUSTIN WOOD RECYCLING (0.88)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.29)
A BROTHERS (OLD PRIME) (0.21)
APAC-TEXAS, INC. (5.66)
CARMA CONSTRUCTION, LLC (2.31)
CHEROKEE SERVICES (0.32)
THE LEVY COMPANY, L.P. (12.72)
MCL CONTRACTING, LLC (0.45)
R K STEPHENS CONSTRUCTION, LLC (2.38)
SCOTT DERR PAINTING CO, LLC (0.25)
SOUTHEAST GRINDING & GROOVING, LLC (0.04)
TEXAS HIGHWAY WALLS (3.07)
OSCAR ORDUNO, INC. (1.10)
Contract #10133028
Totals7773016.781320.187507141.9896.5

CountyTRAVIS
HighwayLP 1
FromTUSCAN TERRACE AT LOOP 1 (MOPAC)
ToAPPROX 500 FT N. OF BARTON CREEK
CSJ3136-01-174
Proj IDSTP 1402(061)MM
Work TypeCONSTRUCT BICYCLE & PED BRDG (PH 1)
 
0.4982985697.492969265.9999.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-14
Work Began01-26-15
Work Completed
Time Computed12-17-14
Contract Working Days250
Addl Days Granted12
Working Days Charged263
Percent Time Used100
Contractor(s)
AUSTIN FILTER SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-174
METALINK CORPORATION (0.04)
AVERY"S LAWN CARE & LANDSCAPE (1.55)
GK CONSTRUCTION, LLC (0.27)
D. I. J. CONSTRUCTION, INC. (0.28)
ROADWAY SPECIALTIES, INC. (3.23)
TURNKEY OPERATIONS (0.93)
VOGES DRILLING CO. (1.85)
S & S BRIDGE PAINTING, INC. (0.62)
THE LEVY COMPANY, L.P. (10.22)
Contract #08143214
Totals2985697.490.002969265.9999.4

CountyTRAVIS
HighwayLP 1
FromBARTON CREEK
ToSOUTHWEST PARKWAY
CSJ3136-01-178
Proj IDSTP 2014(561)
Work TypeOVERLAY FRONTAGE ROADS
 
0.501740923.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-14
Work Began00-00-00
Work Completed
Time Computed06-26-14
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-178
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04143220
Totals740923.260.000.000.0

CountyHAYS
HighwayFM 2770
FromFM 1626
ToRM 150
CSJ3210-01-013
Proj IDSTP 2016(175)
Work TypeMILL & THIN OVERLAY
 
3.047839994.76850531.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-24-15
Work Began05-16-16
Work Completed
Time Computed12-24-15
Contract Working Days40
Addl Days Granted0
Working Days Charged24
Percent Time Used60
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3210-01-013
ENVIRONMENTAL SAFETY SERVICES, INC. (5.48)
TRP CONSTRUCTION GROUP, LLC (4.29)
Contract #10153013
Totals839994.760.00850531.1099.9

CountyTRAVIS
HighwayFM 3177
FromUS 290
To0.02 MI NORTH OF LINDELL LN
CSJ3277-01-013
Proj IDSTP 1302(009)
Work TypeREALIGN RDWY
 
0.8383616126.773875784.7499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-14
Work Began02-03-14
Work Completed
Time Computed01-22-14
Contract Working Days159
Addl Days Granted73
Working Days Charged232
Percent Time Used100
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 3277-01-013
AUSTIN WOOD RECYCLING (0.53)
FLASHER EQUIPMENT COMPANY (1.53)
APAC-TEXAS, INC. (25.79)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84)
DUSTROL, INC. (0.45)
ROADWAY SPECIALTIES, INC. (3.30)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.10)
TREVWAY, INC. (1.12)
Contract #08133051
Totals3616126.770.003875784.7499.9

CountyTRAVIS
HighwayFM 3177
From0.1 MI NORTH OF DAFFAN LN
To0.1 MI SOUTH OF LOYOLA LN
CSJ3277-01-022
Proj IDSTP 2014(116)TE
Work TypeCONSTRUCT SIDEWALKS
 
1.6102045353.10398091.3119.4
Work Order08-05-16
Work Began09-19-16
Work Completed
Time Computed09-04-16
Contract Working Days240
Addl Days Granted0
Working Days Charged67
Percent Time Used27
Contractor(s)
M. A. SMITH CONTRACTING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3277-01-022
ENVIRONMENTAL SAFETY SERVICES, INC. (12.84)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.44)
VOGES DRILLING CO. (1.25)
LONE STAR PAVING COMPANY (1.55)
Contract #03163005
Totals2045353.10218060.68398091.3119.4

CountyBLANCO
HighwayRM 3232
FromRM 2766
ToUS 290
CSJ3351-02-005
Proj IDSTP 2015(719)HES
Work TypePROVIDE ADDITIONAL PAVED SURFACE WI
 
6.3963490778.453333614.6795.4
Work Order04-20-15
Work Began06-25-15
Work Completed
Time Computed05-06-15
Contract Working Days225
Addl Days Granted34
Working Days Charged253
Percent Time Used97
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3351-02-005
AUSTIN WOOD RECYCLING (3.58)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.08)
FLASHER EQUIPMENT COMPANY (4.75)
GEOSOURCE, INC. (2.93)
RELMCO, INC. (15.49)
ROADWAY SPECIALTIES, INC. (4.26)
Contract #03153002
Totals3490778.45102708.553333614.6795.4

CountyTRAVIS
HighwayFM 734
FromLEGENDARY CIRCLE
To0.466 MI. SOUTH OF LEGENDARY CIRCLE
CSJ3417-01-028
Proj IDCC 3417-1-28
Work TypeGR, BASE, ACP, SGNL_& PVMT MKS
 
0.466839340.91837386.8299.7
Work Order04-25-16
Work Began07-25-16
Work Completed
Time Computed05-25-16
Contract Working Days76
Addl Days Granted0
Working Days Charged56
Percent Time Used73
Contractor(s)
BPI - BAUERLE PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3417-01-028
AUSTIN MATERIALS, LLC (6.61)
A BROTHERS (OLD PRIME) (0.59)
EVT CONSTRUCTION (1.04)
N-LINE TRAFFIC MAINTENANCE, L.P. (5.88)
THE LEVY COMPANY, L.P. (39.55)
TRP CONSTRUCTION GROUP, LLC (2.28)
BREDA COMPANY, INC. (0.15)
SRIPE-IT-UP (2.48)
Contract #02163210
Totals839340.91147940.85837386.8299.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8