Lomas Del Sur Overpass
Skip to main content

Lomas Del Sur Overpass

Project CSI: 0086-16-008, etc.

Overhead satellite map view of the Lomas del Sur Interchange project construction site, marked up to highlight the location of the new interchange to be constructed. Text on the image reads: "SL20 at Lomas del Sur Interchange; CSJ: 0086-16-008; Construction cost: $49,586,906.60.
Project Status
  Not Started In Progress Complete
Preliminary Engineering    
Planned Development    
Right-of-Way Acquisition    
Utility Accommodation    
Pre-letting Review    
Construction    
Project Closing    

County:

Webb

Highway:

SL 20

Length:

1.301 miles

Limits:

From 0.580 Miles South of Lomas Del Sur Blvd. to 0.721 Miles North of Lomas Del Sur Blvd.

Existing SL20 at Lomas Del Sur Blvd is a closed intersection that will be upgraded to an elevated bridge structure to allow vehicular movement underneath SL20 and maximize traffic flow.

This project will introduce an overpass structure with 2 main lanes in each direction with the capacity to widen in the future to 3-lanes, frontage roads, and ramps.

Construction will also add a shared-use-path for pedestrians and bicyclists along the west frontage road. 

None.

The construction cost of the project is $49,586,906.60 and is being funded by 80% Federal funds and 20% State funds.

The project will be constructed in 4 phases.

Phase 1 will include the construction of the overpass at the current closed intersection, retaining walls, and ramps. As well include constructing a permanent traffic barrier from 0.5 miles south of SH 359 to 0.5 miles N or Lomas Del Sur, along Loop 20 (Cuatro Vientos).

Phase 2 will be the reconstruction of the frontage roads, northbound and southbound.

Phase 3 will be the construction of the sidewalk along the SB frontage road.

Phase 4 will be the installation of signage and striping. 

Actual Let Date:

November 7, 2024

Contractor:

Anderson Columbia

Scheduled Duration:

33 months

Project Cost:

$49,586,906.60